Download as pdf or txt
Download as pdf or txt
You are on page 1of 41

CEME 352 ENGINEERING MANAGEMENT II

(LECTURE SERIES 2)

TOPIC: Earned Value Management (EVM)

Lecturer: Mr. Herod Malo


School of Engineering (Civil)
Papua New Guinea University of Technology
Reference:
Malo, H. “Total Quality Management(TQM)”. Papua New Guinea University of
Technology, August 07, 2020 Lecture.
BEng (Civil) Semester II

© 2020 School of Engineering (Civil), Papua New Guinea University of


Technology 0
Earned Value Management
What is it?
Where did it come from?
What’s so special about it?
How do you do it?

© 2020 School of Engineering (Civil), Papua New Guinea University of Technology


1
Earned Value Management

What is it ?
 A systematic approach to the integration and measurement of
 cost,
 schedule, and
 technical (scope) accomplishments on a project.

 Provides the ability to examine detailed


 schedule information, critical program and technical milestones,
and
 cost data.
© 2020 School of Engineering (Civil), Papua New Guinea University of Technology
2
Earned Value Management

Why do we care?
 Projects over budget and behind schedule*
 53% of IT projects finish over budget and behind schedule

 52% finish at 189% of their initial budget

 18% are simply never completed

 Statistically proven performance projections


 Performance at a project’s 25% completion point will remain steady
throughout the project’s lifecycle.

 Consistent performance measures allow comparison across the portfolio

© 2020 School of Engineering (Civil), Papua New Guinea University of Technology


3
Earned Value Management

What’s so special about it?


 Fundamental difference with traditional management is the data
used for analysis.
 Budget vs Actuals
 Earned Value Analysis

4
Earned Value Management

Traditional Management Approach:

2500000

2000000

1500000
Actuals Budget
$1,041,000
1000000 Actuals
Budget $1,000,000
500000

0
ov

ov
l

l
n

n
p

p
ay

ay
ar

ar
Ju

Ju
Ja

Ja
Se

Se
M

M
N

N
M

5
Earned Value Management

EVM Integrates cost, schedule, and scope.


Establishes an Integrated Project Baseline

 What is to be done? (scope)

 When will activities be completed? (schedule)

 What will it cost (and when) when to complete those


activities?

6
Earned Value Management

Based on something called Earned Value.


 A concept that task activities earn value as work progresses

 A data point that expresses the value of work accomplished

7
Earned Value

The concept that task activities “earn value” as work


progresses.

 The value earned is the budgeted cost of the activity


completed to date.

8
Earned Value

A data point that expresses the value of work


accomplished

 What is the dollar value of what you have done to date?


 Does not address the money spent in getting there.

9
Earned Value Management

So how do we do this stuff?


EVM depends on three data points
 Planned Value (PV)
 Earned Value (EV)
 Actual Cost (AC)

10
Integrated Project Baseline
Absolutely dependent on the Work Breakdown Structure

New Weather Radar

Antenna and Transmitter and Data Processing


Mechanical Receiver Systems Systems
Systems

 One WBS per program Computer


Hardware
Application
Software
Telecommunications
Systems

 Deliverable-oriented

 Organizational responsibility identified in WBS


 Work not in the WBS is out-of-scope

 All lower-level elements roll up to the WBS total

11
Integrated Project Baseline
Absolutely dependent on the Work Breakdown Structure

New Weather Radar

Antenna and Transmitter and Data Processing


Mechanical Receiver Systems Systems
Systems

Computer Application Telecommunications


Hardware Software Systems

Full (and accurate) definition is key


Defined deliverable(s)
Timeframe for delivery of product

Total cost (direct and indirect) to deliver product

Assigned organizational responsibility

12
Planned Value
Data source is the Integrated Project Baseline

How much did you expect to have done at point X ?


Expressed in dollars (PV)

How much do you expect to have done at completion ?


Budget at Completion (BAC)

13
Planned Value

$2,500,000

$2,000,000 BAC $2,000,000

$1,500,000
Planned Value
$1,000,000

$500,000

$0
l l
n pr Ju ct n pr Ju ct
Ja A O Ja A O

14
Planned Value

$2,500,000

$2,000,000 $2,000,000

$1,500,000
Planned Value
$1,000,000

$500,000
PV = $1,000,000

$0
May

May
Mar

Nov

Mar

Nov
Sep

Sep
Jan

Jan
Jul

Jul

15
Actual Cost
Data source is the Earned Value Management System

The dollar amount actually spent to date.

Has no relationship to work accomplished.

16
Actual Cost

$2,500,000
AC = $1,041,000
$2,000,000

$1,500,000
Planned Value
Actual Cost
$1,000,000

$500,000
PV = $1,000,000
$0
r

r
ct

ct
n

n
l

l
Ap

Ap
Ju

Ju
Ja

Ja
O

17
Earned Value
Data source is the Earned Value Management System

 The dollar value of actual accomplishments to date.

 Does not address the money spent in getting there.

18
Earned Value
Several ways to “earn” it:
Percent Completion Estimates

Start/Finish of WBS Elements


25% 75% 50% 50% 0% 100%

Milestones Completed (0-100%)

Percent Completion Estimate with Milestone Gates

33% 67% 100%

19
Earned Value

$2,500,000

$2,000,000 $2,000,000
PV = $1,000,000
$1,500,000
Planned Value
Earned Value
$1,000,000

$500,000
EV = $851,000

$0
May

May
Mar

Nov

Mar

Nov
Sep

Sep
Jan

Jan
Jul

Jul

20
Integrated Performance Report

 Compares the amount of work completed with what was


scheduled and budgeted, to determine if cost (AC), schedule
(PV), and work accomplished (EV) are progressing as planned.

 By integrating these three measurements, it provides


consistent, numerical indicators with which we can evaluate and
compare projects.

21
Integrated Performance Report

2,500,000

2,000,000
AC = $1,040,979
1,500,000 Planned Value
Actual Cost
1,000,000 Earned Value
PV = $1,000,000

500,000
EV = $851,000
0
May

May
Mar

Nov

Mar

Nov
Sep

Sep
Jan

Jan
Jul

Jul

22
Integrated Performance Report
These three data points allow us to:

 Calculate variances in cost and schedule performance.

 Calculate performance indices that allow direct comparison to other


projects’ performance.

 Analyze trends in project performance.

 Formulate predictions as to how well the project will perform in the


future.

23
Calculating Variances

Cost Variance
 A comparison of the budgeted cost of work performed with
actual cost.

 A negative variance means the project is over budget.


CV = EV – AC

CV = 851,000 – 1,041,000

CV = - $190,000

Note that this is not “budget vs actuals.”


24
Calculating Variances

Schedule Variance
 A comparison of amount of work performed to what was
scheduled to be performed.

 A negative variance means the project is behind schedule.


SV = EV – PV

SV = 851,000 – 1,000,000

SV = - $149,000

25
Calculating Performance Indices

 Cost Performance Index CPI = EV/AC

 A ratio of the budgeted cost of work performed to the actual cost.


CPI = EV / AC

CPI = 851,000 / 1,041,000

CPI = 0.817

An index less than 1.00 means the project is over budget.

26
Cost Performance
Cost Variance (EV-AC)
2,500,000 $851K - $1041K = -$190K
AC = $1,040,979 CPI (EV/AC) = 0.8175
PV = $1,000,000
2,000,000
EV = $851,000

1,500,000 Planned Value


Actual Cost
1,000,000 Earned Value

500,000

0
May

May
Mar

Nov

Mar

Nov
Jan

Jan
Jul
Sep

Jul
Sep

27
Calculating Performance Indices

 Schedule Performance Index SPI = EV/PV

 A ratio of the amount of work performed to what was scheduled


to be performed.

SPI = EV / PV

SPI = 851,000 / 1,000,000

SPI = 0.851

An index of less than 1.00 means the project is behind schedule.

28
Schedule Performance
Schedule Variance (EV-PV)
$851K - $1,000K = - $149K
2,500,000
PV = $1,000,000 SPI (EV/PV) = 0.851
AC = $1,040,979
2,000,000
EV = $851,000

1,500,000 Planned Value


Actual Cost
1,000,000 Earned Value

500,000 And look at this:


$ - 149K = 1 Month Slippage
0
Nov

Nov
Jan

Jan
Jul

Jul
Mar

Mar
Sep

Sep
May

May

29
Predicting Future Performance

Estimate to Complete (ETC)


 How much will we have to spend (after today) to complete?
 Total budget less what we’ve earned to date. (With some
assumptions).

 Performance to date has been anomalous


 Cost Performance to date will continue
 Both Cost and Schedule Performance to date will continue

30
Predicting Future Performance

Estimate to Complete (ETC)


 Performance to date has been anomalous:
ETC = BAC – EV = $1,149,000

31
Predicting Future Performance

Estimate to Complete (ETC)


 Performance to date has been anomalous:
ETC = BAC – EV = $1,149,000

 Cost Performance to date will continue:


ETC = BAC - EV = $1,405,504
CPI

32
Predicting Future Performance

Estimate to Complete (ETC)


 Performance to date has been anomalous:
ETC = BAC – EV = $1,149,000

 Cost Performance to date will continue:


ETC = BAC - EV = $1,405,504
CPI
 Both Cost and Schedule Performance to date will continue:
BAC - EV
ETC = CPI * SPI = $1,651,574

33
Predicting Future Performance

Estimate at Completion (EAC)

 How much will we have spent when we’re actually done?

 Again, based on the same assumptions as ETC.

EAC = AC + (BAC-EV) = $2,190,000

EAC = AC + BAC - EV = $2,446,505


CPI

EAC = AC + BAC - EV = $2,691,856


CPI * SPI

34
Predicting Future Performance

To-Complete Performance Index (TCPI)


 How well do we have to perform to get back on track?
 Again, based on the same assumptions as ETC.

1
TCPIC = = 1.22
CPI

1
TCPIS = = 1.17
SPI

1
TCPICS = = 1.437
CPI * SPI

35
Earned Value Management

On rare cases everything goes


perfectly as show on the graph:
2,500,000

2,000,000 $2,000,000

1,500,000 AC = $1,000,000
PV = $1,000,000
1,000,000 EV = $1,000,000 Planned Value
Actual Cost
500,000
Earned Value

0
n r l ct n r l ct
Ja Ap Ju O Ja Ap Ju O

36
Earned Value Management Systems

ANSI/EIA-748 defines it:

An EVMS is a set of business practices that, when applied to a


project or program:

 integrate scope, schedule, and cost objectives,


 establish a baseline plan for accomplishment of project
or program objectives, and

 employ earned value techniques for performance


management.

37
Earned Value Management Systems

ANSI/EIA-748 prescribes 32 criteria in five categories:

Organization

Planning, Scheduling, and Budgeting

Accounting Considerations

Analysis and Management Reports

Revisions and Data Maintenance

38
EVM In a Nutshell
 Management practices and discipline vs. a tool set
 Work Breakdown Structure (WBS)
 Integrated scope/schedule/budget baseline
 Accounting system that accommodates the WBS
 Change control plan WBS
Project
Schedule

Baseline Budget
Performance
Measurement

EVMS Early Warning


&
Performance Trends

Accounting
System

Informed Management
Decisions
Corrective Actions
Recovering Planning
39
What Could Possibly Go

 Inadequate requirements definition


 No (or Incomplete) Work Breakdown Structure
 Accounting systems that can’t address the WBS
 Lack of management attention to project progress
 Failure to respond to warning signs
 Failure to reconcile baseline to funding shortfalls
(Rebaseline)

40

You might also like