W.B.M work.
(iv) 805 -south- Approaching Road – 1 x 140x 3.75 x 0.425 = completed on Dated:- 31-01-2019.
(V) 805 South Approaching Road – 1 x 190 x 3.75 x 0.425 = Completed on Dated :-31-01-2019.
(vi) 600 South Road (near colane Tower –stage-I)-1 x 190 x 3.75 x 0.425 = completed on Dated:-31-01-
2019.
(Viii) Periferial road near west site and south side Boundary wall = 3800 x 3.75 x 0.075 = completed on
Dated:- 28- 02-2019.
(x) Near admin building road = 1x 370 x7.5 x 0.150 = completed on Dated:- 28-02-2019.
(xi) Near L & T office road = 900 x 3.75 x 0.150 = Completed on Dated- 28-02-2019.