Professional Documents
Culture Documents
Earned Value Management
Earned Value Management
Contains Math
Formulae
A knowledge technology
company
Where knowledge is
cultivated
Give a try!
2 weeks into the project, you have spent $55,000 and completed 4 miles
of sidewalk, and you want to report performance and determine how
much time and cost remain.
Actual % Complete = 4/20 = 20% (we have completed 4 miles of the 20 mile
project)
A positive CV is good, it indicates that we are doing better on costs than we have planned. Conversely
a negative CV indicates costs overrun.
© 2012 DaySpring Limited
+ You are the project manager for the construction of 20 miles of sidewalk. According to your plan, the
cost of construction will be $15,000 per mile and will take 8 weeks to complete. 2 weeks into the
project, you have spent $55,000 and completed 4 miles of sidewalk, and you want to report
performance and determine how much time and cost remain.
Remember
A positive SV is good, it indicates that the project is ahead of schedule. Conversely a negative SV
indicates we are not performing well as we had planned in terms of schedule That is project is behind
the planned schedule.
Remember
Remember
Greater = better
+ You are the project manager for the construction of 20 miles of sidewalk. According to your plan, the
cost of construction will be $15,000 per mile and will take 8 weeks to complete. 2 weeks into the
project, you have spent $55,000 and completed 4 miles of sidewalk, and you want to report
performance and determine how much time and cost remain.