BUILDING WORKS AT HOUGANG TOWN

DAILY SITE PHOTOS


DAILY SITE RECORD Wednesday, September 23, 2020

Activities Location Description of works Remarks


Structural work PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 20 nos.
total Number OF Pile Caps@ Lower Deck 28 nos. 71.43%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
total Number OF Pile Caps 29 nos. 100.00%
Structural work

MSCP PILES 100.00%

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES 100.00%

TOWER CRANE PILE CAP CAST 100.00%

CAPPING BEAMS CAST TO DATE 82.00%

1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%


DETENTION DRAIN CAST TO DATE 88.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW

SITE VIEW
work
Architectural
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 71.43% CAST STAIRCASE #1 PILE CAP

8 MORE Pile caps to complete at lower Deck Level , GREEN SHADES


@ Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PITAPPLIED DAVCO WATERPROOFING
MEMBRANE, ON GOIMG EXCAVATION WORKS FOR PILE CAPS AT
GRIDLINE A 1 1 to 4.

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2

Site Supervisor 1 Safety Supervisor 1 Excavator CL 1 @ IC WORKS #4 TO


@ DETENTION
Safety officer LOWER DECK DEEP IC#3: INSTALL 150MM
BEAM DISMANTLE -
DRAIN: UPDATED
08:30 17:30 1 FORMWORK 2 DETENTION
AT 88% COMPLETE DRAIN
DIAMETER DUCTILE
IRON PIPE
Site engineer 1
BAR BENDER MACHINE 1

RTO BIG BREAKER


ESS REBAR-
1 4 1
@ REMAINING
FORMWORKS
AREA OF
STAIRCASE#1 REBAR 1 TONNE ROLLER- SLAB BOTTOM BARS
FORMWORKS COMPACTOR
DETENTION DRAIN
REMARKS Administrator 1 2 1 AND DROP PANEL
TO COMPLETE
UPPER /LOWER AIR RECEIVER
@12%
Coordinator 1 DECKSLAB/DROP PANEL 12 22 1

ECO 1 TC INSTALLED 1

Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR 1 5
IC WORKS IC#4
FAIR
EXCAV SUPVSR 1
Manpower
8:30AM 5:30PM
TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION SLAB BOTTOM BARS AND DROP PANEL BARS INSTALLED 1ST SEGMENT OF
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF SLAB TARGRET TO CAST ON 29 SEPTEMBER 2020
WORKS

PROJECT SITE ACTIVITIES PHOTOS AND REFERENCE KEY PLANS


Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 60.71% 11 Pile caps more to complete at lower Deck Level , GREEN
SHADES @ Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL SUBSTATION AREA, AT LIFT
PIT PREPARATION TO RECEIVE DAVCO WATERPROOFING MEMBRANE, ON GOIMG EXCAVATION WORKS FOR RC SUMPS AND PIPE
CAST 3 8 MORE
PILE CAPS AT GRIDLINE A 1 1 to 4. PILE CAPS
HAUNCHING @43.00%
PILE
COMPLETE
CAPS
DETENTION DRAIN @88% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED
AT LATER STAGES OF WORKS

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 43.00% COMPLETE STAIRCASE #1 PILE CAP CAST. KEY PLAN SHOWING 8 MORE PILE CAPS KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
TO CAST AT LOWER DECK LEVEL 43.00% COMPLETE

SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS IN
PROGRESS, DONE UNTIL GRIDLINE 12-9C-G @75% COMPLETED FIRST SEGMENT OF SLAB 01B GROUND BEAM AND DROP PANEL,SLAB
TARGET TO CAST ON 29 SEPTEMBER
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G

ESS

AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS WEEK. SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN
REINFORCING BARS IN PROGRESS, DONE UNTIL GRIDLINE 12-9C-G @75% THIS WEEK.
COMPLETED FIRST SEGMENT OF SLAB 01B TARGET TO CAST ON 29
SEPTEMBER

LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE COVERED WITH HARD
POLYFOAM PROTECTION TO NEWLY INSTALLED WATERPROOFING MEMBRANE PRIOR TO
BACKFILLING WORKS REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE
COVERED WITH HARD POLYFOAM PROTECTION TO NEWLY INSTALLED
INSTALLED, 4 SPLIT LEVEL WALLS APPLIED WITH DAVCO WATERPROOFING MEMBRANE
WATERPROOFING MEMBRANE PRIOR TO BACKFILLING WORKS

22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND DOING SITEWORKS: 22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND
INSTALLED 10 DROP PANELS SLAB SPLIT LEVEL BEAM APPLIED
DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP
BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT BOTTOM REINFORCING BARS AND 3 DAVCO WATERPROOF
BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT DISMANTLE
DISMANTLE FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS UPSTAND ROWS OF GROUND BEAMS INSTALLED MEMBRANE
AT GRID LINE 12 T0 9 D E F G FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS UPSTAND
BEAMSFORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 BEAMSFORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP
REBAR WORKERS 8 DEPLOYED WORKERS TO DO WATERPROOFING PREPARATION GRINDING PANEL REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED WORKERS TO
TOUCH UP, ASSIST TOWER CRANE, SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING DO WATERPROOFING PREPARATION GRINDING TOUCH UP, ASSIST
@ELECTRICAL SUBSTATION
TOWER CRANE, SHIFTING OF MATERIALS/ HOUSEKEEPING
AND OTHER SITE WORKS BELOW TRANSFORMER
HOUSEKEEPING AND OTHER SITE WORKS
ROOM : INSTALLING
REBARS FOR UPSTAND
BEAMS TO CAST WITHIN
THIS WEEK

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed


OTHER PERTINENT ACTIVITIES

E
F
G
C

9
9

SLAB REINFORCING BARS IN PROGRESS,


INSTALLING FORWORKS FOR SCUPPER DRAINS,
LEVEL MARKING OF HIGH POINT AND LOW POINT
ON SLAB, TO CAST 12 TO 9 D TO G

CAST STAIRCASE #1 PILE CAP

AT ELECTRICAL SUBSTATION BELOW


TRANSFORMER ROOM , INSTALLING UPSTAND
BEAM REBARS, TO CAST THIS WEEK