THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 202
ON SITE STAFF & LABOUR RECORD Day: Saturday Date: 2020/5/9 ON SITE PLANT & EQUIPMENT RECORD
No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs
2 DGM 1 9 ● 2 Lorry 1 9
10 Financial Manager 1 9 3
11 Construction Staff 9 9 4
12 Office Staff 7 9 5
14 7
15 8
2 2 Formwork for the slab and beam for the basement 1 part 4-1/2 area 80%
3 3 Reinforcement work for the beams and slabs for the basement 1 part 4-1/2 area 70%
4 Reinforcement work for the columns and and shear walls for the part 5 area 80%
5 5 Formwork for the slab and beam for the basement 1 at part 3-3 area 15%
6 Reinforcement work for the columns of basement 1 at part 3-3 area 100%
REMARKS 7 Reinforcement work for the beams and slabs for basement 1 at part 3-2 area 25%
The confirmed COVID-19 in Ethiopian from last month have seriously affected 8 Form work for the beams and slabs for basement 1 part 3-2 area 40%
the project progress .And it has resulted the mobilization delay of chinese
9 MEP work based on the civil work
technican and local labor based the site progress and the local workers
have decreased rapidly at site.And it also resulted delay of the materials 10
1 purcahse ,shipment and transportation .
11
1.Local religon ramadan resulted the low work efficiency.
12
13
Working time of the local workers has to be decreased from 9 hours to 8 hours
for one
2 day due to transportation problem caused by COVID-19 and they also need more Submission : Noted:
payments such as special transportation fee for their work.
Signed by: Song Baoliang Signature Signed by: Signature: