Professional Documents
Culture Documents
Schedule With Time Line
Schedule With Time Line
Porject Name: DS Factory Myanmar Project Sterling Industrial Technologies Co.,Ltd 23/3/2020
MARCH APRIL MAY
No. ACTIVITY
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
2 Utility Buildings
( Oxygen Generator, LPG, Garbage Room, Dangerous warehouse,
Guard House, Bike Shed , Electric Room etc..)
2.1 LPG Start Work
1) lean Concrete Casting
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.2 Gabage Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
8) Column Rebar Installation
9 ) Coulmn Formwork Installation
10) Column Casting
11) RB rebar Installation
12) RB Formwork Installation
13) RB rebar casting
2.3 Utility Houses Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.4 Guard House Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.5 Bike Shed Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
2.6 Electric House Start Work
1) Excavation & Lean Concrete
2) Rebar Installation
3) Formwork Installation
4) Concrete Casting
5) Soil compaction
6) Slab rebar & Formwork Installation
7) Slab Casting
8) Column Rebar Installation
9 ) Coulmn Formwork Installation
10) Column Casting
11) RB rebar Installation
12) RB Formwork Installation
13) RB rebar casting
2.7 Truck scale Start Work
1) Excavation
2) Lean Concrete casting
3) Rebar Installation
4) Formwork Installation
5) Concrete Casting
3 External Works
3.1 Drainage Work
3.1.1 Waste Water Drainage
1) Manhole- W type ( 9 Nos. )
2) D200 PVC Pipe laying ( Total L= 200 m )
3) Septic Tank 1
4) Septic Tank 2
5) Separate Oil Tank
6) Grease Truck
7) Connection to MJTD Manhole