Revision Number / Date

VESHRAND ELECTRICAL ELECTRICAL 01/ 1st Jan 2011


Page Number
ELECTRICAL COMPLETION CERTIFICATE Page 1 of 1

Contract No Drawing No
Client Name Client Ref
Contract Description Identifying No
Plant Area Test Voltage
Test Equipment
Distribution: Distribution Of Completed Certificates
1. Original Copy - To Contractor
2. Actual Copy - To Project Manager
4. Contract Copy - To Site Manager
3. Completion Copy - To Customer
Contract Actual Maintenance Warranty
Hand Over
Completion Completion Expires
Reference Dates :

Notice Is Hereby Given By The IMS Engineer That The Works Have Been Completed Satisfactory In Terms Of The
Contract.
This Document Is Issued Without Prejudice To The Customer's Rights In Terms Of The Contract.
Details Of Plant Included On This Certificate

Work On Punch List Completed : Yes / No Date:

Acceptance / Approval