Professional Documents
Culture Documents
06 - Bridge Foundation PDF
06 - Bridge Foundation PDF
Bridge Foundations
Section 6
BRIDGE FOUNDATIONS
January, 2018 1
Bridge Foundations Section 6.1
January, 2018 2
Bridge Foundations Section 6.1
• Spread Footing
• Piling
• Drilled Shafts
Type Of Excavation
“Dry” Excavation:
• Generally stable with no waterway or
de-stabilizing groundwater
“Wet” Excavation:
• In or near water or significant groundwater
January, 2018 3
Bridge Foundations Section 6.1
Spread Footings
Spread Footings
January, 2018 4
Bridge Foundations Section 6.1
Spread Footings
Spread Footings
January, 2018 5
Bridge Foundations Section 6.1
Spread Footings
Spread Footings
Concrete volume of
a spread footing:
V=LxWxH
January, 2018 6
Bridge Foundations Section 6.1
V = 26 cy
Volume =
January, 2018 7
Bridge Foundations Section 6.1
V = 24 cy
Spread Footings
Open-Pit
Excavations
Walls of excavation
are sloped for
safety.
No shoring required.
Wide enough for
workers outside of
footing.
January, 2018 8
Bridge Foundations Section 6.1
Spread Footings
Open-Pit Excavations are permitted when:
• Not in or near water.
• The soil material is adequately stable to ensure
worker safety.
• The soil can be maintained in a dry condition.
• There is no threat of compromising the stability of
any nearby structure or the structure being built.
Spread Footings
Shored excavations
Shoring & Cribbing:
A series of horizontal and
vertical members that resist
the surrounding soil
pressure.
January, 2018 9
Bridge Foundations Section 6.1
Shoring &
Cribbing
Spread Footings
Shored Excavations must be used when:
• The excavation is greater than 4 feet
deep.
• The soil is not stable enough to ensure
worker safety.
• The presence of adjacent structures limits
the allowable size of the excavation.
January, 2018 10
Bridge Foundations Section 6.1
Spread Footings
Foundations on rock:
• Level
• Stepped
• Serrated
• Against Solid Rock
For Arches
Spread Footings
Unsuitable soils for spread footings:
If any evidence of problematic soils is
discovered during footing construction, work
should be stopped and The Engineer should
be contacted immediately.
January, 2018 11
Bridge Foundations Section 6.1
Spread Footings
Items to inspect for with spread footings:
• Elevation
• Dimensions
• Reinforcement
• Soil Stability
Spread Footings
January, 2018 12
Bridge Foundations Section 6.1
Foundation Location
January, 2018 13
Bridge Foundations Section 6.1
Reference Points
Structure Excavation
January, 2018 14
Bridge Foundations Section 6.1
Structure Excavation
Measuring
Excavation / Backfill
• Cross-Section original
ground before excavation
begins.
• Normal volume bounded
by vertical planes 1 foot
outside the footing.
(510.80(b)(2)(c))
Structure Excavation
Measuring Excavation
• Volume of excavation is
from bottom of footing to
natural ground line.
January, 2018 15
Bridge Foundations Section 6.1
Structure Excavation
Measuring Backfill
• Volume of backfill is
from bottom of footing
to finished construction
line.
January, 2018 16
Bridge Foundations Section 6.1
Volume =
January, 2018 17
Bridge Foundations Section 6.1
Calculate Volume
by Average End Area
• Measure end areas
• Average end areas
• Measure horizontal
distance “d” between
areas
• Multiply average end
area by horizontal
distance “d”
January, 2018 18
Bridge Foundations Section 6.1
Volume =
Volume = 62 cy
January, 2018 19
Bridge Foundations Section 6.1
Foundation Reports
January, 2018 20
Bridge Foundations Section 6.1
January, 2018 21
Bridge Foundations Section 6.1
January, 2018 22
Bridge Foundations Section 6.1
January, 2018 23
Bridge Foundations Section 6.1
Foundation Exercise
Cofferdams
January, 2018 24
Bridge Foundations Section 6.1
January, 2018 25
Bridge Foundations Section 6.1
Cofferdams
A water-tight
enclosure that
allows the
construction of a
bridge foundation
in the dry.
Cofferdams
Used in or
near water.
January, 2018 26
Bridge Foundations Section 6.1
Cofferdams
January, 2018 27
Bridge Foundations Section 6.1
– De-water
– Construct Footing and
Column in The Dry
– Flood Cofferdam
– Remove Cofferdam
– Place Riprap
January, 2018 28
Bridge Foundations Section 6.1
Sheet Piles
January, 2018 29
Bridge Foundations Section 6.1
Vibratory Hammer
Sheet Piles
January, 2018 30
Bridge Foundations Section 6.1
Sheet Piles
Vent Holes
January, 2018 31
Bridge Foundations Section 6.1
Bracing
Cofferdams
require
adequate
bracing.
Wet Excavation
January, 2018 32
Bridge Foundations Section 6.1
Underwater Exploration
• The inspector should take and record
soundings to determine underwater
elevations.
• Under water inspection may be required by
divers to determine proper excavation to the
edges of the cofferdam, so that seals will
hold.
January, 2018 33
Bridge Foundations Section 6.1
January, 2018 34
Bridge Foundations Section 6.1
• Slump of 6″-10″
• Entrained Air not required
January, 2018 35
Bridge Foundations Section 6.1
De-water Cofferdam
00540.48(e)
Completing Construction
January, 2018 36