CONNEUXUS

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Total Float 2020 2021
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Dike 18 Raising works 2019 307 10-Mar-20 A 03-Apr-21 10-Mar-20 03-Apr-21 -1

Key Dates 307 10-Mar-20 A 03-Apr-21 10-Mar-20 03-Apr-21 -1


1 Contractual Commencement Date 0 10-Mar-20 A 10-Mar-20 Contractual Commencement Date, 10-Mar-20 A
2 Contractual Completion Date 0 03-Apr-21 03-Apr-21 -1 Contractual Comp
Submittals 307 10-Mar-20 A 03-Apr-21 10-Mar-20 03-Apr-21 -1
3 Earthwork Method Statement Preparation - Submission 7 10-Mar-20 A 23-Mar-20 A 10-Mar-20 17-Mar-20
4 Topography and Surveying works Preparation - Submission 7 10-Mar-20 A 18-May-20 A 10-Mar-20 17-Mar-20
5 Approval for Borrow area Location 1 10-Mar-20 A 10-Mar-20 A 10-Mar-20 10-Mar-20
6 Submitting Borrow Area Stockpiles Testing Results 2 10-Mar-20 A 12-Mar-20 A 10-Mar-20 12-Mar-20
7 Topography and Surveying Works Approval 0 18-May-20 A 21-May-20 A 14-May-20 14-May-20
8 Workshop Drawing Preparation - Submission 7 20-May-20 A 07-Jul-20 A 14-May-20 27-May-20
9 Workshop Drawings Approval 0 21-May-20 A 23-Jul-20 A 13-Jun-20 13-Jun-20
10 Instruments Submittals 28 06-Jun-20 A 11-Jul-20 A 15-Jun-20 15-Jul-20
11 Preparation and submission of Final As-built Documentation 3 16-Mar-21 20-Mar-21 15-Mar-21 17-Mar-21 -1 16-Mar-21 20-Mar-21
12 Approval of Final As-built By Engineer 0 03-Apr-21 03-Apr-21 03-Apr-21 03-Apr-21 -1 03-Apr-21 03-Apr-21
Site Preparation 31 10-Mar-20 A 30-May-20 A 10-Mar-20 01-Apr-21
13 Maintenance For Access Roads and providing entrance to the site
0 10-Mar-20 A 10-Mar-20 Maintenance For Access Roads and providing entrance to the site, 10-Mar-20 A
14 Mobilization Works 28 14-Mar-20 A 30-May-20 A 14-Mar-20 31-May-20
15 Borrow areas & Stockpile preparartion 0 14-Mar-20 A 14-Mar-20 Borrow areas & Stockpile preparartion, 14-Mar-20 A
16 Sampling and testing of borrow areas material 0 14-Mar-20 A 14-Mar-20 Sampling and testing of borrow areas material, 14-Mar-20 A
Earthworks 282 26-Apr-20 A 16-Mar-21 26-Apr-20 15-Mar-21 16
Stretch Ch. 9+250 to Ch.10+500 178 26-Apr-20 A 22-Nov-20 26-Apr-20 21-Nov-20 -1
Stretch 9+250 to 10+500 (Excavation) 61 26-Apr-20 A 28-Jun-20 A 26-Apr-20 12-Jul-20
17 Excavating Zone 6 material at upstream slope 13 26-Apr-20 A 07-May-20 A 26-Apr-20 13-May-20
Ch. 10+270 to Ch. 10+500 34 09-May-20 A 02-Jun-20 A 13-May-20 27-Jun-20
18 Excavating and stockpiling of Zone 3 material and Salt crust break
7 up ,clean
09-May-20
& scarify
A 11-May-20 A 13-May-20 27-May-20
19 Excavating and stockpiling Zone 4 & Zone 1B materail 6 01-Jun-20 A 02-Jun-20 A 20-Jun-20 27-Jun-20
Ch. 10+000 to Ch. 10+270 33 11-May-20 A 10-Jun-20 A 27-May-20 02-Jul-20
21 Excavating and stockpiling of Zone 3 material and Salt crust break
9 up ,clean
11-May-20
& scarify
A 18-May-20 A 27-May-20 07-Jun-20
22 Excavating and stockpiling Zone 4 & Zone 1B materail 6 03-Jun-20 A 10-Jun-20 A 27-Jun-20 02-Jul-20
Ch. 9+250 to Ch. 10+000 32 25-May-20 A 28-Jun-20 A 07-Jun-20 12-Jul-20
24 Excavating and stockpiling of Zone 3 material and Salt crust break
12 up ,clean
25-May-20
& scarify
A 31-May-20 A 07-Jun-20 20-Jun-20
25 Excavating and stockpiling Zone 4 & Zone 1B materail 8 17-Jun-20 A 28-Jun-20 A 02-Jul-20 12-Jul-20
Stretch 9+250 to 10+500 (Filling) 158 09-May-20 A 22-Nov-20 27-May-20 21-Nov-20 -1
Ch. 10+270 to Ch. 10+500 140 09-May-20 A 02-Nov-20 27-May-20 01-Nov-20 4
27 Filling Zone 1B Material at upstream slope side 9 09-May-20 A 02-Jun-20 A 27-May-20 07-Jun-20
28 Filling Zone 1B Material (Full width ) on crest 8 03-Jun-20 A 27-Jul-20 A 18-Jul-20 27-Jul-20
29 Trimming of Zone 1B slope and Filling Zone 3 material underneath
9 Zone29-Aug-20
6 MaterialA 16-Sep-20 19-Aug-20 30-Aug-20 -1 29-Aug-20 A 16-Sep-20
31 Filling Zone 6 8 03-Oct-20 11-Oct-20 03-Oct-20 11-Oct-20 -1 03-Oct-20 11-Oct-20
32 Trimming of Zone 1B and Filling of Zone 3 at down stream side
10 13-Oct-20 25-Oct-20 13-Oct-20 24-Oct-20 -1 13-Oct-20 25-Oct-20
33 Filling Zone 4 material in new widened dike... 7 25-Oct-20 02-Nov-20 24-Oct-20 01-Nov-20 4
Ch. 10+000 to Ch. 10+270 138 25-May-20 A 09-Nov-20 07-Jun-20 09-Nov-20 4
34 Filling Zone 1B Material at upstream slope side 8 25-May-20 A 14-Jun-20 A 07-Jun-20 15-Jun-20
35 Filling Zone 1B Material (Full width ) on crest 8 14-Jun-20 A 27-Jul-20 A 27-Jul-20 09-Aug-20

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 3 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
 
CONNEUXUS

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Total Float 2020 2021
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
36 Trimming of Zone 1B slope and Filling Zone 3 material underneath
6 Zone 16-Sep-20
6 Material 22-Sep-20 30-Aug-20 06-Sep-20 -1 16-Sep-20 22-Sep-20
38 Filling Zone 6 5 11-Oct-20 17-Oct-20 11-Oct-20 17-Oct-20 -1 11-Oct-20 17-Oct-20
39 Trimming of Zone 1B and Filling of Zone 3 at down stream side
9 25-Oct-20 04-Nov-20 24-Oct-20 03-Nov-20 -1 25-Oct-20 04-Nov-20
40 Filling Zone 4 material in new widened dike... 7 02-Nov-20 09-Nov-20 02-Nov-20 09-Nov-20 4
Ch. 9+250 to Ch. 10+000 137 31-May-20 A 22-Nov-20 20-Jun-20 21-Nov-20 -1
41 Filling Zone 1B Material at upstream slope side 10 31-May-20 A 08-Jul-20 A 20-Jun-20 30-Jun-20
42 Filling Zone 1B Material (Full width ) on crest 10 08-Jul-20 A 22-Aug-20 A 09-Aug-20 19-Aug-20
43 Trimming of Zone 1B slope and Filling Zone 3 material underneath
9 Zone 22-Sep-20
6 Material 03-Oct-20 06-Sep-20 15-Sep-20 -1 22-Sep-20 03-Oct-20
45 Filling Zone 6 7 17-Oct-20 25-Oct-20 17-Oct-20 24-Oct-20 -1 17-Oct-20 25-Oct-20
46 Trimming of Zone 1B and Filling of Zone 3 at down stream side
10 04-Nov-20 15-Nov-20 03-Nov-20 15-Nov-20 -1 04-Nov-20 15-Nov-20
47 Filling Zone 4 material in new widened dike... 6 15-Nov-20 22-Nov-20 15-Nov-20 21-Nov-20 -1 15-Nov-20 22-Nov-20
Stretch 7+000 to 8+300 221 01-Jun-20 A 16-Mar-21 12-Jul-20 15-Mar-21 16
Stretch 7+000 to 8+300 (Excavation) 80 01-Jun-20 A 11-Oct-20 12-Jul-20 29-Sep-20 74
Stretch 7+000 to 7+650 69 01-Jun-20 A 29-Sep-20 12-Jul-20 29-Aug-20 62
48 Excavating Zone 6 material at upstream slope 8 01-Jun-20 A 02-Jun-20 A 12-Jul-20 20-Jul-20
49 Excavation and stockpiling Zone 3 material on slope at upstream
8 and salt
03-Jun-20
crust scarifying
A 06-Aug-20 A 26-Jul-20 08-Aug-20
50 Excavating and stockpiling Zone 4 & Zone 1b materail 7 25-Aug-20 A 21-Sep-20 12-Aug-20 22-Aug-20 62
51 Scraping and mixing on crest of Dike 7 21-Sep-20 29-Sep-20 22-Aug-20 29-Aug-20 62
Stretch 7+650 to 7+850 65 02-Jun-20 A 04-Oct-20 20-Jul-20 02-Sep-20 74
52 Excavating Zone 6 material at upstream slope 5 02-Jun-20 A 04-Jun-20 A 20-Jul-20 26-Jul-20
53 Excavation and stockpiling Zone 3 material on slope at upstream
5 and salt
07-Jun-20
crust scarifying
A 20-Jun-20 A 08-Aug-20 12-Aug-20
54 Excavating and stockpiling Zone 4 & Zone 1b materail 4 22-Aug-20 A 25-Aug-20 A 22-Aug-20 25-Aug-20
55 Scraping and mixing on crest of Dike 4 29-Sep-20 04-Oct-20 29-Aug-20 02-Sep-20 74
Stretch 7+850to 8+300 32 26-Aug-20 A 11-Oct-20 14-Sep-20 29-Sep-20 74
58 Excavating and stockpiling Zone 4 & Zone 1B materail 7 26-Aug-20 A 01-Sep-20 A 14-Sep-20 22-Sep-20
92 Removing Z3 material from downstream slope toe 3 21-Sep-20 24-Sep-20 82
59 Scraping and mixing on crest of Dike 7 04-Oct-20 11-Oct-20 22-Sep-20 29-Sep-20 74
Stretch 7+000 to 8+300 (Filling) 181 23-Jun-20 A 16-Mar-21 29-Aug-20 15-Mar-21 16
Stretch 7+000 to 7+650 120 28-Jun-20 A 07-Jan-21 29-Aug-20 06-Jan-21 50
60 Trail section and Filling Zone 1B Material on the crust & up stream
29 slope
28-Jun-20
side A 27-Oct-20 29-Aug-20 29-Sep-20 62
61 Trimming of zone 1b and Filling Zone 3 material underneath Zone
19 6 Material
27-Oct-20 17-Nov-20 29-Sep-20 20-Oct-20 68
63 Filling Zone 3 material on Downstream slope to top of existing40
crest 14-Nov-20 28-Dec-20 14-Nov-20 27-Dec-20 -1 14-Nov-20 28-Dec-20
64 Filling Zone 6 - Rip Rap material 3 03-Dec-20 07-Dec-20 14-Nov-20 17-Nov-20 68
65 Filling Zone 4 material in new widened dike 10 28-Dec-20 07-Jan-21 27-Dec-20 06-Jan-21 50
Stretch 7+650 to 7+850 98 23-Jun-20 A 19-Jan-21 03-Oct-20 18-Jan-21 44
66 Filling Zone 1B Material on the crust & up stream slope side 6 23-Jun-20 A 02-Nov-20 03-Oct-20 10-Oct-20 62
67 Trimming and Filling Zone 3 material underneath Zone 6 Material
8 17-Nov-20 26-Nov-20 20-Oct-20 31-Oct-20 68
69 Filling Zone 6 - Rip Rap material 2 07-Dec-20 09-Dec-20 17-Nov-20 18-Nov-20 76
70 Filling Zone 3 material on Downstream slope to top of existing20
crest 28-Dec-20 19-Jan-21 27-Dec-20 18-Jan-21 -1 28-Dec-20 19-Jan-21
71 Filling Zone 4 material in new widened dike... 4 07-Jan-21 12-Jan-21 06-Jan-21 11-Jan-21 50
Stretch 7+850 to 8+300 122 31-Aug-20 A 16-Mar-21 10-Oct-20 15-Mar-21 16
76 Filling Zone 1B Material on the crust 19 31-Aug-20 A 24-Jan-21 26-Dec-20 16-Jan-21 62
72 Filling of Zone 1B material on the berm ( Ch. 7+850 to Ch. 8+200
60 ) 02-Nov-20 06-Jan-21 10-Oct-20 15-Dec-20 62
73 Trimming and Filling Zone 3 material underneath Zone 6 Material
7 (Extend
26-Nov-20
of the existing)03-Dec-20 31-Oct-20 07-Nov-20 68
74 Filling Zone 6 - Rip Rap material (Extend of the existing ) 4 09-Dec-20 14-Dec-20 18-Nov-20 23-Nov-20 76

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 3 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
 
CONNEUXUS

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Total Float 2020 2021
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
75 Filling Zone 3 material on berm (berm at Ch. 7+850 to 8+200) 9 06-Jan-21 17-Jan-21 15-Dec-20 26-Dec-20 62
77 Filling Zone 3 material on Downstream slope to top of existing45
crest 19-Jan-21 09-Mar-21 18-Jan-21 08-Mar-21 -1 19-Jan-21 09-Mar-21
78 Filling Zone 4 material in new widened dike... 6 09-Mar-21 16-Mar-21 08-Mar-21 15-Mar-21 -1 09-Mar-21 16-Mar-21
Instrumentation and Monitoring 133 10-Mar-20 A 13-Oct-20 10-Mar-20 01-Apr-21 155
79 Instrumentation Monitoring 0 10-Mar-20 A 10-Mar-20 Instrumentation Monitoring, 10-Mar-20 A
80 Handing over of the existing instrumentation to Contractor 4 15-Mar-20 A 26-Apr-20 A 15-Mar-20 26-Apr-20
81 Settlement Beacons Installation (10+270 to 10+500 ) 1 15-Jun-20 A 15-Jun-20 A 01-Jul-20 02-Jul-20
82 Settlement Beacons Installation (10+000 to 10+270 ) 1 22-Jun-20 A 22-Jun-20 A 08-Jul-20 09-Jul-20
83 Settlement Beacons Installation (9+250 to 10+000) 1 28-Jun-20 A 28-Jun-20 A 18-Jul-20 18-Jul-20
84 Settlement Beacons Installation (7+000 to 8+300) 3 26-Aug-20 A 13-Oct-20 29-Sep-20 03-Oct-20 74
Cone Penetration Testing 43 15-Sep-20 02-Nov-20 01-Sep-20 18-Oct-20 138
85 Mobilization of CPT Machine & Regular Rig. 4 15-Sep-20* 19-Sep-20 01-Sep-20 05-Sep-20 138
86 Pre-drilling of Dike body by using regular rig 16 19-Sep-20 06-Oct-20 05-Sep-20 22-Sep-20 138
87 Cone Penetration test (CPT) with the dissipation test 14 19-Sep-20 04-Oct-20 05-Sep-20 20-Sep-20 140
88 CPT Logs & Dissipation Results 14 07-Oct-20 24-Oct-20 23-Sep-20 10-Oct-20 138
89 Factual Report 8 24-Oct-20 02-Nov-20 10-Oct-20 18-Oct-20 138
Start of Demobilization 10 16-Mar-21 27-Mar-21 15-Mar-21 25-Mar-21 6
90 Demobilization 10 16-Mar-21 27-Mar-21 15-Mar-21 25-Mar-21 6
Handing over 0 03-Apr-21 03-Apr-21 03-Apr-21 03-Apr-21 -1
91 Project handing over 0 03-Apr-21 03-Apr-21 03-Apr-21 03-Apr-21 -1 03-Apr-21 03-Apr-21

Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 3 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation