Professional Documents
Culture Documents
DS1 14.12.2013
DS1 14.12.2013
3 DAILY REPORT
Sub Sl.
Sl. No. Manpower Contractor Total Plant & Equipment Qty.
Contractor No.
1 Carpenter 1 Excavator
2 Steel Fixer 2 Shovel
3 Mason 3 Dumper truck
4 Plumber 4 Dumper
5 Electrician 5 Water tanker
6 Labourer/Helper Orok co. 4 6 Plate compactor
7 Skilled technician 7 Roller compactor
8 Steel fabricator 8 Vibrator
9 Welder 9 Compressor
10 Painter 10 Jack hammer
11 Rigger 11 Concrete cutter
12 Erector 12 Concrete breaker
13 Metal tradesman 13 Concrete mixer
14 Operator 14 Drill machine
15 Mechanic 15 Grinder
16 Skilled labourer 16 Tile cutter
17 Driver Orok co. 1 17 Hoist
18 Charge hand 18 Crane
19 Foreman Orok co. 1 19 Bar bending machine
20 Safety Inspector 20 Wood cutting machine
21 Safety Officer Orok co. 1 21 Generator
22 Surveyor 22 Water pump
23 Supervisor Orok co. 1 23 Dumpy level
24 Store Keeper 24 Theodolite
25 Time Keeper 25 Levelling staff
26 Office boy 26 Ranging rod
27 Secretary 27 Other (specify);
28 Draughtsman 28 GPS
29 Site Engineer Orok co. 1 29 Vehicle 1
30 Quantity Surveyor 30 Measuring wheel
31 QA/QC Engineer 31 Measuring tape
32 Planning Engineer 32 wagon
33 Senior Civil Engineer
34 Project Manager Orok co. 1
IP_Rumaila HQ_MM_E1.3
E1.3 DAILY REPORT
Time keeper:
No concrete pouring
Work in progress:
IP_Rumaila HQ_MM_E1.3
E1.3 DAILY REPORT
Materials received:
Remarks if any:
Received by
Representative Originator
Contractor Client / Engineer
Name
Signature
Ali hadi
Date
14.12.2013
Example Photo’s
IP_Rumaila HQ_MM_E1.3
E1.3 DAILY REPORT
IP_Rumaila HQ_MM_E1.3
E1.3 DAILY REPORT
IP_Rumaila HQ_MM_E1.3