Part B Project Management

No. Task Duration (days) Predecessors


A Develop plan 10 -
B Develop interview questions 5 A
C Perform research 14 A
D Conduct interview 5 B
E Analyse research result 21 C
F Evaluate interview 7 D
G Budget planning 14 E, F
H System design 35 G
I Obtain and installing 30 H
hardware
J Testing and installing 35 H
software
K Testing process of the system 30 I, J
L Staff Training 21 K
M Implement the system 21 K, L