CLIENT CONSULTANT MEETING

PROPOSED REFURBISHMENT OF EXISTING BUILDINGS AND CONSTRUCTION OF NEW INDUSTRIAL COMPLEX


ON LOT 5482, LOT 5483, LOT 26279, LOT 26280, LOT 3921, LOT 4559, LOT 4931, LOT 4930, LOT 3749, LOT 5092,
LOT 5093 AND LOT 5736, JALAN TRAS, MUKIM BENTONG, DAERAH BENTONG, PAHANG DARUL MAKMUR FOR
MESSR. TENAGA KIMIA SDN. BHD.

Date : 14th Nov 2019 Prepared by:

Time : 3.00 p.m BESTARI CONSULTING ENGINEERS SDN BHD

Venue : TENAGA KIMIA SDN BHD


No. 8, Jalan SS 22/21, Damansara Utama,
47400 Petaling Jaya, Selangor Office.

CLIENT CONSULTANT MEETING NO. 10

Attendance:
No Name Company Contact no Email Address
1 Leong Soon Kit TKSB 012-675 6789 skleong@tenagakimia.com

2 Ng Bee Hong TKSB 012-2621656 beehong@tenagakimia.com


3 Lim Xin Ning TKSB 012-370 3675 xnlim@tenagakimia.com
4 Hakeem Hamzah TKSB 012-321 1503 hakeem@tenagakimia.com

5 Ir. Muhamad Abdul Rahman BCE 012-5002091 bcesb2004@gmail.com


6 Nusaibah Yusof BCE 017-424 5800 bcesb2004@gmail.com
7 Abd Rahman b Rosli SAHA 012-660 2695 rahman.manora@gmail.com
8 Ahmad Rasydan b Rossidin SAHA 018-243 6169 dankidal89@gmail.com

9 Nurul Farehah Mohamed JUB HRM 014-814 8153 jub_hrm@yahoo.com


10 Muamar Adib Hakimi HSK Consult 013-370 1554 mu.adibhakimi@gmail.com
11 Muhammad Akram b Abu Bakar HSK Consult 010-4373911 xakamx@gmail.com
12 Salmin b. Husin Uniti Consultants 019-2765930 salminhusin@gmail.com

CCM 10-2019 1
MINUTES OF MEETING

No Descriptions Action by Target Date

1.0 INTRODUCTION

1.1 Chairperson welcomed all representatives from Client and


Consultants.

2.0 CONTRACTUAL MATTERS

2.1 BCE has issued LOA to all consultant. Info


2.2 BCE reminded all consultants to substantiate for claim and work done.. All
Consultants
3.0 PROJECT SCHEDULE & TIMELINE

3.1 TOWN PLANNER

3.11 TK has confirmed the final layout today, thus ESP to work on TK 21st Nov 2019
KM submission and all documents to be finalised by 21st Nov
2019.
3.12 TK confirmed to demolish the bird Nest due to CCC issue. Info

3.13 TK mentioned position of new buildings are confirmed but Info


dimension may have minor changes.

3.14 TK & ESP advised, blasting & burning pad and pond which is Info
not in our boundary to be take out from submission layout.

3.2 ENVIRONMENTAL CONSULTANT

3.21 UCSB informed TOR will be submitted to DOE in two weeks UCSB
time (18th Nov 2019). UCSB require site plan from SAHA and
slope analysis from BCE for the submission.

3.22 UCSB mentioned 2 boreholes will be set as permanent for Info


ground water monitoring well. Additional cost for the standpipe
has emailed to BCE.
3.23 UCSB to maintain existing design of WWTP. UCSB

3.3 ARCHITECT

3.31 SAHA updated there are 17 buildings in total to pass to all SAHA 15th Nov 2019
consultants by tomorrow.

3.32 SAHA to prepare submission drawing and liaise with ESP SAHA
based on local Authorities requirements.
3.33 TK to confirm soonest possible for fencing demarcation and TK

CCM 10-2019 2
specifications to SAHA.

3.34 SAHA to complete site plan and GFA and to submit to ESP for SAHA
parking requirements by MP Bentong. TK need 20 space for
lorry, 30 cars and 100 motorcycles.

3.35 TK to advise covered pedestrian walkway to SAHA to include in TK


site plan.

3.4 C&S CONSULTANT

3.41 BCE to provide layout for “persimpangan jalan masuk” to SAHA BCE
by tomorrow.
3.42 BCE advised to use portal frame design for warehouse to BCE
minimize total number of column.

3.43 BCE to submit Earthwork Package 1 drawing to TK for review. BCE

3.5 M&E CONSULTANT

3.51 HSK to provide suction tank and pump house(booster pump) HSK
location.
3.52 TK to provide load requirements to HSK and loading of each TK
equipment to BCE for design purpose.

3.6 QS CONSULTANT

3.61 HRM to liaise with TK on the demolition and relocation works as HRM
per checklist given.
3.62 TK requested specification of Earthwork and Building works. HRM
3.63 HRM to provide cost comparison of covered and uncovered HRM
walkway to TK.

4.0 OTHER MATTERS

4.1 BCE to revise the work programme and amend the task and duration BCE
in details accordingly. All consultants to give their comments on the
project schedule.

5.0 ADJOURNMENT AND NEXT MEETING

5.1 The next meeting is tentatively on Thursday 21st Nov 2019 at 3.00 Info
p.m. Meeting adjourned at 4.45 p.m.

CCM 10-2019 3
PACKAGING AND SCOPE OF WORKS

1.0 EARTHWORKS (6 Months)

i Site Clearing
ii Demolition & Relocation of existing buildings & utilities
iii Platform (Building)
iv Road (Platform)
v Temporary drain & slit trap, wash through & temporary construction
vi Slope with turfing & retaining wall
vii Retention Pond & Permanent Drain

2.0 INFRA STRUCTURE

i Road works
ii Drainage
iii Sewerage
iv WWTP – Pipe
v S.S.T.P.
vi Work Outside Boundary
NEW BUILDING (9 Months) & REHAB EXISTING BUILDING (5 Months)
3.0

Rehab Building
i Office
B
ii Plant
iii Bird Nest
iv Existing Packaging Warehouse

New Building
i As Per New List
ii Landscape

4.0 FENCING

i Boom Gate
ii Front Gate

5.0 M&E

i Cabling
ii Compound & Street Lighting
iii Telephone & Internet
iv CCTV
v Internal Plumbing & Sanitary
vi Internal Electrical
vii Fire Fighting

6.0 WASTE WATER TREATMENT PLANT ( DIRECT NEGO)


A Structure & External Piping - By package Infra
B Equipment By Specialist – Including Approval By DOE

CCM 10-2019 4