Professional Documents
Culture Documents
CE 352 Lecture 2 PDF
CE 352 Lecture 2 PDF
(LECTURE SERIES 2)
What is it ?
A systematic approach to the integration and measurement of
cost,
schedule, and
technical (scope) accomplishments on a project.
Why do we care?
Projects over budget and behind schedule*
53% of IT projects finish over budget and behind schedule
4
Earned Value Management
2500000
2000000
1500000
Actuals Budget
$1,041,000
1000000 Actuals
Budget $1,000,000
500000
0
ov
ov
l
l
n
n
p
p
ay
ay
ar
ar
Ju
Ju
Ja
Ja
Se
Se
M
M
N
N
M
5
Earned Value Management
6
Earned Value Management
7
Earned Value
8
Earned Value
9
Earned Value Management
10
Integrated Project Baseline
Absolutely dependent on the Work Breakdown Structure
Deliverable-oriented
11
Integrated Project Baseline
Absolutely dependent on the Work Breakdown Structure
12
Planned Value
Data source is the Integrated Project Baseline
13
Planned Value
$2,500,000
$1,500,000
Planned Value
$1,000,000
$500,000
$0
l l
n pr Ju ct n pr Ju ct
Ja A O Ja A O
14
Planned Value
$2,500,000
$2,000,000 $2,000,000
$1,500,000
Planned Value
$1,000,000
$500,000
PV = $1,000,000
$0
May
May
Mar
Nov
Mar
Nov
Sep
Sep
Jan
Jan
Jul
Jul
15
Actual Cost
Data source is the Earned Value Management System
16
Actual Cost
$2,500,000
AC = $1,041,000
$2,000,000
$1,500,000
Planned Value
Actual Cost
$1,000,000
$500,000
PV = $1,000,000
$0
r
r
ct
ct
n
n
l
l
Ap
Ap
Ju
Ju
Ja
Ja
O
17
Earned Value
Data source is the Earned Value Management System
18
Earned Value
Several ways to “earn” it:
Percent Completion Estimates
19
Earned Value
$2,500,000
$2,000,000 $2,000,000
PV = $1,000,000
$1,500,000
Planned Value
Earned Value
$1,000,000
$500,000
EV = $851,000
$0
May
May
Mar
Nov
Mar
Nov
Sep
Sep
Jan
Jan
Jul
Jul
20
Integrated Performance Report
21
Integrated Performance Report
2,500,000
2,000,000
AC = $1,040,979
1,500,000 Planned Value
Actual Cost
1,000,000 Earned Value
PV = $1,000,000
500,000
EV = $851,000
0
May
May
Mar
Nov
Mar
Nov
Sep
Sep
Jan
Jan
Jul
Jul
22
Integrated Performance Report
These three data points allow us to:
23
Calculating Variances
Cost Variance
A comparison of the budgeted cost of work performed with
actual cost.
CV = 851,000 – 1,041,000
CV = - $190,000
Schedule Variance
A comparison of amount of work performed to what was
scheduled to be performed.
SV = 851,000 – 1,000,000
SV = - $149,000
25
Calculating Performance Indices
CPI = 0.817
26
Cost Performance
Cost Variance (EV-AC)
2,500,000 $851K - $1041K = -$190K
AC = $1,040,979 CPI (EV/AC) = 0.8175
PV = $1,000,000
2,000,000
EV = $851,000
500,000
0
May
May
Mar
Nov
Mar
Nov
Jan
Jan
Jul
Sep
Jul
Sep
27
Calculating Performance Indices
SPI = EV / PV
SPI = 0.851
28
Schedule Performance
Schedule Variance (EV-PV)
$851K - $1,000K = - $149K
2,500,000
PV = $1,000,000 SPI (EV/PV) = 0.851
AC = $1,040,979
2,000,000
EV = $851,000
Nov
Jan
Jan
Jul
Jul
Mar
Mar
Sep
Sep
May
May
29
Predicting Future Performance
30
Predicting Future Performance
31
Predicting Future Performance
32
Predicting Future Performance
33
Predicting Future Performance
34
Predicting Future Performance
1
TCPIC = = 1.22
CPI
1
TCPIS = = 1.17
SPI
1
TCPICS = = 1.437
CPI * SPI
35
Earned Value Management
2,000,000 $2,000,000
1,500,000 AC = $1,000,000
PV = $1,000,000
1,000,000 EV = $1,000,000 Planned Value
Actual Cost
500,000
Earned Value
0
n r l ct n r l ct
Ja Ap Ju O Ja Ap Ju O
36
Earned Value Management Systems
37
Earned Value Management Systems
Organization
Accounting Considerations
38
EVM In a Nutshell
Management practices and discipline vs. a tool set
Work Breakdown Structure (WBS)
Integrated scope/schedule/budget baseline
Accounting system that accommodates the WBS
Change control plan WBS
Project
Schedule
Baseline Budget
Performance
Measurement
Accounting
System
Informed Management
Decisions
Corrective Actions
Recovering Planning
39
What Could Possibly Go
40