Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 27

Universid

Gerenci
Universidad Libre de Colombia

Lina María Sánchez Ballesteros

Gerencia de Proyectos con enfoque PMI


Taller valor ganado
In month 9 the following project information is available: actual cost is $2,000,
earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the
project.

Período 9
AC $ 2,000
EV $ 2,100
PV $ 2,400
SV= -$ 300
CV= $ 100
On day 51 a project has an earned value of $600, an actual cost of $650, and a
planned cost of $560. Compute the SV, CV, and CPI for the project. What is your
assessment of the project on day 51?

Período 51
EV= $ 600
AC= $ 650
PV= $ 560
SV= $ 40
CV= -$ 50
CPI= 0.92 Cost Pefomance Index (Índice de desempeño de costo)
SPI= 1.07 Scheduled Perfomance Index (Índices de desempeño del cronograma)
el cronograma)
Given the project network and baseline information below, complete the form to
develop a status report for the project at the end of period 4 and the end of period 8.
From the data you have collected and computed for periods 4 and 8, what information
are you prepared to tell the customer about the status of the project at the end
of period 8?

Final período 4
Tarea % de avance EV AC PV CV SV
A Finalizado 400 300 400 100 0
B 50% 1200 1000 800 200 400
C 33% 499.5 500 600 -0.5 -100.5
D 0% 0
E 0%
F 0%
Acumulado 2099.5 1800 1800 299.5 299.5

Final período 8
Tarea % de avance EV AC PV CV SV
A Finalizado 400 300 400 100 0
B Finalizado 2400 2200 2400 200 0
C Finalizado 1500 1500 1500 0 0
D 25% 400 300 0 100 400
E 33% 297 300 -3 297
F 0%
Acumulado 4997 4600 4300 397 697
Given the following project network, baseline, and status information, develop status
reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate
the EACf and the VACf. Based on your data, what is your assessment of the
current status of the project? At completion?

Reporte de estado al final período 2 En Miles ($000)


Tarea % de avance EV AC PV CV SV
A 75% 30 25 20 5 10
B 50% 16 12 12 4 4
Acumulado 46 37 32 9 14

Reporte de estado al final período 4 En Miles ($000)


Tarea % de avance EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
Acumulado 72 59 72 13 0

Reporte de estado al final período 6 En Miles ($000)


Tarea % de avance EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 75% 36 24 24 12 12
D 0% 0 6 0 -6
E 50% 14 10 8 4 6
Acumulado 122 93 110 29 12

Reporte de estado al final período 8 En Miles ($000)


Tarea % de avance EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 100% 48 32 48 16 0
D 33% 5.94 20 10 -14.06 -4.06
E 100% 28 20 28 8 0
F
Acumulado 153.94 131 158 22.94 -4.06

Resumen Índice desempeño


Período EV AC PV SPI CPI PCIB
2 46 37 32 1.4375 1.243243 0.223301
4 72 59 72 1 1.220339 0.349515
6 122 93 110 1.109091 1.311828 0.592233
8 153.94 131 158 0.974304 1.175115 0.747282

1.6

1.4

1.2

1
1.6

1.4

1.2

0.8

0.6

0.4

0.2

0
1 2 3 4

SPI CPI
250

PERÍODO PV EV AC
0 0 0 0 200

2 32 46 37
4 64 72 59 150
6 110 122 93
8 158 153.94 131 100
10 166
12 206
50

0
0 2 4 6 8 10

PV EV AC
6 8 10 12 14

PV EV AC
Given the following projecti network, baseline, and status information,
develop status reports for periods 1-4 and complete the project summary
grapch (or a similar one). Report the final SV, CV, CPI and PCIB. Based on your
data, what is your assessment of th current status of the project? At
completion?

Reporte de estado al final período 1


Tarea % de avance EV AC PV CV SV
1 50% 6 6 4 0 2
2 40% 6 8 3 -2 3
3 25% 2 3 4 -1 -2
Acumulado 14 17 11 -3 3

Reporte de estado al final período 2


Tarea % de avance EV AC PV CV SV
1 100% 12 13 12 -1 0
2 80% 12 14 10 -2 2
3 75% 6 8 8 -2 -2
Acumulado 30 35 30 -5 0

Reporte de estado al final período 3


Tarea % de avance EV AC PV CV SV
1 100% 12 13 12 -1 0
2 80% 12 15 15 -3 -3
3 100% 8 10 8 -2 0
4 50% 3 4 3 -1 0
5 0% 0 0 0 0 0
6 33.3% 3 4 3 -1 0
Acumulado 38 46 41 -8 -3

Reporte de estado al final período 4


Tarea % de avance EV AC PV CV SV
1 100% 12 13 12 -1 0
2 100% 15 18 15 -3 0
3 100% 8 10 8 -2 0
4 100% 6 8 6 -2 0
5 30% 3 3 6 0 -3
6 66.7% 6 8 6 -2 0
7 0% 0 0 0 0 0
Acumulado 50 60 53 -10 -3
PERÍODO PV EV AC
1 11 14 17
2 30 30 38
3 41 38 46
4 53 50 60

70

60

50

40

30

20

10

0
1 2 3 4

PV EV AC
The following labor hours data have been collected fot a nanotechnology project for
periods 1 throungh 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the
AC on the summary graph provided (or a similar one). Plot the SPI, CPI and PCIB on the
index graph provided (or a similar one). What is your assessment of the project at the end
of period 6.

Reporte de estado al final período 1


Tarea % de avance EV AC PV CV SV
1 50% 10 5 10 5 0
Acumulado 10 5 10 5 0

Reporte de estado al final período 2


Tarea % de avance EV AC PV CV SV
1 100% 24 15 10 9 14
Acumulado 24 15 10 9 14

Reporte de estado al final período 3


Tarea % de avance EV AC PV CV SV
1 100% 20 15 20 5 0
2 0% 0 0 16 0 -16
3 10% 3 2 5 1 -2
4 20% 5 5 10 0 -5
Acumulado 28 22 51 6 -23

Reporte de estado al final período 4


Tarea % de avance EV AC PV CV SV
1 100% 20 15 20 5 0
2 50% 12 10 24 2 -12
3 30% 9 8 10 1 -1
4 40% 10 15 20 -5 -10
Acumulado 51 48 74 3 -23

Reporte de estado al final período 5


Tarea % de avance EV AC PV CV SV
1 100% 20 15 20 5 0
2 100% 24 20 24 4 0
3 50% 15 8 20 7 -5
4 60% 15 15 22 0 -7
5 25% 4 4 4 0 0
Acumulado 78 62 90 16 -12

Reporte de estado al final período 6


Tarea % de avance EV AC PV CV SV
1 100% 20 15 20 5 0
2 100% 24 20 24 4 0
3 80% 24 21 23 3 1
4 80% 20 18 24 2 -4
5 50% 8 6 8 2 0
Acumulado 96 80 99 16 -3

Resumen Índice desempeño


Período EV AC PV SPI CPI PCIB
1 10 5 10 1 2 0.05
2 24 15 10 2.40 1.60 0.12
3 28 22 51 0.55 1.27 0.14
4 51 48 74 0.69 1.06 0.25
5 78 62 90 0.87 1.26 0.38
6 96 80 99 0.97 1.20 0.47

0
1 2 3 4 5 6

SPI CPI
PERÍODO PV EV AC
1 10 10 5
2 10 24 15
3 51 28
4 74 51 48
5 90 78 62
6 99 96 80

120

100

80

60

40

20

0
1 2 3 4 5 6

PV EV AC
40

20

0
1 2 3 4 5 6

PV EV AC
The folloing data have been collected for a British health care it project for two
week reporting periods 2 thtough 12. Compute the Sv, CV, SPI and CPI for each
period. Plot the EV and the AC in the summary graph provided. Plot the SPI,
CPI and PCIB on the index graph provided

Reporte de estado al final período 2


Tarea % de avance EV AC PV CV SV
1 50% 4 4 4 0 0
Acumulado 4 4 4 0 0

Reporte de estado al final período 4


Tarea % de avance EV AC PV CV SV
1 100% 8 10 8 -2 0
Acumulado 8 10 8 -2 0

Reporte de estado al final período 6


Tarea % de avance EV AC PV CV SV
1 100% 8 10 8 -2 0
2 25% 10 15 10 -5 0
3 33% 10 12 10 -2 0
4 0% 0 0 10 0 -10
Acumulado 28 37 38 -9 -10

Reporte de estado al final período 8


Tarea % de avance EV AC PV CV SV
1 100% 8 10 8 -2 0
2 30% 12 20 20 -8 -8
3 60% 18 25 25 -7 -7
4 0% 0 0 20 0 -20
Acumulado 38 55 73 -17 -35

Reporte de estado al final período 10


Tarea % de avance EV AC PV CV SV
1 100% 8 10 8 -2 0
2 60% 24 30 30 -6 -6
3 100% 30 40 30 -10 0
4 50% 10 20 20 -10 -10
5 0% 0 0 0 0 0
6 30% 18 24 20 -6 -2
Acumulado 90 124 108 -34 -18

Reporte de estado al final período 12


Tarea % de avance EV AC PV CV SV
1 100% 8 10 8 -2 0
2 100% 40 50 40 -10 0
3 100% 30 40 30 -10 0
4 100% 20 40 20 -20 0
5 50% 20 30 20 -10 0
6 50% 30 40 40 -10 -10
Acumulado 148 210 158 -62 -10

Resumen Índice desempeño


Período EV AC PV SPI CPI PCIB
2 4 4 4 1 1 0.02
4 8 10 8 1.00 0.80 0.04
6 28 37 38 0.74 0.76 0.14
8 38 55 73 0.52 0.69 0.18
10 90 124 108 0.83 0.73 0.44
12 148 210 158 0.94 0.70 0.72

Chart Title
1

0
1 2 3 4 5 6

SPI CPI
PERÍODO PV EV AC
2 4 4 4
4 8 8 10
6 38 28 37
8 73 38 55
10 108 90 124
12 158 148 210

Chart Title
250

200

150

100

50

0
1 2 3 4 5 6

PV EV AC
6
You are in charge of the Aurora Project. Given the following project network,
baseline and status information, develop status reports for periods 1-8 and
complete the performance indexes table. Calculate the EAC and VAC. Based on
your data, what is the current status of the project? At completion?

Reporte de estado al final período 1


Tarea % de avance EV AC PV CV SV
1 25% 25 50 50 -25 -25
Acumulado 25 50 50 -25 -25

Reporte de estado al final período 2


Tarea % de avance EV AC PV CV SV
1 50% 50 100 100 -50 -50
Acumulado 50 100 100 -50 -50

Reporte de estado al final período 3


Tarea % de avance EV AC PV CV SV
1 100% 100 200 100 -100 0
2 0% 0 0 100 0 -100
3 0% 0 0 150 0 -150
Acumulado 100 200 350 -100 -250

Reporte de estado al final período 4


Tarea % de avance EV AC PV CV SV
1 100% 100 200 100 -100 0
2 60% 150 100 150 50 0
3 50% 225 200 300 25 -75
Acumulado 475 500 550 -25 -75

Reporte de estado al final período 5


Tarea % de avance EV AC PV CV SV
1 100% 100 200 100 -100 0
2 100% 250 200 250 50 0
3 100% 450 400 450 50 0
Acumulado 800 800 800 0 0

Reporte de estado al final período 6


Tarea % de avance EV AC PV CV SV
A 100% 100 200 100 -100 0
B 100% 250 200 250 50 0
C 100% 450 400 450 50 0
D 75% 150 100 100 50 50
Acumulado 950 900 900 50 50

Reporte de estado al final período 7


Tarea % de avance EV AC PV CV SV
A 100% 100 200 100 -100 0
B 100% 250 200 250 50 0
C 100% 450 400 450 50 0
D 100% 200 150 200 50 0
E 20% 60 100 0 -40 60
F 5% 15 50 0 -35 15
Acumulado 1075 1100 1000 -25 75

Reporte de estado al final período 8


Tarea % de avance EV AC PV CV SV
A 100% 100 200 100 -100 0
B 100% 250 200 250 50 0
C 100% 450 400 450 50 0
D 100% 200 150 200 50 0
E 100% 300 350 200 -50 100
F 10% 30 100 100 -70 -70
Acumulado 1330 1400 1300 -70 30

Período EV AC PV SPI CPI PCIB


1 25 50 50 0.50 0.50 0.12
2 50 100 100 0.50 0.50 0.24
3 100 200 350 0.29 0.50 0.49
4 475 500 550 0.86 0.95 2.31
5 800 800 800 1.00 1.00 3.88
6 950 900 900 1.06 1.06 4.61
7 1075 1100 1000 1.08 0.98 5.22
8 1330 1400 1300 1.02 0.95 6.46
6.43 23.33

2.50

2.00

1.50

1.00

0.50

0.00
1 2 3 4 5 6 7 8

SPI CPI
0.50

0.00
1 2 3 4 5 6 7 8

SPI CPI
PERÍODO PV EV AC
1 50 25 50
2 100 50 100
3 350 100 200
4 550 475 500
5 800 800 800
6 900 950 900
7 1000 1075 1100
8 1300 1330 1400

Chart Title
1600
1400
1200
1000
800
600
400
200
0
1 2 3 4 5 6 7 8

PV EV AC

You might also like