Formato Taller Valor Ganado 2020-2
Formato Taller Valor Ganado 2020-2
Gerenci
Universidad Libre de Colombia
Período 9
AC $ 2,000
EV $ 2,100
PV $ 2,400
SV= -$ 300
CV= $ 100
On day 51 a project has an earned value of $600, an actual cost of $650, and a
planned cost of $560. Compute the SV, CV, and CPI for the project. What is your
assessment of the project on day 51?
Período 51
EV= $ 600
AC= $ 650
PV= $ 560
SV= $ 40
CV= -$ 50
CPI= 0.92 Cost Pefomance Index (Índice de desempeño de costo)
SPI= 1.07 Scheduled Perfomance Index (Índices de desempeño del cronograma)
el cronograma)
Given the project network and baseline information below, complete the form to
develop a status report for the project at the end of period 4 and the end of period 8.
From the data you have collected and computed for periods 4 and 8, what information
are you prepared to tell the customer about the status of the project at the end
of period 8?
Final período 4
Tarea % de avance EV AC PV CV SV
A Finalizado 400 300 400 100 0
B 50% 1200 1000 800 200 400
C 33% 499.5 500 600 -0.5 -100.5
D 0% 0
E 0%
F 0%
Acumulado 2099.5 1800 1800 299.5 299.5
Final período 8
Tarea % de avance EV AC PV CV SV
A Finalizado 400 300 400 100 0
B Finalizado 2400 2200 2400 200 0
C Finalizado 1500 1500 1500 0 0
D 25% 400 300 0 100 400
E 33% 297 300 -3 297
F 0%
Acumulado 4997 4600 4300 397 697
Given the following project network, baseline, and status information, develop status
reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate
the EACf and the VACf. Based on your data, what is your assessment of the
current status of the project? At completion?
1.6
1.4
1.2
1
1.6
1.4
1.2
0.8
0.6
0.4
0.2
0
1 2 3 4
SPI CPI
250
PERÍODO PV EV AC
0 0 0 0 200
2 32 46 37
4 64 72 59 150
6 110 122 93
8 158 153.94 131 100
10 166
12 206
50
0
0 2 4 6 8 10
PV EV AC
6 8 10 12 14
PV EV AC
Given the following projecti network, baseline, and status information,
develop status reports for periods 1-4 and complete the project summary
grapch (or a similar one). Report the final SV, CV, CPI and PCIB. Based on your
data, what is your assessment of th current status of the project? At
completion?
70
60
50
40
30
20
10
0
1 2 3 4
PV EV AC
The following labor hours data have been collected fot a nanotechnology project for
periods 1 throungh 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the
AC on the summary graph provided (or a similar one). Plot the SPI, CPI and PCIB on the
index graph provided (or a similar one). What is your assessment of the project at the end
of period 6.
0
1 2 3 4 5 6
SPI CPI
PERÍODO PV EV AC
1 10 10 5
2 10 24 15
3 51 28
4 74 51 48
5 90 78 62
6 99 96 80
120
100
80
60
40
20
0
1 2 3 4 5 6
PV EV AC
40
20
0
1 2 3 4 5 6
PV EV AC
The folloing data have been collected for a British health care it project for two
week reporting periods 2 thtough 12. Compute the Sv, CV, SPI and CPI for each
period. Plot the EV and the AC in the summary graph provided. Plot the SPI,
CPI and PCIB on the index graph provided
Chart Title
1
0
1 2 3 4 5 6
SPI CPI
PERÍODO PV EV AC
2 4 4 4
4 8 8 10
6 38 28 37
8 73 38 55
10 108 90 124
12 158 148 210
Chart Title
250
200
150
100
50
0
1 2 3 4 5 6
PV EV AC
6
You are in charge of the Aurora Project. Given the following project network,
baseline and status information, develop status reports for periods 1-8 and
complete the performance indexes table. Calculate the EAC and VAC. Based on
your data, what is the current status of the project? At completion?
2.50
2.00
1.50
1.00
0.50
0.00
1 2 3 4 5 6 7 8
SPI CPI
0.50
0.00
1 2 3 4 5 6 7 8
SPI CPI
PERÍODO PV EV AC
1 50 25 50
2 100 50 100
3 350 100 200
4 550 475 500
5 800 800 800
6 900 950 900
7 1000 1075 1100
8 1300 1330 1400
Chart Title
1600
1400
1200
1000
800
600
400
200
0
1 2 3 4 5 6 7 8
PV EV AC