Details Execution plan of W.B.M Road in site plant.

W.B.M work.

(i) 840-south Road – 1 x 830 x 7.5 x 0.425 = completed on Dated:- 28/02/2019

(ii) Near switch yard Road – 1X 350 x 0375 x 0.075 = Completed

(iii) 805 South Road – 1 x 530 x 3.75 x 0.225 = completed on Dated:-31-01-2019.

(iv) 805 -south- Approaching Road – 1 x 140x 3.75 x 0.425 = completed on Dated:- 31-01-2019.

(V) 805 South Approaching Road – 1 x 190 x 3.75 x 0.425 = Completed on Dated :-31-01-2019.

(vi) 600 South Road (near colane Tower –stage-I)-1 x 190 x 3.75 x 0.425 = completed on Dated:-31-01-
2019.

(Vii) 137 East Road – 1 x 100 x 7.5 x 0.225 = Completed on Dated:-31-01-2019.

(Viii) Periferial road near west site and south side Boundary wall = 3800 x 3.75 x 0.075 = completed on
Dated:- 28- 02-2019.

(ix) Approaching of H2 plant Road = 1x 100 x3.75 x 0.425 = completed on Dated:-28-02-2019.

(x) Near admin building road = 1x 370 x7.5 x 0.150 = completed on Dated:- 28-02-2019.

=1 x 300 x 3.75 x 0.150 = completed on Dated :- 28-02-2019.

(xi) Near L & T office road = 900 x 3.75 x 0.150 = Completed on Dated- 28-02-2019.

(xii) Near central Store Road = 1 x 130 x 3.75 x 0.150

= 1 x 140 x 3.75 x 0.150

= 1 x 135 x 3.75 x 0.15 = completed on Dated:- 28-02-2019.

Balance Road work completed Hindrance dump at steel structure.

B.M and premix work started on Dated:-01-03-2019.