ZTC-DR-Dike 18 - 169 (22-09-2020)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Dike 18 - Raising 2019 works Ch. 6+900 to Ch. Weather Report No.

169
8+300 and Ch. 9+250 to Ch. 10+750 7 am - 11 am - 3 pm -
Time Date 22-Sep-2020 Tuesday
Employer : Arab Potash Company 11 am 3 pm 7 pm
Consultant : Royal Haskoning DHV Temperature 34°C 38°C 36°C Shift Day ✓ Night x
Contractor : ZTC Weather
Sunny Temperature min: 34°C max: 38°C
Condition
Description No. Description No. On site Borrow area
Project Manager 1 Cook 0 work
work
Description No. ing Description No. ing
Construction Manager 1 Site Engineer (Aces) 1
QS/Planning Engineer 1 lab technician 1 Generators 1 ✓ Generators 0
Admin & logistic Manager 1 Office Engineer 1 Vibrators 0 Vibrators 0
A. Labor force

Doc. Controller 1 Geologists / Engineers 0 Dozers 0 Excavators 0

B. Equipment
H.S.E Manager 1 Helper 0 Excavators 0 Excavators 0
Surveyor 1 Drillers 0 Loaders 0 Loaders 0
Surveyor Assistance 0 Screening Plants 0 Screening Plants 0
Site Forman 1 Graders 0 Graders 0
Accountant 1 Trucks 0 Trucks 0
QA/QC / Geo. Engineer 1 Mobile Cranes 0 Mobile Cranes 0
Supervisor 0 Compactor 0 Compactor 0
Drivers 0 Lowbed 0 Lowbed 0
Operators 0 Drilling Rigs 0 Drilling Rigs 0
Flagman 0
Workers 0 0
Total man power = 13 Total man hours = 117
Executed Works / Performance:
No. Description UoM Remarks
C. Executed works

---- --------- ---- ----


SL. Job Description Daily Trips Total Trips Unit Daily Quantity Cumulative Quantity
1
2
3

Constraints / Delays
/ Incidents

Unplanned Events /
Add. Works /
Instructions

Qty Description Remarks Name / Surname


Material

Visitors
E. Site
D.

Stoppage of all work activities due to the announced lockdown isolation of Ghour Assafi
H. Engineer Representative Note

Which resulted in droppage of staff and stoppage of activity


Contractor Note

Contractor: ZTC Consultant : Royal Haskoning DHV

Date / Signature Date / Signature