Professional Documents
Culture Documents
Xecutive Ummary: Surface Mining System 432/532
Xecutive Ummary: Surface Mining System 432/532
Xecutive Ummary: Surface Mining System 432/532
EXECUTIVE SUMMARY
The purpose of this report is to investigate and analysis mining processes and their key
drivers, and infrastructure and equipment requirements. A dimensioned diagram showing the
overall layout of the stages of the pit has been designed. Two hauling systems have been
evaluated in this report, the option 1 is the electric shovel and trucks hauling system, and
option 2 is the backhoe hydraulic excavator and trucks hauling system. This report
demonstrates a detailed description of the proposed material handling systems for the mine
together with a detailed equipment selection, labour and equipment schedules. For option 1
7945HD electrical shovel has been chosen, and the truck 793F and HD1500-7 have been
chosen as the hauling trucks to haul ore and waste respectively, and for option 2, the PC4000-
6 and 793D have been chosen as the excavator and the hauling trucks. Core risk identification
and mitigation have been researched related only to the system being considered, and it is not
a generic risk assessment, the risk assignment in this report are considering economic,
environmental, and social and OHS considerations. On completion of the project, we have
estimated of overall capital and operating cash costs and unit cost (A$/t) for materials
handing in ore and waste. The cost estimates have provided details of how they have been
derived, including referencing sources. According to the result of the estimation, even though
option 1 cost more in maintenance cost and capital cost, the overall cost of option 1 is less
than option 2. Option 2 requires more money on fuel consumption. Regarding to OHS and
the technical aspects, both of the options have their own advantages and disadvantages;
therefore, basing on the mining design, the requirements of productivity and feasibility and
efficiency requirement of the excavators, the final decision for this mine is option 1. This
report has also identified and evaluates core risks and sensitivities associated with each truck
or excavators combinations adopted to ameliorate the major risks. As a result, a realistic ore
and waste removal schedule in order to carry out a safe and efficient truck and shovel
operation for the mine has been given and recommend at end of the report.
TABLE OF CONTENT
Executive Summary.................................................................................................................................................1
Table of content........................................................................................................................................................2
List of Tables............................................................................................................................................................4
List of Figures..........................................................................................................................................................5
Assumptions:....................................................................................................................................................6
Pit design..........................................................................................................................................................8
Estimation of total ramp lengths in year 1(on the side hill) and in year 20(in the pit)..........10
Equipment Selection..............................................................................................................................................13
haul trucks..............................................................................................................................................15
Fleet selection.................................................................................................................................................15
Equation 1..............................................................................................................................16
Equation 2..............................................................................................................................18
Fleet size.........................................................................................................................................................21
Cost estimation.......................................................................................................................................................25
Assumptions...................................................................................................................................................25
Operating cost................................................................................................................................................26
Fuel.........................................................................................................................................................26
Capital cost.....................................................................................................................................................29
Cost summary.................................................................................................................................................31
Technical factors exert the greatest influence on both systems for the pit:...................................................33
Hydraulic pump......................................................................................................................................34
Oil filter..................................................................................................................................................35
Relief valve............................................................................................................................................35
Economic Risks:.............................................................................................................................................37
Reference................................................................................................................................................................40
Appendices.............................................................................................................................................................41
Appendix 1:....................................................................................................................................................41
Appendix 2:....................................................................................................................................................43
Appendix 3:....................................................................................................................................................52
Appendix 4:....................................................................................................................................................54
LIST OF TABLESY
Table 1Haul distance to plant in year 1, 3, 5, 10, 20......................................................................................11
Table 5Comparison of open pit loading equipment (Introductory mining engineering, P143).....................13
Table 7Typical bucket fill factors for an electric shovel (Introductory mining engineering, P260).............17
Table 9 Cycle times under different digging conditions and bucket sizes for a shovel (Introductory mining
Engineering, P259).................................................................................................................................17
Table 10Num. of Passes when matching Shovel CAT 7495HD with Truck CAT 797F...............................18
Table 11No of Passes when matching Shovel CAT 7495HD with Truck CAT 793F...................................19
Table 12 Based on table 3 and the selected equipment, designing parameters of pit are summarised..........19
Table 14Ratios of capacity (struck) over ore volume based on different models..........................................20
Table 15Num. of Passes for ore when matching Shovel CAT 7495HD with Truck HD1500-7...................21
Table 2 Total operating cost over the 20 years for option 1 and option2......................................................28
Table 26 No of Passes for waste when matching Backhoe Komatsu PC4000 with Truck CAT 793D.........41
Table 44The risk assignment of Ultra-large electric shovels with suitable trucks........................................54
List of Figure
Figure 3Typical loading modes of an electric shovel (left) and a backhoe excavator (Right)......................16
Based on this project, this mine has high grade iron ore, which located in 400kms east of Port
Hedland, also called Mt Wombat. In terms of this deposit, which above the surrounding area
around 40 meters, while continues under the natural surface in the depth exceeding 150
meters as well.
Sales of iron ore is determined as 20 Mtpa in a two-year period from now then increase in 30
Mtpa in year 3 continuing five years currently. Furthermore, the strip ratio is 2 to 1 by weight
in the first nine years, then chanced to 3 to 1 by weight as well in year ten after mine go
beneath the natural surface. In addition, waste dumps surround the pit area remains constant
in 20 years with other information, which are flat hauls along natural surface of 1.7 kms,
dump height of 30 m and along dump top surface is 0.7 kms. To meet the optimal fleet, many
elements will be considered, such as technical fit, environmental, social and OHS
considerations, labor, capital and operating costs. Additionally, all group members share
workload and have group meeting and discussions weekly to finish this project on time.
Pilbara region is the home to iron ore in WA. In 2012 iron ore was the State’s highest valued
sector, accounting for $51 billion (or 70 per cent) of total mineral sales. The iron ore deposit
known as Mt Wombat lies in Pilbara 400km east of Port Hedland and has a diameter of
3300m (approximate estimation about hill foundation diameter is attached in Appendix A). It
stands 40m above the surrounding flat plain and continues to a depth of more than 150m.
Open cut operation is started at the top of the hill and progressively mined downwards. Two
fleet options are explored, i.e. Option 1—ultra large electric shovels with large trucks; Option
2—backhoe hydraulic excavators with 200t capacity trucks. In this project, Terms Mountain
and hill are interchangeable
ASSUMPTIONS:
11. The hauling distance from the pit to dump which includes the level, the up and down
ramp would be as same as the calculation, and the traveling speed of the truck follows
ideally with the calculation.
12. Life for a truck is 10 years, life for a truck tire is 7000 hours, for an electric shovel is 20
years, for a hydraulic back-hoe is 8 years.
13. Assume there are enough stuffs and they are 100% available.
14. Assume the tax and royalty cost is negligible. Fixed cost, which including Depreciation,
PIT DESIGN
BENCHES AND PIT SLOPES
In this project the two massive iron ore bodies are dipping to the west 40° to the horizontal.
Therefore benches in the east are left inactive to maintain slope stability, in which case slope
angle can be larger. Benches except inactive ones are under progressive development with a
less steep slope. The overall slope should be set as steep as possible to reduce the waste
removal amount while not compromising production, safety or future plan. Given the general
data on rock strength, discontinuities, water presence, etc. the overall slope angle of inactive
benches is 67°; that of working benches is 54°.
Working benches should be wide enough to accommodate the turning radius of the largest
haul truck plus the width of the safety berm, ranging from 30 m to several hundred meters
(SME Mining handbook, P858).
Haul road length should be minimized with an average ramp grade of 10% for conventional
rear dump trucks. On two way straights and in two way bends haul roads with width 3-3.5
and 3.5-4 times the largest width of haul trucks are considered to provide space required for
the truck to make a 180° turn without backing. Conventional safety berms are left in place
along bench crests with a dimension mentioned above. Road surface is sloped 2% to sides to
allow for drainage. With the consideration of the convenience, two exits to waste dump have
been designed in this pit as the graph above shows. Ditches are recommended to facilitate
that purpose. Haul truck speed at corners should be limited to 15 km/h otherwise corners are
superelevated. Haul road profiles especially haul road length are discussed in the next
section.
connecting waste dump of 301m and a flat haul along dump top surface of 700m. Two haul
roads are planned for waste haulage. Depending on the loading and hauling locations, trucks
can choose the closer haul road. One haul road is proposed for ore haulage straight to the
processing plant in the east.
Height of dump 30
As the Figure shows, grade = => a= = 300m.
a 0.1
Haul road profiles on the hill and in the pit constantly change as the mining activity
progresses. To help estimate these distances, assume the hill has a circular foundation. A
radius of 1650 m is found.
E STIMATION OF TOTAL RAMP LENGTHS IN YEAR 1( ON THE SIDE HILL ) AND IN YEAR 20( IN THE
PIT )
Assume a ramp grade of 10% is adopted throughout the life of mine. As the initial height of
the hill is 40 m, using Pythagorean's theorem, total ramp length l:
So a 402 m long ramp is required in year 1 to reach the hill top. In year 20, the ultimate pit
depth is 40 m (Figure cross-section of ramp in year20). Using Pythagorean's theorem, total
ramp length s: s = √ 402 + a2=√ 402 + 4002=402m
For hill haul road in year 1, a 402 m long ramp is required to reach the hill top assuming a
ramp grade of 10% is used throughout the life of mine. Having compared the ramp length and
the radius, it is observed that a significant amount of level road segments or interim benches
on side hill are required to interconnect ramp segments. Because the height of the hill is
insignificant compared to the large size of the hill foundation, the total length of the level
parts of the haul road is assumed to be constant for 20 years and equal to the length of the
radius i.e. 1650 m. Therefore in year 1, length of haul road on side hill is approximated as the
sum of length of ramps and length of levels interconnecting ramps i.e. 402 + 1650 = 2052 m.
Assume the hill is depleted at a uniform annual rate i.e. for mountain mining, annual
height 40 40
shortening = = = 4.44m; for open pit mining, annual shortening = = 4m.
years 9 10
Besides, assume the ramp length is proportional to the hill height:
height ∈ year n
Haul road length∈ year n= ∗402+ 1650
40
Year 1 3 5 10 20
Mountain/Pit Mountain Mountain Mountain Pit Pit
Haul distance on Up ramp 0 402
hill/in pit Down ramp 402 313 223
Level 1650 1650 1650 1650 1650
Haul distance to plant 2500 2500 2500 2500 2500
Total 4552 4463 4373 4150 4552
Year 1 3 5 10 20
Mountain/Pit Mountain Mountain Mountain Pit Pit
Haul distance on Up ramp 0 402
hill/in pit Down ramp 402 313 223
Level 1650 1650 1650 1650 1650
Haul distance to Up ramp 301 301 301 301 301
dump Level 2400 2400 2400 2400 2400
Total 4753 4664 4574 4351 4753
In this project, waste dumps surround the pit area. For 20 years out of pit haulage profiles
remain relatively constant. The travelling distance to dump is calculated by adding up each
travel segment: the distance on the side hill—depending on hill height or the distance on the
21
pit side—depending on pit depth, the distance of flat hauls on natural surface of 1700m, the
slope of the waste dump of 301m, the dump top surface of 700m and the radius of 1650 m
accounting for level road distance on the mountain or in the pit.
The ore once out of pit is hauled 2500m along natural surface to a processing plant. The
travelling distance to the processing plant is calculated by adding up three travel segments:
the distance on the side hill—depending on hill height or the distance on the pit side—
depending on pit depth, a 2500m long haul along natural surface, and the radius of 1650 m
accounting for level road distance on the mountain or in the pit.
During the development of Mt Wombat, topsoil is stockpiled for the reclamation of the mined
area. The site must ensure convenient disposal and retrieval but must not interfere with
production or related auxiliary operations.
Pit design specifications are summarised in Table 3 for later reference once specific
equipment models are known.
120000000
100000000
80000000
20000000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
EQUIPMENT SELECTION
ELECTRIC SHOVELS VS. BACKHOE HYDRAULIC EXCAVATORS
TABLE 4COMPARISON OF OPEN PIT LOADING EQUIPMENT (INTRODUCTORY MINING ENGINEERING, P143)
Table 5 shows the relative advantages and disadvantages of common loading units. Both
electric shovels and hydraulic excavators serving in mining industry are track mounted thus
generate low ground pressure. Although the shovel has a much larger size compared to the
hydraulic excavator, the working life is shorter as it is less sensitive to poor maintenance.
Due to distinct electric configuration of the electric shovel, specialized technicians are
required. Consequently operations deploying shovels require high capital costs and low
operating costs (dependent on costs for electricity). The small size of the hydraulic excavator
certainly brings advantages such as better mobility, ability to mine selectively and short cycle
time. The front–end loader is usually proposed as a buck-up loading unit when the primary
one experiences unexpected downtime.
In the case of loading using an electric shovel, a typical operating cycle consists of a digging
cut, a loaded swing to the truck, and empty return swing to the digging face. The larger the
swing angle, the longer the cycle time. A similar operating cycle exists for backhoe excavator
including a cutting pass through the bank, a loaded swing to the truck, and empty swing back
to the digging face. Since the backhoe sits on top of the mineral and loads the truck which sits
on the bench below it at the bottom of the mineral, the swing angle can be reduced. If the
haul truck loading point can be located in the front and slightly to either side of the backhoe,
cycle time may be significantly reduced (Martin et al. 1982, P655). Typical loading modes
with an electric shovel and a backhoe excavator are shown in Figure 2.
Figure 3Typical loading modes of an electric shovel (left) and a backhoe excavator (Right)
21
As Table 8 Cycle times under different digging conditions and bucket sizes for a shovel
(Introductory mining Engineering, P259).Shows in page17 E is Easy digging, loose, free-
running material; For example, sand, small gravel. M means Medium digging, partially
consolidated materials; e.g. clayey gravel, packed earth. M-H is Medium-hard digging; e.g.
well blasted limestone, weaker ores, gravel with large boulders. H means hard digging; e.g.
granite, strong limestone, strong ores.
HAUL TRUCKS
Mining trucks can fall into classes depending on the payload capacity. Ultra large class
usually refers to a capacity close to 300 t or beyond. With higher payload, capital costs
increase and certain models need specialized maintenance. Haul trucks in a fleet are usually
of the same models to give the same haulage cycle time.
Australian Mines Atlas suggests haul trucks can carry over 300 tonnes in Pilbara region.
According to that, the largest truck available—CAT 797F and the shovel with largest payload
—CAT 7495 are selected for Option 1. To fully compare the two options, in Option 2 a
medium sized backhoe is chosen – PC 4000 with a bucket capacity of 22 m^3, and CAT
793D with a nominal payload of 218 t.
FLEET SELECTION
According to mine management requirement, two fleet options are considered i.e. one
matching trucks with electric shovels and the other matching trucks with hydraulic backhoe
excavators. The method to find the matches is by trial and error based on the assumption that
it should take three to five passes to load a haul truck. However, with different excavators and
shovels, the range can be from three to seven (Kennedy 1990). Where hydraulic backhoes are
used, the number of passes is generally somewhat higher (Introductory mining engineering,
P262). Additionally, assume that the boundary between waste rock and iron ore is well
21
defined such that drilling and blasting of each is done separately. The dilution is negligible.
After drilling and blasting, loading and hauling of waste and iron ore are done separately.
Assume deswelling is 90% for waste rock and iron ore after being loaded into haul trucks.
If the shovel is fully loaded with blasted ore, the minimum weight exceeds its payload i.e.
110.54t>100t. Hence shovels with a similar payload but less dipper capacity are the next trial.
Shovel CAT 7495 HD is tried using Equation 1 and evaluation presented in Table
7Evaluation of Shovels—CAT 7495 HD
2.7 2.5.17
Hence blasted waste density = = 2.288 t/m^3; blasted ore density = = 4.25
1+ 0.18 1+0.2
t/m^3;
Material weight per bucket=bucket dipper capacity∗blasted material density∗bucket fill factor
E QUATION 1
Min Blasted waste weight per bucket=30.6∗2.288∗0.85 = 59.5 t/bucket
Material Factor
Rock-soil mixtures 1.10
Easy digging material (sand, small gravel) 1.00
Medium digging material (coal, light clay, wet soil, soft ores) 0.90
Medium-hard digging material (iron ore, phosphate, copper ore, hard 0.85
limestone)
Hard digging material (blocky iron ore, sandstone, basalt, heavy clay) 0.80
Table 8 suggests within certain dipper capacity ranges, the weights per bucket are under
payload i.e., 69.00t<81.8t. Hence Shovel CAT 7495 HD with a dipper capacity of 19.1 m3 is
selected for Option 1.
The cycle time of Shovel CAT 7495 HD is determined from Table 7Evaluation of
Shovels—CAT 7495 HD, i.e. 37s.
TABLE 8 CYCLE TIMES UNDER DIFFERENT DIGGING CONDITIONS AND BUCKET SIZES FOR A SHOVEL
(INTRODUCTORY MINING ENGINEERING, P259).
9 24 29 32 37
11.5 26 30 33 38
15 27 32 35 40
19 29 34 37 42
35 30 36 40 45
As the table above shows E stands for easy digging, loose, free-running material; for
example, sand, small gravel. M stands for medium digging, partially consolidated materials;
for example, clayey gravel, packed earth. M-H means Medium-hard digging; for example,
well blasted limestone, weaker ores, gravel with large boulders. H represents hard digging for
example, granite, strong limestone, strong ores.
Next, test whether Truck CAT 797F matches with Shovel CAT 7495HD (a dipper capacity of
19.1 m^3) by using Equation 2. Table 9Num. of Passes when matching Shovel CAT 7495HD
with Truck CAT 797F displays the results.
E QUATION 2.
363
Num . of passes for waste ¿ load a haul truck= =9.78=9.
37.1
363
Num . of passes for ore ¿load a haul truck= =5.26=5.
69
TABLE 9NUM. OF PASSES WHEN MATCHING SHOVEL CAT 7495HD WITH TRUCK CAT 797F
Num. of passes for waste is nowhere near expectation. Hence CAT 797F is not suitable. The
calculation suggests Num. of passes for waste is twice Num. of passes for ore. So ideally,
21
Num. of passes for ore is 3, so that No. of passes for waste would be 6 or 7 which is still
acceptable.
Based on the ideal truck capacity, Truck CAT 793F is tried. Table 11 shows Num. of passes
required using Equation 2.
TABLE 10NO OF PASSES WHEN MATCHING SHOVEL CAT 7495HD WITH TRUCK CAT 793F
TABLE 11 BASED ON TABLE 3 AND THE SELECTED EQUIPMENT, DESIGNING PARAMETERS OF PIT ARE
SUMMARISED
Width 4m
For Option 1—electric shovels and trucks, Shovel CAT 7495HD and Truck CAT 793F are
selected to load and haul waste rock. Truck parameters used in spread-sheet are presented in
(struck) over ore volume are tabulated Table 13Ratios of capacity (struck) over
ore volume based on different models and the model with the smallest ratio is
chosen.
TABLE 13RATIOS OF CAPACITY (STRUCK) OVER ORE VOLUME BASED ON DIFFERENT MODELS
The smaller the ratio is, the more the iron ore occupies the truck body. Hence HD1500-7
from Komatsu is chosen. Based on the model chosen 54% (29.22/54) of the dump body is
occupied. To further increase this percentage, consultancy with dealers is required. A tailored
truck body with smaller size (less self-weight) can bear more weight. A rugged and durable
dump body with high tensile strength high hardness is desirable considering special attributes
of iron ore.
TABLE 14NUM. OF PASSES FOR ORE WHEN MATCHING SHOVEL CAT 7495HD WITH TRUCK HD1500-7
Truck HD1500-7
Parameters
Capacity (t) 144.1
Num. of passes for ore 2
Ore volume (m3/truck) 29.223
Truck HD1500-7
Gross Power – SAE J1995 (kW) 1109
Empty weight (t) 105.3
Max gross vehicle weight (t) 249.5
Loading height –empty (m) 4.965
Overall tire width (m) 5.985
Last check: Shovel CAT 7495HD dumping height at maximum electric crowd limit 8.45m>
Truck HD1500-7 loading height-empty 4.965m, therefore, they match each other.
The selection process for Option 1 suggests no available truck models on market from
Caterpillar or Komatsu can efficiently haul iron ore. A consultancy with suppliers is
necessary to obtain models with a small truck body and larger payload capacity. The
selection process for Option2 is basically a repetition of the above in appendix 1.
FLEET SIZE
In our project, four cases are considered, each option with iron ore and waste rock. Assume
that in all cases, queue and spotting time is 2.0min, spotting time at shovel is 0.2min,
dumping time is 1.0min, carry back is 3%, nominal capacity is 100%, moisture is 4%,
productive hours/year is 6570hr, effective minutes/hour is 50min, 3 shifts/day, 8hr/shift.
Truck specifications used in spread-sheet are found in manufacturers’ brochures thus not
elaborated here. Loading time varies as Num. of passes differs in four cases (Refer to Table
22). The number of haul units required to keep the loading unit busy is given in following
along with the formulas.
Cycle time of a haul unit=t 1+t 2+ t 3+t 4+t 5+ t 6+t 7+t 8+ t 9+t 10+ t 11+t 12
LCT
Fleet size N is determined as:N =
STL+¿
50 50
44
40 41 41
36 36 35 35 35 35 35 36 36
33 34 34 34 34 34 34 34
30 29
28
26 26 26
25 26
25 26
25
23 23 23 22
23 23
20 20 20 20
10
7 7
6 6 6 6 6 6 6 6 6 6 6
5 5 5 5 5 5 5 5 5 5 5
4 4 4 4 4 4 4 4 4 4 4
3 3 3 3 3 3
Assuming 100% truck availability, fleet productivity in tonnes per year is calculated as:
truck productivity∈tonnes per year∗fleet Num .∈that year
Fleet productivities at 100% truck availability at year 1, 3, 5, 10, 20 are attached in Appendix
H.
Assume the electric shovel has a service life of 20 years; the hydraulic back-hoe has a life of
10 years. Literatures indicate major components of the mining trucks can be serviced or
replaced except for the frame. Experience tells a mining truck can have a service life of 10
years. Support and auxiliary equipment and functions are mainly sourced from Surface
mining P401 and other literatures.
A dozer is required to perform clean-up around the shovel as well as for proper dump
construction.
A water truck is necessary to sprinkle haulage roads to control dust especially in arid areas
such as Pilbara.
One large rubber tired front-end loader or two of lesser bucket size is proposed when the
loading unit in either option experiences prolonged downtime
A rubber tired bulldozer can move rapidly from one site to other performing duties such as
cleaning up loading area, crowding the muck pile to facilitate bucket loading and keeping a
smooth haulage road in the close proximity of the shovel when there are no excessive lumps
of very large coarse rock.
The dozing power of a track mounted bulldozer exceeds that of the rubber tired one but has a
low mobility. This type is able to cut for new benches and haul roads.
Other ancillary equipment include smaller dump trucks for miscellaneous use, mobile field
fuel/lube truck, mechanical field service truck, off-road tire service truck etc.
21
As far as two mining system is concerned, electrical reticulation related equipment are used
exclusively to Option1.
COST ESTIMATION
In order to provide a comprehensive evaluation for both option 1 and 2, another vital factor
should be taken into account in the process of the estimation is the cost. This feasibility study
will cover the capital costs, the operating costs for option 1 and 2 and the total production
cost. The estimation is made based on various assumptions.
The fuel price for diesel fuel is around168 c/liter in September 2013 based on the Terminal
Gate Prices for diesel fuel at Mt Wombat. In addition, the electricity would supplied by the
near-by power station called Kingston Power Station with a price of 24$/MWH .
ASSUMPTIONS
The life of the equipment and ancillaries could only be predicted and assumed.
Some assumptions made are listed as follow,
Assumptions:
The hauling distance from the pit to dump which includes the level, the up and down
ramp would be as same as the calculation, and the traveling speed of the truck follows
ideally with the calculation.
Life for a truck is 10 years, life for a truck tire is 7000 hours, for an electric shovel is
20 years, for a hydraulic back-hoe is 8 years.
Assume there are enough stuffs and they are 100% available.
Assume the tax and royalty cost is negligible. Fixed cost, which including
Depreciation, interest, on investment taxes, and storage, and insurance are negligible.
21
Inflation rate: 3%
OPERATING COST
The fuel cost, the maintenance cost, the lubricant cost, the labor cost as well as tire replacement cost
are the main considerations to the total operating cost estimation. The major two factors that bring
significant influence to the total operating cost are the total fuel and lubrication cost as well as the
capital cost. This is due to different number of equipment have been used during the 20 years and the
price of the equipment various from each other especially the price of the electric shove 7495HD cost
greater amount of money than other equipment. The fuel consumption and lubrication consumption is
high in option 2.
FUEL
Diesel fuel cost could be one of the most significant factors that will contribute abundantly to the total
operating cost. The equation for fuel burn calculation could use are as follow,
Or, Fuel burn ( l )=fuel burn per productive hour ( hrl )∗total operating hour ( hr ) ,
Or, Fuel Cost ($ /h)=engine (kW )× 0.3(L/h per kW )× FJF ×unit cost ($ / L),
Where: FJF equals to 0.5 in this case.
The fuel burn rate depends on the truck engine power and engine loading as above shows. For a truck,
which travels up ramp and down ramp, the changes of traveling distance will significantly impacts the fuel
burn rate in unit of liter per hour (l/h) as the engine loading is constant according to the equation. In
addition, up ramp speed need to be find and calculated with the consideration of the ramp grade (0 for
level, 10% for up ramp, -10% for down ramp) and rolling resistance (2.5%) to find the engine loading as
equation of engine loading and up ramp truck speed shows.
Up Ramp Truck Speed × Total Truck Weight × 9.81∗( RampGrade+ Rolling Resistance)
Engine Loading= 0.5
3.6 ×GrossEnginePower ×TransmissionEfficientcy × ( 1+ RampGrade × RampGrade )
3.6 ×GrossEnginePower × 80 % × ( 1+ RampGrade × Rampgrade )0.5
Up Ramp Truck Speed=
Total ruckWeight × 9.81×(RampGrade × Rolling Resistance)
While the cycle time changes with the change of travel distance and travel speed.
With the process of production going on, the hauling distance up and down ramp distance of the pit would
change annually, shows how the ramp distance changed over the 20 years. However, the speed of the truck
would not always be as the same as the calculated speed. In reality, the trucks might travel to a different
dump side to dump when the original road has been blocked by a stop sign for construction purpose or
maintenance purpose, etc. The truck may have to speed down when there is a coming vehicle or there
might be some obstacles in front of the way along the travel that needs the truck to slow down to pass or
due to the wet surface.
21
In terms of the total fuel consumption cost per year, option2 spends significantly greater amount of money
on fuel than option 1, which can be seen from following table. As the fuel cost per unit (168 cent/l) has
been assumed constant over the 20 year, the total liter of fuel consumption in option 2 is greater than fuel
consumption in option 1. There is about 223 M$ difference between option 2 and option 1.
Not only consuming diesel fuel is not environmental-friendly, the Australian government limits the carbon
emission from an industry and the exceeded carbon emission from the industry is obligated to pay the
government carbon tax. However, the carbon tax cost is negligible compare with the fuel consumption
cost.
TABLE 17 FUEL CONSUMPTION COST
in 20 years was due to the hauling distance is changing annually, which in addition will
change the annual cycle time and total fuel consumption. As the cycle time changed, the
number of truck would also be changed. The changes of total fuel consumption would mainly
contributed by the variation of the up and down ramp distance and the truck number.
It is obvious that in term of the total operating cost, option 1 which applying the electric
shovel and truck hauling system is much more favorable.
120,000,000
100,000,000
80,000,000
60,000,000 Option 1
Option 2
40,000,000
20,000,000
0
0 5 10 15 20 25
FIGURE 7 TOTAL OPERATING COST IN 20 YEARS
CAPITAL COST
While different equipment have been chosen for option1 and 2, the number of trucks used would be
significantly different from each other with the associated capital cost. Different excavators with its
associated different ancillaries would be another factor that needs to be taken into account. Electric
shovel is expensive, Table 19 Capital cost for option 1 shows that total capital cost of option 1 is
about 90 M$ greater than the total capital cost of option 2
TABLE 19 CAPITAL COST FOR OPTION 1
COST SUMMARY
The total production cost consists of the capital cost and operating cost. Beside the capital cost and
operating cost for these two hauling systems, there are other capital cost and operating cost to run the
whole mine. The summary costs are listed in table Table 21 Cost summary for option 1 and Table 22 Cost
summary for option 2.
21
Option 1 Option2
Total production Cost
($/t) 1.60 1.70
Operating cost ($/t) 0.57 0.70
In conclusion, even though option 1 cost more in maintenance cost and capital cost, option 2 requires a great
higher cost on fuel consumption and lubrication consumption.
Above all, after considering both the operating cost and capital cost for both option 1 and 2, option 1 is much
more favourable and economy than option 2 with respect to the cost estimation in the 20 years.
If factors identified above are not occurred during operating time, haulage system on the
basis of ultra-large electric shovels and suitable truck will reach the optimum production.
Firstly, optimized temperature control is the best approach to avoid shovels dysfunction.
Secondly, drive programming and analysis software would help to operators to work more
efficiently. Further, control logic software assist engineers to design proper station for the
shovels. Finally, input/output device monitoring and fault detection are the main resources to
prevent shovels from presenting potential dangers. There are still several technical factors
excepted the elements mentioned before affect the shovels operating, including automatic
boom soft sit-down and boom profile protection envelope, anti-swing-in-bank system and
automatic lubrication and compressed air systems control. However, all these factors are not
the major influences compared with others.
HYDRAULIC PUMP
At present, there are three main types of hydraulic pumps used extensively, which are gear
pumps, axial piston pumps, and vane pumps. These three hydraulic pumps are positive
displacement pumps and each has its own advantages and disadvantages. Hydraulic pump is a
main mechanical device with its function that converts energy from the prime mover (electric
motor or engine) to fluid power energy. The energy for pumps is rated by pressure and flow
and units for hydraulic pressure is in psi and bar. Furthermore, flow is measured in gpm
21
(gallons per minute) or 1/m (litres per minute) and is a result of volumetric displacement x
rpm. If the gear pumps are brand new, most of them have an actual efficiency of 85% to 90%
and would decrease after use. Moreover, the efficiencies for never used piston and vane pump
are almost 90% to 95% and will lose efficiency as the pump wears as well. The pump
lifetimes under industrial standards are approximately between 8000 to 1000 hours of
operation. All pumps work by mechanically squeezing the fluid between mating surfaces.
The function for gear pumps is to mesh of the gears pushing against the pump housing wall,
but in piston pumps it is the piston pushing in the piston silo against a valve plate, besides, in
vane pumps it is the vanes pushing against the pump housing wall. According to all studies
resulting from pump maintain, the pumps are dependent on maintaining lubricate between
mating surfaces to prevent material on material wear. Furthermore, all these three different
types of pumps are sensitive to fluid contamination, some more than others. Moreover, gear
pump is the least sensitive pump compared with the other two while piston and vane pumps
are the most sensitive. All pumps are also sensitive to fluid cavitation or air bubbles that form
in the fluid. These bubbles when compressed will explode creating pitting and pockets in the
pump material.
OIL FILTER
Well- functioning hydraulic system has its own important characteristic. Water glycol fluids
are compatible with most filter types. The main issue should be concern is the compatibility
of water glycol with paper media spin-on filters. The paper media reacts with the water in
water glycol causing the paper to dissolve. This property defeats the purpose of the filter and
actually adds contaminants into the system. Substitution of the paper media spin-on with a
fiberglass media spin-on is an easy fix for the problem. Water glycols are compatible with
other media types such as polypropylene. Filter ratings do not change when using water
glycol and remain the same μm rating as with the manufacturer’s recommendation for use
with mineral oils.
RELIEF VALVE
There is another major characteristic that can be added to help control hear and to conserve
energy, if the system did not come with one, is the install a bypass valve which can be also
called dump valve. The function of relief valve is to return hydraulic fluid back to the oil
reservoir when the system is unloaded without going over the pressure relief valve.
Furthermore, if the fluid can be allowed to return to the tank over the pressure relief it is
under full system pressure and will generate high heat as it travels over the valve. Although
this is easy to fix, it can add savings, reduce the water glycol fluid maintenance and
21
ultimately extend the life of the hydraulic system components. Moreover, there are three
functions of relief valve. Firstly, the relief valve if a safety device which is used to protect the
breaker when the pressure rises in the hydraulic circuit. Secondly, the operating pressure if
the breaker determines the setting of the relief valve in the pressure line. Thirdly, the relief
valve setting should be adjusted to the specifications of each Vulcan model.
HIGH PRESSURE LINES
The high pressure lines can be found in the hydraulic pressure system of aircraft fuel, shaft
hydraulic pressure stand, oil field exploiting, engineering machinery equipment. The main
requirement for the high pressure line is to transmit of engine oil, red oil etc. of high
temperature and pressure. Furthermore, the working conditions for high pressure pipes are
pretty high, because high pressure lines have to ensure long lasting, high impulse life and
wire braid reinforced pipe provides constant pressure, flexibility and amazing bend radius.
Moreover, the pressure lines have also need the reinforcement from the high tensile steel and
durability, resistant to abrasion, oil and temperature variations. According to the consumers
need, the high pressure hoses come in a variety of lengths to ensure the freedom of movement
and manoeuvrability. A lighter hose makes the whole unit easier to guide with regard to a
target area in need of the cleaning application. The High pressure hose also finds great use in
cleaning purposes and mobile spraying units. The premium nitrile tube of the hose minimizes
permeation and will not contaminate product going through the hose. Furthermore, the
premium nitrile tube is also suitable for defueling service at low pressures. The high pressure
lines has also make sure under a safety working environment, durability, and resistance to
extreme conditions of temperature and pressure.
In terms of ultra-large electric shovel with suitable trucks, power consuming is the main
pollutant resource. Firstly, electric shovels produce heavy dust during mining process. The
dust from the mine site suspended in the air and breathed by workers and local residents.
21
Furthermore, the dust causes heavy net loss to the local agriculture. Moreover, trucks
consumed tones of fossil fuel daily, the emission is also another pollutant.
Compared with ultra-large electric shovels, back-hoe hydraulic excavators have a lighter
impact on the local environment. Since the power used to excavators running is oil, which
generates little emission. Besides, hydraulic excavators work more efficiently that means
fewer power consumed in production. According to this reason, hydraulic excavators is more
eco-friendly than electric shovels system.
ECONOMIC RISKS:
For both of the systems economic risks will lead to the discrepancy of investment and
potential influence financially feasible. A key reason would be a growth of the capital
expenditure and operative budgets. To minimalize this threat and avoid the profit reduction, a
carefully and reasonable strategic should be done before the project begin, it is vital that the
21
company need keep the total operating expense below 20% of the total revenue to prevent
risk.
Another main factor would be the fluctuating of ore price. The decrease of ore price will lead
to the final revenue decrease. To minimize this risk, the company should set up a system to
research market and contracts to confirm a confident amount of ore can be sold in certain
time period.
Other uncertainties factor which effect on mining industries is the equipment and energy
prices rise by mining industry development, since mining is greatly equipment and energy
dependent, this risk also can influence on the mine profits. This risk can control by selecting
well-organized equipment group to decreases the consuming of equipment working and
maintenance. However, this risk can reduce by a reasonable mining method selecting and
mining design.
21
RECOMMENDATIONS
Based on the results of the evaluation it is recommended that further actions need to be
undertaken to maximise the production and lowest the cost.
Plan and schedule the position of the shovel in advance and cleans up the obsolescence
before conducting the operations.
Haul road grade should be kept as low as possible to let the electrical shovel travel
safely.
CONCLUSION :
In conclusion, based on some critical assumption, a comprehensive evaluation of both options
has been made with consideration of the major aspects, such as OHS, social and
environmental, economic as well as the technical aspects, and recording to the result option 1
is the better option. Option 1 operating and hauling in comparatively environmental-friendly
form that also economical, longer life time and high in productivity make it is a favourable
choice for this iron ore mine. Due to the electrical shovel low in moveability and flexibility, it
is recommended that the electrical shovel need to place somewhere safe and need less
movement. Therefore, the bench height and bench width should be contrasted suitable for it
to conduct the operations, and the recommended bench height and width are 15m and 30m
respectively.
21
REFERENCE
Martin, J. W., T. J. Martin, T. P. Bennett, and K. M. Martin. 1982. Surface mining
equipment. Golden: Martin Consultants.
Kennedy, B.A., ed. 1990. Surface Mining. 2nd ed. Littleton: SME
Hustrulid, W., and M. Kuchta. 2006. Open pit mine planning &design. 2nd ed. London:
Taylor and Francis.
Darling, P., ed. 2011 SME Mining Engineering Handbook. 3rd ed. Littleton: SME.
Hartman, H. L., and J. M. Mutmansky. 2002. Introductory mining engineering. 2nd ed.
Hoboken: John Wiley & Sons.
21
APPENDICES
APPENDIX 1:
SELECTION OF OPTION 2 FOR WASTE
According to Table 5, hydraulic shovel (hydraulic excavator) has a higher bucket fill factor.
Assume bucket fill factor is 0.9 for the backhoe used in this project.
Hydraulic backhoe excavator Komatsu PC4000 and Truck CAT 793D are tried in this case.
Table 16 indicates weights per bucket for ore and waste. Lifting capacity is estimated using
bucket volume times 2.2t/m3, which gives 48.4t. Ore weight per bucket exceeds the lifting
capacity. Discussion is presented in the next section.
Table 9 indicates Num. of passes needed for waste rock to load a truck. Num. of passes for
waste is 4 hence acceptable. Waste volume per truck is close to and under truck payload
hence this match is acceptable to handle waste.
TABLE 25 NO OF PASSES FOR WASTE WHEN MATCHING BACKHOE KOMATSU PC4000 WITH TRUCK CAT 793D.
Komatsu Backhoe PC4000 is matched with Cat 793D to load and haul waste rock. Truck
parameters used in spread-sheet are presented in Table 18. Unloaded weight is the sum of
21
chassis weight and average body weight. Max truck weight is the sum of unloaded weight
and actual loading.
Ore volume per truck is close to and under truck payload hence this match is acceptable to
handle ore.
21
Cycle time is the total time spent on loading a haul truck. A summary of cycle times is
presented in Table 22.
APPENDIX 2:
TABLE 31 OPTUION 1 COMPARE WITH OPTION 2
Truck Cycle Time and Fuel Year 1 Year 3 Year 5 Year 10 Year 20
Burn Calculations
Truck productivity (tonnes) per 647 662 678 723 542
Productive Hour
Truck Fuel Burn (kilolitres) per 130 128 126 121 161
Productive Hour
Truck productivity (tonnes) per 4,248,346 4,350,247 4,457,156 4,748,925 3,559,494
Year
Truck Cycle Time and Fuel Burn Year 1 Year 3 Year 5 Year 10 Year 20
Calculations
Truck productivity (tonnes) per 477 493 509 555 444
Productive Hour
Truck Fuel Burn (kilolitres) per 96 96 95 94 108
Productive Hour
Truck productivity (tonnes) per Year 3,136,271 3,236,922 3,344,248 3,646,514 2,917,748
Sum of Loading and Spotting Time 1.43 1.43 1.43 1.43 1.43
No of Trucks Ore 10 10 10 9 11
Fleet Productivity (tonnes) per Year 31,362,710 32,369,222 33,442,479 32,818,626 32,095,231
Target Production (tonnes) per Year 20000000 20000000 30000000 30000000 30000000
No of sets 1 1 1 1 1
Total number of trucks Ore 10 10 10 9 11
Truck Cycle Time and Fuel Burn Year 1 Year 3 Year 5 Year 10 Year 20
Calculations
Truck productivity (tonnes) per 603 620 638 688 498
Productive Hour
Truck Fuel Burn (kilolitres) per 135 133 131 127 162
Productive Hour
Truck productivity (tonnes) per 3,964,427 4,075,335 4,192,627 4,517,685 3,274,538
Year
Sum of Loading and Spotting Time 1.87 1.87 1.87 1.87 1.87
No of Trucks 8 8 8 7 10
Fleet Productivity (tonnes) per Year 31,715,414 32,602,678 33,541,014 31,623,794 32,745,37
9
Target Production (tonnes) per Year 40000000 40000000 60000000 90000000 90000000
No of sets 2 2 2 3 3
Total number of trucks Waste 16 16 16 21 30
Truck Cycle Time and Fuel Year 1 Year 3 Year 5 Year 10 Year 20
Burn Calculations
Truck productivity (tonnes) per 665 683 702 756 622
Productive Hour
Truck Fuel Burn (kilolitres) per 137 136 134 130 154
Productive Hour
Truck productivity (tonnes) per 4,366,544 4,486,980 4,614,247 4,966,412 4,084,706
Year
Years 1 3 5 10 20
21
Year 1 3 5 10 20
Mountain/Pit Mountain Mountain Mountain Pit Pit
Haul distance on Up ramp 0 402
hill/in pit Down ramp 402 313 223
Level 1650 1650 1650 1650 1650
Haul distance to plant 2500 2500 2500 2500 2500
Total 4552 4463 4373 4150 4552
Year 1 3 5 10 20
Mountain/Pit Mountain Mountain Mountain Pit Pit
Haul distance on Up ramp 0 402
hill/in pit Down ramp 402 313 223
Level 1650 1650 1650 1650 1650
Haul distance to dump Up ramp 301 301 301 301 301
Level 2400 2400 2400 2400 2400
Total 4753 4664 4574 4351 4753
Years 1 3 5 10 20
Ore (Tonnes) 20000000 20000000 30000000 30000000 30000000
Waste (Tonnes) 40000000 40000000 60000000 90000000 90000000
Total tonnage 60000000 60000000 90000000 120000000 120000000
Years 1 3 5 10 20
Year 2014 2016 2018 2023 2033
Days 365 366 365 365 365
UOA 80.00% 80.00% 80.00% 80.00% 80.00%
Hours/Day 19 19 19 19 19
Hours/Year 7008 7027 7008 7008 7008
Years 1 3 5 10 20
Ore (Tonnes/Day) 54795 54645 82192 82192 82192
Waste (Tonnes/Day) 109589 109290 164384 246575 246575
Total tonnage/Day 164384 163934 246575 328767 328767
Ore (Tonnes/Hour) 2854 2846 4281 4281 4281
Waste (Tonnes/Hour) 5708 5692 8562 12842 12842
Total tonnage/Hour 8562 8538 12842 17123 17123
Years 1 3 5 10 20
Ore sweel (Volume) 784314 784314 1176471 1176471 1176471
Waste sweel (Volume) 2666667 2666667 4000000 6000000 6000000
Total sweel Volume 3450980 3450980 5176471 7176471 7176471
21
Years 1 3 5 10 20
Ore Volume 4705882 4705882 7058824 7058824 7058824
Waste Volume 17481481 17481481 26222222 39333333 39333333
Total Volume 63450980 63450980 95176471 127176471 127176471
Years 1 3 5 10 20
Year 2014 2016 2018 2023 2033
Days 365 366 365 365 365
UOA 80.00% 80.00% 80.00% 80.00% 80.00%
Hours/Day 19 19 19 19 19
Hours/Year 7008 7027 7008 7008 7008
Years 1 3 5 10 20
Year 2014 2016 2018 2023 2033
Ore Volume / Day 12893 12858 19339 19339 19339
Waste Volume / Day 47894 47764 71842 107763 107763
Total Volume / Day 173838 173363 260757 348429 348429
Ore Volume / Hour 672 670 1007 1007 1007
Waste Volume / Hour 2495 2488 3742 5613 5613
Total Volume / Hour 9054 9029 13581 18147 18147
APPENDIX 3:
TABLE 41 COST COMPARATION OF DIFFERENT EQUIPMENT
TABLE 43THE RISK ASSIGNMENT OF ULTRA-LARGE ELECTRIC SHOVELS WITH SUITABLE TRUCKS
21
TABLE 2 THE RISK ASSIGNMENT OF THE BACK-HOE HYDRAULIC EXCAVATORS WITH TRUCKS OF 200 TONNES
NOMINAL PAYLOAD:
tool