Good IPST01Paper084

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Long-Term Stability of a Combined Cycle Plant

and Two Interconnected Oil Platforms


S. Henschel V. Rygg T. Lauvdal
Siemens AG, EV SE NC Siemens AS, Oil & Gas Norsk Hydro Production AS
Paul-Gossen-Str. 100 stre Aker vei 90 Postboks 7190
90515 Erlangen, Germany 0518 Oslo, Norway 5020 Bergen, Norway

Abstract { This paper presents an analysis of Even with all three generators in service, the foreseen
the electrical stability of two North Sea oil load demand on Snorre TLP is likely to exceed the avail-
platforms, Snorre TLP and Snorre B, which able power reserve in the years to come. In order to pro-
are to be interconnected by a subsea cable of vide the lacking power for this platform, a 10.5 km sub-
10.5 km length. While the older platform TLP is sea cable connection to Snorre B is presently planned.
equipped with a standard con guration of three The presented long-term dynamics study was ini-
gas turbines (one standby), the new platform B tiated lest a particular loading scenario or electrical
houses a combined cycle plant consisting of two contingency could lead to such a signi cant drop of
gas turbines and an intermediate pressure steam thermal energy and steam pressure that would necessi-
turbine. The modelling of the combined cycle tate a shut-down of the CCP. A complete black-out of
plant and its control and protection strategies the Snorre B platform would be the worst-case conse-
are presented. Simulation results show the im- quence.
pact of the controls on the rotary stability and For this analysis and other investigated aspects, a
long-term dynamics of the platform systems. very detailed model of both platforms and the subsea
Keywords: Industrial application, combined cycle connection has been built. While it would be beyond
generation, long-term stability, active power and fre- the scope of this paper to present all the modelling de-
quency control, power system modelling. tails for this analysis, the main aspects concerning the
modelling for long-term simulation are described in Sec-
tions II{IV. These sections include a simpli ed repre-
I. INTRODUCTION sentation of the CCP, and a description of the control
and protection philosophies. Note that the modelling
Combined cycle plants (CCP) appear to combine detail is not suited for electromagnetic transients simu-
many advantages for practical platform operation, both lation or harmonics analysis. The simulation results of
with respect to economical considerations such as power a worst-case contingency are presented and discussed
capacity versus generator weight and size, and with re- in Section V. Section VI concludes the paper.
gards to compliance with increasingly tougher environ-
mental regulations. This gives reason to believe that II. COMBINED CYCLE PLANT
CCP's will become the preferred type of platform gen-
eration in the next few decades. Parallel to this de- The combined cycle plant consists of two gas turbines
velopment, there has been a recent trend toward in- (GTA, GTB) and one steam turbine (ST). The data of
stalling subsea interconnections between various plat- the respective generators is given in Table I. A model of
forms. This allows power sharing among platforms to the gas turbines is presented in Fig. 2. Besides the gas
improve the loading of the gas turbines, whose eciency turbine, details of the speed governor and temperature
is much reduced when operating at low load levels. control are shown. The elements re ecting the behav-
In this light, Siemens and Norsk Hydro have con- ior of the fuel gas temperature and of the exhaust ow
ducted an extensive analysis of the feasibility and sta- have been represented in great detail as they determine
bility of the interconnected platforms, Snorre TLP (i.e. the interaction with the steam turbine during combined
Tension Leg Platform) and Snorre B o the Norwegian cycle operation. Owing to the complexity of the model,
shore. some characteristic relationships have been condensed
A schematic diagram of the platforms is shown in in the blocks F1, F2, and F3. These functions are de-
Fig. 1. The Snorre B platform houses the CCP which scribed below.
consists of two gas turbines and one steam turbine. While an accurate model of the combined cycle plant
Snorre TLP is equipped with a standard con guration would require intense application of thermodynamics
of three gas turbine generators, one of which is standby. and combustion theory [1],[2], these processes can gen-
The overall power demand on Snorre TLP is approx. erally be simpli ed to a degree suitable for the purpose
62.5 MVA, whereas 56 MVA are needed on Snorre B. of system dynamics analysis [3],[4].
SNORRE TLP SNORRE B

GTA ST GTB
GTA GTB GTC
40 MVA 21.61 MVA 40 MVA
25 MVA 25 MVA 25 MVA
Cable 10.5 km, 36 kV 0.8 p.f. 0.8 p.f. 0.8 p.f.
0.8 p.f. 0.8 p.f. 0.8 p.f.

G G G G G G

BUS A BUS B, 11 kV BUS A, 11 kV BUS B, 11 kV

M 7 MVAr M M
M
6.8 MVA 6.8 MVA 21.1 MVA 7.7 MVA
21.4 MVA 0.89 p.f.27.4 MVA 0.89 p.f. 10.6 MVA 16.9 MVA
0.91 p.f. 0.88 p.f.
0.89 p.f. 0.89 p.f. 0.88 p.f. 0.87 p.f.

Fig. 1. Interconnected platforms Snorre TLP and B

W F Tmech
F2
LV 1.0
Gate 1+s0.1
nREF n0, DROOP
F1
!
Dw
= 1.0 pu

1.0 1.0 Thermocouple Radiation shield


_
!
Dw +
25.0 1+s3.3
_
1.0 +
0.2
Tx
nROTOR _
+ 1+s0.4 s250 1+s2.5 1+s15
+ +
0.1 droop mode 0.1

0.8
isochronous
0.9
mode
_
1+s2.5
s0.104 1.0
0.0 +
+
1+s4.0 1.0 W IGV Qx
0.0
F3
_ s20.0 1+s3.0
n0, ISOCHR. 0.46
Inlet Guide Vanes

TRA Fuel overdrive


+ _
SPEED GOVERNOR 83.3 1.0
+ +

TEMPERATURE CONTROL

Fig. 2. Gas turbine model

1.0
1.0
!
Dw +
0.9
20.0 _ 1+s0.4

0.0

1.11 1.0
Funct.
Q in Q out
Q x1 1.0 1.0 1.0 + 1.0 P mech
0.5
1+s90 1+s90 1+s4.0 s92.0 YIP
-
0.0 0.0

Q x2

1.11

Relationship between the Characteristic time


Steam turbine and droop
gas turbine exhaust flow response of the boiler
mode speed governor
and steam mass flow section

Fig. 3. Boiler and steam turbine models


TABLE I is a small speed-dependent in uence to represent ro-
Snorre B: generator data tor friction in the bearings. Normally this factor can
GTA ST be neglected, however, in long-term studies, it deter-
GTB mines the slowing rate of the rotor when turbine ring
MVA-rating MVA 40.0 21.61 is stopped.
rated voltage kV 11.0 11.0
power factor { 0.8 0.8
frequency Hz 60.0 60.0 C. Calculation of the Exhaust Flow
TM (starting time) s 4.0 6.0
Ta (aperiodic time) s 0.140 0.120 For the combined cycle operation, the mass ow of
X` pu 0.140 0.120 the exhaust gases determines the amount of thermal
Xd pu 1.690 1.880 energy that can be absorbed by the steam in the boiler
Xd (saturated)
0
pu 0.233 0.285 section. The following formula gives an approximation
Xd (saturated)
00
pu 0.149 0.162 for the exhaust gas mass ow, Wx :
Xq pu 1.580 1.790
Xq (saturated)
0
pu 0.306 0.850 288
0:257
Xq (saturated) pu 0.147 0.160 Wx = (1 + !)  WIGV  (4)
273 + TA
00

Td (short-circuit)
0
s 0.840 0.850
Td (short-circuit) s 0.022 0.024 With TA = 15C, the last factor becomes 1.0 and can
00

Tq (short-circuit)
0
s 0.188 0.188
Tq (short-circuit)
00
s 0.022 0.022 be dropped from the equation. The thermal power, Qx,
that can be used for combined cycle operation is propor-
A. Calculation of the Exhaust Temperature tional to the mass ow times the temperature di erence
between exhaust temperature, Tx = F1, and the tem-
The turbine exhaust temperature is usually a ected perature, Texit, with which the exhaust gas leaves the
by many in uences. The main in uences however can machine. In per units:
be characterized as the fuel gas mass ow, WF , rotor
speed variations, !, and the position of the inlet guide F3 = Qx = Wx TTx ;;TTexit (5)
vane, WIGV , which can vary between 0.46 pu and 1 pu. RA exit
This corresponds to a vane tilting angle between 57 and The exiting temperature of the exhaust gas was as-
84 degrees, respectively. All these in uences act on a sumed to be 98C.
constant temperature control reference point, TRA , for
constant ring temperature. Mathematically, this is
expressed as follows: D. Boiler Section and Steam Turbine
F1 = TRA ; 390(1 ; WF ) ; 306! +163(1 ; WIGV ) (1) A block diagram of the steam turbine model used in
this study is presented in Fig. 3. In the heat exchanger,
The temperature control reference value depends pri- the exhaust power of both gas turbines is related to
marily on the compressor discharge pressure, which has the generated thermal energy to produce steam power.
been assumed to be constant in this model. The con- This relationship in per unit is given by:
trol point then becomes a linear function of ambient
temperature TA : 1 (Q ; 0:1)
Qout = (6)
TRA = TR ; 0:6(TISO ; TA); (2) 0:92 in

where TR = 541C is the rated exhaust temperature. where Q is the addition of both gas turbines' exhaust
in

Note that (1) becomes inaccurate if the ambient tem- powers, Qx, and division by 2 in order to obtain per
perature di ers considerably from ISO conditions. For unit values.
simplicity, we have assumed ISO temperature, that is The steam chest and boiler section are represented by
TA = TISO = 15C.
a series of characteristic time delays which establish the
relationship between the heating power in (6) and the
steam mass ow [5]. The associated time constants are
B. Calculation of the Turbine Torque in the order of several minutes. Note that there is only
a medium pressure (18 bar) section in this application;
The mechanical torque that is exerted on the rotor the model could be easily expanded to represent a high
shaft by one of the gas turbines is described as pressure section and reheat duct, however.
The resulting steam mass ow is led directly into the
turbine where it is expanded to produce a mechanical
F2 = 01:9 (WF ; 0:1) ; 5  10;4! (3) torque on the rotor shaft. The steam is then led through
the condenser and pumped back to the economizer. The
A minimum fuel gas ow of WF;min = 0:1 pu is re- steam valve is controlled by a droop mode governor
quired to unlock the rotor shaft. Furthermore, there shown in Fig. 3.
TABLE II
Snorre B: 11 kV motor data
1 2 3 4 5 6 7
switchboard bus { A B B B B A B
mechanical power kW 5480 5480 1360 1360 5900 4300 1250
eciency  % 96.0 96.0 96.4 96.4 97.4 97.3 96.3
rated cos n { 0.87 0.87 0.86 0.86 0.86 0.89 0.86
rated slip sn % 1.19 1.19 0.474 0.474 0.367 0.562 0.449
breakdown torque Tp pu 1.98 1.98 2.41 2.41 2.00 2.00 2.58
starting torque Ta pu 0.48 0.48 0.69 0.69 0.45 0.52 0.86
starting current Ia pu 4.5 4.5 6.4 6.4 5.5 5.4 6.3
starting cos a { 0.26 0.26 0.32 0.32 0.21 0.23 0.33
shaft inertia J kgm2 185 185 35.8 35.8 495 465 15.2
normal loading P pu 0.91 0.91 1.0 1.0 0.93 0.93 0.80

III. PLATFORM LOADS inter-platform hunting can be avoided. While the dy-
namics involved with power transfer controls are usually
Fig. 1 shows the equivalent loads and high-voltage in- slow, i.e. order of several seconds, the response time of
duction motors, which comprise pipeline compressors, the APTL is in the range of a few hundred milliseconds
seawater lift pumps and water injection pumps. Be- to prevent hunting. This device therefore plays an in-
sides the feeders to the low-voltage drilling stations, tegral part not only in long-term analysis but also in
emergency switchboard and living quarter distribution transient stability investigations.
networks, there are 19 high-voltage motors connected The reactive power transfer between the platforms is
to the main switchboard on Snorre TLP, while there minimized through tap changer controls at the trans-
are 7 high-voltage motors on Snorre B. The data of the formers to the 36 kV subsea cable. To provide addi-
latter is shown in Table II. All high-voltage motors tional reactive power on Snorre TLP, a capacitor bank
and some of the low-voltage motors are represented is installed. This way, the voltage drop during start-
as detailed dynamic models, obtained from provided up of large induction motors can be contained to an
torque characteristics by parameter identi cation. Ow- acceptable level. Primary voltage control is left to the
ing to their fast dynamic response, AC motor drives excitation systems of the generators. They have been
and other low-voltage loads are modelled by passive el- modelled with standard IEEE Type 2 exciters.
ements (Thevenin equivalent circuit). With regards to the protection system, there is a
load-shedding system superimposed to regular induci-
IV. SYSTEM CONTROL & PROTECTION ton motor protection. This shedding system has been
devised for intentional fast-tripping of certain motor
loads in fault situations in order to prevent turbines
The general operating mode of the speed controls for and generators from overloading.
the gas turbines on Snorre B and TLP is isochronous In order to determine the number of loads to be
mode. While droop mode had been assumed in a shed, the system constantly calculates and compares
prior study, Fig. 4 reveals an important di erence for the amounts of available power generation and of con-
long-term analysis: In droop mode there would be a sumed power. A drop in available power generation,
post-fault frequency deviation from 60 Hz which would e.g. by tripping a generator due to an internal failure,
last inde nitely if it is not corrected by additional would then cause an equal amount of load to be shed.
secondary, i.e. slower acting, frequency controls. In
isochronous mode however, the frequency quickly re-
turns to 60 Hz, assuming that the respective gas turbine 5

has sucient power reserves to establish a balance be-


tween generated and consumed power at that frequency. 4

The steam turbine of the combined cycle system on Droop mode


Frequency deviation (percent)

Snorre B is not intended to ful ll primary control ac-


3

tions such as speed regulation. Its power generation is


therefore governed by a 4 % speed droop.
2

In order to avoid the hunting phenomenon [6] caused 1

by isochronously controlled gas turbines on the plat- Isochronous mode


forms, a load-sharing system is in place to establish 0

equal power supply from all gas turbine generators. In


addition, there is an automatic power transfer and load -1
0 1 2 3 4 5 6

(APTL) control system which acts on the gas turbines Time (s)

on Snorre B to establish a de ned power transfer of 22 Fig. 4. Comparison of droop mode and isochronous mode gov-
MW to Snorre TLP. With this de ned pwoer transfer, ernors for GTB on Snorre B
It is quite obvious that even in such relatively small This causes the gas turbine GTB to further reduce its
power system, there is a vast number of possible switch power output in order to maintain the power balance
con gurations so that calculating these amounts is not a at synchronous speed. These processes occur in the
trivial task. A simpli ed shedding system has therefore rst 5 seconds after the fault as shown in Fig. 5. Note
been modelled which only monitors the circuit-breaker that, at the moment of separation of the Buses A and
positions essential for the analysed cases. B, the load-sharing system for GTA and GTB becomes
ine ective.
V. SIMULATION RESULTS The situation is di erent for the generators on Snorre
TLP. Here, the fault and subsequent tripping of the ca-
The simulated case that is presented here assumes ble connection mean a loss of 22 MW of power from
a worst-case situation, in which a simultaneous three Snorre B. This leads to a temporary overloading of the
phase fault occurs at Bus A of Snorre B's 11 kV main two gas turbines GTA and GTC, as shown in Fig. 6.
switchboard. Because of the high short-circuit current, This is accompanied by a sudden deceleration of the
it can be expected that the Ip-limiter trips and sepa- rotors. Since the gas turbines were at their maximum
rates Buses A and B in, at the most, 5 ms. loading level prior to the fault, their temperature con-
The busbar protection isolates the fault in 115 ms trols take the lead over speed control (see Fig. 2).
by tripping the generator GTA, the cable connection
to Snorre TLP and all outgoing feeders. As a result of A continued deceleration of the rotors would be the
the changed system con guration, the protective load- consequence. This is prevented by the load-shedding
shedding system determines a power imbalance and 175 ms after the fault. This way an approximate power
executes its prede ned shedding sequence: the high- balance is established, and the rotor speed increases
voltage water injection pump no. 2 (see Table II) on again. Note that the gas turbines remain in temper-
Snorre B and 29 MVA of motor loads on Snorre TLP ature control mode for several seconds, while the fre-
are tripped 110 ms and 170 ms, respectively, after the quency stabilizes little above system frequency.
Is-limiter trip.
As can be seen, there is no danger of rotary insta-
bility, with fault durations of 115 ms. In fact, the in-
A. Transient Stability Analysis terconnected platform system is stable with respect to
rotor oscillations for much longer fault durations. What
Due to the fast separation of Buses A and B, the seems to be more problematic is that the sudden voltage
initial rotor dynamics of the generators, ST and GTB, drop during the fault leads to a general slow-down of the
are hardly a ected by the fault itself. The temporary induction motor loads. After fault clearing, these mo-
acceleration that can be noticed in Fig. 5 is primar- tors draw a large amount of reactive starting power to
ily due to the changed load situation at Bus B. The re-accelerate to their normal speeds. This causes quite
sudden unloading of these generators is aggravated by a signi cant sag of the post-fault voltage (not shown in
tripping water injection pump no. 2. In order to bring this paper). Fault durations longer than 185 ms cause
the speed back to normal, the isochronous governor of such low voltage levels during re-acceleration of the mo-
GTB minimizes the power output of that turbine. The tors that some large pumps cannot be brought back to
steam turbine also reduces its power generation yet, as normal operation and must be shut down.
the rotors speeds return to 3600 rpm, it resumes its
pre-fault operating point.

40 40
Active power (MW)

Active power (MW)

30 35

20
ST 30
GTA & GTC
10
GTB 25

0 20
0 1 2 3 4 5 6 0 1 2 3 4 5 6
Time (s) Time (s)
Speed deviation (percent)

Speed deviation (percent)

2.5 0.5

2
0
1.5 GTB & ST
-0.5
1 GTA & GTC
-1
0.5

0 -1.5
0 1 2 3 4 5 6 0 1 2 3 4 5 6
Time (s) Time (s)

Fig. 5. Post-fault behavior at Snorre B Fig. 6. Post-fault behavior at Snorre TLP


B. Long-term Dynamics VI. CONCLUSION
Fig. 7 shows the power output of the generators GTB This paper has demonstrated several important as-
and ST on Snorre B over a period of 10 minutes. Also pects that should be considered for combined cycle gen-
shown is the thermal energy stored in the boiler section eration on interconnected oil platform systems. For a
of the combined cycle plant. It can be seen that the rigid analyis of the electrical stability of such systems,
power drop of GTB due to its isochronous speed control both transient rotor dynamics and long-term boiler dy-
and the shut-down of GTA after the fault lessen the namics must be investigated.
amount of thermal energy, since the unloaded machines While an accurate simulation of the rotor dynamics
do not produce an adequate level of heat. requires detailed models of the platform machines, mid-
Consequently, the steam turbine cannot longer main- term and long-term dynamics are primarily in uenced
tain this level of power generation and reduces its out- by the turbine controls and boiler characteristics. This
put. However, the feared black-out due to overloading article illustrates these aspects with a model of the Nor-
does not occur because the isochronous gas turbine con- wegian interconnected platforms, Snorre TLP and B.
trol senses the slight drop of frequency and corrects the Detailed models of the gas and steam turbines of the
situation by injecting more power. This way, the power combinbed cycle plant on Snorre B and their associ-
generation is smoothly transferred from the steam tur- ated controls have been presented. Practical strategies
bine, ST, to the gas turbine, GTB, until a stable oper- for system control and protection have been discussed.
ating point is achieved for both turbines. The simulation results have shown that it is highly
improbable that the combined cycle steam turbine
C. Simulation Aspects would run out of steam due to an electrical contingency
or unforeseen loading condition, and cause a black-
out of the entire platform. As long as the gas tur-
The simulations have been performed with the power bine GTB has a sucient amount of power reserves, its
system simulation tool Netomac R by Siemens. Af- isochronous speed governor will prevent an overloading
ter the fault scenario and the decay of fast rotor tran- of the steam turbine and establish a stable post-fault
sients, the simulation time step is increased from 3 ms operating point for both turbines.
to 300 ms for long-term simulation.
Unlike in programs such as ETMSP [7], the simu-
lation time step is here simultaneously applied to all References
models. Considerations of the sti ness of the di eren-
tial equations show that the response time of all used [1] H. A. van Essen, Modelling and Model Based Control of
Turbomachinery, Ph.D. Thesis, Cip-Data Library Technis-
models are suciently long to permit this choice of time che Universiteit Eindhoven, Netherlands, 1998, ISBN 90-
steps. 386-0830-6.
While transient network dynamics, i.e. electromag- [2] A. H. Lefebvre, Gas Turbine Combustion, McGraw-Hill
netic transients, are typically too fast for an accurate Series in Energy, Combustion and Environment, Hemisphere
Publishing Corporation, New York, NY, U.S.A., 1983, ISBN
simulation with these time steps [8], their impact on 0-07-037029-X.
the machine and boiler dynamics is approximated by [3] B. Schonfeld, Modellbildung eines Kombi-Kraftwerks zur
the quasi-steady state admittance matrix representa- Untersuchung des Systemverhaltens mit dem Netz (Com-
tion of the electric network. This is common practice bined Cycle Plant Modelling for the Analysis of Power Sys-
tem Interaction, Ph.D. Thesis, Technical University of
in stabililty analysis, and its implications have been well Berlin, Verlag Shaker, Aachen, Germany, 1993, ISBN 3-
documented, e.g. in [6]. 86111-635-9.
[4] F. P. de Mello, \Boiler Models for System Dynamic Per-
formance Studies," IEEE Transactions on Power Systems,
40 vol. 6, pp. 66{74, February 1991.
[5] VDI/VDE, \Blockregelung von Warmekraftwerken. (Con-
Active power (MW)

30 trol of Thermal Power Units)," VDI/VDE-Guidelines, no.


ST GTB 3508, July 1984.
20
[6] P. Kundur, Power System Stabiliy and Control, EPRI
10 Power System Engineering Series. McGraw-Hill, Inc., New
York, NY 10020, U.S.A., 1994, ISBN 0-07-035958-X.
0 [7] E. G. Cate, K. Hemmaplardh, J. W. Manke and D. P. Gelop-
ulos, \Time Frame Notion and Time Response of the Mod-
0 100 200 300 400 500 600
Time (s)
els in Transient, Mid-Term and Long-Term Stability Pro-
grams," IEEE Transactions on Power Apparatus and Sys-
Thermal energy (percent)

1.5

tems, vol. 103, no. 1, pp. 143{151, January 1984.


1 [8] H. W. Dommel, EMTP Theory Book, Microtran Power
System Analysis Corporation, 4689 W. 12th Avenue, Van-
0.5 couver, B.C. V6R 2R7, Canada, 2nd edition, May 1992.
0
0 100 200 300 400 500 600
Time (s)

Fig. 7. Long-term behavior of Snorre B

You might also like