Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

KMA-SUZUE LOGISTICS CENTER EXTENSION PROJECT

Safe Work Plan for Erection of Steel Structure


General Safety
All working crew shall go through with MBL / SIT in-house rules and regulation by SIT's HSE team
before commencing of works. (Refer. ATT 1)

HOT Work Safety


Every of modification or newly fabricated job in the plant, contractor shall be followed which has
been issued on safety Memo as per KSL - Construction Safety Memorandum (Hot Work Safety) . (Refer. ATT 2)
Shall brief to working crew before commencing of work.

Working At Heigth Safety


All working at height work shall be comply with KSL - Construction Safety Memorandum ( Working at Height
Safety ) . (Refer. ATT 3)

PPEs
- Safety Helmet
- Fully body harness
- Safety Shoe
- Hand Glove
- Ear Plug

Housekeeping & Waste Disposal


- Any Construction waste such as pieces of metal plate, used welding electrode, used grinding disc,
welding sludge, grinding particles shall be contain and properly house keep is required to control
and prevent for client's working enviroment and good for hygiene of daily working enviroment as
well.

Page 1 of 3 Prepared by SIT


KMA-SUZUE LOGISTICS CENTER EXTENSION PROJECT

SCOPE OF WORK AND MAJOR Scaffold Erection / Dismantling for steel structure installation work at
TASK bucket elevator.

EQUIPMENT INVOLVED Scaffolding Material and necessary tools


WORK ACTIVITY To carry out scaffold material to erect scaffolding at bucket elevator.

Vehicular accident, Blockage access, Falling object, Falling from height,


HAZARD
Damaged to client facilities.

Long Sleeve, Long Pant, Hard Hat, Safety Shoe, Safety Harness, Hand
PPE
Glove.

LOTO NA

To prevent the accident:-


¨ Ensure Daily tools box talk must be done by SIT's HSE team.
¨ Contractor to apply PTW one day in advance for SIT PIC to review and approval.
¨ Ensure working shall attend the toolbox talk before start work.
¨ Beaware of truck and forklift movement when delivering the scaffold material crossing road to
working area.
¨ Cordon off the working area with suitable warning sign must provided.
¨ All scaffold members must be fastened with effective couplers and right to use as per equipment.
(Eg. Fixed coupler, Swivel coupler).
¨ The couplers, Sole plate, base plate, joint pin and other scaffold material free from defect.
¨ The planks/Toe board should free from defect and damage such as cracks, splits, etc.
¨ The access ladders free from corrosion, cracks, rusts, oil and other damage.
¨ Make sure to check all scaffold material are in good conditions before erecting.
¨ Contractor to submit scaffold inspection checklist every week.
¨ The scaffold tag shall be available and visible to indicate scaffold safe for use after erection.
¨ Only authorized scaffold builder to do erection and modification of scaffolding.
¨ Only competence and trained person to do erection and modification of scaffold.
¨ Shall STOP work any work deviated from original plan and do proper investigate before
resuming work.

Page 2 of 3 Prepared by SIT


KMA-SUZUE LOGISTICS CENTER EXTENSION PROJECT

SCOPE OF WORK AND MAJOR


Using mobile crane to erection of steel structure
TASK

EQUIPMENT INVOLVED Mobile crane


WORK ACTIVITY Using mobile crane to install steel column, member and beam

May collapse crane, Failure crane during lifting, Broken off webbing sling
HAZARD
of steel rope, Slip of load, hitting by load to other facilities or human

LOTO NA

To prevent the accident:-


¨ Ensure Daily tools box talk must be done by SIT's HSE team.
¨ Make sure apply the lifting permit and approved by SIT.
¨ Ensure worker shall attend the daily tool box talk before start work.
¨ All lifiting activity shall be comply with lifiting plan.
¨ Contractor engineer or supervisor must explained approved MOS and JSRA to their co-follow
worker such as crane operator, lifting supervisor, rigger man and signal man.
¨ Make sure to use tag line to prevent for the swinging of load.
¨ All lifiting crews such as crane operator, lifiting supervisor, rigger man and signal man and signal
man, they shall have quilified certificate and competence to perform lifiting activities.
¨ Crane operator to check crane condition daily and control by crane checklist prior to start lifiting
operation.
¨ Ensure to check soil condition prior to travel in to gravel area.
¨ Outrigger must be fully extended with suitable outrigger mats.
¨ Crane operator ensure to check crane limit switch is in good functioning.
¨ Anchor point of Chain block shall enough stronger point to hook.
¨ Ensure that chain block capacity must be more than load capacity.
¨ All lifiting gear and appliance shall be inspected and safe for lifiting operation.
¨ Cordon off the lifiting operation area with suitable warning sign.
¨ Mobile crane shall be inspected and safe to use by crane company.
¨ All lifiting activity shall be under control by competence lifiting supervisor.
¨ Beaware of truck and forklift movement around lifiting area.
¨ To do proper housekeeping after work done.
¨ Shall STOP work any work deviated from original plan and do proper investigate before
resuming work.

Page 3 of 3 Prepared by SIT


Project : KMA-SUZUE LOGISTICS CENTER EXTENSION PROJECT ATTACHEMENT - 1
Client : KMA-SUZUE MYANMAR LOGISTICS

Date : 23-Jun-2019
TO : All Project Members, Contractors and Sub-contractors
RE : Construction Safety Memorandum # 1 : Working at height safety

Working at height is the largest single cause among serious acciendents in the construction industry therefore risk
control shall be carried out for all works more than 1.8 meters above the ground level from which workers or
materials could possibly fall.

Please pay serious attension and comply with safety instructions mentioned below before you start working in
KMA-SUZUE Logistics Center Extension Project Construction Site.
· All Scaffold should be erected and dismentled by those who are adequately experienced and
competent in the erection and dismentling of scaffolding.
· A competent person should inspect all scaffolds at least three days after erection. The outcomes
of inspections must be recorded, documented and kept available.
· Tages shall be fitted to all scaffolds to indicate whether they are safe for use or not.
Scaffolding Foreman (or) Supervisor shall sign all “Safe for Use” Green Tags.
· Make sure to access the soil condition prior to the commencement of any scaffold erection works.
· Ensure to use standard base plates on the scaffolding foundation.
· All the employees must ware the safety harness whenever working at height 1.8 m and above.
· Always hook up at the anchorage point (above shoulder).
· Provide safe access, guard rail, hand rail for prevention of fall and to install safety net or toe
board for prevention of falling objects.
· Secure all the tools, devices and equipment of installation work to avoid the following objects.
· Provide the "Life Line" if the working platform is insufficient or working at roof area.
· Must comply with basic ladder safety requirement while using A-frame ladder or straight ladder.
· Assit one person ro hold the ladder to maintain balance of the ladder and "Top 3 Rungs" of ladder
is not allowed to use to prevent over reaching.
If you have any concern about the clarification on facts mentioned above, please feel free to contact me.
Thank you for your cooperation.

Memo#1 Safety Memo SIT

You might also like