BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Monday, September 21, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 17 nos.
total Number OF Pile Caps@ Lower Deck 28 nos. 60.71%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
total Number OF Pile Caps 29 nos. 100.00%
Structural work

MSCP PILES 100.00%

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES 100.00%

TOWER CRANE PILE CAP CAST 100.00%

CAPPING BEAMS CAST TO DATE 82.00%

1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%


DETENTION DRAIN CAST TO DATE 88.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW
Architectural
work

@ LIFT CORE WALL SURFACE PREPARATION


TO RECEIVE DAVCO WATERPROOFING
MEMBRANE
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% LIFT COREWALL GRINDING TOUCH UP DO CHAMFER TO RECEIVE
WATERPROOFING MEMBRANE
11 Pile caps more to complete at lower Deck Level , GREEN SHADES
@ Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PIT PREPARATION TO RECEIVE DAVCO
WATERPROOFING MEMBRANE

MAIN C ON STRUC TURAL ARC HITEC TURAL M&E MAC HINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2

Site Supervisor 1 Safety Supervisor 1 Excavator CL 1


@ DETENTION @ IC WORKS #4 TO SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and 2
Safety officer LOWER DECK DEEP BEAM
IC#3: INSTALL 150MM WORKERS INSTALLED DAVCO WATERPROOF
DISMANTLE - FORMWORK DRAIN: UPDATED MEMBRANE MATERIALS, WALL BESIDES INSTALLED
08:30 17:30 1 2 DETENTION
AT 88% COMPLETE DRAIN
DIAMETER DUCTILE SUBSOIL PERFORATED PIPES
IRON PIPE
Site engineer LIFT PIT REBAR FORMWORKS / BAR BENDER MACHINE
1 4 1
CAST
RTO BIG BREAKER
ESS FORMWORKS
1 4 1
@ REMAINING
AREA OF
PREPARATION FOR WATER 1 TONNE ROLLER- COMPACTOR
Administrator
PROOFING GRINDING TOUCH DETENTION DRAIN
REMARKS 1 2 1
UP TO COMPLETE
UPPER /LOWER AIR RECEIVER
@12%
DECKSLAB/DROP PANEL/ 22
Coordinator 1 8 1
INSTALLATION

TC INSTALLED
ECO 1 1

Weather G Worker 10

TC OPERATOR 1
LB D HAC K TEAM 3
EXCAV. OPTR 1 IC WORKS IC#4 5
FAIR
EXC AV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and 2 WORKERS INSTALL
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF DAVCO WATERPROOF MEMBRANE MATERIALS
WORKS
Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 60.71% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE CAP @
96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND FORMWORKS RC SUMPS AND PIPE
INSTALLATION IN PROGRESS HAUNCHING REMAINS
@42.86% COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING 11 MORE PILE CAPS TO CAST AT LOWER DECK KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
LEVEL, STAIRCASE #1 PILE CAP TO BE CAST THIS WEEK 42.86% COMPLETE

SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS AND TOP REINFORCING BARS
DONEUNTIL GRIDLINE 12-9F-G 70% COMPLETED, GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
ESS

RWDP INSTALLED
AWAITING
INSPECTION

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS

REINFORCING BARS AND TOP REINFORCING BARS DONEUNTIL GRIDLINE 12- WEEK.

9F-G 70% COMPLETED,

RC COREWALL: SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOF MEMBRANE

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL WALLS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE RC COREWALL: SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOF
WB4a WB4 WB5 CAST MEMBRANE

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM FORMWORK 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALLED 10 DROP PANELS SLAB SPLIT LEVEL BEAM APPLIED
INSTALL / 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS DISMANTLE DEEP BEAM
BOTTOM REINFORCING BARS AND 3 DAVCO WATERPROOF MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / 6
FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED TO
ROWS OF GROUND BEAMS MEMBRANE
WORKERS , WATERPROOFING PREPARATION GRINDING TOUCH UP, ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4
INSTALLED
HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER

/LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8


@ELECTRICAL SUBSTATION DEPLOYED TO WORKERS , WATERPROOFING PREPARATION GRINDING
BELOW TRANSFORMER
TOUCH UP, ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/
ROOM : INSTALLING
REBARS FOR UPSTAND HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS
BEAMS TO CAST WITHIN
THIS WEEK

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed


OTHER PERTINENT ACTIVITIES

INSTALLING HARD POLYFOAM PROTECTION TO NEWLY


APPLIED DAVCO WATERPROOFING MEMBRANE PRIOR TO
BACKFILLING

SPLIT LEVEL BEAMS AND RC WALL INSTALLING DAVCO


WATERPROFING MATERIALS COVERED WITH HARD
POLYFOAM PROTECTION PRIOR TO BACKFILLING WORKS

LIFT COREWALL GRINDING TOUCH UP DO CHAMFER AT


BASE TO RECEIVE DAVCO WATERPROOFING MEMBRANE

DETENTION DRAIN TOP SLAB CAST AT 88% COMPLETE

ESS -ELECTRICAL SUBSTATION BELOW TRANSFORMER ROOM


UPSTAND BEAMREBAR IN PROGRESS TO CAST WITHIN THIS WEEK