Professional Documents
Culture Documents
Prepared By: Bestari Consulting Engineers SDN BHD
Prepared By: Bestari Consulting Engineers SDN BHD
Attendance:
No Name Company Contact no Email Address
1 Leong Soon Kit TKSB 012-675 6789 skleong@tenagakimia.com
CCM 10-2019 1
MINUTES OF MEETING
1.0 INTRODUCTION
3.11 TK has confirmed the final layout today, thus ESP to work on TK 21st Nov 2019
KM submission and all documents to be finalised by 21st Nov
2019.
3.12 TK confirmed to demolish the bird Nest due to CCC issue. Info
3.14 TK & ESP advised, blasting & burning pad and pond which is Info
not in our boundary to be take out from submission layout.
3.21 UCSB informed TOR will be submitted to DOE in two weeks UCSB
time (18th Nov 2019). UCSB require site plan from SAHA and
slope analysis from BCE for the submission.
3.3 ARCHITECT
3.31 SAHA updated there are 17 buildings in total to pass to all SAHA 15th Nov 2019
consultants by tomorrow.
3.32 SAHA to prepare submission drawing and liaise with ESP SAHA
based on local Authorities requirements.
3.33 TK to confirm soonest possible for fencing demarcation and TK
CCM 10-2019 2
specifications to SAHA.
3.34 SAHA to complete site plan and GFA and to submit to ESP for SAHA
parking requirements by MP Bentong. TK need 20 space for
lorry, 30 cars and 100 motorcycles.
3.41 BCE to provide layout for “persimpangan jalan masuk” to SAHA BCE
by tomorrow.
3.42 BCE advised to use portal frame design for warehouse to BCE
minimize total number of column.
3.51 HSK to provide suction tank and pump house(booster pump) HSK
location.
3.52 TK to provide load requirements to HSK and loading of each TK
equipment to BCE for design purpose.
3.6 QS CONSULTANT
3.61 HRM to liaise with TK on the demolition and relocation works as HRM
per checklist given.
3.62 TK requested specification of Earthwork and Building works. HRM
3.63 HRM to provide cost comparison of covered and uncovered HRM
walkway to TK.
4.1 BCE to revise the work programme and amend the task and duration BCE
in details accordingly. All consultants to give their comments on the
project schedule.
5.1 The next meeting is tentatively on Thursday 21st Nov 2019 at 3.00 Info
p.m. Meeting adjourned at 4.45 p.m.
CCM 10-2019 3
PACKAGING AND SCOPE OF WORKS
i Site Clearing
ii Demolition & Relocation of existing buildings & utilities
iii Platform (Building)
iv Road (Platform)
v Temporary drain & slit trap, wash through & temporary construction
vi Slope with turfing & retaining wall
vii Retention Pond & Permanent Drain
i Road works
ii Drainage
iii Sewerage
iv WWTP – Pipe
v S.S.T.P.
vi Work Outside Boundary
NEW BUILDING (9 Months) & REHAB EXISTING BUILDING (5 Months)
3.0
Rehab Building
i Office
B
ii Plant
iii Bird Nest
iv Existing Packaging Warehouse
New Building
i As Per New List
ii Landscape
4.0 FENCING
i Boom Gate
ii Front Gate
5.0 M&E
i Cabling
ii Compound & Street Lighting
iii Telephone & Internet
iv CCTV
v Internal Plumbing & Sanitary
vi Internal Electrical
vii Fire Fighting
CCM 10-2019 4