Scope of Works SG Lolo
Scope of Works SG Lolo
1. INTRODUCTION
The Employer, Pengurusan Air Selangor Sdn. Bhd has identified such
areas and plan to improve the distribution system progressively to provide
reliable and continuous supply in its supply areas. Particular areas
identified for this project is in Sg Lolo and Sg Pangsoon WTP supply
areas.
2. SCOPE OF WORKS
(a) Laying a new 300mm Ductile Iron (DI) pipe of about 8.5km from
Sg Lolo towards Batu 18 junction.
(b) Laying 150mm by-pass pipe between suction tank inlet and pump
house outlet.
(c) To demolish existing Sg Lui Elevated Water Tank (EWT) and to
construct new R.C Elevated Water Tank.
(d) Laying a new 225mm & 315mm OD HDPE pipe from the EWT
approximately 3.2km towards Paya Lebar.
The works under this Contract shall comprise the construction and
completion of the following works :-
a) To collect from Pengurusan Air Selangor Sdn Bhd and lay 300mm
diameter Ductile Iron pipes and 315mm & 225mm High Density
Polyethylene (HDPE) pipe.
1
b) Supply and lay 200mm and 300mm diameter mild steel pipes for
interconnection and over-ground pipe-works.
c) Supply and lay mild steel, ductile iron, and HDPE pipe specials
including tees, bends, mechanical couplings, flange adaptors, etc.
g) To replace the existing meter stand with a new stainless steel type
meter stand and to be located outside of house area or at the
boundary of the land.
j) To obtain work permit from the relevant road authorities before start
of works.
l) Any additional works not detailed here but necessary for the
completion of the Works as may be ordered by the Employer or the
C.A. in accordance with the terms of the Contract.
All works shall be carried out in good engineering practice, adhering to the
Employers guidelines on health, safety and environment, and in
accordance with the conditions of contract, construction drawings and
specification.
2
3. DRAWINGS
These drawings are intended to assist the Tenderer in preparing his tender
but may be subsequently altered in detail to suit the site layout. The
alignment, levels and dimensions of the existing works shown on the
drawings are approximate only.
The C.A.’s Consulting Engineer shall carry out design and provide
construction drawings for the plan and longitudinal section of the pipeline.
The Contractor shall however will still need to carry out piloting to
determine the most suitable pipeline route and submit the proposal to the
C.A. for approval. Details and requirements given in the construction
drawings which may differ from the tender drawings shall not be
considered as additional work nor variation and shall not be a basis for
application of additional time and cost.
3
Each drawings shall give the following particulars in a title block at the right
side of the drawing in accordance with Pengurusan Air Selangor Sdn Bhd
standard title block and subject to the approval of the C.A.:
All notes and legends on drawings shall be in English, and all dimensions
shown in metric units of measurement.
The notice of the C.A.’s approval of any drawings will only signify his
general approval of the design and shall not make him liable for any error
of the Contractor in detail or lack of strength or efficiency of any part.