CONSTRUCTION SCHEDULE

Porject Name: DS Factory Myanmar Project Sterling Industrial Technologies Co.,Ltd 23/3/2020
MARCH APRIL MAY
No. ACTIVITY
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Workshop Building TODAY


1.1 Ground Beam Concrete Casting
Along GL. Y1 ~ ( X6-X12 )
1) Concrete Casting
2) Deshuttering of Formwork
Along GL. Y1 ~ ( X1-X6 ) & GL. X1 ~ ( Y1-Y7 )
1) Concrete Casting
2) Deshuttering of Formwork
Along GL. Y7 ~ ( X1-X13 )
1) Concrete Casting
2) Deshuttering of Formwork
Ground Beams Near water tank
Along GL. Y1 ~ ( X13-X16 ) & GL. Y1A ~ ( X13-X16 )
1) Backfilling & Compaction around water tank
2) lean Concrete Casting
3) Rebar Installation
4) Formwork Installation This casting schedule already behind and is
5) Concrete casting likely to impact on slab casting schedule.
Water Tank Top Slab
1) Formwork Installation
2) Rebar Installation
3) Concrete Casting
together with ground beams above
1.2 Internal Remaining Pile Cap Works ( Total= 101 nos.)
1st Casting: 5 nos. of PC-1, 5 nos. of PC-1A, 4 nos. of PC-4,
1 nos. Of PC-2A and 1nos. of PC-2E ( Total= 16 nos.)
2nd Casting: 4 nos. of PC-4, 4 nos. of PC-1A, 6 nos. of PC-1,
2 nos. Of PC-2A ( Total= 16 nos.)
3rd Casting: 4 nos. of PC-4, 10 nos. of PC-1 and 2 nos. of PC-2A
( Total= 16 nos. )
4th Casting: 4 nos. of PC-4, 10 nos. of PC-1 & 1 nos. of PC-2A.
( Total= 15 nos. )
5th Casting: 4 nos. of PC-4, 12 nos. of PC-1 and 2 nos. of PC-2F.
( Total= 18 nos. )
6th Casting: 4 nos. of PC-4, 2 nos. of PC-2A & 2 nos. of PC-10, This area backfilling not yet finished coz GL.Y1A
( Total= 8 nos. ) and some parts of Y16 beams are not yet casted.
7th Casting: 10 nos. of PC-1 & 2 nos. of PC-8 Compaction has been started from GL.Y7.
( Total= 12 nos. )
1.3 Backfilling and Compaction
Along GL. ( Y1A- Y7 ) ~ ( X16-X17 ) B B C
Along GL. ( Y1A- Y7 ) ~ ( X13-X16 ) B B C For the other remaining areas, Appx 35% of
Along GL. ( Y1A- Y7 ) ~ ( X10-X13 ) B B C backfilling finished. Compection not yet started.
Along GL. ( Y1A- Y7 ) ~ ( X7-X10 ) B= Backfilling B B C
Along GL. ( Y1A- Y7 ) ~ ( X4-X7 ) C = Compaction B B
Along GL. ( Y1A- Y7 ) ~ ( X1-X4 ) B B

1.4 Ground Slab Concrete Casting


For 1st slab casting, at least compaction shoud
Along GL. ( X16-X17 ) ~ ( Y1A-Y7 ) ( V=102.84 m3 ) Start Work
1) lean Concrete Casting be done and lean casting should be started this
2) Rebar Installation date. (27/3/2020)
3) Formwork Installation
4) Floor Concrete Casting The chance is slim for this date
Along GL. ( X14-X16 ) ~ ( Y1A-Y7 ) ( V=120 m3 ) 31/3/2020 casting. We promised to
1) lean Concrete Casting KAS.
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting
Along GL. ( X12-X14 ) ~ ( Y1A-Y7 ) ( V=120 m3 )
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting
Along GL. ( X10-X12 ) ~ ( Y1A-Y7 ) ( V=120 m3 )
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting
Along GL. ( X7-X10 ) ~ ( Y1B-Y7 ) ( V=180 m3 )
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting
Along GL. ( X4-X7 ) ~ ( Y1B-Y7 ) ( V=180 m3 )
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting
Along GL. ( X1-X4 ) ~ ( Y1B-Y7 ) ( V=180 m3 )
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Floor Concrete Casting

1.5 RC Walls Casting ( total: H= 4m,50 m & H=5.3m,43m )


RC Wall H=4000, THK= 250 mm ( L= 15 m ) Start Work
1) Rebar Installation
2) Formwork Installation
3) Concrete Casting
RC Wall H=4000, THK= 250 mm ( L= 15 m )
1) Rebar Installation
2) Formwork Installation
3) Concrete Casting
RC Wall H=4000, THK= 250 mm ( L= 20 m )
1) Rebar Installation
2) Formwork Installation
3) Concrete Casting
RC Wall H=5300, THK= 250 mm ( L= 20 m )
1) Rebar Installation
2) Formwork Installation
3) Concrete Casting
RC Wall H=5300, THK= 250 mm ( L= 23 m )
1) Rebar Installation
2) Formwork Installation
3) Concrete Casting

1.6 Masonry & Plastering Work


Brick Wall H=3100, THK= 250 mm ( L= 36.5m ) Start Work
1) Brick Laying
2) Stud & Lintel casting
3) Plastering
Brick Wall H=1000, THK= 250 mm ( L= APX 162m ) Start Work
1) Brick Laying
2) Stud & Lintel casting
3) Plastering

2 Utility Buildings
( Oxygen Generator, LPG, Garbage Room, Dangerous warehouse,
Guard House, Bike Shed , Electric Room etc..)
2.1 LPG Start Work
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.2 Gabage Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
8) Column Rebar Installation
9 ) Coulmn Formwork Installation
10) Column Casting
11) RB rebar Installation
12) RB Formwork Installation
13) RB rebar casting
2.3 Utility Houses Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.4 Guard House Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.5 Bike Shed Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.6 Electric House Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
8) Column Rebar Installation
9 ) Coulmn Formwork Installation
10) Column Casting
11) RB rebar Installation
12) RB Formwork Installation
13) RB rebar casting
2.7 Truck scale Start Work
1) Excavation
2) Lean Concrete casting
3) Rebar Installation
4) Formwork Installation
5) Concrete Casting

3 External Works
3.1 Drainage Work
3.1.1 Waste Water Drainage
1) Manhole- W type ( 9 Nos. )
2) D200 PVC Pipe laying ( Total L= 200 m )
3) Septic Tank 1
4) Septic Tank 2
5) Separate Oil Tank
6) Grease Truck
7) Connection to MJTD Manhole

3.1.2 Storm Water Drainage


1) Manhole- G1 type ( 3 Nos. )
2) Manhole- G2 type ( 8 Nos. )
3) Grease Trap
3) Brick Trench ( Total Length= 370 m )
4) D800 Concrete Culvert Installation ( Total L= 84m )
5) D400 Concrete Culvert Installation ( Total L= 18m )
6) D200 PVC Pipe laying ( Total L= 61m )

3.2 Fence & Gate


3.2.1 Fencing Work
Brick Fence 1) Lean Concrete Remaining Lean Casting ( 60 m )
( L= 254.9m ) 2) Footing Rebar Installation
3) Formwork Installation
4) Footing Concrete Casting
5) Brick Laying Up to ( - 0.100 )
6) Ground Beam ( GT-1 type )
7) RC columns
8) Brick wall Laying
Start Work
Steel Fence 1) Excavation & Lean Concrete E E E L L L
( L= 150.5m ) 2) Footing Rebar Installation
3) Formwork Installation
4) Footing Concrete Casting
5) Brick Laying Up to ( - 0.100 )
6) Ground Beam ( GT-1 type )
7) RC columns
8) Steel Fence Installation
3.2.2 Gate Start Work
(5mX2.4m) 1) Excavation & Lean Concrete
2) Footing Rebar Installation
3) Formwork Installation
4) Footing Concrete Casting
5) RC Column casting
6) Brick Laying Up to ( - 0.100 )
7) Ground Beam
8) Brick Laying
9) Tie Beam casting

3.3 Road, Paving Work


Earth Work Start Work
1) Excavation
2) Remove Surplus Soil
3) Soil Compaction
4) Geotextile laying
5) Crushed Stone Laying
6) Crushed Stone Compaction
7) PE film laying
Curb Setting Work
1) Concrete Curb Setting

Road Concrete Work


1) Rebar Installation
2) Formwork Installation
3) Concrete Casting

Interlocking Brick Laying


1) Ground Soil Compaction
2) Sand Compaction
3) Interlocking Brick Laying