Professional Documents
Culture Documents
Welding Procedure Specification (WPS)
Welding Procedure Specification (WPS)
Engineer Description
Versi Prepare Quality Safety Approv
Status ing Date of
on d by ed by
Reviewed by Modification
Ltd. Without written permission of the Company, this Document shall not be
PAGE 1 of 31
Welding procedure specification TEPC-Welding-A04-002
Table of Contents
1. Preface ..................................................................................................................................................................... 3
3.4 PWHT......................................................................................................................................................................... 5
PAGE 2 of 31
Welding procedure specification TEPC-Welding-A04-002
1. Preface
This specification is applicable to the welding work at site work of Iraq Amara Transformation Project from
Single Cycle to Combined Cycle, and specifies the range of various parameters and variables in the welding
process. According to the joint stress characteristics of the site erection weld, the welding work is divided into
the welding of pressure parts and the welding of non-pressure parts. Welding Procedure Specification for
pressure parts are prepared per ASME Section IX welding and brazing, and Welding Procedure
Specification for non-pressure parts are prepared per AWS D1.1 Steel structure welding Specification.
2. Scope of Application
Containers bearing internal or external pressure greater than 0.1MP are classified as pressure parts.
Pressure parts involved in site welding mainly include thermal pipelines, fluid delivery pipelines, buried
pipelines, oil and gas pipelines, steam pipelines, supports and hangers welded with pipelines, closed
containers, vessels, etc.
Welding methods are shielded manual arc welding (SMAW) and gas tungsten arc welding (GTAW).The weld
is designed as completed penetration weld of butt joint. Back gouging process is applied to root-clearing for
plate butt joints. In principle, all GTAW process should be applied for pipeline butt weld with wall thickness
less than 10.97mm.For pipes with wall thickness greater than 10.97mm, GTAW is applied to root welding
pass, and other are welded by SMAW.
Containers bearing internal or external pressure are less than 0.1MPa, steel frame structure with statically or
cyclically load is classified as Non-Pressure Parts. the welding work involves Non-Pressure Parts mainly
include boiler steel structure, module casing, the bypass damper, import and export duct and chimney, pipe
rack, supports and hangers of pipelines, stair structure, platform, railings, open containers, etc.
Welding methods are Shielded Manual Arc Welding (SMAW) and Gas Metal Arc Welding (GMAW).Weld
design is mostly fillet weld and partial penetration. For butt joints with full penetration requirements, back
gouging with root-cleaning or additional backing process will be applied.
b) All welding grooves must be made and assembled in accordance with the drawings and WPS
requirements. The base metal surface of groove and its outer 20mm area shall be polished to reveal the
metal luster, and oil, rust and other debris affecting the welding quality shall be removed. No cracks, residues,
pores and other defects shall be allowed.
PAGE 3 of 31
Welding procedure specification TEPC-Welding-A04-002
c) Welding materials shall be stored, kept and used in accordance with the on-site welding material
management system. Baking and keeping the welding material warm and clean before use.
a) When the surface temperature of the base material is lower than 0℃, welding is not allowed and
preheating must be carried out. The preheat temperature shall meet the requirements of WPS, and the
heating area shall be 2 times the wall thickness around the welding place or 75mm (whichever is larger).The
inter-pass temperature shall not be lower than the preheat temperature.
b) All welding process variable shall be controlled within the WPS range.
c) During welding, welding slag, flux and other sundries on the welding path must be removed in time
before welding. Stainless steel welds shall be cleaned with a stainless steel wire brush and a ferrite free
grinding wheel that has not been polished the ferrite material.
d) Cracks and pores appearing in the weld bead before application of the next bead must be removed
promptly.
e) The allowed welding position depends on the PQR. Without special PQR, downward welding is not
allowed.
f) Alloy pipes shall be aligned by adjusting devices. For removal the temporary adjustment accessories of
alloy pipe, leave about 3mm on the base material, and then grind off the remaining parts. It is not allowed to
knock off the accessories directly with a hammer. After grinding and removing welding scar, perform 100%PT
inspection, and have field record.
g) The start and stop position of the weld pass shall not coincide with other pass start and stop position, at
least 10mm apart.
h) If carbon arc air gouging applied to remove root weld on the back, the carburized layer shall be removed
by grinding.
i) Alloy pipes shall be welded in thin strip and narrow pass as far as possible.
For joints with preheat requirements specified in WPS, the following conditions shall be met before welding is
interrupted.
a) The thickness of the cladding metal has reached 10mm or 25% of the groove weld thickness, whichever
is greater, and sufficient strength shall be considered.
b) When the welding of P91 joint is forced to be interrupted, the preheat temperature should always be
maintained during the interruption until the welding is restarted, to prevent the occurrence of cracks and other
PAGE 4 of 31
Welding procedure specification TEPC-Welding-A04-002
defects. Before welding again, carefully check and confirm that no crack is found, then continue welding
according to the WPS requirements.
c) Other base materials can be cooled to room temperature slowly with thermal insulation after welding is
interrupted. Visual inspection should be carried out before welding again to ensure no cracks. Then heating
to the preheat temperature requirements specified by WPS, welding can be going on.
3.4 PWHT
a) The weld surface shall not have defects such as lack of penetration, lack of fusion, crack, porosity,
undercut, inclusion, etc.; the weld surface shall be free from rough ripples, groove weld lap, pits and other
defects, and the weld shall have smooth transition from the base material.
b) The weld shall not be lower than the base material, and the residual height shall not exceed 3mm unless
otherwise specified.
c) The foot height of fillet weld is strictly prohibited to be smaller than that required in the drawing.
d) Detailed inspection in accordance with ASME IX and AWS D1.1 technical requirements.
3.5.2 NDT
The weld that needs to be NDT must pass the visual inspection, NDT should be carried out according to the
drawing and on-site NDT procedure requirements.
a) Accurately mark the location of defects on the welds according to the NDT inspection report, which shall
be inspected and confirmed by the inspectors.
b) Defects shall be removed by mechanical method or carbon arc gouging. Preheat at least 150℃ before
carbon arc gouging, and the preheat range of each side of the weld shall be no less than 2 times the wall
thickness of the base material or 75mm (the larger value shall be taken). After carbon arc gouging, the
carburized layer shall be removed by grinding.
c) The groove size requires that a margin of 2-5mm be increased on all direction compared to the defect
location. The inside and outside of the groove and around the edge are polished to reveal the metallic luster
within a range of more than 20mm, and 100%PT inspection is carried out to confirm that the defect has been
completely removed, which is qualified by the inspector.
d) The repair welding procedure shall follow the original WPS of the weld. After the repair, the original NDT
shall be re-inspected according to the original NDT requirements on the basis of qualified visual inspection.
PAGE 5 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 6 of 31
Welding procedure specification TEPC-Welding-A04-002
4.2 WPS
PAGE 7 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 8 of 31
Welding procedure specification TEPC-Welding-A04-002
Travel
Voltage
Filler Metal Current Speed Other
Weld Layer(s) Process (V)
(mm/min) s
Class Dia.(mm) Polarity Amp.(A)
1 GTAW ER90S-B3 2.5 DC 100-130 unlimited 40-70
2 SMAW E9015-B3 2.5 DC 80-100 unlimited 70-130
3 to end SMAW E9015-B3 3.2 DC 100-130 unlimited 100-160
PAGE 9 of 31
Welding procedure specification TEPC-Welding-A04-002
Travel
Voltage
Filler Metal Current Speed Other
Weld Layer(s) Process (V)
(mm/min) s
Class Dia.(mm) Polarity Amp.(A)
1 GTAW ER90S-B3 2.5 DC 100-130 unlimited 25-90
2 to end GTAW ER90S-B3 2.5 DC 100-130 unlimited 25-90
PAGE 10 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 11 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 12 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 13 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 14 of 31
Welding procedure specification TEPC-Welding-A04-002
Travel
Voltage
Filler Metal Current Speed Other
Weld Layer(s) Process (V)
(mm/min) s
Class Dia.(mm) Polarity Amp.(A)
1 GTAW ER316L 2.4 DC 90-130 unlimited 30-90
2 GTAW ER316L 2.4 DC 90-130 unlimited 30-90
3 to end GTAW ER316L 2.4 DC 90-130 unlimited 30-90
PAGE 15 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 16 of 31
Welding procedure specification TEPC-Welding-A04-002
PAGE 17 of 31
Welding procedure specification TEPC-Welding-A04-002
5.2 WPS
WPS NO. G01
5 Preheat (QW-406)
4. Positions (QW-405)
5.1 Minimum Preheat Temp. Min. 0°C Heating to 20℃ if below 0℃
4.1Position(s) of Groove N.A
5.2 Maximum Inter-pass Temp. Max. ≤300 °C
4.2 Welding Progression
5.3 Preheat Maintenance None .
Up □Down
口 Flame □Heater □Furnace
4.3 Position(s) of Fillet ALL
5.4 Dehydrogenation Temp./Time rang:None
PAGE 18 of 31
Welding procedure specification TEPC-Welding-A04-002
7 Gas (QW-408)
6 PWHT(QW-407) Gas(es) Mixture Flow Rate
6.1 Temp. Range N.A ℃
6.2 Time Range N.A 7.1Shielding N.A N.A. N.A
6.3 Others None 7.2Trailing N.A N. A. N. A.
7.3Backing N.A N. A. N. A.
Only ∅3.2 electrode shall be used when the weld thickness 4mm; When the the weld thickness more than 4mm, but < 6mm, the
max. size electrode∅4.0 is allowed to use.
9 Technique (QW-410)
9.1Straight Welding or Swing Welding String or Weave Bead
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side) □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Work Distance N. A.
9.8 Closed to Out Chamber N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging □ Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 19 of 31
Welding procedure specification TEPC-Welding-A04-002
PQRNO.BG-002-SMAW-1.1+1.1-1
Welding Procedure Specification(WPS) A 2020-08-10
G(2G\3G)
1 Base Metal(QW-403)
2 joint
1.1Material Spec. GB1591 Q355B / GB700 Q235 To
2.1 Joint design See Below
GB1591 Q355B / GB700 Q235
2.2 Backing □ Yes No
1.2Type or Grade
2.3 Backing Material NA
1.3P-No. Group No. To
2.4No molding blocks
P-No. Group No.
1.4Thickness Range
Groove 5-28 mm Fillet ALL mm
1.5Pipe Diameter Range
Groove 5-28 mm Fillet ALL mm
See Drawing for the Details of Groove
1.6Others None
3 Filler Metals (QW-404) GTAW SMAW
3.1 Specification No.(SFA) N.A 5.1
3.2 AWS AWS NO.(Class) N.A E7015
3.3 F-No./A-No. N.A 4
3.4 Size of Filler Metals N.A ∅3.2, ∅4.0
3.5 Thickness Range of Deposit Groove N.A ALL
Metal Fillet N.A ALL
3.6 Electrode-Flux (Class) N.A. N.A.
3.7 Flux Trade Name N.A. N.A.
3.8 Electrode Trade Name Not Specif Not Specif
3.9 Flux Type N.A. N.A.
Alloy Flux N.A. N.A.
Alloy Elements N.A. N.A.
Supplemental Filler Metal N.A. N.A.
3.13 Recrushed Slag N.A. N.A.
3.14 Deletion or Addition of Filler Metal N.A. N.A.
Filler Metal Product Form N.A. N.A.
melting stuff N.A. N.A.
Addition or Deletion of Flux N.A. N.A.
5 PREHEAT (QW-406)
4 POSITIONS (QW-405) 5.1 Minimum Preheat Temp. Min. 0°C Heating to 20℃ if below
4.1 Position(s) of Groove :1G/2G/3G 0℃(preheating to 100 ℃ with thickness greater than 25mm)
4.2 Welding Progression 5.2 Inter-pass Temp. Max. ≤300 °C
Up □Down 5.3 Preheat Maintenance None .
4.3 Position(s) of Fillet 1F/2F/3F 口 Flame □Heater □Furnace
5.4 Dehydrogenation Temp./Time range None.
PAGE 20 of 31
Welding procedure specification TEPC-Welding-A04-002
7 GAS (QW-408)
6 PWHT(QW-407) Gas(es) Mixture Flow Rate
6.1Temp. Range N.A ℃
6.2Time Range N.A Min 7.1Shielding N.A N.A N.A
6.3Others None . 7.2Trailing N.A N. A N. A
7.3Backing N.A N. A N. A
9 TECHNIQUE (QW-410)
9.1Straight Welding or Swing Welding Straight Welding or Swing Welding
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Workpiece Distance N. A.
9.8 Closed-chamber Welding or Outdoor Welding N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging □ Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 21 of 31
Welding procedure specification TEPC-Welding-A04-002
1 Base Metal(QW-403)
2 joint
1.1Material Spec. GB1591 Q355B / GB700 Q235 To
2.1 Joint design See Below
GB1591 Q355B / GB700 Q235
2.2 Backing □ Yes No
1.2Type or Grade
2.3 Backing Material NA
1.3P-No. Group No. To
2.4No retainer
P-No. Group No.
1.4Thickness Range
Groove 5-28 mm Fillet ALL mm
1.5Pipe Diameter Range
Groove N.A mm Fillet All mm
See Drawing for the Details of Groove
1.7Others None
3Filler Metals (QW-404) GTAW SMAW
3.1Specification No.(SFA) N.A. 5.1
3.2 AWSAWS NO.(Class) N.A. E7015
3.3 F-No./A-No. N.A. 4
3.4 Size of Filler Metals N.A. ∅3.2, ∅4.0
3.5 Thickness Range of Deposit Groove N.A. ALL
Metal Fillet N.A. ALL
3.6 Electrode-Flux (Class) N.A. N.A.
3.7Flux Trade Name N.A. N.A.
3.8 Electrode Trade Name Not Specif Not Specif
3.9Flux Type N.A. N.A.
Alloy Flux N.A. N.A.
Alloy Elements N.A. N.A.
Supplemental Filler Metal N.A. N.A.
3.13 Recrushed Slag N.A. N.A.
3.14 Deletion or Addition of Filler Metal N.A. N.A.
Filler Metal Product Form N.A. N.A.
melting stuff N.A. N.A.
Addition or Deletion of Flux N.A. N.A.
5 PREHEAT (QW-406)
4 POSITIONS (QW-405) 5.1 Minimum Preheat Temp. Min. 0°C Heating to 20℃ if below
4.1 Position(s) of Groove 1G 2G 3G 0℃(preheating to 100 ℃ with thickness greater than 25mm)
4.2 Welding Progression 5.2 Maximum Inter-pass Temp ≤300 °C
Up □Down 5.3 Preheat Maintenance None .
4.3 Position(s) of Fillet 1F 2F 3F 口 Flame □Heater □Furnace
5.4 Dehydrogenation Temp./Time rang None
PAGE 22 of 31
Welding procedure specification TEPC-Welding-A04-002
Only ∅3.2 electrodes shall be used when the weld thickness 4mm; When the weld thickness is more than 4mm, but < 6mm, the
maximum allowable electrode size is ∅4.0.
9 TECHNIQUE (QW-410)
9.1Straight Welding or Swing Welding_ Straight Welding or Swing Welding
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side) □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Workpiece Distance N. A.
9.8 Closed-chamber Welding or Outdoor Welding N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging Grinding Arc-air Gouging Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 23 of 31
Welding procedure specification TEPC-Welding-A04-002
5 PREHEAT (QW-406)
4 POSITIONS (QW-405)
5.1 Minimum Preheat Temp. Min. 0°C heat to 20℃ if below 0℃
4.1 Position(s) of Groove N.A
5.2 Maximum Inter-pass Temp ≤300 °C
4.2 Welding Progression
5.3 Preheat Maintenance None .
Up □Down
口 Flame □Heater □Furnace
4.3 Position(s) of Fillet ALL
5.4 Dehydrogenation Temp./Time rang None .
PAGE 24 of 31
Welding procedure specification TEPC-Welding-A04-002
9TECHNIQUE (QW-410)
9.1Straight Welding or Swing Welding _Straight Welding or Swing Welding
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side) □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Workpiece Distance N. A.
9.8 Closed-chamber Welding or Outdoor Welding N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging
□ Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 25 of 31
Welding procedure specification TEPC-Welding-A04-002
PQRNO.
Welding Procedure Specification(WPS) A 2020-08-10
BG-012-SMAW-8.1+8.1-2G
WELDING PROCESS(ES): □GTAW SMAW □SAW □GMAW □ESW
TYPE(S): □ Automatic Manual □ Machine □ Semi- Automatic
2 joint
1 Base Metal(QW-403) 2.1 Joint design See Below
1.1 Material 316 To 316 2.2 Backing □ Yes No
1.2Type or Grade 2.3 Backing Material NA
1.3P-No. 8 Group No. 1 To 2.4No retainer
P-No. 8 Group No. 1
1.4Thickness Range
Groove N.A mm Fillet ALL mm
1.5Pipe Diameter Range
Groove N.A mm Fillet ALL mm
1.7Others None
See Drawing for the Details of Groove
5 PREHEAT (QW-406)
4 POSITIONS (QW-405)
5.1Minimum Preheat Temp. Min. 0°C Heating to 20℃ if below 0℃
4.1 Position(s) of Groove N.A
5.2 Maximum Inter-pass Temp ≤300 °C
4.2 Welding Progression
5.3 Preheat Maintenance None .
Up □Down
口 Flame □Heater □Furnace
4.3 Position(s) of Fillet ALL
5.4 Dehydrogenation Temp./Time rang None .
PAGE 26 of 31
Welding procedure specification TEPC-Welding-A04-002
Only ∅3.2 electrodes shall be used when the weld thickness 4mm; When the weld thickness is more than 4mm, but < 6mm, the
maximum allowable electrode size is ∅4.0.
9 TECHNIQUE (QW-410)
9.1Straight Welding or Swing Welding Straight Welding or Swing Welding
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side) : □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Workpiece Distance N. A.
9.8 Closed-chamber Welding or Outdoor Welding N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging □ Machine None
9.11 Peening □Yes None
9.12Others N.A.
PAGE 27 of 31
Welding procedure specification TEPC-Welding-A04-002
PQRNO.
Welding Procedure Specification(WPS) A 2020-08-10
BG-012-SMAW-8.1+8.1-2G
WELDING PROCESS(ES): □GTAW SMAW □SAW □GMAW □ESW
TYPE(S): □ Automatic Manual □ Machine □ Semi- Automatic
2 joint
1 Base Metal(QW-403) 2.1 Joint design See Below
1.1 Material 409 To 409 2.2 Backing □ Yes □ No
1.2Type or Grade 2.3 Backing Material NA
1.3P-No. 8 Group No. 1 To 2.4No retainer
P-No. 8 Group No. 1
1.4Thickness Range
Groove N.A mm Fillet ALL mm
1.5Pipe Diameter Range
Groove N.A mm Fillet ALL mm
1.7Others None
See Drawing for the Details of Groove
5 PREHEAT (QW-406)
4 POSITIONS (QW-405)
5.1 Minimum Preheat Temp. Min. 0°C Heating to 20℃ if below 0℃
4.1 Position(s) of Groove N.A
5.2 Maximum Inter-pass Temp ≤300 °C
4.2 Welding Progression
5.3 Preheat Maintenance None .
Up □Down
口 Flame □Heater □Furnace
4.3Position(s) of Fillet ALL
5.4 Dehydrogenation Temp./Time rang None .
PAGE 28 of 31
Welding procedure specification TEPC-Welding-A04-002
Only ∅3.2 electrode shall be used when the weld thickness 4mm; When the weld thickness is more than 4mm, but < 6mm, the
maximum allowable electrode size is ∅4.0.
9 TECHNIQUE (QW-410)
9.1Straight Welding or Swing Welding Straight Welding or Swing Welding
9.2 Swing Method N. A.
9.3Multiple or Single Pass (per side) : □ Single Pass Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5 Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A
9.7 Contact Tube to Workpiece Distance N. A.
9.8 Closed-chamber Welding or Outdoor Welding N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging □ Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 29 of 31
Welding procedure specification TEPC-Welding-A04-002
Revision
Date Supporting PQR No. (s)
No.
5PREHEAT (QW-406)
4. POSITIONS (QW-405)
5.1 Preheat Temp. Min. 0°C Heating to 20℃ if below 0℃
4.1 Position(s) of Groove N.A
5.2 Inter-pass Temp. Max. ≤300 °C
4.2 Welding Progression
5.3 Preheat Maintenance None .
Up □Down
口Flame □Heater □Furnace
4.3 Position(s) of Fillet ALL
5.4Dehydrogenation Temp./Time rang None
PAGE 30 of 31
Welding procedure specification TEPC-Welding-A04-002
7 GAS (QW-408)
6PWHT(QW-407)
Gas(es) Mixture Flow Rate
6.1Temp.rang N.A ℃
7.1Shielding N.A N.A. N.A
6.2Time.rang N.A Min
7.2Trailing N.A N.A. N.A
6.3Others None .
7.3Backing N.A N.A. N.A
Only ∅3.2 electrode shall be used when the weld thickness 4mm; When the the weld thickness more than 4mm, but < 6mm, the
max. size electrode∅4.0 is allowed to use.
9 TECHNIQUE (QW-410)
9.1String or Weave Bead Weave Bead
9.2 Oscillation No control
9.3Multiple or Single Pass (per side): Single Pass 口 Multiple Pass
9.4 Multiple or Single Electrodes □ Multiple Electrode 口 Single Electrode
9.5Electrode Spacing. N. A.
9.6 Orifice or Gas Cup Size N.A.
9.7 Contact Tube to Work Distance N. A.
9.8Closed to Out Chamber N. A.
9.9 Initial and Inter-pass Cleaning Brushing or Grinding
9.10 Method of Back Gouging □ Grinding □ Arc-air Gouging □ Machine None
9.11 Peening □ Yes None
9.12 Others N.A.
PAGE 31 of 31