Professional Documents
Culture Documents
Bike Rack Vidir
Bike Rack Vidir
Bike Rack Vidir
Prepared for:
TABLE OF CONTENTS
Introduction ·································································································································· 3
Introduction ·············································································································· 4
Serial Number ··········································································································· 4
Installation Sequence·································································································· 5
What to expect ·········································································································· 6
Section 1: Primary BMS Fixture ······································································································· 7
Track Arm Descriptions ······························································································· 8
Track Arm—1st & 2nd Level ····················································································· 9-10
Track Arm—Anchoring ······························································································ 10
Track Arm—3rd Level, Front and Rear ········································································· 11
Track Arm—Braces ······························································································ 12-13
Track Arm—Braces, Backside Skyhook ········································································ 14
Slide-out Carrier & Skyhook Mechanism, Mounting to Track Arm ······································· 15
Carrier Assembly
Slide-out Parts (1st & 2nd Level) ············································································ 16
Slide-out Installation(1st & 2nd Level)·································································· 17-18
Skyhook Carrier—3rd Level ·················································································· 19
Skyhook Mechanism (3rd Level) ············································································ 20
Shepherd Hook Hanger ····························································································· 21
Section 2: Backside Components ············································································· 22
Wall Standards ········································································································ 23
Wall Standards Extension Option ············································································ 24-25
Power Wheel Shelf & Vehicle Shelf ·············································································· 26
Power Wheel Shelf······························································································ 27
Power Wheel Shelf Alignment Clamp ································································· 28
Scooter Shelf ·········································································································· 28
Scooter Bracket ·································································································· 28
Bike Ski ············································································································ 29-30
Rear Slide Out Support ····························································································· 31
Rear Slide Out ········································································································ 32
Rear Slide Out with Bolts ··························································································· 33
Section 3: End Displays ················································································································ 34
Juvenile Bike Display ································································································ 35
Operator/Parts Manual Mounting ················································································· 36
Half Cone ··········································································································· 37-45
Section 4: Seismic Information ······································································································ 46
Seismic Bracing ··································································································· 47-48
Section 5: General Operation ········································································································ 49
Operation ··············································································································· 50
Prepared for:
TABLE OF CONTENTS
Section 6: BMS Parts List ············································································································· 51
End Frame & Track Arm Components ······································································ 52-53
Slide-out Carrier Components ················································································· 54-55
Skyhook Carrier Components ················································································· 56-57
Juvenile Bike Display ································································································ 58
Miscellaneous ········································································································· 58
Backside Components ·························································································· 59-60
Bike Cone Components························································································· 61-62
Seismic Parts ·········································································································· 63
BMS Part Kits ····································································································· 64-70
Parts Order Forms ······························································································· 71-75
Section 7: Complete Installation ···································································································· 76
BMS—check list ······································································································ 77
BMS Reconfiguration—check list ················································································· 78
Section 8: Warranty & Liability ······································································································ 79
Warranty and Limitation of Liability··············································································· 80
Prepared for:
Introduction
Prepared for:
INTRODUCTION
Congratulations on the installation of your Vidir Bike Merchandising System. This system has
been carefully designed and constructed to provide you with many years of dependable service.
It has been built to meet or exceed current U.L./C.S.A. standards. With proper care in operation
and maintenance, this system will assist you in maximizing your efficiency.
To ensure the utmost value and performance from your system, please read this manual careful-
ly to be sure correct procedures are followed.
If help is needed or if any of these procedures are unclear, please do not hesitate to contact
Vidir Machine Inc. at 1-800-417-9557.
SERIAL NUMBER
Please be sure to record the serial number for any future service calls and parts ordering
bmssupport@vidir.com
Head Office U.S. Sales Office
Vidir Machine Inc Vidir Inc.
Box 700 179 US Hwy. 27 North, Suite G
Arborg, Manitoba, Canada Clermont, Florida, USA
R0C 0A0 34711-2432
Service: 1-800-417-9557 Service: 1-800-417-9557
Toll Free: 1-800-210-0141 Toll Free: 1-866-898-4347
Phone: 1-204-364-2442 Phone: 1-352-243-7310
Fax: 1-204-364-2454 Fax: 1-352-243-7320
Prepared for:
INSTALLATION SEQUENCE
Prepared for:
WHAT TO EXPECT
Refer to the packing list for part quantities related to your store.
STEP #2
Two people are required to remove the
STEP #1 end frames from the crate.
Remove carrier bundle before removing end Unbolt one frame at a time and remove
frames. from crate.
Once 2 end frames have been re-
moved, locate track arms as per de-
scriptions on page 7.
STEP #3
Small parts and hardware packages to
be removed once end frames have
been removed.
Prepared for:
Section 1:
Primary
BMS Fixture
Prepared for:
The 1st and 2nd level track arms will be required for the first step of the assembly process.
64” 74”
3rd Level, Backside – track arm (64”) offset 3rd Level, Front – track arm (74”) offset
p/n 5-55650 p/n 5-55644
64”
Level 2
p/n 55645
Level 1 1st & 2nd Level, Front & Rear – track arm (64”)
p/n 5-55645 p/n 5-55645
Prepared for:
Figure 1
End frame
p/n 5-55630
Figure 2
Prepared for:
Anchoring
(for seismic anchoring see pg. 48)
Anchor plate
welded to frame
Note:
When using floor anchors, the anchors on the
outside uprights should be installed pointing
inward. This will eliminate a tripping hazard.
Note:
The short offset track arms are installed on the backside of the display.
Level 3 backside
Track arm
p/n 5-55650
Level 3 front
Track arm
p/n 5-55644
Prepared for:
TRACK ARM—BRACES
1. Start installation of the front track arm bracing at level 1.
2. Insert the flat brace stud into the mounting plate located on the side of the 1st level track arm
(see next page).
3. Position the other end of the flat brace stud into the 2nd level track arm rear mounting plate
(see next page).
4. Insert the flat brace stud into the mounting plate located on the side of the 2nd level track
arm as shown in (see next page).
5. Position the other end of the flat brace stud into the 3rd level track arm rear mounting plate
(see next page).
6. Position the square brace stud into the 3rd level mounting plate located on the side of the 3rd
level track arm (see next page).
7. Insert the other end of the square brace stud into the 2nd level track arm rear mounting plate
(see next page).
8. Once all braces are in place, insert the 5/32” x 1” roll pins into the holes located on all 1st
and 2nd level track arm mounting plate (shown below).
9. Tap into hole with hammer.
Prepared for:
TRACK ARM—BRACES
Tube brace
Flat brace
Flat brace
Prepared for:
TRACK ARM—BRACES
BACKSIDE SKYHOOK
1. The backside skyhook brace is a 1” square tube with a C bracket welded to the bottom end of
it.
2. To install this brace, clamp the C bracket over the back of the second level track arm (Detail
B).
3. Once in position, lift the backside skyhook track arms and insert the brace stud into the track
arm mounting plate (Detail A).
4. Install plastic end caps on both ends of each track arm (end of BMS unit only).
Prepared for:
k
Bac
Tip
Prepared for:
The following components will be required to complete the slide out carrier assembly.
Short tire latch (28”) Long tire latch (34”) Safety cap
p/n 5-55628 p/n 5-55629 p/n 5-6280
1st and 2nd level 1st and 2nd level 1st and 2nd
level
Alignment fork
p/n 5-55627
2nd level only
Prepared for:
Prepared for:
After the 1st and 2nd level slide out carriers have been installed on the track arms, loosen the
front track wheel carriage bolt and insert the safety cap. Tighten to secure the safety cap in
place.
Note: Do not over tighten the carriage bolt and locknut. Track wheel must roll freely.
Insert the tire latches through the carrier retaining hoops and align to the mounting hole located
on the carrier upright. Fasten using the 5/16” x 1 ¾” hex bolt and locknut. Tighten till snug, loos-
en till latch is free.
Mount the front and rear tire saddles to the carrier as shown.
SECOND LEVEL CARRIER ONLY
The alignment fork will be required for all second level carriers.
When installing the rear tire saddle, mount the alignment fork and fasten to the carrier using the
supplied nut and bolt on the opposite side of the carrier rear saddle tab.
Prepared for:
1. Insert the tire clamp through the skyhook carrier retaining hoop located on the side of the
front frame.
2. Use the 5/16” x ¾” hex bolt and 5/16” lock nut to secure to the carrier post. Tighten until
snug, then loosen 1/2 turn (until latch moves freely).
Retaining
hoop
Tire clamp
p/n 5-55652
3rd level
Prepared for:
Note:
The skyhook mechanism contains a pressurized gas shock.
To extend the mechanism, grip the mounting arm and pull
downward until the safety latch lock engages.
Prepared for:
Figure 1
Detail A
End Frame
p/n 5-55630
Prepared for:
Section 2:
Backside
Components
Prepared for:
WALL STANDARDS
Using the 3/8” x 3” x 2-1/2” U-bolts, washer and nuts, mount the wall standard to the back of the
display.
The- bolts are placed over the track arm horizontal tubes and bolted to the wall standards.
(Detail A)
Note:
Check store modular for correct placement.
Ensure the starting wall standard is mounted with the bottom resting on the floor and as close
as possible to the outside of the end frame.
For display’s that include the juvenile bike display or the end grid it is recommended the wall
standards are mounted last.
6 wall standards
Prepared for:
2. Install accessory grid & spacer to leg of the main BMS frame (see next page).
Prepared for:
4. Install the 19 slotted wall standard extension attachment on top of wall standard for Power
Wheel Shelf. Use carriage bolts, and flange nuts shown in View A.
5. Install 2nd of the 19 Slotted Wall Standard Extension Attachment 48” from the bottom of the
Wall Standard to the bottom of the Extension for Vehicle Shelf.
6. Vehicle Carton shelf must be installed in the middle of the Wall Standard Extension.
Prepared for:
Prepared for:
1. Hang the smaller shelf from the top slot of the wall standard. (48” x 49”)
2. Hang the cross bar below the shelf (13 slots top to top).
3. Insert shelf arm tube into the 3rd shelf rod from bottom (Detail C). Then slide it over the cross
bar (Detail B).
4. Hang the larger shelf below the top cross bar (21slots from top of shelf to top of cross bar).
(48” x 60”)
5. Hang the cross bar below the shelf (13 slots top to top).
6. Insert shelf arm tube into the 5th shelf rod from bottom (Detail C). Then slide it over the cross
bar. (Detail B)
7. Install price tag holder on front of power wheel shelf as shown.
Detail C
Prepared for:
SCOOTER BRACKET
st
1. Hook scooter brackets onto 1 rod from the top (Detail A & B).
Prepared for:
BIKE SKI
1. Starting from the bottom, hang the top hook of cross bar into the 17th slot from bottom (Detail
A, see next page).
2. Hang the second cross bar above bottom cross bar (leave 8 empty slots).
3. Hang the third cross bar (leave 27 empty slots).
4. Hang the forth cross bar (leave 8 empty slots).
5. Insert bike arm support into cross bar (see Detail A, see next page).
6. Slide the bike channel into the cross bar (see detail C, see next page).
7. Install bolt and nut on bike channel to arm support (see detail D, see next page).
8. Install front saddle (Detail B, see next page). Note: washer must be inside the ski channel.
9. Install ¼ lock nuts on front saddle.
10. Install rear saddle (Detail C).
Prepared for:
DETAIL A DETAIL B
17th Slot
DETAIL C DETAIL D
Prepared for:
Prepared for:
Prepared for:
1. Install plate with 1-5/8” x 5” u-bolt, ½” washer and ½” nuts as shown. (Detail A)
2. See page 9-10 for installation of track arms.
3. See page 32 for steps to install braces.
4. See page 15-18 for steps to assemble and install slide out carrier.
Prepared for:
Section 3:
End
Displays
Prepared for:
Using u-bolt kit p/n 001-0318, mount the juvenile display bike hook bar 133” from floor.
Note: Slide mounting plate up against the bottom of the top track mounting bracket.
Mount the lower tire retaining grid 88 3/4” from the floor.
Note: Slide mounting plate down against the top of the 2nd level track mounting bracket.
Juvenile display
Bike hook bar
& lower tire
grid kit
p/n 5-44114
Accessory Grid
p/n 5-44179
Prepared for:
The store’s parts/operators manual will be hung with a zip-tie on the cross piece on the main
frame behind the accessory grid.
Prepared for:
HALF CONE
List of tools needed
A 3/8” socket set
Set of open end wrenches 3/8” to 3/4”
A carpenters level
Adjustable wrench
Tape measure
1. Install leveling bolts on each back corner of the bike cone. Using an adjustable wrench lev-
el the cone, turning the leveling legs as needed. Leveling legs are located on each corner
of the half cone.
Prepared for:
HALF CONE
2. Take sign side frame (1” square 93” long tubing, open ends) and slide both side frame
tubes (stud at each end) into bottom sign frame tubing, one at each end. Slide top frame
tubing onto the side frame tubes.
3. Take sign back frames and slide the two pieces together securing them with 1/4” x 1 1/2”
bolts. (2 Pcs. Needed)
4. Mount back frame to the sign frame. Using 1/4” x 2 1/2” bolts (4 bolts needed, two at the
top and two at the bottom)
5. Roll the blue tarp out in the frame and slide round stretcher tubes into loops provided at the
top and bottom of tarp. Uses 1/4” x 2 1/2” bolts, 3 pcs at the top 3 pcs at the bottom, and
tighten the graphic tarp.
Prepared for:
HALF CONE
6. Erect the assembled graphic tarp frame and mount to the back of Bike cone, using 4 Pcs
1/4” x 2 1/2” Bolts. Place the half cone in its desired location.
7. Install back covers and sign holder on half cone using self tap screws provided.
Prepared for:
HALF CONE
8. Locate bike skis on front of bike cone spacing them as per drawing. Use the U bolts that
are provided to fasten skis to frame. (2 U-Bolts required per ski)
9. Fasten Price point graphic holders to each Bike ski using ¼” x 1” bolts with lock nut.
5/16 nut
”
10
”
26
”
26
”
26
”
”
26 26
”
26
Prepared for:
HALF CONE
10. Place the 6 - “Ask For Assistance” stickers, centered, between the 7 skis. The stickers
should be placed so the words are nearest to the top of the half cone.
Prepared for:
Signing Kit
Prepared for:
Prepared for:
Prepared for:
Prepared for:
Section 4:
Seismic
Information
Prepared for:
Prepared for:
Anchor plate
welded to frame
Torque anchor
bolts to 45 ft-lb
(seismic only)
Section 5:
General
Operation
Prepared for:
GENERAL OPERATION
Pulling bike out (1-4) Putting bike back (1-3)
Prepared for:
Section 6:
BMS
Parts List
Prepared for:
9) Single backside track arm 64” 10) Single slide out track arm 74” 11) Single slide out track arm 64”
p/n 5-55649 (back level 3) p/n 5-55646 (front level 3) p/n 5-55647 (front level 1-2)
Prepared for:
64” 74”
64”
12) Skyhook backside track arm 13) Skyhook front track arm 14) Slide out track arm
p/n 5-55650 (rear level 3) p/n 5-55644 (front level 3) p/n 5-55645 (front level 1-2)
15) Tube track arm brace 16) Track arm carrier bumper kit 17) Track arm molded end cap
p/n 5-43678 p/n 206-1010 p/n 206-0089
Prepared for:
1) Slide out carrier 2) Slide out carrier 3) Front tire saddle kits—6” off-
p/n 5-43789 complete with 6” saddles set
p/n 5-43794 p/n 5-43571
4) Rear tire saddle kits—6” offset 5) Tire saddle Mounting hard- 6) & 11) Tire saddle Mounting
p/n 5-43567 ware—5/16”x 1-1/4” hex bolt hardware—5/16” lock nuts
p/n 001-0244 p/n 004-0043
7) Short tire latch kit 8) Long tire latch kit 9) Alignment fork
p/n 5-55628 p/n 5-55629 p/n 5-55627
10) Hex bolt—5/16” x 1-3/4” 12) Track wheel bolt and nut 13) Track wheel cover
p/n 001-0315 p/n 001-0337 p/n 5-6280
Prepared for:
14) Track wheel kit 15) Black cosmetic tubes 16) Black cosmetic tubes
p/n 5-55805 4” black 1/2” I.D. p/n 206-0132 4” black 3/8” I.D. p/n 206-0130
17) Black cosmetic tubes 18) Slider guide 19) Track arm end cap
3” black 1/2” I.D. p/n 206-1027 p/n 206-0022 1” x 3” p/n 206-0036
Prepared for:
10) Skyhook Carrier Complete 11) Skyhook gas shock 12) Skyhook mechanism
p/n 5-55654 p/n 111-0053 p/n 5-43776
Prepared for:
13) Skyhook retainer 14) Skyhook tire clamp 15) Spring carrier lock
p/n 5-43736 p/n 5-55652 p/n 119-0028
16) Tire clamp spring 17) U-latch 18) Kink Latch Rod
p/n 119-0011 p/n 5-7130 p/n 5-43831
19) Skyhook tube brace w/clip 20) Shepherd’s Hook Hanger 21) Decal Hang Shepherd’s Hook
p/n 5-44103 p/n 5-65419 Here (English)
p/n 110-3145
Prepared for:
1) Bike hook bar assembly 2) Bike hook bar 3) Lower tire grid
p/n 5-44114 p/n 5-55670 p/n 5-55671
MISCELLANEOUS
1) Leg Shims
p/n 5-43611
Prepared for:
BACKSIDE COMPONENTS
1) 36” x 42” Vehicle carton shelf 2) 36” x 49” Power wheel shelf 3) 48” x 49” Power wheel shelf
p/n 5-58911 p/n 5-57182 p/n 5-57002
4) 48” x 60” Power wheel shelf
p/n 5-53914
5) Wall standard kit 6) Wall standard Extension Kit 7) Bike hook bar hanger 36”
p/n 5-54392 p/n 5-59868 p/n 5-44159
8) Bike hook bar hanger 48” 9) Kids bike ski for 12-20” bikes 10) Bike ski channel
p/n 5-44158 p/n 5-57688 p/n 5-57689
11) Rear Scooter saddle bracket 12) Price Tag holder 13)Rear leg support
p/n 5-54817 p/n 5-55582 p/n 5-58670
Prepared for:
BACKSIDE COMPONENTS
14) BMS Scooter Bracket Assm 15) Shelf Alignment kit 16) Shelf arm
p/n 5-55679 p/n 5-55095 p/n 5-55678
17) Ski arm 18) Ski front saddle 19) Ski rear saddle
p/n 5-57691 p/n 5-57692 p/n 5-58256
20) 1/4” x 3/4” Carriage Bolt 21) 1/4” Flange Nut 22) Track Arm Clamp
p/n 001-0018 p/n 004-0013 p/n 5-58405
Prepared for:
BIKE CONE
1) 1” x 1” Cosmetic Plug T-32-U2 2) 1/4” Flat Washer 3) 1/4” x 3-1/2” Hex Bolt
p/n 206-0136 p/n 003-0114 (Banner Pipes) p/n 001-0093
4) 1/4” Lock Nut 5) 1/4” x 1-1/2” Hex bolt 6) 1/4” x 2-1/2” Hex bolt
p/n 004-0042 p/n 001-0088 (H Frame Bars) p/n 001-0091
7) 1/4” x 3/4” Hex Bolt 8) 1/4” x 3/4” Screw D&T HWH 9) Round Cosmetic Plug
(Price Tag Holder) p/n 001-0086 p/n 002-0092 p/n 206-0095
10) Bolt U 5/16” x 2”ID x 4” 11) Leg Leveling Bolt 12) “Ask for assistance” Decal
p/n 001-0339 p/n 001-0247 p/n 110-0134
Prepared for:
BIKE CONE
13) Sign Frame Assm w/ hardware 14) Sign Support Frame (Top) 15) Sign Support Frame (Bottom)
p/n 5-53831 p/n 5-51811 p/n 5-51807
16) Vertical Frame Bars 17) Horizontal Frame Bars 18) Banner Support Bars
p/n 5-51816 p/n 5-51813 p/n 5-55452
19) Price Tag Holder 20) Sign Holder 21) Bike Skis
p/n 5-51777 p/n 5-59215 p/n 5-51770
22) Back Side Panels 23) Back Middle Panel 24) BC Back Cover Kit w/self-tap
p/n 5-55781 p/n 5-55782 screws p/n 5-56444
Prepared for:
SEISMIC PARTS
1) Seismic Cross Bracing Kit 4) Bolt Hex 1/2 x 5 5) 1/2” Flange Nut
p/n 5-54391 p/n 001-0154 p/n 004-0017
Kit Includes Qty
- Cross Brace Mount Strap (4)
- Cross Brace U-Clamp (8)
- Bolt Hex 1/2” x 5” (8)
- Nut Hex 1/2” (8)
- Two Holed Anchor Strap (2)
- Bolt Anchor 1/2” x 4-1/2” (4)
Prepared for:
BMS48SKI2L
Qty P/N Description
BMS48SKI2L
BMS36SKI2L
Qty P/N Description
BMS36SKI2L
Prepared for:
BMSVEHICLESHELF36
Qty P/N Description BMSPWSHELF-48x60
1 5-58911 VEHICLE CARTON SHELF 36 x42 Qty P/N Description
1 5-55095 SHELF ALIGNMENT KIT
2 5-55678 SHELF ARM ASMB
1 5-55724 BMSPWSHELF 48 X 60
1 5-44158 BIKE HOOK BAR HANGER 48"
BMSPWSHELF-36x49
Qty P/N Description
1 5-57182 BMSPWSHELF 36 X 49
1 5-44159 BIKE HOOK BAR HANGER 36" BMSPWSHELF-48x49
Qty P/N Description
1 5-55095 SHELF ALIGNMENT KIT
2 5-55678 SHELF ARM ASMB
1 5-57002 BMSPWSHELF 48 X 49
1 5-44158 BIKE HOOK BAR HANGER 48"
Prepared for:
BMS555REARSKYHK BMS1055REARSKYHK
Qty P/N Description Qty P/N Description
1 5-55650 SKYHOOK BACKSIDE TRACK ARM
1 5-55650 SKYHOOK BACKSIDE TRACK ARM
2 5-44103 SKYHOOK TUBE BRACE W/ CLIP
1 5-44103 SKYHOOK TUBE BRACE W/ CLIP
Prepared for:
BMS527REARSKYHK
Qty P/N Description
1 5-55649 SINGLE BACKSIDE TRACK ARM
1 5-44103 SKYHOOK TUBE BRACE W/ CLIP
1 5-55654 SKYHOOK CARRIER, ASMB
1 5-43776 SKY HOOK MECHANISM
BMS527
Qty P/N Description
2 5-43794 SLIDEOUT CARRIER COMPLETE ASM
1 5-55630 VERT LEG 3 LEVEL, ASMB
SINGLE SKYHOOK FRONT TRACK
1 5-55646
ARM 74"
SINGLE SLIDEOUT TRACK ARM LVL
2 5-55647
1&2
1 5-55654 SKYHOOK CARRIER, ASMB
2 5-43675 FLAT TRACK ARM BRACE
Prepared for:
BMS1055ST BMS1055ADD
Qty P/N Description
Qty P/N Description
4 5-43794 SLIDEOUT CARRIER COMPLETE ASM
4 5-43794 SLIDEOUT CARRIER COMPLETE ASM
2 5-55630 VERT LEG 3 LEVEL, ASMB
1 5-55630 VERT LEG 3 LEVEL, ASMB
1 5-55644 SKYHOOK FRONT TRACK ARM 74"
1 5-55644 SKYHOOK FRONT TRACK ARM 74"
2 5-55645 SLIDEOUT TRACK ARM LEV 1 & 2
2 5-55645 SLIDEOUT TRACK ARM LEV 1 & 2
2 5-43776 SKY HOOK MECHANISM
2 5-43776 SKY HOOK MECHANISM
2 5-55654 SKYHOOK CARRIER, ASMB
2 5-55654 SKYHOOK CARRIER, ASMB
4 5-43675 FLAT TRACK ARM BRACE
4 5-43675 FLAT TRACK ARM BRACE
2 5-43678 TUBE TRACK ARM BRACE
2 5-43678 TUBE TRACK ARM BRACE
Prepared for:
BMS855REARSOWD BMS855REARSOBO
Qty P/N Description Qty P/N Description
4 5-43794 SLIDEOUT CARRIER COMPLETE ASM 4 5-43794 SLIDEOUT CARRIER COMPLETE ASM
2 5-43678 TUBE TRACK ARM BRACE 2 5-43678 TUBE TRACK ARM BRACE
Prepared for:
BMS427REARSOWD BMS427REARSOBO
Qty P/N Description Qty P/N Description
2 5-43794 SLIDEOUT CARRIER COMPLETE ASM 2 5-43794 SLIDEOUT CARRIER COMPLETE ASM
2 5-55647 SNGL TRACK 28 IN 64" FR SLIDEOUT 2 5-55647 SNGL TRACK 28 IN 64" FR SLIDEOUT
ASMB ASMB
1 5-43675 FLAT TRACK ARM BRACE 1 5-43675 FLAT TRACK ARM BRACE
1 5-43678 TUBE TRACK ARM BRACE 1 5-43678 TUBE TRACK ARM BRACE
Prepared for:
Prepared for:
For info call: 1-800-417-9557 Fax completed parts order to 352-243-7320
Prepared for:
For info call: 1-800-417-9557 Fax completed parts order to 352-243-7320
Prepared for:
For info call: 1-800-417-9557 Fax completed parts order to 352-243-7320
Prepared for:
For info call: 1-800-417-9557 Fax completed parts order to 352-243-7320
QUANTITY
BMS PART KITS
Parts Kits Vidir P/N WM SAP A* B* C*
pg #
64 36"SEC 2LVL 4SKI 4CROSS BAR 5-58942 BMS36SKI2L 100502536
Prepared for:
For info call: 1-800-417-9557 Fax completed parts order to 352-243-7320
Section 7:
Complete
Installation
Prepared for:
Installed 1 1/2” x 3” plastic caps on the ends of track arms. (both ends of BMS only) [See pg 14]
Tire latches must all pivot freely (safety reasons)
All saddles are installed correctly see pg 18.
All rollers roll freely
Safety caps are installed on top rollers on level 1 & 2.
Roll pins are installed on the bottom and middle level track flat braces
Wall standards spaced properly and secured firmly.
Leveling bolts are properly adjusted (upright leveled on the backside with a level)
Every frame leg is anchored to the concrete floor (two spots) (Inspector may need to be present during
anchoring)
Bike rack must be cleaned
Tested to ensure lower and upper safety locking latches operate properly on skyhooks
Skyhook retainer is installed properly as shown on pg 15.
Make sure to leave 1 shepherd’s hook with each BMS, install shepherd’s hook hangers
Demonstrated to the store associate(s) how to use the BMS
Show and explain the parts manual to store manager on duty
Installed Parts Manual on main frame
Installed Bike Cone as per instruction manual
Installed Seismic braces as per instruction manual
Installed backside fixtures (shelves) as per backside fixture installation instructions
BMS anchored in correct location Name_____________________ Signed _______________________
Installation: Complete Incomplete
Detailed scope of work to be completed _____________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
Estimated time to complete install______ List of parts attached
Who will complete install? Installer Another Tech Store
Contact Name: ________________________
Install must be completed by:___/___/___ Store Grand Opening date: ___/___/___
For onsite install support contact BMS Installation Support bmssupport@vidir.com
Toll Free (800)417-9557 ext 2228 or after hours call 855-886-4671
Reported install (12hrs) Completed check list Sent check list (48 hrs)
Sent pictures (12 hrs) Installed correctly SRO NUMBER ______________
NOTE: Ensure all information is complete and fax checklists to 352-243-7320 Prepared for:
Installed 1 1/2” x 3” plastic caps on the ends of track arms. [See pg 14] (new unit only)
Tire latches must all pivot freely (safety reasons) (new unit only)
Replaced ALL track wheels on old BMS and checked that they roll freely
Safety caps are installed on top rollers on level 1 & 2. (complete BMS)
Roll pins are installed on the bottom and middle level track flat braces (new unit only)
Wall standards secured firmly. (complete BMS)
Leveling bolts are properly adjusted (upright leveled on the backside with a level) (complete BMS)
Every frame leg is anchored to the concrete floor (two spots) (complete BMS) (Inspector may need to be
present during anchoring)
BMS must be cleaned (complete BMS)
Tested to ensure lower and upper safety locking latches operate properly on skyhooks (complete BMS)
Skyhook retainer is installed properly as shown on pg 15 (complete BMS)
Demonstrated to the store associates how to use the BMS
Show and explain the parts manual to store manager on duty
Installed Parts Manual on Main frame
Installed Bike Cone as per instruction manual
Installed Seismic braces as per instruction manual (new unit only)
Installed backside fixtures (shelves) as per backside fixture installation instructions
BMS anchored in correct location Name____________________ Signed___________________________
* * * * * * * * * * * * * * * * * * * * * * * * * *
Installation: Complete Incomplete
Detailed scope of work to be completed_____________________________________________________
______________________________________________________________________________________
______________________________________________________________________________________
______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
Estimated time to complete install______ List of parts attached
Who will complete install? Installer Another Tech Store
Contact Name: ________________________
Install must be completed by:___/___/___ Store Grand Opening date: ___/___/___
For onsite install support contact BMS Installation Support bmssupport@vidir.com
Toll Free (800)417-9557 ext 2228 or after hours call 855-886-4671
Reported install (12hrs) Completed check list Sent check list (48 hrs)
Sent pictures (12 hrs) Installed correctly SRO NUMBER _____________________
NOTE: Ensure all information is complete and fax checklists to 352-243-7320 Prepared for:
Section 8:
Warranty &
Liability
Prepared for:
Vidir Machine Inc. (“Vidir”) warrants solely that the equipment shall be free from any defect due to faulty workman-
ship or material deficiency at the time of delivery to the buyer thereof (the “Buyer”) and for a period of one year
therefrom.
All work except minor repairs or adjustments to the equipment furnished on an emergency basis, will be performed
during regular working hours. If the Buyer requests that repair work be performed outside of regular working
hours, it is the responsibility of the Buyer to pay the difference between regular and premium labour rates at the
then standard hourly billing rate.
This warranty shall be voided by any modifications to the equipment or any use of the equipment for any purpose
other than that for which it was specifically intended.
This warranty is the only warranty made by Vidir. The Buyer hereby expressly waives any obligations or liability, in-
cluding liability for loss or damages due directly or indirectly, any obligations including, without limitation, loss
of use, revenue, or profit, shipping and handling, and injury to person or property.
It is the responsibility of Buyer to know, understand and comply with the work and safety laws and regulations in
effect and governing Buyer’s use of the equipment. To the extent governing law requires inspections, records
keeping and/or after-purchase modifications to the equipment, it is the responsibility of the Buyer to arrange for
and comply with such requirements and any associated costs are the sole responsibility of the Buyer. Vidir as-
sumes no responsibility or liability for Buyer’s performance under or compliance with such laws and regulations.
If the equipment is found by the Buyer to be defective, the Buyer must notify Vidir within a period of 30 days of dis-
covery of the defect.
The Buyer is expected to provide access to all equipment covered by this warranty. Vidir shall not be responsible for
any expense incurred in removing, replacing, or refinishing any part of the building structure necessary for the
performance of Vidir’s obligations under this warranty.
In the event that any alterations, additions, adjustments or repairs are made by others without Vidir’s prior written
consent, Vidir may, at its option, immediately terminate this warranty by providing written notice to the Buyer.
In the event Vidir is required to make emergency calls, repairs and/or replacements under this warranty occasioned
by the Buyer or any user’s negligence, improper operation or misuse of the equipment or by fire, explosion,
flooding, the elements, strikes, labour troubles, vandalism, riots or civil commotion, or by any cause beyond Vidi-
r’s control. The Buyer shall reimburse Vidir for such emergency calls, repairs and/or replacements in accordance
with the then current rates for such services.
Vidir’s liability for injury to persons or property shall, in any event, be limited to that caused directly by its negli-
gence. Vidir shall not be liable, however, on any account, for any damage or loss to the Buyer or its dealers, rep-
resentatives, affiliates or agents resulting from business interruption, inconvenience, loss of profits, or special or,
indirect or consequential damage. Vidir shall not be deemed to guarantee or warrant the continuing operation
or operating efficiency of the equipment covered, nor shall Vidir be liable for any breakdowns thereof or for any
damage to any other property of the Buyer not covered by this warranty but resulting from any breakdowns in
or operating mishaps of the equipment covered.
Should any payment due by the Buyer become thirty days or more delinquent, Vidir may terminate this warranty by
written notice, and all moneys owed Vidir shall be immediately payable on demand.
This warranty is not transferable or assignable by the Buyer.
Vidir reserves the right to determine, in its sole and absolute discretion the best means and methods to be employed
for any corrective or repair work deemed necessary by Vidir pursuant to this warranty.
Prepared for: