Brief of The Claims

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Brief of the claims raised by Concessionaire & awarded by AT with comments / remarks of

CE-RO, Bhopal

Claim Claim raised by Decision of AT Details of Court Grounds of relief for challenging the
no. Concessionaire on claim cases on claims Award U/s 34
under AT Award
1(a) Rs 32.43 Cr+ interest AT declared an amount of Claim challenged During the extended period of
@12% towards Rs. 17.25 Cr + interest before High Court, completion, calculation of claim amount
additional cost of which is the difference Delhi by the State towards deployment of plant &
deployment of plant & between accepted Govt. machinery, overhead cost, loss of
machinery, overhead financial bids as per recovery overhead and profit during
cost, loss of recovery Schedule-‘H’ (page 378 of extended period of construction,
overhead and profit CA) and construction cost increase in cost of labour, plant &
during extended increased in audited machinery and other materials
period of balance sheets for the including POL are not given.
construction, increase year 2009. One of the Further, due to delay in approval by
in cost of labour, arbitrator rejected the Railways, Contractor could have
plant & machinery claim and the claim was completed road work but did not do so,
and other materials decided by the majority until design of ROB is approved.
including POL (2:1)
Article 5.2 (c) (i), it was the obligation of
Concessionaire to “apply for and obtain
all necessary clearances and/or
approvals for the construction of Road
Over Bridge (ROB) / from the Ministry
of Railways” and under Article 5.3 (iii),
the Government of India was required
to provide necessary assistance to the
Concessionaire in securing applicable
permits which was done on the request
of Concessionaire.
One of the Arbitrator also rejected the
claim of additional cost of deployment
of plant and machinery etc during the
extended period from the ground that
working front to take up the work were
available for road works. The non-use
of mobilized equipment and inaction on
the part of claimant to carry out and
complete work other than ROB on the
available front, cannot be ground to
grant compensation for idling charges,
escalation etc
Moreover, costs actually incurred and
certified by the statutory auditor of
concessionaire due to Force Majeure
event have not been brought before the
AT.
Claim has been challenged by State
Govt. after approval of Ministry in OMP
1666/2014 filed before Hon’ble High
Court, Delhi, Decision pending.
1(c) 29 months extension AT decided that on Claim challenged Article 5.2 (c) (i), it was the obligation of
in concession period account of delay in before High Court, Concessionaire to “apply for and obtain
handing over of GAD from Delhi by the State all necessary clearances and/or
19.08.2002 (signing of Govt. However,approvals for the construction of Road
Agreement) to 17.11.2005 High Court in
Over Bridge (ROB) / from the Ministry
(date of GAD approval) petition filed by theof Railways” and under Article 5.3 (iii),
and further on account of Concessionaire in the Government of India was required
delay in removal of HT/LT January 2020to provide necessary assistance to the
lines a period of 23+6= 29 (OMP(I) (comm) Concessionaire in securing applicable
months extension in 26/2020 in its Order permits which was done on the request
concession period has dated 12.3.2020 has of Concessionaire.
been considered as awarded the claim
As per Definition of Concession Period
reasonable. in favour of
in CA vide Clause 2.2 provides 12 yrs
Concessionaire
of concession period including
implementation period. Further, the
State PWD has challenged the Award
in High Court, Delhi in OMP 1666/2014,
decision on which is pending. Despite
case being pending in Court, High
Court Delhi in petition filed by
Concessionaire vide Order dated
12.03.2020 has allowed collection of
toll for 29 months.
3 Modification of TollThe AT noted that there is Claim upheld by the With regard to instant claim, following is
notification dated
some miss-match between High Court Order brought out –
20.02.2018 for
the Definition of the dated 12.9.2014 in
Definition of Concession Period in CA
enabling Concession period saying OMP 1015/2014
vide Clause 2.2 provides 12 yrs
Concessionaire to
it 12 years including filed by
including implementation period.
collect toll for
implementation period and Concessionaire for
operation period of 12
the accepted financial bid implementation of Further, as per Article 1.2.3 (ii) in case
years ending on vide Schedule-H, Award in High of ambiguities or discrepancies
22.02.2020. Appendix ‘B’, CSD at page Court, Delhi. Appeal between the Articles and the
no. 334-335 of the CA filed by State Govt. Schedules, the Article shall prevail.
providing the operation vide FAO (OS) Accordingly as per Article 2.2,
period of 12 years 115/2018 pending concession period comprises operation
commencing from the before High Court, period being implementation period.
COD. Accordingly, AT Delhi.
considering the ‘Doctrine Case was challenged before High
of Contra Preferentum’ Court Delhi and High Court vide Order
also known as dated 22.12.2017 dismissed objection
“interpretation against the of Authority. Subsequently State PWD
draftsman” concluded that filed appeal against the Court Order on
notification dated 22.12.2017 which is pending.
20.02.2008 should be
modified to provide toll tax
collection for operation
period of 12 years and
ends on 22.02.2020.
4 Rs. 5.05 Lakhs as Claim allowed with interest Claim challenged Claim is challenged in High Court,
difference of Fees @ 18% before High Court, Delhi.
unpaid towards cost Delhi by the State
of Arbitration Govt. in OMP
1666/2014 Decision
pending

You might also like