LOOK AHEAD - JUNIO 2012

Gestión de Riesgos
PROYECTO: PIQUE JACOB TIMMERS

Datos Actualizados al dia: Monday, 11-Jun-12

Acumulado Eficiencia Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
Avance
ITEM DESCRIPCION DE ACTIVIDAD Und
Mensual
Al dia Mensual 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun RESPONSABLE IPER
11-Jun-12 Acumulada D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N
X X X X X X X X X X X X X X X X x x x x x x
1.00 PROFUNDIZACION DE PIQUE

Prog ml - -
1.01 Excavación. - DUMAS 8
Real ml -
Prog ml - -
1.02 Sostenimiento - DUMAS 8
Real ml -
Prog ml - -
1.03 Revestimiento. - DUMAS 8
Real ml -
Prog ml 6.00 - 1.00 1.00 1.00 1.00 1.00 1.00
1.04 Montaje de SET. - DUMAS 8
Real ml -
2.00 LOADING POCKT

Prog ml 3.20 3.20 1.6 1.6


2.01 Excavación. 150% DUMAS 8
Real ml 4.80 2.4 2.4
Prog ml 14.00 14.00 1 1 1 1 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
2.02 Limpieza 96% DUMAS 8
Real ml 13.50 0.75 0.75 0.75 0.75 0.75 1 1 1 0.75 1.0 1.00 1.00 1.0 1.0 1.00
Prog ml 4.00 4.00 1.0 1 1 1.00
0.00 Sostenimiento (hydrobolt+malla) 95% DUMAS 8
Real ml 3.80 0.5 0.45 0.45 0.45 1 1.00
Prog ml 3.00 1.00 1.0 1.0 1.0
0.00 Sostenimiento (cable bolting) - DUMAS 8
Real ml -
Prog ml 30.50 2.50 0.25 0.25 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
2.04 trabajos civiles 20% DUMAS 8
Real ml 6.50 0.50 0.25 0.25 1.00 1.00 1.00 1.00 1.00 1.00
Prog ml 1.32 - 0.33 0.33 0.33 0.33
2.05 Estructuras Pocket (Dosificadores y Columnas)
Real ml - -

3.00 MANTENIMIENTO DE EQUIPOS

Prog Hrs - -
3.01 FRONTIER. - PJT 13
Real Hrs -
Prog Hrs - -
3.02 CRYDERMAN . - DUMAS 8
Real Hrs -
Prog Hrs - -
3.03 TIMBERLAND 1. - PJT 13
Real Hrs -
Prog Hrs - -
3.04 TIMBERLAND 2. - PJT 13
Real Hrs -
Prog Hrs - -
3.05 TIMBERLAND 3. - PJT 13
Real Hrs -
Prog Hrs - -
3.06 COMPRESORA. - PJT 8
Real Hrs -

4.00 TRABAJOS EN ESTACIÓN Y NIVEL NV. 155

INST. DE COMPUERTA Y TAPON PEATONAL DE LIMITACIÓN Prog % 0% 0%


4.01 - PJT 5
INDUSTRIAL OPERACIONAL Nv. 155. Real % 0%
Prog % 0% 0%
4.02 DESQUINCHES Y REALCES DE CÁMARAS: 2-4 L. POCKET Nv. 150. - PJT 8
Real % 0%
Prog % 0% 0%
4.03 BY PASS CÁMARA 2-4 L. 3.5x3.5 mtrs2. - PJT
Real % 0%
SOSTENIMIENTO DEFINITIVO DE CÁMARA 2- 4. L. POCKET. NV. 150; Prog % 0% 0%
4.04 - DUMAS 8
By PASS. (Shotcrette + Hidro Malla + Shotcrette) Real % 0%
Prog % 0% 0%
4.05 ENCOFRADO Y ARMADO DE LOZAS CAMARA 2-4. RAISE BORER. - PJT
Real % 0%
Prog % 0% 0%
4.06 SOSTENIMIENTO PERNO - MALLA. CÁMARA PARA SE ELÉCTRICA. - DUMAS / PJT
Real % 0%
Prog % 0% 0%
4.07 ENCOFRADO DE BASES Y LOZAS S.E. Nv. 150. PJT. - PJT
Real % 0%

5.00 TRABAJOS PIQUE J. TIMMERS - NV. 121.

Prog % 0% 0%
5.01 Instalación de puerta en rampa en Nv. 121 -
Real % 0%
Prog % 0% 0% -
5.02 Voladura y sostenimiento de cámara de bombeo NV. 121.
Real % 0%
LOSA PARA UBICACIÓN TEMPORAL DE BAÑO Y COLOCADO DE Prog % 0% 0%
5.03 -
BAÑO QUÍMICO Nv. 121. Real % 0%
Prog % 0% 0%
5.04 Sostenimiento NV 121, (cámara de control) -
Real % 0%

6.0 TRABAJOS DE OBRAS CIVILES 18

Prog % 0% 0%
6.01 CORTES/HABILITACIONES EN CANALETA DE CASA DE WINCHES - PJT
Real % 0%
DEMOLICIÓN DE BASES DE CONCRETO PARA BASES METÁLICAS Prog % 0% 0%
6.02 - PJT
WINCHE NORDBERG Real % 0%
Prog % 0% 0%
6.03 CONSTRUCCIÓN DE MAN HOLE CASA WINCHES - PJT
Real % 0%
7.0 MONTAJE WINCHE NORDBERG 18

PREPARACIÓN DE CIMENTACION Y VERIFICACIÓN DE PÚNTOS Prog % 0% 0%


7.01 - BM ING
TOPOGRÁFICOS Real % 0%
Prog % 0% 0%
7.02 INSTALACIÓN DE LEVELIN PLATE - BM ING
Real % 0%
Prog % 0% 0%
7.03 MONTAJE DE BASES METÁLICAS - BM ING
Real % 0%
Prog % 0% 0%
7.04 NIVELACIÓN Y ALINEAMIENTO DE BASES METÁLICAS - BM ING
Real % 0%
Prog % 0% 0%
7.05 RECEPCION Y ARMADO DE GRÚA DE 160 Tn - BM ING
Real % 0%
Prog % 0% 0%
7.06 RECEPCIÓN DE COMPONENTES DE ALTO TONELAJE EN MINA - BM ING
Real % 0%
Prog % 0% 0%
7.07 DESMONTAJE DE LATERALES Y TECHO DE CASA DE WINCHES - BM ING
Real % 0%
Prog % 0% 0%
7.08 INSTALACIÓN DE MEDIAS LUNAS INFERIORES - BM ING
Real % 0%
INSTALACIÓN, NIVELACIÓN Y ALINEAMIENTO DE CHUMACERAS Prog % 0% 0%
7.09 - BM ING
PRINCIPALES Real % 0%
Prog % 0% 0%
7.10 MONTAJE, VERIFICACIÓN Y ASENTAMIENTO DE EJE PRINCIPAL - BM ING
Real % 0%

Leyenda ELABORADO REVISADO APROBADO


Trabajos programados
Trabajos ejecutados
Normand Dube Javier Ponce de León Jorge Mendoza R.
Residente de Obra DUMAS SUPERVISOR MINERO PJT SUPERVISOR GENERAL PROYECTO PJT
CONTROL DE EFICIENCIA
Datos Actualizados al dia: Friday, 29-Jun-12

X X X X X X X X x x x #REF!
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat #REF!
1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun #REF!
Prog 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación Real 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Efic 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #REF!
Prog 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Revestimiento Real 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Efic 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #REF!
Prog 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 4.00 6.00 6.00 6.00 6.00
Montaje Set Real 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Efic 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #REF!

Excavación - Revestimiento - Montaje Set -


3.50
INDICADOR DE EFICIENCIA

3.25
3.00
2.75
2.50
2.25
2.00
1.75
1.50
1.25
1.00
0.75
0.50
0.25
0.00
3-Jun

5-Jun

#REF!
1-Jun

2-Jun

4-Jun

6-Jun

7-Jun

8-Jun

9-Jun

10-Jun

11-Jun

12-Jun

13-Jun

14-Jun

15-Jun

16-Jun

17-Jun

19-Jun

20-Jun

21-Jun

22-Jun

23-Jun

24-Jun

26-Jun

28-Jun

29-Jun

30-Jun
18-Jun

25-Jun

27-Jun
FECHA

TIPO PARADA
Tue, 01-May-12 T/Dia: Celebracion por el dia del trabajo de 2:00pm a 7:00pm 5.0 Otros
Tue, 01-May-12 T/Noche: Reparacion de manija de valvula de cryderman de 2:00 am a 3:15 am 1.3 Falla Mecánica
Thu, 03-May-12 T/Noche:Demora al desencofrar la forma metalica "C" debido a que el shotcrete lanzado por CIA se impregno en dicha forma de 1:00am a 7:00am 6.0 Falla Operativa
Fri, 04-May-12 T/Noche:Winche timberland N° 2 inoperativo por ploblemas en el freno de 2:00 am a 6:00 am 4.0 Falla Mecánica
Thu, 10-May-12 T/Noche:Winche Paro de operaciones Por corte de energia de 6:30 am a 7:00 am 0.5 Falla Eléctrica
Fri, 11-May-12 T/Dia Paro de operaciones Por corte de energia de 8:00 am a 11:30 am 3.5 Falla Eléctrica
Fri, 11-May-12 T/Noche:Prolongacion de tuberia para agua y aire 8:00 pm a 10:30 pm 2.5 Otros
Sat, 12-May-12 T/Dia: Cambio e instalacion de manguera de cuchareo del cryderman de 8:00 am a 9:00 am 1.0 Falla Mecánica
Sat, 12-May-12 T/Noche:problemas con la alimetacion en el comedor arenales, no hubo insumos para hacer los alimentos de 7:30 pm a 9:00 pm 1.5 Otros
Mon, 14-May-12 T/Día: Se reemplazo manga de ventilacion en el Nv 310. 1.5 Mantenimiento
Tue, 15-May-12 T/Noche:problemas con el cryderman cambio del piston del cuchareo 4.4 Falla Mecánica
Wed, 16-May-12 T/Día: Por mantenimiento progeamado del cryderman 2.0 Mantenimiento
Wed, 16-May-12 T/Noche: Por retira de bomba hidraulica malograda 0.7 Falla Mecánica
Fri, 18-May-12 T/Día: Por reparacion de manga de ventilacion en el Nv 155 1.1 Mantenimiento
Sat, 19-May-12 T/Día: Instalacion de electrobomba en el fondo del pique. 1.2 Otros
Mon, 21-May-12 T/Día: Instalacion de electrobomba en el fondo del pique. 3.8 Otros

39.8
Falla Eléctrica 4.0 10%
Falla Mecánica 11.3 28%
Mantenimiento 4.6 11%
Falla Operativa 6.0 15%
Inspección 0.0 0%
Otros 13.9 35%
FECHA TURNO HORAS DESCRIPCION
10-Apr D 2.50 Problemas con el personal de DUMAS por reclamo de utilidades.
11-Apr D 4.00 TD: Reunion de trabajadores Dumas y N. Dube (4.0 hrs)
TD: Bomba inoperativa en el fondo del pique (1.5 hrs), reparacion de la bomba (1.0 hrs)
TD: Bombeo de agua del fondo del pique (1.5 hrs)
11-Apr D/N 5.33 TN: Reparacion de bomba del fondo del pique (1.33 hrs)
15-Apr D 11.00 TD: Capacitacion del ISEM a personal (11.00 hrs)
16-Apr N 9.67 TN: Orden y limpieza del Nv. 155 (5.67 hrs) TN: Orden y limpieza del Nv. 310 (4.00 hrs)
17-Apr D 3.00 mantenimiento de galloway (Limpieza de concreto adherido)
17-Apr D 2.50 Desmontaje y retiro de winche JOY del galloway (deteriorado), e Instalacion de winche INGERSOL RAND
18-Apr D 8.00 Sostenimioento con shotcrete en comunicación realizado por Mina chungar
20-Apr D 2.00 parada de profundizacion por espera de sostenimiento en comunicación e instalacion de aire en el Nv.150
21-Apr D 11.00 Colocacion de desmonte para tener altura de perforacion para cables bolting (hecho por cia)
21-Apr N 6.00 Colocacion de desmonte para tener altura de perforacion para cables bolting (hecho por cia)
semana 3 53.17