Planning Strategy 11 Gross Requirement Planning
--------------------------------------------------------------------------------------------------------------------------------------
Make to Stock

Strategy 11:- Gross requirement planning

Planned Independent Requirement type is BSF

Customer Requirement type is KSL

Strategy 11 is gross requirement MTS strategy, which does not considers available stock, customer
requirement is getting displayed only for information purpose.

--------------------------------------------------------------------------------------------------------------------------------------
Created by: - Devidas Karad
SAP PP Certified Consultant
E-mail:- devidas.karad@gmail.com
https://sites.google.com/site/sapppdocs
Planning Strategy 11 Gross Requirement Planning
--------------------------------------------------------------------------------------------------------------------------------------

Example:-

Available stock is 10 PC

Customer order is for 5 PC

PIR is created for 15 PC and MRP Run is carried out

Result: - Planned order for all quantity i.e. for 15PC is created

--------------------------------------------------------------------------------------------------------------------------------------
Created by: - Devidas Karad
SAP PP Certified Consultant
E-mail:- devidas.karad@gmail.com
https://sites.google.com/site/sapppdocs
Planning Strategy 11 Gross Requirement Planning
--------------------------------------------------------------------------------------------------------------------------------------

System does not consider stock in planning strategy 11.

--------------------------------------------------------------------------------------------------------------------------------------
Created by: - Devidas Karad
SAP PP Certified Consultant
E-mail:- devidas.karad@gmail.com