Professional Documents
Culture Documents
Principles of Project Management: Hisham Rafik, Presented by
Principles of Project Management: Hisham Rafik, Presented by
Project Planning
Schedule Development
Scope Definition
Schedule Development
Budgeting
1. Activity Definition
Convert work packages to manageable tasks Æ project activities
2. Activity Sequencing
Sequence and link the tasks and milestones Æ PERT chart (Network
Diagram)
3. Activity Resource Estimating:
Identify the resources available and Assign Responsibility for each
task (or group of tasks) Æ Responsibility Assignment Matrix
4. Activity Duration Estimating:
Estimate the Duration for each activity Æ Activity Duration
Estimates
5. Schedule Development:
Calculate the Critical Path and Develop project schedule Æ GANTT
Chart
1. Decomposition
Subdividing project work package into smaller, more
manageable components called schedule activities.
2. Templates
A standard activity list or a portion of an activity list from a
previous project. It can also contain a list of resource
skills and their required hours of effort, identification of
risks, expected deliverables, and other descriptive
information.
3. External dependencies
Are those that involve a relationship between project
activities and non-project activities.
© Knowledge 2008 Principles of Project Management 16
Dependencies Relationships
Predecessor Successor
(A) Finish-To-Start
Activity A Activity B
(B) Start-To Start
Activity A
Activity B
(C) Finish-To-Finish
Activity A
Activity B
(D) Start-To-Finish
Activity A
Activity B
© Knowledge 2008 Principles of Project Management 17
Applying leads and lags
Finished to start
- Activity (A) must finish
1 2 3 4 5 6 7 8 9 10
before (B) can start
A (du = 4) FS 0
Finished to start (FS + 3wks lag)
- Activity (A) Must be finished for
3 weeks before (B) can start B (du=3)
- The start of activity (B) lags
the finish of (A) by 3 week A (du = 4)
- The finish of A leads the start FS+3
of B by 3 weeks
B (du=3)
Finished to start (FS - 3wks lag)
- Activity (B) can start three weeks prior to
A (du = 4)
the finish of (A) .
FS-3
- The start of activity (B) leads the
projected finish of (A) by 3 weeks B (du=3)
- The finish of (A) lags the start
of (B) by 3 weeks
© Knowledge 2008 Principles of Project Management 18
Project Time Management
3. Activity Resource Estimating
Estimating schedule activity resource involves determining
what resources (persons, equipment, or material) and what
quantities of each resource will be used, and when each
resource will be available to perform project activities.
2. Resource Allocation
Assign the resources needed to each activity
We can use the Responsibility Assignment Matrix
to document this allocation
4. Reserve Analysis
Additional time frame, called reserve, buffer, or
contingency, that can be added to the activity duration
or elsewhere in the schedule as recognition of schedule
risk.
Activity A
Activity B
Activity C
Activity D
Milestones Chart/Table
Similar to bar chart, but only identify the scheduled start or
completion of major deliverables.
Financials, Approvals, Deliverables, handover points
Report progress to Management and Customer
3. Schedule Baseline
Is the accepted and approved version of the project
schedule.
resources
Schedule Compression
Fast Tracking:
6 6
A 2 4 6 4 0.67 0.44
B 3 5 7 5 0.67 0.44
C 4 7 10 7 1 1
D 4 5 6 5 0.33 0.11
Crashing Cost B
A
C D
2. Resource Allocation
3. Resource Utilization
Draw the resource Histogram that shows the total
number of resources needed during each time period of
the project
4. Resource leveling
Smoothen the use resources across the project total
duration to ensure that resources needed (shown on the
histogram) do not exceed resources available (as per list
of identified resources)
200
175
Senior Designers
150
125
100
75
50
25
0
9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22
Jan Feb Mar Apr May
1. Activity Definition
Convert work packages to manageable tasks Æ project activities
2. Activity Sequencing
Sequence and link the tasks and milestones Æ PERT chart (Network
Diagram)
3. Activity Resource Estimating:
Identify the resources available and Assign Responsibility for each
task (or group of tasks) Æ Responsibility Assignment Matrix
4. Activity Duration Estimating:
Estimate the Duration for each activity Æ Activity Duration
Estimates
5. Schedule Development:
Calculate the Critical Path and Develop project schedule Æ GANTT
Chart