Professional Documents
Culture Documents
TCM Division: Bull'S Eye Post Weld Heat Treatment (PWHT)
TCM Division: Bull'S Eye Post Weld Heat Treatment (PWHT)
Per
ASME BPVC SECTION VIII DIV. 1
NBIC RD-1100
For
PETROLEOS DE VENEZUELA S.A. (PDVSA)
Cardon, Venezuela
By
TEAM INDUSTRIAL SERVICES, INC.
Estado Falcon, Venezuela
1.0 OVERVIEW
The following table summarizes the specifications for this thermal processing procedure.
PARAMETER SPECIFICATION
Client Petroleos De Venezuela S. A. (PDVSA)
Location Cardon, Venezuela
Work Piece Identification Vessels C6-12, C6-13, and C6-14
Weld Identification Nozzles N3 & N4 attachment weld
Shell & Nozzle Material SA-516-70 & SA-106-B (ASME P-No. 1) CS
Shell Thickness & Inner Diameter 1-7/16-inch & 15-1/2-ft
Nozzle Dimensions 8-inch NPS
Governing Codes Section VIII, ASME BPVC, and NBIC
Heating Method Electric Resistance Heat Treating System
PWHT Soak Temperature 1150 °F ± 25 °F
PWHT Soak Time 2-1/4 hours, minimum
Max. Heating Rate above 800 °F 140 °F/hr
Max. Cooling Rate above 800 °F 180 °F/hr
2.0 SCOPE
2.1 Background
Welding produces high temperatures, severe temperature gradients, and rapid cooling and
solidification, which increase residual stresses, grain size, and brittleness in the weld and its
adjoining base material. These, in turn, can reduce fatigue life, corrosion resistance, and
dimensional stability of the weldment assembly. Post weld heat treatment (PWHT) can
relieve these ill effects by reducing residual stress and hydrogen content, and by restoring
ductility and corrosion resistance.
2.2 Purpose
The purpose of this procedure is to define specifications for a Bull’s Eye PWHT of nozzles
N3 and N4 attachment welds on vessels C6-12, C6-13, & C6-14, in compliance with ASME
BPVC Section VIII Div. 1 and NBIC requirements. This procedure identifies the locations
and attachment methods for thermocouples, electric resistance heaters, and thermal
insulation, to ensure that code requirements for heating, soak, cooling, and gradient control
are achieved.
Team PWHT Procedure 022509-01, Rev. 0 Page 2 of 10
• The 2007 edition of Section VIII, Division 1 of the American Society of Mechanical
Engineers (ASME) Boiler and Pressure Vessel Code (BPVC)
• Paragraph UW-40 for soak band width requirements
• Table UCS-56.1 for PWHT soak temperature and time
• Article UCS-56 for heating and cooling rates
• The 2004-06 edition of the National Board Inspection Code (NBIC) RD-1100
• An as yet unidentified PDVSA welding procedure specification (WPS)
The majority of the tasks described in this procedure are within Team's scope of activity.
However, the purpose of this document is to describe those tasks or activities, and not to
assign responsibility for them. The Team supervising technician will coordinate with the
client to assign these duties, and is empowered to make minor alterations to this procedure,
such as heater selection, in order to improve the quality of the PWHT by accommodating
variations in available equipment and space. Major revisions must be approved by the
client and Team’s Technical Support Group (TSG), to ensure the quality of the PWHT.
Vessels C6-12, C6-13, & C6-14 and nozzle N2 are illustrated in PDVSA drawing RCN-523.806,
Rev. 3, of July 17, 2006, containing the following features:
4.0 UW-40 REQUIREMENT FOR ATTACHMENT WELD SOAK BAND (SB) WIDTH
Paragraph UW-40 (a) (7) requires that the local PWHT of a nozzle attachment weld employ a soak
band that shall extend beyond the weld in all directions a minimum distance of the wall thickness
or 2 inches, whichever is less, as illustrated in Figure 1, below.
t
The Lesser of t or 2" The Lesser of t or 2"
Therefore, the 2-inch NPS diameter nozzle N3 will have a 4-3/4-inch diameter SB based on a 1/2-
inch fillet weld and a 1-7/16-inch thick shell. Similarly, the 8-inch NPS diameter nozzle N4 will
have a 19-3/16-inch diameter SB based on a 14-15/16-inch diameter by 1-7/16-inch thick repad
and a 1-inch wide fillet weld.
NBIC RD-1100 requires that the radial gradient from the SB not exceed 250 °F/ft. Therefore, at a
distance of 1-ft from the edge of the SB, the temperature in the HB must not be below 925 oF, with
a maximum PWHT soak temperature of 1175 oF.
Figure 2 on the following page illustrates the bull’s eye PWHT heater and thermocouple
arrangement for both the N4 and the N3 nozzle and/or repad attachment welds, incorporating code
SB requirements as defined above. All heaters are to be attached to the shell by means of capacitor
discharge welded stud pins and friction washers, in compliance with Team Standard Practices SP-
01 and SP-08.
Each FCP heater has a surface area of 120 in². When powered by 80-VAC from a standard
Team 6-zone power and control (6-PAC) console, it will develop a thermal power capacity
of 3.6 kW, which is a uniform area power density of 30 W/in². Heaters are identified by
their flexible width dimension. For example, a CP12 heater is has a flexible 12-inch width,
and a rigid 10-inch length. Up to three heaters can be powered in parallel in a single
temperature control zone, in accordance with Team Standard Practice SP-08.
Team PWHT Procedure 022509-01, Rev. 0 Page 4 of 10
TC4 4A
5A
4C
CP12 CP12
CP10 4B CP10 CP8 CP8
CP12
TC5 CP18
8B 10B
3B
5B CP15 TC3
TC8
2A TC10
1A
2CP10s 1CP29
5C N4 1B N3 TC9
TC1 N-1
CP12 3A
2B
6A
CP18 CP15 CP4
CP12 7C CP8
CP8
TC6 TC7
6C 7A
Figure 2 – Plan View of Bull’s Eye Thermocouples & Heaters for PWHT of Nozzles N3 & N4
Team PWHT Procedure 022509-01, Rev. 0 Page 5 of 10
The bull’s eye HB heater and thermocouple pattern is illustrated in Figure 2 on the previous
page. It consists of three heater bands, as described below.
Surrounding nozzle N4 on the shell will be an average 7-inch wide rectangular band
of 2 CP15 heaters alternated among 2 CP18 heaters, arranged into two 2-heater
temperature control zones, with a 1/2-inch space between heater ends. In addition,
an 8-inch wide heater band will be installed for N3, consisting of 1 CP8 heater on
each side of N3, arranged into a single 2-heater temperature control zone.
Immediately surrounding the innermost rectangular HB for nozzles N4 and N3, will
be nominal 1-ft wide band, consisting of 7 CP12 heaters, 4 CP10 heaters, 2 CP8
heaters, and a single CP4 heater. This band will be arranged into four 3-heater
temperature control zones, and a single 2-heater zone, with a nominal 1-inch space
between heaters.
The precise thermocouple locations are illustrated in Figure 2, and described in sub-section
6.2. Basically, each thermocouple is to be as close to the geographic center of its
temperature control zone as possible.
The heater bands inside nozzle N4, around nozzle N3, and on the shell immediately
surrounding nozzles N4 and N3, as described in sub-sections 6.2.1, 6.2.2, and 6.2. are each
to have the PWHT soak temperature as set-point. The outermost shell heater band, as
described in sub-section 6.2.4, has its control thermocouples on average a distance of 1-ft
from the edge of the soak band (SB). Consequently, those control thermocouples are to
have a set-point temperature 250 oF lower than the PWHT soak temperature, for a value of
925 oF. This will place the temperature of the outer edge of the HB at a value of
approximately 800 oF.
The entire bull’s eye is to be covered with a layer of 1-inch thick 6-lb/ft3-density non refractory
ceramic fiber (Non-RCF) thermal insulation, which is to extend 2-ft. beyond the edges of all
heaters. It is to be secured to the shell with the same type of capacitor discharge welded stud pins
and friction washers that hold the heaters in place, and banded to nozzle N3. The insulation that is
inserted into nozzle N4, with its attached heaters, is to consist of the same insulation material
rolled into a cylindrical plug.
The diamond plate walk-way with its flat-bar kick-plates must be removed from the top of
each vessel to enable the installation of thermocouples and heaters directly on the vessel
shell, and to avoid toxic out-gassing from their painted and/or oil soaked surfaces.
An 1/8-inch diameter weep hole must be drilled into the N4 repad before installing PWHT
thermocouples and heaters.
Team PWHT Procedure 022509-01, Rev. 0 Page 7 of 10
9.4 Safety
Team site personnel will work with the client’s safety personnel, to ensure that the
following on-site safety steps are taken:
All Team personnel shall wear protective clothing and equipment, as described in
the Team Safety Manual, and shall satisfy all site-specific safety requirements.
A type ABC fire extinguisher shall be available to Team personnel within ready
access to the PWHT location.
Equipment specifications and preparation instructions relevant to this field procedure are provided
in the Team Standard Practices listed on the following page.
The following heating, soak, and cooling specifications are in accordance with those of article UCS-
56 and Table UCS-56.1 for a combined repad and shell thickness of 2-13/16-inch (71.5-mm) P-No.
1 carbon steel.
11.1 Heating
From ambient to 800 °F, Team recommends that the heating rates not exceed 400
°F/hr, in an effort to minimize temperature differences within concentric heater
bands.
Team PWHT Procedure 022509-01, Rev. 0 Page 8 of 10
Above 800 °F, heating rates shall not exceed 140 °F/hr.
While heating above 800 °F, there shall not be a greater variation in temperature than
150 ºF among thermocouples within any given concentric heater band. The heating
rate may be reduced to ensure that these differentials are not exceeded.
During the heating period, there shall not be a temperature greater than 1175 ºF.
In the event of a thermocouple failure during the controlled portion of the heating
cycle, the cycle may be held at that point until the transfer to a spare thermocouple is
completed.
11.2 Soak
11.2.1 Temperature
Soak temperature shall be between 1125 ºF and 1175 ºF. The soak period is to begin
when the core HB soak temperature reaches 1125 ºF. At no time shall the
temperature of these thermocouples either exceed 1175 ºF, or fall below 1125 ºF.
11.2.2 Time
In the event of a thermocouple failure during soak, the transfer to the spare
thermocouple is to be done immediately. If the temperature of the soak
thermocouple falls below 1125 ºF at any time during the transfer, the soak period is
to be resumed when it reaches 1125 ºF. The total accumulated time above 1125 ºF is
to be the soak time.
The set-point temperature for the control thermocouples in the outermost heater band
is to be not less than 925 oF, as defined in Subsection 7.3, in compliance with the
NBIC mandated maximum allowable temperature gradient.
Team PWHT Procedure 022509-01, Rev. 0 Page 9 of 10
11.3 Cooling
Above 800 °F, the maximum cooling rate shall not exceed 180 °F/hr.
While cooling above 800 °F, there shall not be a greater variation in temperature than
150 ºF among thermocouples in any given concentric heater band. Cooling rates
may be reduced to ensure that these differentials are not exceeded.
At and below 800 °F, the cooling rate need not be restricted, and cooling can be
completed in still air. Thermal insulation can be removed whenever it is deemed
safe to do so.
In the event of a thermocouple failure during the controlled portion cooling, the
cycle may be held at that point until the transfer to the spare thermocouple is made.
13.0 DOCUMENTATION
A Team Job Folder is to be submitted to the client, containing the following documents:
• Date
• Identification of work piece
• Thermocouple type
• Stress relieving company
• Stress relieving operator and signature
• Chart recorder serial number and date of latest calibration
A daily HTR shall be submitted to document personnel, time, material, and equipment.
13.5 Approvals