Water System Permitting - Process Flowchart

Initial Application Checklist WDEQ and Campbell County


Complete?
Yes
No WDEQ is the Permitting CCPW Complete WDEQ
Publicly Owned?
Authority Annual Report
Yes
CCPW is the Permitting WDEQ to review Permit Archive Complete App.
Authority Requirements Documents

No Notify Applicants of Notify WDEQ and CCPW


New Water Well Required?
Permit Requirements Bldg. Div.
Yes
WDEQ to issue Well PTC prior to WDEQ signs PTC - Copy
CCPW Issues PTC
any PTC to CCPW

DEQ ch 23 subdivision review No Yes


required? City WSA or I&S No Hold all PTC and Notify
Yes agreement in place? Applicant
WDEQ to issue ch 23
recommendaiton prior to PTC Distribution Systems
WDEQ Ch. 12

Eng. Design Report WDEQ Ch. Notes


12 1. "CCPW" is Campbell County Public Works Water Storage WDEQ
2. "WDEQ" is Wyoming Dept. of Environmental Quality Ch. 12
3. "PTC" is Permit to Construct
Plans & Specs WDEQ Ch. 12
4. City permits regional extensions 12" dia. Pumping Facilities
or less. WDEQ to permit all others WDEQ Ch. 12
5. WDEQ permits all water supply wells and treatment facilities Jurisdiction Decision
General Design WDEQ Ch. 12
6. "WSA" is Water Service Agreement between City and District CCPW Task
WDEQ Task