You are on page 1of 3

TECHNICAL NOTE

the field or artificiaUy in the laboratory, are carefully aligned in the test
apparatus. As this is an extremely time consuming and difficult process,
I.'I )I;irma the ring shear apparatus was developed. In this apparatus an annulus of
soil is sheared by rotation allowing large strains to be readily obtained.

)rocec ure 'or~: ie 2.0 BS 1377 Rlug shear test


Part 7 of BS 1377 classes the ring shear test as a Total Stress Test, which
the majority of civil engineers assume to be an undrained test. The ring
shear test is however a drained test; and although the total and effective

rinc s >ear I:es:


AJ Harris and PDJ Watson, School of Civil Engineering,
stresses are the same when the sample is drained, some confusion may
arise regarding the soil properties derived from the test. It would appear
more logical, therefore, for the test tobe included in Part 8 of BS 1377.
The BS test also includes some procedures that make it difficult and
time consuming. These procedures negate the advantages of this
Kingston University, Penrhyn Road, Kingston-Upon particular apparatus, which are simplicity and speed (Hawkins &
Privett 1981).Part 7, section 6.4.2.states that the sample should be subject
Thames, Surrey, KT1 2EE. to a consolidation stage. This is in agreement with the authors, however
BS 1377 recommends that the time to 100% primary consolidation (ti~) is
determined. This would be possible if the sample was of sufficient
thickness, however the small thickness of the ring shear sample has
The test procedure given in BS 1377 Part 7 to determine the residual meant that monitoring of the consolidation stage is inaccurate. This
shear strength of a soil using the Bromhead ring shear apparatus problem can be compounded by the fact that with some soft clays, soil
contains a number of procedures that make the test both difficult and maybe squeezed out between the confining rings and the upper platen.
time consuming. A test procedure used at Kingston University since the Similarly, the use of separate consolidation stages throughout the test
development of the Bromhead ring shear apparatus is therefore gives little additional benefit to the overall result. From the time to 100%
proposed. The procedure is in effect a multi-stage test and commonly consolidation, it is possible to determine the rate of strain at which the
results in a value for the drained residual shear strength within three sample should be tested. By calculating the correct rate of strain, it can
working days. The residual shear strength values obtained have been be ensured that pore pressures dissipate during the test, but this
found to be close to those derived from back analyses of slope failures, commonly results in very slow strain rates. These calculated rates of
especially when there is a strong element of bedding control on the strain are generally too slow as they are based on a drainage path of half
location of the slip surface and when the back analysis is not unduly the sample thickness. However, it is commonly found that the shear
affected by uncertainties in pore pressures and end effects. A review of surface forms within 1 mm of the upper platen. Hence, the drainage path
alternative uses and test procedures for the Bromhead ring shear is shorter than assumed and the tendency for excess pore pressures to
apparatus is also included. develop due to shear is reduced. In any event the influence of strain rate
on the measured properties can be assessed by raising or lowering the
1.0Inbwluc5on strain rate and observing the effect on the measured torque. Lowering
The ring shear test was first proposed by A Casagrande as reported by the strain rate should result in an increase in the measured torque if
Hvorslev (1939).More recent developments include those by Bishop et al. excess pore water pressures are being generated due to shear. However,
(1971)and Bromhead (1979), whose simplified apparatus (see Fig. 1) uses it should be noted that high rates of shear may result in disturbance of
a thin sample of remoulded soil. It is this design concept that forms the the residual soil fabric (aligned clay particles) with consequent increase
basis for the test recommended by BS 1377 (1990).The apparatus has also in inferred strength.
been further developed for particular investigations notably by Steward Problems with the BS test can also result from formation of the shear
& Cripps 1983, Hawkins & Privett 1985, Stark & Eid 1993, and Dewhurst et plane during the initial stage. The test recommends that the shear plane
al, 1996. is formed "by using the motor drive or hand wheel (if fitted) to rotate the
The alteration of a soil fabric caused by the formation of a shear zone specimen by one to five revolutions within a period of approximately 2
or shear surface, results in changes to the strength properties of the soil. min". This high shear rate can result in substantial extrusion of the
The strength of the soil with its original fabric is termed the peak sample, the generation of undrained pore water pressures, which
strength, and its strength under large deformation conditions in a shear ultimately dissipate, as well as non-fully aligned clay particles. It is
zone or on a shear surface is referred to as the residual strength. therefore recommended that a slow shearing rate is used to complete the
Conventional triaxial and direct shear box tests do not allow sufficient formation of this feature correctly (see section 3.2).
strain for the residual strength to be fully developed. These tests can only To overcome the problems posed by the BS procedure, the following is
be used if preformed shear surfaces, that have been developed either in recommended for the small ring shear test, particularly for those using
the Bromhead Ring Shear
apparatus.
Pillar for settlement gauge
3.0Optimal test procedure
3.1 Sample prepartruon
1. The first step is to remould the
soil sample at a moisture content
either at or lower than the plastic
limit. This is because shear
surface formation is a result of
soil brittleness, which is more
unter likely to occur at moisture
ghted contents lower than the plastic
ding
limit.
Note: Remoulded specimens are
quite adequate for residual
strength determination alone.
This is because the development of
a shear surface in a clay soil
completely changes the soils
IJ Zn initial fabric in the vicinity of the
shear surface. There is therefore
Counterweight Rest for load arm Load hanger little or no merit in attempting to
preserve such an initial fabric or
structure in the test specimen,
Rgnre1: Ring shear ayyarnhia eleeaeon and soneinl taronL unless it is specifically desired to

26 GROUND ENGINEERING JULY 1997


TECHNICAL NOTE

examine the process of shear surface formation.


2. The remoulded soil is then kneaded into the sample container with Extended Stop rotation
//resuh
if torque held,
is nol strain rate sensitive
time in
the fingers, or rammed into position with a wooden spatula, and the ie fimt siege
surface trimmed flush with the container by using a palette knife.
3. The top loading platen is placed on the sample, and the lever loading
i Matches first /
measured resrduat2
arm placed on this. The bath is then filled with water and the sample torque indicates / 'teady

drainage completed l /
left to saturate fully. Torque removed before/r lf not, repeat
other load stages
Note: Settlement readings may be taken but squeeze effects tend to decreasing normal load
make readings valueless (see earlier comments). Time axis or rotation seats

3.2 lnlmal shearing


1. It is necessary to select an appropriate rate of shear, before shearing I stasas pt-oad
can take place. If high rates of shear are used substantial extrusion of
the sample can occur. Although a shear surface of sorts is usually Houre 2:t)ttttoal tost resuns, sttotolueoNootortNI-ttuttuo at outlot tost.
formed by this rotation, this surface may not have the desired
properties. This can be either as a result of the generation of undrained sample holder. These measures not only prevented solution leaking into
pore water pressures, or because viscous inter particle drag forces have the water bath, but also forced it to flow through the sample to the upper
prevented the formation of an ideal, strongly particle oriented, low porous plate. The solution was then collected for analysis from holes in
strain rate, shear surface. Therefore, a slow shearing rate is the loading platen. This modification of the ring shear apparatus
recommended to complete the formation of this feature correctly— produced some conclusive results, suggesting that this is an appropriate
commonly a rate of 0.048 degrees/min is used. method for assessing the sensitivity of the residual shear strength of a
2. The first load —for instance 2kg, equivalent to 52kN/m' is applied. soil to its pore solution composition. However, it should be noted that
Then by using the coarse adjustment, the cross arm is brought into testing times were increased by up to two or three days.
contact with the proving rings, so that both proving rings mutually meet The Bromhead ring shear apparatus has also been subject to a review
the cross arm simultaneously. by Stark & Vettel (1992) and Stark & Eid (1993).Both of these reviews are
3. Readings of settlement may be taken at 0, 1, 2, 4, 6, 10, 2030, 45 min and critical of the magnitude of wall friction that is developed along the
then at 15 min intervals, to monitor the process of consolidation. inner and outer circumferences of the confined specimen, and its
Frequency of readings is variable but should be sufficient to ensure that resultant effect on the drained residual strength measured by the
consolidation is complete. apparatus. The reviews state that the magnitude of wall friction
4. Once consolidation is complete, usually less than one hour after increases with the depth of the remoulded specimen, and thus the plane
applying the load, the machine is switched on and left rotating of least wall friction occurs at or near the soil/top porous stone
overnight. It maybe datalogged, or merely left to run. interface. Therefore, as the top porous stone settles into the specimen
Note: Taking up "slack" in the system may take a considerable time, container, the wall friction influencing the shear plane increases, which
which can result in a lag between starting the motor and readings being causes an increase in the measured residual strength.
recorded. Careful setting up reduces this lag significantly. Stark & Vettel (1992) proposed limiting the total settlement of the top
5. Readings are taken for 30 min on the following day. If constant porous stone to 0.75mm. This is accomplished by adding soil and then
readings are obtained, a constant torque has been obtained in the soil. reconsolidating the specimen such that settlement of the top platen is
This indicates that shear-induced pore water pressures, which cause less than 0.75mm during consolidation and drained shear. This process
changes in the shear strength of the soil, have dissipated and that a fully is time consuming and commonly results in 16 to 18 days of testing to
formed residual shear strength surface has been formed. obtain a drained residual failure envelope from four tests on clays of
6. The motor is then stopped, and the gauges observed for a further 15 moderate plasticity.
min. If the readings are found to drop substantially the shearing rate Stark & Eid (1993) refined the procedure of Stark & Vettel (1992) by
was too fast. The soil is therefore still strain rate sensitive, as a result proposing a new specimen container for the Bromhead ring shear
viscous inter particle drag forces preventing the formation of an ideal apparatus. This container allows a remoulded specimen to be
shear surface (Bromhead, 1992). In this case, it would be necessary to overconsolidated and pre-cut prior to shearing, limiting the amount of
repeat the shearing at a slower rate. settlement to significantly less than 0.75mm. The significant reduction
Note: This step may be omitted, with the sensitivity check being of settlement allows the performance of multistage tests that reduce the
carried out at the highest load stage. time required to measure a drained residual failure envelope to five or
six days.
3.3Subsequent load stages The optimal procedure recommended earlier is also a multi stage test.
1. The load is increased by a further nominal amount, eg 2 kg, on the This procedure however can not only be carried out within three
hanger and shearing re-commenced. It is not necessary to allow the working days, but also utilises the original specimen container. Overall,
sample to consolidate under the new load as pore pressure dissipation is wall friction has not been found to effect the drained residual shear
rapid and torque readings indicate whether there are excess pore strengths (tt'„> greatly. This has been confirmed from back analyses on
pressures present or not. slip surfaces, which has resulted in test values of tt', being within '/4 of a
2. Readings are taken at 0, 2, 4, 6, 10, 15, 20 min and at 5 min intervals until degree of the actual value (Bromhead 1992).
three readings the same are achieved (see typical test results shown in The ring shear apparatus has also been subject to a conversion into a
Fig 2). permeameter (Dewhurst et al, 1996). In this case the sample is sealed at
3. Optionally, the motor is stopped and readings taken at 1 min intervals the top by two pairs of 0 rings, and the apparatus is capable of being
for 5min. taken incrementally to much higher vertical effective stresses (over 10
4. Several more load stages are carried out by repeating steps 1 to 3, MN/m'). However, difficulties have arisen with this apparatus due to
finishing with a test on strain rate sensitivity. enhanced side friction caused by the 0 rings. This has resulted in a
5. At the end of the final load stage, the torque is released on the sample, curved shear surface, which has meant that the effect of the sheared
using the adjusters on the proving rings. portion of the sample on the overall permeability cannot be accurately
6. The sample is then unloaded to the first load stage and steps 2, 3 and 5 quantified.
repeated.
7. The sample is unloaded and the apparatus dismantled carefully. The 4.2Analysls of the failure envelope
shear surface formed in the sample can then be examined. Extensive research into the residual shear strength failure envelope has
been carried out by Hawkins & Privett (1985). They highlighted the
4.00verall teat cummutttu curved nature of the failure envelope, particularly at effective normal
stresses below 200kN/m'nd in soils with a high clay fraction. This
4.t Modified tost procedures results in higher values of tt', at low normal stresses. It was also found
Steward & Cripps (1983)modified the Bromhead ring shear apparatus so that as the effective normal stress increases the failure envelope
that the composition of pore solutions could be altered during shearing. becomes straighter and the residual friction coefficient approaches a
This was to determine if the residual shear strength of the soil was constant value (see Fig 3).
found to be sensitive to different pore solutions. Brass nipples were In Fig 3, the failure envelope has a straight line section which denotes
connected to the lower plate drainage channels so as to allow the pore the lowest residual shear strength. This was redefined by Hawkins &
solution to be introduced into the system. Sealing screws were then McDonald (1992) as the ultimate residual shear angle, tt'<~tr They also
placed in the side exit holes and a rubber gasket placed beneath the suggested that the value of 4', should always be accompanied by the

GROUND ENGINEERING JULY 1997


particularly when:
Complete failure envelope ') There
i) i a strong element of beddin g cont
re is o ro o locatlonof th I
jvi
$ Lowest residual strength
an ysis is not undul y affected by uncertaint'es in pore
)Ig pressure, end-effect,s,e t c..
er test p roc edures were also examined '

Constant valve
id 1993 dSt
3 hh
d&C 1983), but for ro
proce ure is recommended.
K'ipps, 'esidual

References
Kf
I- Bishop, AW, G,,
Green, GE, arga, VK,, Andersen,
An A and Brown, JD I
app ication io the measurem en I of residual strength," Geotechnique, n,"
ensign I sation
o.
uer
Bromhead, EN,(1979) "ASim s," Grou
impleI Ring Shear Apparatus," round Engineering, Vol.12, No.5,
lo>
\
e d se"
Bromhead, EN, (1992) "The Stabili o % ie ca emic & Professional, 2nd
dr Gl
GuN'O

o'e appropriate for e'„appropriate for ve normal


Effective no I '
BS 1377, (1990) "Soils foor Civil Engineering rength Tests (Total
shallower slide d caper slide t'iu '
ss)," British Standards In stiiution, Part 7, pp16-19.

R8we 3:Cawpfefe reshlual shearr


'f888).
shen8lh fallwe nnagfepe(affw Handdnsaprfvelt Dewhursi, DN, Clenn ll,
co ductivityof sh ared I
MB,, ', .,
KM
o
) "Fabric and
No. 4, pp 761-768.
hydraul'ia,"
lc

McDonald, C, (1992 "


'

associatedvalu ue of effective normal stress a'„.


Hawkins,
d tlo
AB &
'ull
residual
'arihCIClay,"Geot hni u,Vob42,N o. 3, pp 453-464. .,
"
KD,,(1985)"

'I
Hawkins, AB & Priveti, ent and s ren of
5.0 Conduslon "GroundEngine id Vo.
I I8,No.s,pp22-29.
The BS 1377 ring shear test roc
es procedur s been sh
g. o the Hvorslev, MJ, (1939) "Torsion shear les
h f il" M Vol

hni dfo th fo Eid, HT (1993) "Modified B pparaius," Geotechnical


'stage Anewprocedureisthere ear T
'
al Vol Noo.l, March 1993, pp 100-107.

drain
ocd
de Io
'd
h b
m i-stage test and r
residual shear str engt h within th
m operation'
at Km s
tofth Bomb d g ear apparatus. It has been found to
Stark, TD & Veitel, JJ (1992)"
"BromheadRingShe
el VI N M h 992 pp 24-32.

Steward, HE & Cripps, JC (1983) "Some en in


c, otechnical

'c is c ose to that obtained from b ack analyses, of iti hal " Q J Geol Lo do Vol 16

1 1 ~ I I :8 I ~ i= ~ I="
'' ~-
I I
Ik ~ ivi ~ 44 ~ ~ ~

'UIM
P ile Driving Analyzer
Measures...
~ Hammer Performance
P ~ Driving St
~ Pile Inte g r'ity ~ Bearing Capacity
The PDA economicall y testste many piles for 'ca

and is in use on
ce, an
im proved quality assurance Pile Integrity Tester™
94, measuring
force and velocity Use a hand-held hammer to inves-
wit that are
sensors uickl tigate pile shafts for major
easily attached too d riven piles or drilled defects. The battery-powered
s a . ThePDAroutinelycom utesth PIT has an easy-to-use touch
bearing capaci, rrep laacing expensive static ',
screen for data entry and data
'
esting, and rovides display. Optionally, the PITWAP
d' tr a ndh ammer performance. software estimates pile shape.
Integrity,

Other products from PDI include: SPT Anal y zer too check energy transfer and
Angle Analyzer to accurately measure incl'" 'pd""'p
or ers to automaticauy d~c~m~~t d n nd CFA Pile insta
p'iving
by impact or vibrato iy h

/+//
~
c y record blow count an iesel hammer
and diesel etecuon
n detection
stroke using sound
..
~ ham

>I:nl1:I= ~ ei «e
-.<a«~Wl:svrmenalHm . j
~ rfP- Ifa ''I ' I'u 7 7 i%i, .- e4 ':%1 r'. I:e
IiJrh ~irI 'ie)Ll
a 1 isu „,
~
I

~I tmot <
~ I

.. n:seen ll |lf
~ ~ r~a r2 41 ~ ~ I I
Iw: ~ irw e. im. ~ V 9 ~~S nae
e > n o ~ ma ~ ~
:>etswaam va %'de w - s sun "= ecru

28 E Reader Enquiry No. 14 GROUND ENGINEERING JULY 1997


I (

You might also like