1 2 3 4
Activities 1 to 4 5 to 8 9 to 12 13 to 16
1.1. Initiating
1.1.1 Develop Scope and Plan $ 500.00
1.1.2 Engage Stakeholders $ 170.00 $ 170.00 $ 134.00 $ 134.00
1.1.3 Raise Funds $ 300.00 $ 600.00
1.2 Planning
1.2.1 Flight Delivery $ 500.00 $ 1,700.00
1.2.2 Cost Estimate $ 900.00 $ 900.00
1.2.3 Approvals $ 400.00
1.3 Construction
1.3.1 Purcharse Materials $ 210.00 $ 2,570.00
1.3.2 Rent Equipment $ 100.00 $ 1,680.00
1.3.3 Engage Specialist $ 900.00 $ (300.00)
1.3.4 Complete Delivery
1.4 Testing
1.4.1 Priscriptions Testing
1.4.2 Flight Testing
1.5 Delivering
1.5.1 Travel
1.5.2 Event
$ 500.00
$ 134.00 $ 134.00 $ 86.00 $ 86.00 $ 62.00 $ 1,110,00
$ 900.00
$ 2,200.00
$ 1,800.00
$ 400.00
$ 4,670.00
$ 1,790.00
$ 600.00
$ 3,100.00 $ 1,500.00
$ 900.00 $ 900.00
$ 700.00 $ 700.00