Professional Documents
Culture Documents
Bab 4 Betul
Bab 4 Betul
REFLOW PROCESS
4.1 Introduction
Reflow process is a process to melt the solder and heat the adjoining
the conventional reflow soldering process, there are usually four stages,
called “zones”, which are preheat, thermal soak, reflow and cooling.
i. Reflow machine
40
4.2.1 PYRAMAX 100N reflow oven
41
4.2.2 Reflow oven
i. Put the PCB board on the reflow jig in the correct position.
iii. Make sure the correct profiled is used for each different model.
42
4.4.1 Type of working process
how fast the temperature on the printed circuit board changes. The
between 1.0 oC and 3.0 oCper second, often falling between 2.0 oC
and 3.0 oC per second. If the rate exceeds the maximum slope,
incomplete.
43
4.4.2 Thermal soak zone
The third section is also referred as the “time above reflow “ and is
44
4.4.4 Cooling zone
ignored. It may be that the ramp rate is less critical above certain
usually with larger ovens, some of edge conveyor system, often with a
conveyor, for example, has pins protruding from the sides of the chain to
provides an edge support that carries the board through the reflow system
conveyor has lateral warpage of greater than this amount, the product will
46
CHAPTER 5
SYRINGE MEASUREMENT
5.1 Introduction
Frequency of this monitoring is two times every day for three weeks at all 3
47
5.2.1 Infrared thermometer
48
5.2.2 Empty syringe
ii. Use the empty syringe to measure the solder level (put the empty
iv. Explanation are given from trainer how to measure the solder.
i. Measurement taken must be the 2nd board and above after the machine
49
iv. Measure the solder then followed by speed and pressure.
v. Measure at three points, above piston, ½ inch below piston and 1 inch
50
5.4.2 ½ inch below piston
51
Is the laser pointer of the infrared thermometer.
CHAPTER 6
6.1 Introduction
52
4 5
1
6
Machine Parts
1. Input elevator loading table
2. Left epoxy controller
3. Right epoxy controller
4. Monitor
5. Output elevator loading table
6. Mouse controller
7. Keyboard
8. EMO
All metal can board direction. Board two holes and undercut
53
Figure 6.3.1.1
Dispenser operation :
iii. Put magazine on the Input elevator, ensure PCB in bottom area
of magazine.
alignment.
54
vi. Learn Z for dispense solder. Access to set up – Process set up
vii. Back to main table and confirm that Output elevator buttons
Wafer PR, confirm that hole location on top if can have hole.
Up-look PR, confirm that hole location on top if can have hole.
Post bond PR, confirm that image created without solder and position
of the PCB.
Map” bottom.
Select left three column and right three column to enable, then run
the machine.
55
100% inspection under minimum 10x microscope, no rotation, ring is
6.4.1.1
Procedures) required.
idle 6 hours.
change.
56
v. Dispensing adaptor must be changed after needle
removal by operator.
6.4.4 Solder
ii. Collect rest can in bowl and pack them in the bag
57
6.4.5.1 Metal can track
ii. Once needle clog / needle broken / needle scratch PCB or find
58
CHAPTER 7
7.1 INTRODUCTION
Sisonic microphone is in batch process, a batch of ten PCB board and one
59
i. FR4 Strip Attach
Before After
Plasma clean the wire bond PCB pad to remove any possible
Before After
60
iii. Die Bond
Die mount IC, MEMS. Place and attach the IC and MEMS onto the PCB.
Before After
iv. Curing
61
Oven
v. Wire Bond
Attach and bond the wires from MEMS to IC and to PCB pad per the wire
vi. Encapsulate
62
Encapsulation process Before After
vii. Curing
Oven
63
Solder dispense process Before After
x. Reflow solder
64
Reflow machine Before After
Mount the tape on the PCB to secure the units during the dicing process
65
Tape mount process Before After
xiii. Dice
xiv. UV Cure
66
UV cure process Before After
xvi. Tape-n-reel
67
Tape-n-reel machine Before After
xvii. Warehouse
68
CHAPTER 8
CONCLUSION
8.1 Conclusion
Working with Knowles Electronic (M) Sdn. Bhd. is one of opportunity to learned
For a four and half months training period, a new knowledge were exposed. For
example, even from mechatronic course, student also can learn the system in the
production where the function of each machines and how it is work. To gain the
technician and engineer, new things were gain. With helping from other engineer
also can help in working. Getting information, collecting data and analysis the
data is one of routine task since internship period started. With own effort,
and technician) needs to be applied. In this company, mostly they used English as
applied still the same. The Knowles Company also applied Lean manufacturing
system.
69
CHAPTER 9
9.1 Suggestion
need to extend internship period at least six months. It is because for that period,
more tasks can be given and can study more about machines. For the tasks
given, it is success made student understood about the works. Even not fully
enough the whole process was understood, but at least tasks given is success
finished.
70