Professional Documents
Culture Documents
Construction Method Statement: 1 Lexham Mews, W8 6JW
Construction Method Statement: 1 Lexham Mews, W8 6JW
Construction Method Statement: 1 Lexham Mews, W8 6JW
Office 17
Wingate Business Exchange
64-66 Wingate Square
London
SW4 0AF
www.toynbeeassociates.com
CONSTRUCTION
METHOD STATEMENT
1 Lexham Mews, W8 6JW
Job #: 1516 – 1 Lexham Mews
Page 1
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 2
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 3
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
The following report has been written to in relation to Figure 4 of the RBKC Final Basements SPD of April
2016.
The following is summary of the of finding of the report
• The ground conditions for the site show made ground to about 3.9m BGL, with the Kempton
Park gravels and then the London Clay below that.
• The site does not have a high water table, the site investigation did not encounter any water
within the bore hole.
• Flooding
o The site was shown to be within a Flood Zone 1
o The site was not within a Tidal or Fluvial Flood Warning Area.
o The area was shown to lie within an area with a very high (>75%) susceptibility for
Groundwater Flooding.
o The site was located in an area of increased potential for elevated groundwater due to
the presence of permeable Superficial Deposits (Kempton Park Gravel Member).
o The site was located in an area where the suitability of infiltration SUDS was uncertain,
with Enhanced Site Investigation required
• Ground Water and Hydrology
o No water table was encountered on site in the site specific investigation.
o The proposed development is located on a Secondary A Aquifer relating to the
superficial deposits of the Kempton Park Gravel Member. The underlying bedrock
deposits of the London Clay Formation were classified as an Unproductive Strata.
o Based on a visual inspection of the soil samples the Kempton park gravels have a
relatively high permeability.
o It was considered possible that perched water will be encountered within the Made
Ground, especially after periods of prolonged rainfall. However, it was considered
unlikely that water would be encountered within the deposits of the Kempton Park
Gravel Member during basement construction.
• It is not expected that the construction of the basement will have cumulative effects on the
ground water as the basement is above the water table and there are no adjacent basements
within the vicinity of the proposed address.
• As the total impermeable area (building plus hard landscaped areas) is not increasing, there is
no proposal for SUDS and the existing drainage system can be reused.
• A Ground movement assessment has been carried out and that this predicts the category of
damage to be negligible to the adjacent properties with in the immediate vicinity of 1 Lexham
Mews.
• The attached reports shows the permanent works design for the retaining walls and temporary
works details for propping and construction sequencing.
Page 4
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
The property is a two-storey, end of terrace Mews house. It is of masonry construction with timber
floors to all levels and timber joists to form the roof. The adjoining property at number two is assumed
to be of similar construction and looks to be in sound condition from an external non–intrusive visual
examination. Neither of the properties are listed on the Statutory List of Buildings of Special
Architectural or Historic Interest.
The proposed works require the construction of:
• A new basement under the property.
• Internal light wells to the rear of the property
• Superstructure works at top floor level.
The superstructure works has been considered but is not required to be detailed at planning so has not
been included in the Basement Impact Assessment.
The excavation method to be utilized at 1 Lexham Mews is as follows:
Excavation will commence from the front of the property, progressing towards the rear.
• A grab lorry will remove the spoil from the future patio.
• The existing property will be underpinned in the usual 1 to 5 underpinning sequence. See
drawing TW / 01 for the construction sequence of a typical underpin, and see Underpinning
Specification in the Appendices.
• The underpins to form the new basement may require horizontal propping until completion of
the basement slab.
• As excavation progresses, any existing foundations found will be broken out and removed from
site to make way for the new basement construction.
• The existing walls of the building over will be temporarily propped using steel beam needles at
regular centres, as necessary. Temporary concrete pad foundations may be required beneath
the props, or the props may be supported on the concrete bases of underpins already
constructed, wherever the location allows.
Page 5
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Waterproof internal space with an internal membrane system with internal sumps and drains.
Page 6
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
To NHBC guidance, compliance is only required to other floors if a material change of use happens to
property
Initial Building Class 1
Proposed Building Class 1
If class has changed No
Lateral Stability
Stability is not a concern of the basement design, as the existing superstructure provides lateral stability
for the property. The new basement will act as a reinforced concrete box. The internal wall density will
stay as it is at all floors.
Lateral Forces applied include soil pressure, surcharge pressures transmitted through the soil, and
hydrostatic pressures. These produce a lateral force which is spread through the basement slab and
resisted by the equal force from the counterpart retaining wall on the opposite side of the basement.
Geology
Geological surveying information from the British Geological Survey website shows that the bedrock
geology is London Clay, with the Kempton Park Gravels over lying this.
Page 7
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Figure 3 Borehole Extract from ground and water report GWPR2385 Ground Investigation report
Page 8
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Trees
No existing trees will be felled during the construction of the proposed basement. In addition, there are
no trees protected by Tree Preservation Orders in the vicinity of the proposed basement that will be
damaged by the construction works.
Refer to the arboculturists report for the effects on nearby trees.
Flooding
For information regarding groundwater flow and hydrological, please refer to groundwater report
GWPR2385 FRA and Geotechnical Desk Study, Section 5.0 (pg 9) but a summary is below:
• The site was shown to be within a Flood Zone 1
• The site was not within a Tidal or Fluvial Flood Warning Area.
• The area was shown to lie within an area with a very high (>75%) susceptibility for
Groundwater Flooding.
• The site was located in an area of increased potential for elevated groundwater due to the
presence of permeable Superficial Deposits (Kempton Park Gravel Member).
• The site was located in an area where the suitability of infiltration SUDS was uncertain, with
Enhanced Site Investigation required
Page 9
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Figure 4 extract from Arup Report Camden geological, hydrogeological and hydrological study, Guidance for Subterranean
development.
While there may be seasonal ground water flow in with in the made ground there will be little or to
effects due to damming from the basement for the following reasons:
• The basement is isolated and bounded by a car park to one side and a road to the other under
which a basement is unlikely to be built.
• There is no recorded water table with in the site specific borehole and ground investigation
reports.
Page 10
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Basement Design
We design our basement assuming worst case soil conditions, and with a water level 1000mm below soil
ground level, unless specific evidence is found from trial pit or borehole data. Our standard underpins
sizes have been refined from many previous designs with many contractors and have been designed
with constructability in mind. As the basement slab will act as an effective base prop, we only need to
design the retaining wall for overturning and bearing pressure checks, and not sliding. See section 2 for
specific, worst-case retaining wall design, to prove shape and form.
Page 11
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
As we do have a specific soil investigation for this project we can estimate the water table. As no water
table was struck during the borehole process it is likely that it is below basement formation level. But
the design will take into account a worst case design of 1.0 m below ground level for accidental water
levels from burst water mains or other external influences.
However, to air on the side of caution, we will still assume a water level 1000mm below ground level, as
the drilling process can sometimes obscure groundwater strikes. This also allows for unforeseen
circumstances such as a local failure at water mains or storm water.
As previously stated, all sides of the property will be designed with a 10kN/m2 surcharge load due to car
loading. The attached neighbour’s foundations will be taken as 1.5kN/m2 + 4kN/m2 for the concrete
ground-bearing slab.
Movement Assessment
Ground works such as a basement excavation naturally pose a threat to adjacent properties. The
disturbance of the soil near the footing of a neighbour could cause settlement issues resulting in cracks
in finishes or problems with fittings such as windows and doors. Certain precautions must be taken to
try to minimize the possibility of this settlement:
- The party wall is to be underpinned in 1m sections. This lowers the risk of movement to the
adjacent property.
- The works must be carried out in accordance with the party wall act and conditioning schedules
should be taken and the beginning and end of the works, to define what new damages have
been caused by the works.
- The method statement provided in this report is formed from experience gained in 5 years+
basement design experience.
- The design of retaining walls is completed to Eurocode 3.
Page 12
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Entrance Arch
The entrance arch while this is in close proximity to the basement excavation would only suffer damage
similar to that of 2 Lexham Mews refer to the table below.
The temporary works design for the excavation for the underpins allows for support of soil below load
bearing walls with a surcharge from a load bearing wall of 100 kN/m² foundation pressures.
The permanent works design would allow for the wall surcharge and intermediate floor beams at
ground floor prop the top of the retaining wall preventing further movement of the wall in the
permanent condition.p
Page 13
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Figure 7 extract from BIA report GWPR2385 showing ground movements to adjacent buildings and predicted movement criteria
Temporary Works
Our underpins are designed in both the temporary and permanent case. In the temporary case, we
sometimes require a top prop force to restrain the overturning moment, as the vertical load will be
lowered. In this situation it is important for the Temporary Works designer to know the force so they
can adequately design the prop system. This should be as simple as possible and is likely to be a system
of wailer beams, which are propped back to the central berm. Particular attention should be paid to
Page 14
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 15
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 16
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Project Job Ref
The following calculations detail the structural design as per the architectural planning drawings.
Dead Loads
Floor (including joists, tile boards, tiles, ceiling and services) = 1.0 kN/m²
Pitched Roof (including tiles, rafters and ceilings) = 1.2 kN/m²
Flat Roof (including, joists, insulation, ceilings and services) = 1.0 kN/m²
Existing Concrete Slab nominal thickness 200 with screed and finishes = 6.3 kN/m²
Walls:
Live Loads
The design of the structural elements will be carried out in such a way to limit the impact of the
structural works on the existing buildings construction and that of the neighbouring properties.
Deflection Limits
The existing load – bearing structure will be underpinned in a traditional ‘1 to 5’ sequence. The
underpins will comprise of a vertical stem which will be immediately beneath the existing wall and
will be at least the same thickness as the existing wall. In the case of a party wall, the rear face of
the stem will be in line with the face of the wall above so as not to encroach in to the adjacent
property’s space, should they wish to construct a similar basement in the future. The reinforcement
in the stems will be designed for bending about the top of the base in the permanent case.
The vertical loads applied to the underpin stems from the existing structure will be calculated
according to the thickness and height of the existing structure above. Any upper floors and roof
loads will be ignored as this will give a minimum value for the vertical load, which will be the most
onerous case for overturning and sliding of the underpin section.
The underpins will be designed for the temporary and permanent cases, as follows: In the
temporary case, the underpins will be designed for soil pressures and a surcharge. The factor of
safety against overturning and sliding will be taken as 1.5.
In the permanent case, the underpins will be designed for soil pressures, a surcharge and water
pressures calculated at 1 m below the retained height. The new basement slab will be structurally
connected to the underpinning bases using dowel bars, therefore it will be assumed that the new
basement slab will restrain the under pins against sliding.
The basement slab will be designed for uplift due to water pressure, spanning between the bases of
opposite underpins. The net uplift pressure is taken as the head of water minus the dead load of the
basement slab and any permanent finishes, e.g. screed.
Project Job Ref
Geotechnical Design
The basement retaining walls have been designed with the following geotechnical design
parameters:
SOIL PARAMETERS
Sand and Gravels
Dry Soils = 20 kN/m3
Wet soil = 10 kN/m3
Water = 10 kN/m3
φ = 38˚
Ka = 0.23
Clay
Dry Soils = 20 kN/m3
Wet soil = 10 kN/m3
Water = 10 kN/m3
φ = 23˚
Ka = 0.43
The retaining walls will be designed using ‘active’ pressures (where movement of the retaining wall
is likely and acceptable), as opposed to ‘at rest’ pressures (where movement of the retaining wall is
unlikely or unacceptable). The underpinning process, where soil is excavated underneath an existing
load – bearing wall and a vertical shear face of soil is exposed, allows the excavated face of soil to
move, thus mobilizing the ‘active’ pressures. In addition, once the underpin has been constructed
and is working as a retaining wall, the retaining wall is likely to deflect, thus mobilizing the ‘active’
pressures. These movements will be very slight and will most likely have a negligible effect on the
vertical settlement of the retained soil behind the underpinning / retaining walls. These movement
are considered acceptable.
Ground – bearing pressures below the underpinning bases will be calculated for the temporary
condition. In the permanent condition, the new basement slab will be tied in to the retaining wall
bases, hence the entire substructure will act as a raft foundation. Ground – bearing pressures will
not be an issue in this condition.
Water Table
Borehole records for the area do not show a high water table.
An assumed accidental case will be assumed of 1.0 m below ground level for design of uplift on the
slab and lateral forces on the retaining walls.
Project Job Ref
Bearing Pressures
The geological drift maps for the area indicate Kempton Par Gravels of variable thickness from 5-8
m above the London Clay formation at depth. Bearing pressure in the gravels formation will be of
250 kPa will be acceptable. We will design our basement on 150 kPa to limit the potential
movement of the party wall structures during and after construction and reduce overall bearing
pressures at the formation level. We do not take into account the beneficial surcharge load from
overburden pressure at the basement formation level, this further reduces the risks of potential
settlement of the building.
Project Job Ref
Temporary Works
The retaining walls will be designed where possible to be self supporting under surcharge and soil
loading in the construction stage of the project. The underpins will need to be propped during
construction to avoid any sliding failure at the abase in the granular materials, alternatively a nib
can be cast to stop the walls from kicking out at the base in the temporary case until the basement
slab is cast.
In the permanent case the walls bases will be propped by the slab and the structural topping.
Therefore the most onerous design case is the temporary condition.
Project Job no.
1 Lexham Mews 1516
1650 350
1825
P1
0.8 kN/m 2
7.8 kN/m 2
3150
3150
3500
2150
Prop
350
43.4 kN/m 2
2000
General arrangement
Bearing pressure at toe; qtoe = 52.3 kN/m2; Bearing pressure at heel; qheel = 56.3 kN/m2
Factor of safety; FoSbp = 2.219
PASS - Allowable bearing pressure exceeds maximum applied bearing pressure
Concrete details - Table 3.1 - Strength and deformation characteristics for concrete
Concrete strength class; C32/40
Char.comp.cylinder strength; fck = 32 N/mm2; Mean axial tensile strength; fctm = 3.0 N/mm2
2
Secant modulus of elasticity; Ecm = 33346 N/mm ; Maximum aggregate size; hagg = 20 mm
Design comp.concrete strength; fcd = 21.3 N/mm ; 2
Partial factor; γC = 1.50
Reinforcement details
Characteristic yield strength; fyk = 500 N/mm2; Modulus of elasticity; Es = 200000 N/mm2
Design yield strength; fyd = 435 N/mm ; 2
Partial factor; γS = 1.15
Cover to reinforcement
Front face of stem; csf = 50 mm; Rear face of stem; csr = 50 mm
Top face of base; cbt = 50 mm; Bottom face of base; cbb = 75 mm
Loading details - Combination No.1 - kN/m2 Shear force - Combination No.1 - kN/m Bending moment - Combination No.1 - kNm/m
1.25
9.45
9.45
Stem
101.7
11.81
11.81
1.25
9.45
12.76
28.47
X
-73.3 71.5
Toe
70.9
75.98
82.7
Project Job no.
1 Lexham Mews 1516
Loading details - Combination No.2 - kN/m2 Shear force - Combination No.2 - kN/m Bending moment - Combination No.2 - kNm/m
1.08
8.59
8.59
Stem
81.4
8.75
8.75
1.08
8.59
11.6
21.09
X
-61.3 61.1
Toe
46.31
69.83
72.5
50 50
75
12 dia.bars @ 100 c/c
Reinforcement details
Job #: 1516 – 1 Lexham Mews
a. Ground conditions for the site indicate the Kempton Park Gravel Member overlying the
London Clay Formation, with a significant depth of made ground down to 3.9 BGL.
b. Sacrificial back shuttering will be required in the upper soil layers to retain the friable soil
at high level.
c. For single underpins no more than 1000 mm wide in London clay the site foreman will need
to assess the local ground conditions during the excavation of the underpins to determine
if sacrificial back shuttering is required.
a. Note the externals and Party Walls are assumed to be 9” thick, 225 wide. The walls will
have a mass concrete foundation and the setting out of the RC underpin should take this
into account to ensure the back face of the underpin aligns with the back face of the party
wall.
b. In maximum 1.0m segments excavate down to new basement formation level. Shore the
faces of the trench with Mabey M6/KD4 lap trench sheeting driving into the soil to provide
a toe-in depth of 500mm. Shore the back face of the excavation with Sacrificial shuttering
of knauf Cementous board. If required and original footing is of poor condition install
sacrificial acrow prop to the base of the wall. Back Shuttering to be propped as per side
and rear faces, using trench props or similar in boxed out holes to be infilled once main
shuttering has been struck. The front face of the excavation is to be shored as per the sides
of the excavation.
c. Install C24 timber walers to shore the sides of the excavation. Install trench props to walers
one at each end. Cross Propping between the vertical trench sides with minimum 2 props,
one at high level and one at minimum 500mm above proposed SSL. Walers and trench
props at regular centres to the base of the excavation.
d. 4”x2” timber posts, double handrail and toe boards will be erected around the top of all
excavations to prevent falls.
e. All the underpin sections shown on drawing (S-RC(1)) will be excavated by hand.
f. If required and ground conditions dictate blind the base of the excavation as soon as
formation level is reached.
g. If required and the quality of the existing mass concrete underpinning is loose install
sacrificial trench props to hold the mass concrete base in place until the underpin has
been completed. Note this is cast in place and not removed
h. Reinforced Concrete underpins to have H20 dowel bars 600(lg) @ 600 c/c vertically with
equal embedment between sections. Dowels to be driven into earth faces with corrosion
protection to exposed ends.
i. Fix the reinforcement as per the permanent works drawings for the base. Continuity
reinforcement between the RC Bases and the Insitu Infill RC Slab are to be driven into
the Earth berm with sufficient corrosion protection to the exposed legs of the bars. And
cast with concrete. Note chamfer the back face of the underpin to allow for the mass
concrete heels and support to the soil above.
j. Fix wall reinforcement, remove back shutter if possible and ground conditions allow and
form shuttering to front face, prop back to the central berm with trench props at 500
vertical centres, note trench props at base of wall to avoid kicking out of shuttering under
concrete pressure.
k. The underpins are to be cast up to 50 mm (but no more than 75 mm) from the underside
of the existing masonry walls to allow for installation of the dry pack.
Page 17
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
a. Carry out the bulk excavation from the rear of the property moving back. Install system
Maybe S3/KP/7 props a 1.0 m centres at 500 mm above basement slab level, provide
temporary shoring to front light well berm using trench street and trench props. Refer to
TW-03p for details.
b. Once bulk excavation complete.
c. Install below slab drainage.
d. And fix slab rebar and cast slab.
e. Once 5 days has accrued remove cross propping.
f. Once main slab has been completed, refer to light well construction section for final
sections of Lightwell slab to be constructed.
Padstone Cutting
a. Cut the pad stones (as per structural engineer drawings/specifications) using angle
grinder and hand chisel no hand held percussive tools allowed.
b. Padstones to be a maximum of a half brick thickness/depth of the party wall.
c. Shutter and cast the pad stones where required
d. Install spreader beams as per structural engineers details, line and level, grout and dry
pack to underside of masonry above.
e. After 48 hours of the pad stones spreaders being cast cut/remove brickwork (to be done
by hand chisel and using angle grinder to minimise any vibration) to allow for the
installation of the steel beams
f. Install the beams and cast concrete/brick up around the steels and Dry pack between the
top of the steels and the brickwork approximately 50mm
g. Repair and make good to leave it flush with the party wall.
Page 18
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 19
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
1. The walls to the perimeter of the new basement shall be underpinned in reinforced concrete.
The underpins shall take the vertical loads from the walls and horizontal loads from the earth.
2. Underpinning bases shall be excavated in short sections not exceeding 1000mm in width.
3. The sequence of the underpinning shall be such that any given underpin will be completed, dry-
packed and a minimum period of 48 hours lapsed before an adjacent excavation commenced to
form another underpin.
4. In the event that the existing foundations to the wall are found to be unstable, sacrificial steel
jacks shall be installed underneath the foundation to prop the bottom few courses of bricks.
These steel jacks shall be left in place and shall be incorporated into the concrete stem.
5. In the event that the ground is unstable, lateral propping shall be provided as required to the
rear of the excavation and to the sides of the excavated working trench. The front and side faces
of the excavation shall be propped using trench sheeting or 2 layers of plywood, timber boards
and acrow props as appropriate. Sacrificial back shutters shall be used to the rear face of the
excavation (i.e. underneath the wall) if required. Cementitious grout will be poured behind the
back – shutters to fill up the voids behind the back – shutters.
6. The rear of the underpin is to be flush with the back face of the party wall on the adjoining
owners side.
7. Excavation for an underpin section shall be dug in a day, and the concrete to the base shall be
poured by the end of the same day.
8. The concrete to the stem of the underpin shall be poured the following day. This shall be poured
up to within 50 – 75mm of the underside of the existing wall foundations.
9. On the following day, the gap between the concrete and the underside of the existing
foundation shall be drypacked with C35 concrete using 5 – 10mm coarse aggregate and
“Combex 100” expanding admixture by Fosroc UK Ltd in accordance with their instructions.
Page 20
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
11. A minimum of 48 hours shall be allowed before adjacent sections are excavated to form a new
underpin.
12. Adjacent underpins shall be connected using T16 dowel bars 600mm long, 300mm embedment
each side, at 300mm vertical centres.
13. Concrete cover to reinforcement shall be 35mm for cast against shutter or the top surface of the
basement slab, 50mm for cast against blinding and 75mm for cast against earth.
14. Grade of concrete shall be C35 with minimum cement content 300kg/m3, maximum free water
to cement ratio 0.60, slump 100mm.
See drawing S-TW-01 in the Section 4 for an underpinning sequence to the property and a section of the
underpin, and light well construction.
Page 21
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
DEFINE:
3-SPAN 2D ANALYSIS
Page 22
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Analysis
Tedds calculation version 1.0.17
Geometry
Geometry (m)
Z
1 2 3 4
0.5 2.2 0.5
X
1 2 3
Loading
Self Weight - Loading
Soil - Loading
24.99
21.09
21.09
3.9
3.9
Surcharge - Loading
Results
Total deflection
ALL (Strength) - Total deflection
Page 23
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Member results
Load combination: ALL (Strength)
Member Shear force Moment
Pos Max abs Pos Max Pos Min
(m) (kN) (m) (kNm) (m) (kNm)
Member1 0.5 23.9 1.717 5.4 0.5 -8
Page 24
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
4-SPAN 2D ANALYSIS
Analysis
Tedds calculation version 1.0.17
Geometry
Geometry (m)
Z
1 0.5 2 1.1 3 1.1 4 0.5 5
X
1 2 3 4
Loading
Self Weight - Loading
Surcharge - Loading
1.95 24.99
1.9521.09
1.9521.09
12.5
12.5
1.95
1.95
1.95
1.95
1.95
3.9
3.9
Results
Total deflection
ALL (Strength) - Total deflection
1 2 3 4 5
X
Page 25
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 26
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
For 3-Span, R = 69 kN
PROVIDE: Mabey System 160 props @ 2m C/C
Cross Props
Cross props should be placed one third of the way up the wall as measured from bottom slab.
Surcharge; sur = 10 kN/m2
Soil Density; γ = 20kN/m3
Angle of Friction; φ = 25°
Soil Depth; Dsoil = 3000mm
ka = (1-sin(φ))/(1+sin(φ)) = ?
kp = 1/ ka = ?
1 – sin(φ) = ?
Page 27
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 28
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Office 17
Wingate Business Exchange
64-66 Wingate Square
London SW4 0AF
Tel: +44 (0)208 622 5302
info@toynbeeassociates.com
www.toynbeeassociates.com
© Toynbee Associates 2018
Office 17
Wingate Business Exchange
64-66 Wingate Square
London SW4 0AF
Tel: +44 (0)208 622 5302
info@toynbeeassociates.com
www.toynbeeassociates.com
© Toynbee Associates 2018
Office 1
Wingate Business Exchange
64-66 Wingate Square
London SW4 0AF
Tel: +44 (0) 20 8622 5302
info@toynbeeassociates.com
www.toynbeeassociates.com © Toynbee Associates 2015
Job #: 1516 – 1 Lexham Mews
Page 29
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 30
1516 - 1 Lexham Mews - Construction Method Statement Final.docx
Job #: 1516 – 1 Lexham Mews
Page 31
1516 - 1 Lexham Mews - Construction Method Statement Final.docx