ID Task Task Name Duration Start Finish August 2020 September 2020 October 2020 November 2020 December

September 2020 October 2020 November 2020 December 2020 January 2021
Mode 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7
1 PLANNING PHASE 16.5 days? Tue 9/8/20 Wed 9/23/20
2 make guest list 3 days Tue 9/8/20 Thu 9/10/20
3 create invites 3 wks? Tue 9/8/20 Mon 9/21/20
4 proofreed invites 3 days Sun 9/20/20 Tue 9/22/20
5 mail invites 4 hrs Wed 9/23/20 Wed 9/23/20
6 SHOPPING PHASE 3 days Sun 12/20/20 Wed 12/23/20
7 buy food and drink 0.5 days Tue 12/22/20 Wed 12/23/20
8 buy decorations 3 days Sun 12/20/20 Wed 12/23/20
9 PARTY PHASE 0.38 days Wed 12/23/20 Wed 12/23/20
10 Greet guests 2 hrs Wed 12/23/20 Wed 12/23/20
11 have fun 4 hrs Wed 12/23/20 Wed 12/23/20
12 party over 0 hrs Wed 12/23/20 Wed 12/23/20 12/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Test_Project1
Summary Manual Summary Rollup Progress
Date: Wed 9/9/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 20
7 12 17 22 27 1 6 11 16 21 26 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8

12/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Test_Project1
Summary Manual Summary Rollup Progress
Date: Wed 9/9/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2