Pokhara Metropolitan City Office of The Executive Detail Estimate and Abstract of Cost
Pokhara Metropolitan City Office of The Executive Detail Estimate and Abstract of Cost
Pokhara Metropolitan City Office of The Executive Detail Estimate and Abstract of Cost
S.N Description No. Length Breadth Height Quantity(m3) Unit Rate Amount Remarks
1 Site clearance Works Lumsum 10000
Earthworks in excavation in ordinary soil
with all complete Including 10m lead & 1.5m
2 lift
a. Column 9 2.5 2.5 2.5 140.63
b. Wall
1. Hall
long wall 2 10.05 0.6 0.8 9.65
Short Wall 2 7.92 0.6 0.8 7.60
2. Stair Case With T/B
long wall 2 4.03 0.6 0.8 3.87
short wall 1 3.65 0.6 0.8 1.75
Total 163.50 cum 504.7 82516.9359
Stone soling work in foundation with all
3 complete
a. Column 9 2 2 0.15 5.40
b. Wall
1. Hall
long wall 2 10.05 0.5 0.15 1.51
Short Wall 2 7.92 0.5 0.15 1.19
2. Stair Case With T/B
long wall 2 4.03 0.5 0.15 0.60
short wall 1 3.65 0.5 0.15 0.27
3. Floor 1 13.58 11.07 0.15 22.55
Total 31.52 cum 3210 101189.9214
S.N Description No. Length Breadth Height Quantity(m3) Unit Rate Amount Remarks
S.N Description No. Length Breadth Height Quantity(m3) Unit Rate Amount Remarks
8
Hollow Concrete Block Works
a. Wall
1. Hall
long wall 2 10.05 0.15 3.04 9.17 cum
Short Wall 2 7.92 0.15 3.04 7.22 cum
2. Stair Case With T/B
long wall 2 4.03 0.15 3.04 3.68 cum
short wall 1 3.65 0.15 3.04 1.66 cum
Deduction
Door 2 0.76196 0.15 2.1335 -0.49
Windows 2 1.52393 0.15 1.52393 -0.70
Rolling Shutter (RS) 3 4.41 0.15 2.74 -5.44
Ventilation 2 0.60957 0.15 0.60957 -0.11
14.99 cum 7582.15 113686.77105177
9 12.5mm thick plaster in 1:4 cement mortar
a. Wall
1. Hall
long wall 2 10.05 2.7 54.27 Sqm
Short Wall 2 7.92 2.7 42.77 Sqm
2. Stair Case With T/B
long wall 2 4.03 2.7 21.76 Sqm
short wall 1 3.65 2.7 9.86 Sqm
Deduction
Door 2 0.76196 0.15 2.1335 -0.49
Windows 2 1.52393 0.15 1.52393 -0.70
Rolling Shutter (RS) 3 4.41 0.15 2.74 -5.44
Ventilation 2 0.60957 0.15 0.60957 -0.11
121.92 Sqm 7582.15 924420.29124177
Floor 1 13.58 11.07 150.33 Sqm 364.43 54784.980558
Celling 1 13.58 11.07 150.33 Sqm 422.43 63504.155358
Omega Engineering Consultant, Pokhara-27,Kaski
Er.Bhim Prasad Dahal
POKHARA METROPOLITAN CITY
office of the Executive
Newroad, Kaski
Gandaki Province ,Pokhara
Detail Estimate And Abstract of Cost
Name of project :- Milan Sar Tamu Samaj Begnas 31, Bahu Uddeshya Bhawan F/Y :- 075/76
Site:- Pokhara Metropolitan City -31 Date:- 2075-10-11
S.N Description No. Length Breadth Height Quantity(m3) Unit Rate Amount Remarks
10 3mm Thick Cement Punning Work 1 13.58 11.07 150.3306 Sqm 237.71 35735.086926
S.N Description No. Length Breadth Height Quantity(m3) Unit Rate Amount Remarks
13 Painting Work
a. 2 Coat White Washing In New Surface In
Wall
1. Hall
long wall 4 10.05 2.7 108.54 Sqm
Short Wall 4 7.92 2.7 85.54 Sqm
2. Stair Case With T/B
long wall 4 4.03 2.7 43.52 Sqm
short wall 2 3.65 2.7 19.71 Sqm
Total 257.31 Sqm 387.27 99648.4437
b. 2 Coat White Washing In New Surface In
ceiling 2 13.58 11.07 300.66 Sqm 396.17 119112.947604
14 Roolling Shutter (18-20 Gauge) 3 195.02 585.06 Kg 171.8 100513.308
15 Horizontal Pipe (2") 4 4.5 271.89 Kg 171.8 46710.702
26 Gauge C.G.I Sheet roofing Work Including
16 Material Collection 1 4.5 3.65 16.43 Sqm 3015.46 49528.9305
Sub- Total 4161321.85
contengecies @ 3 % 124,839.66
Grand total 4,286,161.51