Building Works at Hougang Town: Lower Deck: Pile Cap Status
Building Works at Hougang Town: Lower Deck: Pile Cap Status
DAILY SITE RECORD Thursday, September 17, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural w PILE CAP STATUS
SITE VIEW
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% INSTALL ING REINFORCING BARS, AND CLOSING FORMWORKS @ LIFT PIT
AREA
10 Pile caps more to complete at lower Deck Level , GREEN
TO CAST FRIDAY WITH WATERPROOF CONCRETE
SHADES @Upper Deck Level PILE CAP @ 96.67% Complete YELLOW
CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT
LIFT PIT REINFORCING BARS AND FORMWORKS INSTALLATION IN
PROGRESS
TC INSTALLED
ECO 1 1
G Worker
Weather 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
AT Lower Deck Level REMAINS @ 62.96% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND RC SUMPS AND PIPE
FORMWORKS INSTALLATION IN PROGRESS HAUNCHING @42.86%
COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT
LATER STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE
GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM
REINFORCING BARS STARTED TO INSTALL AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
ESS
LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION
BARS, SLAB BOTTOM REINFORCING BARS STARTED TO INSTALL AT GRIDLINE IN PROGRESS.
12 TO 7 / G TO D
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS
INSTALLED, 4 SPLIT LEVEL WALLS WB4a WB4 WB5 CAST
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK BEAM GH11b GH11c 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALLED 10 DROP PANELS SLAB
DEEP BEAM FORMWORK INSTALL / CAST= 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS BOTTOM REINFORCING BARS AND 3 CAST MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / CAST= 6
FORMWORKS=4 WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK ROWS OF GROUND BEAMS
SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED TO WORKERS ASSIST TOWER INSTALLED WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4
CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER
/LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8
DEPLOYED TO WORKERS ASSIST TOWER CRANE/ SHIFTING OF
@ELECTRICAL MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS
SUBSTATION BELOW
TRANSFORMER ROOM :
FABRICATE FORMWORKS
FOR DEEP BEAMS,
upstand beams