BRIEF NOTE ON HKR ROAD WORKS FOR THE REVIEW OF HON'BLE MINISTER FOR FINANCE

Sl. Work to be
Status as on Date Action Required Remarks
No. Completed

Bypass proposal against the 0.550 km realignment as per CA not


completed due to public protest. 2.8 kms length of alternate Bypass
proposal also submitted to Client for approval. In view of long delay in
approval of Bypass proposal, Client decided to take up 4-laning works
Duddeda Realignment
1 along the existing road. Based on IE report, Client agreed for the works Decision on this issue required from Client
@ km 92
of drain, additional lane on both sides of MCW, Electrical lighting to the
4-laning works under COS and concessionaire submitted the COS for
the review of IE. Client after meeting with Hon'ble R&B minister on this
issue, Client asked to submit after approval of same from R&B Minister.

3-lane Flyover as per CA deleted in the construction state due to public


representations. ENC Committee after formation of Telangana State
proposed 3-lane Flyover for Siddipet-Hyderabad bound traffic not
2 Flyover at Siddipet Pending from Concessionaire.
completed due to LA issue. In view of long delay, Client instructed
Concessionaire to take up the Flyover works as per CA. IE already
approved the Designs & Drawings for taking up the works.

For Rest Area at km 122, internal roads partially completed up to


subgrade level and no further progress as on date. Balanced works to
completed by the concessionaire. LA required for other 3 locations as
3 Rest Areas in km 122 Not yet completed.
these three locations proposed in Bypasses during the construction.
Concessionaire agreed to complete the Rest Area works @ km 122 by
31.05.2020.

Proposed 4 Nos of Bus Shelters at Shanigaram, Bejjanki, Gagillapur and


4 Bus bays / Shelters Works completed.
Thotapally.

ROB approaches at 650 m length of Diversion road work completed against 1500 m length
5 LA process in progress.
Kukunoorpally and LA not completed

No junction improvement as per CA. The proposed junction


improvement required structural acquisition, shifting of water pipeline,
Narsapur Junction Junction improvement can be done only after completion of the
6 electrical utilities, LA etc. The tentative cost of Junction improvement
improvement required works.
excluding LA is 3.5 Cr. required to be considered under Change of
Scope and submitted to Client for taking further action.

Page 1 of 2
Sl. Work to be
Status as on Date Action Required Remarks
No. Completed

IE advised Client to permit the works of Median Opening, 250 m length


MO & Service road at
of 7 m wide Service road & Bus shelter at their own cost at Double
Double Bedroom
7 Bedroom houses location on Siddipet Bypass and also advised Client Action from Client side required.
Houses on Siddipet
that the cost for shifting of electrical / water utilities for taking up the
Bypass
works should be born by the requested agency.

Page 2 of 2