Professional Documents
Culture Documents
695013-D-A-Z-P-001-C00 - Priced BoQ - CONFIDENTIAL
695013-D-A-Z-P-001-C00 - Priced BoQ - CONFIDENTIAL
695013-D-A-Z-P-001-C00 - Priced BoQ - CONFIDENTIAL
The Swiss Confederation, represented by the Swiss Federal Department of Foreign Affairs, acting through the
Swiss Agency for Development and Cooperation (SDC)
Embassy of Switzerland in Nepal
CONSULTANT:
PROJECT TITLE:
ROCKFALL PROTECTION ALONG SIDDHABABA SECTION OF
SIDDHARTHA HIGHWAY
Ch. 28+200 km – Ch. 30+600 km
DPR DESIGN
PROJECT CODE:
Credit Proposal no. 7F-03971.03.01
DOCUMENT TITLE:
Doc. n. Doc. n.
695013-D-A-Z-P-001 695013-D-A-Z-P-001-C00.DOC
Rev Date Description Prepared Checked Approved
C00 27/05/2019 First Issue BON/BRO FON/BAR MUB
SIDDHABABA ROCKFALL HAZARD – DPR Design -Priced BoQ
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY .................................... 4
2 BILL OF QUANTITIES...................................... 5
approved by MUB
Recipients
Date name institution / company hard
copy
27/05/2019 Mr. Aman Jonchhe SDC Nepal -
1 EXECUTIVE SUMMARY
This report presents the BoQ and costs estimation for the rehabilitation and tunnel of the Siddhababa
the Siddhartha Highway, between Chainage 28+200 Km to 30+600 Km.
The cost estimates are based on applicable DoR norms and relevant district rates. In cases where DoR norms
available, especially for tunnel, new unit rates, based on European Swiss standards have been defined here.
The unit item rates for each item have been calculated on the basis of approved District rates of Rup
fiscal year 2075/76, but not for before mentioned additional items, for which new rates have been dev
derived from costs analysis.
The item rates are calculated by assuming that a qualified contractor will undertake construction follow
mechanized approach for road works and drill & blast approach for tunnel works (except for tunnel por
2 BILL OF QUANTITIES
In the following pages the BoQ of the project is presented. For estimating the cost of the project, de
estimation had been done for each item of works to be included in the project activities. The quantities of r
such as cutting, embankment filling, backfilling and pavement are calculated by design software.
Date: 27/05/2019 695013-D-A-Z-P-001-C00 - Priced BoQ -CONFIDENTIAL.docx
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
001 - Road Works
001 - Exavation, Filling and Paving
90 - Excavation
N. CODE
N. CODE
-2-
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
001 - Road Works
001 - Exavation, Filling and Paving
980 - Precast rectangular channeling
N. CODE
3 NP.CW.20.01 AMOUNT CARRIED FORWARD 4.900,
Providing and laying concrete channeling - Laying (Joining) of Precast concrete panel 00
900,00
Total m Total 980 - Precast rectangular channeling NPR
CARRY FORWARD Exavation, Filling and Paving
CARRY FORWARD Road Works 900,00
CARRY FORWARD Road Alignement MR1 - Main Road - 900,00
...
CARRY FORWARD
-3-
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
001 - Road Works
001 - Exavation, Filling and Paving
1420 - Paving
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
...
CARRY FORWARD
18.806,50
18.806,50
-4-
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
001 - Road Works
004 - Signaling
1610 - Signaling
N. CODE
N. CODE
CH 0+050 / CH 0+070
20,00 * 5,00 100,00
20,00 * 1,00 20,00
CH 0+110
20,00 * 2,00 40,00
CH 0+170 / CH 0+370
20,00 * 3,50 70,00
20,00 * 8,00 160,00
20,00 * 7,00 140,00
20,00 * 2,00 40,00
20,00 * 5,00 100,00
20,00 * 7,50 150,00
20,00 * 6,00 120,00
20,00 * 5,50 110,00
20,00 * 7,50 150,00
20,00 * 9,00 180,00
20,00 * 1,00 20,00
CH 0+450 / CH 0+750
20,00 * 1,00 20,00
20,00 * 2,50 50,00
20,00 * 7,00 140,00
20,00 * 1,00 20,00
20,00 * 2,00 40,00
20,00 * 4,00 80,00
20,00 * 4,00 80,00
20,00 * 5,00 100,00
20,00 * 1,50 30,00
20,00 * 1,00 20,00
20,00 * 2,00 40,00
20,00 * 3,00 60,00
20,00 * 3,50 70,00
20,00 * 8,00 160,00
20,00 * 2,00 40,00
20,00 * 3,00 60,00
CH 0+790 / CH 0+830
20,00 * 3,00 60,00
20,00 * 1,50 30,00
20,00 * 2,00 40,00
Total sqm 2.540,00 8.500,
00
10 NP.CW.02.02 Wire mesh D. 6/100/100 for Shotcrete - external areas
CH 0+050 / CH 0+070
20,00 * 5,00 100,00
20,00 * 1,00 20,00
N. CODE
N. CODE
10 * 5,00 50,00
10 * 6,00 60,00
10 * 8,00 80,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 5,00 50,00
10 * 6,00 60,00
(10*2) * 8,00 160,00
10 * 5,00 50,00
10 * 6,00 60,00
(10*2) * 8,00 160,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 12,00 120,00
10 * 5,00 50,00
CH 0+450 / CH 0+750
10 * 5,00 50,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 5,00 50,00
10 * 5,00 50,00
10 * 5,00 50,00
10 * 6,00 60,00
N. CODE
1.692,00
1.692,00 3.000,00
-9-
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
003 - Rockfall Protection Measures
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
160 - Protezione scavi
N. CODE
513,00
1.935,00
213,00
4.788,00 9.350,00
16 NP.CW.04.06
782,40
2.620,80
- 10 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
003 - Rockfall Protection Measures
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
160 - Protezione scavi
N. CODE
2.130,00
2.130,00 3.000,00
- 11 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
003 - Rockfall Protection Measures
009 - ROCKFALL BARRIER
160 - Protezione scavi
N. CODE
- 12 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
003 - Rockfall Protection Measures
010 - Scaling of unstable blocks
160 - Protezione scavi
N. CODE
N. CODE
N. CODE
- 15 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
019 - Culvert 1
1005 - culverts
N. CODE
24 07.02.00.D AMOUNT CARRIED FORWARD 16.857,39
25 20.02.00.A Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts - 900 mm 11.539,20
26 20.02.00.G internal dia. 13.966,07
27 20.03.00.0 11,70 110.464,93
28 20.04.00.G.0p Total m 14.843,16
29 20.05.00.0 Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 2,50 * 2,50 * 0,20 11,70 110.464,93
30 22.01.00.A 11,00 * 1,30 * 0,20 11,70 437.000,00
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 2,10 * 2,10 * 0,30
Total cum 1,25
Providing and laying , fitting and placing un-coated Mild steel / HYSD 2,86
reinforcement complete in foundation
stell ratio 1,32 * 0,100 4,11
Total tonne
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m
2 * 1,50 * 2,50 * 0,30
2,10 * 2,50 * 0,30 1,32
2,10 * 4,00 * 0,30 1,32
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio
6,35 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,150 0,1320
Total tonne 0,1320
Total 1005 - culverts NPR
Total 019 - Culvert 1 NPR
CARRY FORWARD Hydraulic Works
2,25
CARRY FORWARD Road Alignement MR1 - Main Road - 1,58
... 2,52
CARRY FORWARD
6,35
0,6350
0,6350
0,1500
0,1500
- 16 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
020 - Culvert 2
90 - Excavation
N. CODE
N. CODE
- 18 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
020 - Culvert 2
1005 - culverts
N. CODE
33 20.02.00.A AMOUNT CARRIED FORWARD 11.539,20
34 20.02.00.G Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 culvert 13.966,07
35 20.03.00.0 13,25 * 2,10 * 0,10 110.464,93
36 20.04.00.G.0p shaft 14.843,16
2,78
37 20.05.00.0 2,60 * 2,60 * 0,20 110.464,93
1,35
38 22.01.00.A Total cum 437.000,00
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 culvert
8,35
shaft 2,03
Total cum 4,13
Providing and laying , fitting and placing un-coated Mild steel / HYSD
reinforcement complete in foundation
stell ratio 10,38 * 0,100
Total tonne 8,35
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m 2,03
culvert 24,35
shaft 11,84
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio 10,38
36,19 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,250
Total tonne
Total 1005 - culverts NPR 1,0380
Total 020 - Culvert 2 NPR 1,0380
CARRY FORWARD Hydraulic Works
CARRY FORWARD Road Alignement MR1 - Main Road -
... 24,3
CARRY FORWARD 5
11,8
4
36,19
3,6190
3,6190
0,2500
0,2500
- 19 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
021 - Culvert A1
90 - Excavation
N. CODE
N. CODE
- 21 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
021 - Culvert A1
1005 - culverts
N. CODE
41 07.02.00.F AMOUNT CARRIED FORWARD 21.807,99
42 20.02.00.A Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts - 1200 mm 11.539,20
43 20.02.00.G internal dia. 13.966,07
44 20.03.00.0 14,50 110.464,93
45 20.04.00.G.0p Total m 14.843,16
46 20.05.00.0 Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 2,50 * 2,50 * 0,20 14,50 110.464,93
47 22.01.00.A 14,20 * 1,70 * 0,20 14,50 437.000,00
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 2,10 * 2,10 * 0,30
Total cum 1,25
Providing and laying , fitting and placing un-coated Mild steel / HYSD 4,83
reinforcement complete in foundation
stell ratio 1,32 * 0,100 6,08
Total tonne
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m
2 * 1,50 * 2,50 * 0,30
2,10 * 2,50 * 0,30 1,32
2,10 * 4,00 * 0,30 1,32
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio
6,35 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,150 0,1320
Total tonne 0,1320
Total 1005 - culverts NPR
Total 021 - Culvert A1 NPR
CARRY FORWARD Hydraulic Works
2,25
CARRY FORWARD Road Alignement MR1 - Main Road - 1,58
... 2,52
CARRY FORWARD
6,35
0,6350
0,6350
0,1500
0,1500
- 22 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
022 - Culvert 3
90 - Excavation
N. CODE
N. CODE
- 24 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
022 - Culvert 3
1005 - culverts
N. CODE
50 07.02.00.F AMOUNT CARRIED FORWARD 21.807,99
51 20.02.00.A Providing and Laying Reinforced Cement Concrete Flush jointed Pipe for culverts - 1200 mm 11.539,20
52 20.02.00.G internal dia. 13.966,07
53 20.03.00.0 16,80 110.464,93
54 20.04.00.G.0p Total m 14.843,16
55 20.05.00.0 Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 2,50 * 2,50 * 0,20 16,80 110.464,93
56 22.01.00.A 16,50 * 1,70 * 0,20 16,80 437.000,00
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 2,10 * 2,10 * 0,30
Total cum 1,25
Providing and laying , fitting and placing un-coated Mild steel / HYSD 5,61
reinforcement complete in foundation
stell ratio 1,32 * 0,100 6,86
Total tonne
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m
2 * 1,50 * 2,50 * 0,30
2,10 * 2,50 * 0,30 1,32
2,10 * 4,00 * 0,30 1,32
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio
6,35 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,150 0,1320
Total tonne 0,1320
Total 1005 - culverts NPR
Total 022 - Culvert 3 NPR
CARRY FORWARD Hydraulic Works
2,25
CARRY FORWARD Road Alignement MR1 - Main Road - 1,58
... 2,52
CARRY FORWARD
6,35
0,6350
0,6350
0,1500
0,1500
- 25 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
023 - Culvert A2
90 - Excavation
N. CODE
N. CODE
- 27 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
023 - Culvert A2
1005 - culverts
N. CODE
59 20.02.00.A AMOUNT CARRIED FORWARD 11.539,20
60 20.02.00.G Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 culvert 13.966,07
61 20.03.00.0 15,50 * 2,10 * 0,10 110.464,93
62 20.04.00.G.0p shaft 14.843,16
3,26
63 20.05.00.0 2,60 * 2,60 * 0,20 110.464,93
1,35
64 22.01.00.A Total cum 437.000,00
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 culvert
9,77
shaft 2,03
Total cum 4,61
Providing and laying , fitting and placing un-coated Mild steel / HYSD
reinforcement complete in foundation
stell ratio 11,80 * 0,100
Total tonne 9,77
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m 2,03
culvert 23,72
shaft 10,37
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio 11,80
34,09 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,250
Total tonne
Total 1005 - culverts NPR 1,1800
Total 023 - Culvert A2 NPR 1,1800
CARRY FORWARD Hydraulic Works
CARRY FORWARD Road Alignement MR1 - Main Road -
... 23,7
CARRY FORWARD 2
10,3
7
34,09
3,4090
3,4090
0,2500
0,2500
- 28 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
024 - Culvert 4
90 - Excavation
N. CODE
N. CODE
- 30 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
024 - Culvert 4
1005 - culverts
N. CODE
67 20.02.00.A AMOUNT CARRIED FORWARD 11.539,20
68 20.02.00.G Plain/Reinforced Cement Concrete in Foundation - PCC Grade M 15 culvert 13.966,07
69 20.03.00.0 12,90 * 4,90 * 0,10 110.464,93
70 20.04.00.G.0p shaft 14.843,16
6,32
71 20.05.00.0 2,60 * 2,60 * 0,20 110.464,93
1,35
72 22.01.00.A Total cum 437.000,00
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 30 culvert
18,96
shaft 2,03
Total cum 7,67
Providing and laying , fitting and placing un-coated Mild steel / HYSD
reinforcement complete in foundation
stell ratio 20,99 * 0,100
Total tonne 18,96
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 30 - Height upto 5 m 2,03
culvert 42,18
shaft 20,52
Total cum
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure stell ratio 20,99
62,70 * 0,100
Total tonne
Providing, Fabricating, assembling and erecting structural steel
components/elements
steel grating cover 0,250
Total tonne
Total 1005 - culverts NPR 2,0990
Total 024 - Culvert 4 NPR 2,0990
CARRY FORWARD Hydraulic Works
CARRY FORWARD Road Alignement MR1 - Main Road -
... 42,1
CARRY FORWARD 8
20,5
2
62,70
6,2700
6,2700
0,2500
0,2500
- 31 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
006 - Hydraulic Works
025 - Culvert 5
90 - Excavation
N. CODE
N. CODE
27,16
2,7160
2,7160
0,2500
0,2500
- 33 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
050 - Wall CH 0+050 / CH 0+110
90 - Excavation
N. CODE
- 34 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
050 - Wall CH 0+050 / CH 0+110
560 - Structures
N. CODE
81 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
82 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
83 20.05.00.0 80,00 * 0,70 * 0,10 110.464,93
84 NP.CW.04.01 Total cum 7.780,00
85 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
86 NP.CW.16.01 reinforcement complete in foundation 5,60 16.220,39
87 NP.CW.18.01 steel rate 12,00 * 0,080 5,60 15.188,18
88 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
25,57 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 27 * 3,50 0,9600
Total m 0,9600
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 32 * 4,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
2,0456
20.04.00.H.0p + 7%)
wall 2,0456
80,00 * 1,00 * 0,30
protection cap
27 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 80,00 * 0,50 * 0,30
94,50
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 94,50
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
33 * 5,00
Total m
Total 560 - Structures NPR
Total 050 - Wall CH 0+050 / CH 0+110 NPR 144,00
CARRY FORWARD Civil Works
144,00
CARRY FORWARD Road Alignement MR1 - Main Road -
...
CARRY FORWARD
24,00
1,57
25,57
12,00
12,00
165,00
165,00
- 35 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
051 - Wall CH 0+150 / CH 0+250
90 - Excavation
N. CODE
N. CODE
12,00
27,00
3,48
63,48 16.220,39
96 NP.CW.18.01
18,00
18,00 15.188,18
97 NP.CW.19.01
200,00
200,00 2.900,00
- 37 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
051 - Wall CH 0+150 / CH 0+250
560 - Structures
N. CODE
AMOUNT CARRIED FORWARD
Total 560 - Structures NPR
Total 051 - Wall CH 0+150 / CH 0+250 NPR
CARRY FORWARD Civil Works
CARRY FORWARD Road Alignement MR1 - Main Road -
...
CARRY FORWARD
- 38 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
052 - Wall CH 0+350
90 - Excavation
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 39 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
052 - Wall CH 0+350
560 - Structures
N. CODE
12,58
3,00
3,00
30,00
30,00
- 40 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
053 - Wall CH 0+390
90 - Excavation
N. CODE
- 41 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
053 - Wall CH 0+390
560 - Structures
N. CODE
108 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
109 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
110 20.05.00.0 20,00 * 0,70 * 0,10 110.464,93
111 NP.CW.04.01 Total cum 7.780,00
112 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
113 NP.CW.16.01 reinforcement complete in foundation 1,40 16.220,39
114 NP.CW.18.01 steel rate 3,00 * 0,080 1,40 15.188,18
115 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
12,41 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 7 * 8,00 0,2400
Total m 0,2400
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 14 * 7,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
0,9928
20.04.00.H.0p + 7%)
wall 0,9928
20,00 * 2,00 * 0,30
protection cap
7 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 20,00 * 0,50 * 0,30
56,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 56,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
6 * 5,00
Total m
Total 560 - Structures NPR
Total 053 - Wall CH 0+390 NPR 105,00
CARRY FORWARD Civil Works
105,00
CARRY FORWARD Road Alignement MR1 - Main Road -
...
CARRY FORWARD
12,00
0,41
12,41
3,00
3,00
30,00
30,00
- 42 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
054 - Wall CH 0+450
90 - Excavation
N. CODE
N. CODE
6,58
3,00
3,00
30,00
30,00
- 44 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
055 - Wall CH 0+530 / CH 0+550
90 - Excavation
N. CODE
- 45 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
055 - Wall CH 0+530 / CH 0+550
560 - Structures
N. CODE
126 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
127 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
128 20.05.00.0 40,00 * 0,70 * 0,10 110.464,93
129 NP.CW.04.01 Total cum 7.780,00
130 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
131 NP.CW.16.01 reinforcement complete in foundation 2,80 16.220,39
132 NP.CW.18.01 steel rate 6,00 * 0,080 2,80 15.188,18
133 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
24,81 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 14 * 8,00 0,4800
Total m 0,4800
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 27 * 7,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
1,9848
20.04.00.H.0p + 7%)
wall 1,9848
40,00 * 2,00 * 0,30
protection cap
14 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 40,00 * 0,50 * 0,30
112,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 112,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
13 * 5,00
Total m
Total 560 - Structures NPR
Total 055 - Wall CH 0+530 / CH 0+550 NPR 202,50
CARRY FORWARD Civil Works
202,50
CARRY FORWARD Road Alignement MR1 - Main Road -
...
CARRY FORWARD
24,00
0,81
24,81
6,00
6,00
65,00
65,00
- 46 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
056 - Wall CH 0+630 / CH 0+650
90 - Excavation
N. CODE
N. CODE
24,81
6,00
6,00
65,00
65,00
- 48 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
057 - Wall CH 0+790
90 - Excavation
N. CODE
- 49 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
057 - Wall CH 0+790
560 - Structures
N. CODE
144 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
145 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
146 20.05.00.0 20,00 * 0,70 * 0,10 110.464,93
147 NP.CW.04.01 Total cum 7.780,00
148 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
149 NP.CW.16.01 reinforcement complete in foundation 1,40 16.220,39
150 NP.CW.18.01 steel rate 3,00 * 0,080 1,40 15.188,18
151 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
6,58 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 10 * 3,50 0,2400
Total m 0,2400
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 8 * 4,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
0,5264
20.04.00.H.0p + 7%)
wall 0,5264
20,00 * 1,00 * 0,30
protection cap
10 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 20,00 * 0,50 * 0,30
35,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 35,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
6 * 5,00
Total m
Total 560 - Structures NPR
Total 057 - Wall CH 0+790 NPR 36,00
CARRY FORWARD Civil Works
36,00
CARRY FORWARD Road Alignement MR1 - Main Road -
...
CARRY FORWARD
6,00
0,58
6,58
3,00
3,00
30,00
30,00
- 50 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
058 - Wall CH 0+870 / CH 0+890
90 - Excavation
N. CODE
N. CODE
127,60
3,13
130,73
49,20
49,20
125,00
125,00
- 52 -
Priced Bill of Quantities
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904
007 - Civil Works
058 - Wall CH 0+870 / CH 0+890
560 - Structures
N. CODE
AMOUNT CARRIED FORWARD
Total 058 - Wall CH 0+870 / CH 0+890 NPR
Total 007 - Civil Works NPR
Total 01 - Road Alignement MR1 - Main Road - South
Stretch - CH 0+000 to 0+904 NPR
CARRY FORWARD
- 53 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
001 - Road Works
001 - Exavation, Filling and Paving
1420 - Paving
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
23.069,00
23.069,00
- 54 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
001 - Road Works
004 - Signaling
1610 - Signaling
N. CODE
N. CODE
- 56 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350
175 - Embankment/Filling
N. CODE
135,00
135,00 9.893,01
- 57 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
189,33
20,42
109,51
82,93
1.807,65 11.300,00
172 NP.CW.02.03
64,62
90,06
19,26
57,96
- 58 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
630,00
315,00
270,00
75,00
4.524,00 11.990,00
174 NP.CW.04.05
- 59 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
28,42
9,56
37,98 15.188,18
- 60 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
102 - Technological Building South
280 - Foundation Slabs
N. CODE
Foundation
((13,56+7,70)/2) * 19,25 * 0,10 20,46
(1/2) * 13,56 * 4,70 * 0,10 3,19
(1/2) * 14,00 * 3,13 21,91
1,90 * 0,60 1,14
Total cum 46,70 9.893,01
178 20.03.00.0 Providing and laying , fitting and placing un-coated Mild steel / HYSD
20.02.00.h + 7%)
((13,34+7,52)/2) * 19,11 * 0,40 79,73
(1/2) * 13,34 * 4,71 * 0,40 12,57
(1/2) * 13,83 * 3,00 * 0,40 8,30
6,32 * 0,80 * 0,30 1,52
6,16 * 0,30 * (0,30/2) 0,28
6,49 * 0,30 * (0,30/2) 0,29
11,28 * 0,80 * 0,30 2,71
11,11 * 0,30 * (0,30/2) 0,50
11,53 * 0,80 * (0,80/2) 3,69
11,33 * 0,50 * 0,55 3,12
9,06 * 0,80 * 0,30 2,17
8,89 * 0,30 * (0,30/2) 0,40
9,26 * 0,50 * (0,50/2) 1,16
9,10 * 0,55 * 0,20 1,00
(16,53+1,16+5,96+11,35) * 0,80 * 0,30 8,40
(15,85+1,16+5,96+10,40) * 0,30 * (0,30/2) 1,50
slab +0.00
((8,29+6,93)/2) * 4,50 * 0,20 6,85
Total cum 134,19 15.188,18
Total 280 - Foundation Slabs NPR
N. CODE
20.04.00.H.0p + 7%)
Over ground floor
7,23 * 0,40 * 4,00 11,57
7,63 * 0,40 * 4,50 13,73
5,12 * 0,40 * 4,70 9,63
6,93 * 0,40 * 4,70 13,03
4,90 * 0,30 * 4,70 6,91
7,30 * 0,30 * 4,50 9,86
11,63 * 0,30 * 4,00 13,96
3,00 * 0,30 * 4,00 3,60
11,75 * 0,40 * 4,00 18,80
8,38 * 0,30 * 4,50 11,31
2 * 2,50 * 0,30 * 4,00 6,00
7,10 * 0,30 * 4,00 8,52
5,45 * 0,30 * 4,00 6,54
1,20 * 0,30 * 4,00 1,44
5,95 * 0,30 * 4,00 7,14
-2 * 2,00 * 0,30 * 2,30 -2,76
-1 * 1,20 * 0,30 * 2,30 -0,83
-1 * 4,00 * 0,30 * 3,00 -3,60
((1,48+0,90)/2) * 0,40 * (4,40+0,70+0,70) 2,76
Over first floor
19,98 * 0,40 * 3,00 23,98
6,93 * 0,40 * 3,00 8,32
23,82 * 0,30 * 3,00 21,44
3,00 * 0,30 * 3,00 2,70
11,75 * 0,40 * 3,00 14,10
5,93 * 0,30 * 3,00 5,34
4,73 * 0,30 * 3,00 4,26
4,78 * 0,30 * 3,00 4,30
1,75 * 0,20 * 3,00 1,05
5,33 * 0,30 * 3,00 4,80
0,80 * 0,20 * 3,00 0,48
1,24 * 0,30 * 3,00 1,12
6,01 * 0,20 * 3,00 3,61
2,99 * 0,20 * 3,00 1,79
4,28 * 0,20 * 3,00 2,57
1,86 * 0,20 * 3,00 1,12
CARRY FORWARD Vertical Elements
CARRY FORWARD Technological Building South
CARRY FORWARD Main Tunnel - South portal -Technological Building
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 62 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
102 - Technological Building South
300 - Vertical Elements
N. CODE
N. CODE
- 64 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
101 - Main Tunnel - South portal -Technological Building
102 - Technological Building South
685 - Completion work
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
5,00 25.000,00
- 65 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
90 - Excavation
N. CODE
N. CODE
230,00
230,00 9.893,01
- 67 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
252,72
537,81
69,36
310,95
34,17
150,89
14,19
561,56
- 68 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
180,00
210,00
900,00
75,00
1.845,00 20.140,00
199 NP.CW.05.01
400,00
- 69 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi
N. CODE
- 70 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
103 - Technological Building North
280 - Foundation Slabs
N. CODE
200 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
201 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
202 NP.CW.18.01 (1/2) * 15,60 * 15,60 * 0,10 15.188,18
4,10 * 15,60 * 0,10 12,17
6,40
19,70 * 2,10 * 0,10
Total cum 4,14
Providing and laying , fitting and placing un-coated Mild steel / HYSD
reinforcement complete in foundation
Steel ratio 95.00 kg/mc 162,01 * 0,095 22,71
Total tonne
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%)
(1/2) * 15,50 * 15,50 * 0,30
4,00 * 15,50 * 0,30
(14,70+17,30) * 0,30 * (0,30/2)
(15,50+18,00) * 0,80 * 0,30 15,3910
19,50 * 2,00 * 2,51 15,3910
Total cum Total 280 - Foundation Slabs NPR
CARRY FORWARD Technological Building North 36,04
CARRY FORWARD Main Tunnel - North portal -Technological Building 18,60
1,44
CARRY FORWARD Road Alignement TU – Tunnel - CH 8,04
0... 97,89
CARRY FORWARD
162,01
- 71 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
103 - Technological Building North
300 - Vertical Elements
N. CODE
20.04.00.H.0p + 7%)
Over underground floor
1,75 * 0,30 * (3,60+0,30+0,30+0,30) 2,36
15,50 * 0,40 * 3,60 22,32
7,74 * 0,30 * 3,60 8,36
11,76 * 0,30 * 3,40 12,00
0,50 * (0,50/2) * 3,40 0,43
9,02 * 0,30 * 3,40 9,20
12,90 * 0,30 * 3,60 13,93
3,60 * 0,30 * 3,60 3,89
3 * 4,42 * 0,20 * 3,60 9,55
11,74 * 0,30 * 3,60 12,68
1,45 * 0,30 * 3,60 1,57
1,12 * 0,30 * 3,60 1,21
3,98 * 0,20 * 3,60 2,87
1,76 * 0,20 * 3,60 1,27
0,71 * (0,71/2) * 3,60 0,92
4,96 * 0,30 * 3,40 5,06
5,78 * 0,30 * 3,40 5,90
0,50 * (0,50/2) * 3,40 0,43
-5 * 0,80 * 0,30 * 0,60 -0,72
-1 * 0,80 * 0,20 * 0,60 -0,10
Over ground floor
1,75 * 0,30 * (4,50+0,40) 2,57
15,50 * 0,40 * 4,50 27,90
8,04 * 0,30 * 4,50 10,85
4,96 * 0,30 * 4,70 6,99
5,78 * 0,30 * 4,70 8,15
0,42 * 0,30 * 4,50 0,57
12,73 * 0,30 * 4,50 17,19
3,60 * 0,30 * 4,50 4,86
3,10 * 0,20 * 4,50 2,79
6,38 * 0,30 * 4,50 8,61
2,40 * 0,30 * 4,50 3,24
1,45 * 0,30 * 4,50 1,96
5,78 * 0,30 * 4,50 7,80
1,32 * 0,30 * 4,50 1,78
1,61 * 0,20 * 4,50 1,45
CARRY FORWARD Vertical Elements
CARRY FORWARD Technological Building North
CARRY FORWARD Main Tunnel - North portal -Technological Building
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 72 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
103 - Technological Building North
300 - Vertical Elements
N. CODE
N. CODE
- 74 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
102 - Main Tunnel - North portal -Technological Building
103 - Technological Building North
685 - Completion work
N. CODE
- 75 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
180 - Filling
N. CODE
209 12.01.00.a AMOUNT CARRIED FORWARD 1.996,
Providing and laying Granular Sub-Base Material - By Mechanical means section type 0 11
54,5 * 14,86
Total cum Total 180 - Filling NPR
CARRY FORWARD Main Tunnel - section type 0 straight ...
CARRY FORWARD Main Tunnel 809,87
CARRY FORWARD Road Alignement TU – Tunnel - CH 809,87
0...
CARRY FORWARD
- 76 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
800 - Tunnel excavation
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 77 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
810 - Pre-Support
N. CODE
1.475,32
1.475,32
CARRY FORWARD
- 78 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 79 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
845 - Waterproofing system
N. CODE
- 80 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
110 - Main Tunnel - section type 0 straight line (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
N. CODE
- 82 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
111 - Main Tunnel - section type 1 straight line (only excavation and lining)
180 - Filling
N. CODE
- 83 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
111 - Main Tunnel - section type 1 straight line (only excavation and lining)
800 - Tunnel excavation
N. CODE
224 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 1 42
137 * 108,36
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 1 straight ...
CARRY FORWARD Main Tunnel 14.845,32
CARRY FORWARD Road Alignement TU – Tunnel - CH 14.845,32
0...
CARRY FORWARD
- 84 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
111 - Main Tunnel - section type 1 straight line (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
3.729,14
3.729,14
- 85 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
111 - Main Tunnel - section type 1 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
- 88 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
111 - Main Tunnel - section type 1 straight line (only excavation and lining)
853 - Lining upper side
N. CODE
- 89 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
180 - Filling
N. CODE
- 90 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
800 - Tunnel excavation
N. CODE
238 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 2 42
75,5 * 109,74
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 2 straight ...
CARRY FORWARD Main Tunnel 8.285,37
CARRY FORWARD Road Alignement TU – Tunnel - CH 8.285,37
0...
CARRY FORWARD
- 91 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
2.049,83
2.049,83
2.067,95
2.043,79
4.111,74
- 92 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 93 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
845 - Waterproofing system
N. CODE
- 94 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
112 - Main Tunnel - section type 2 straight line (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
N. CODE
- 96 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
180 - Filling
N. CODE
- 97 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
800 - Tunnel excavation
N. CODE
255 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 3 42
103 * 111,40
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 3 straight ...
CARRY FORWARD Main Tunnel 11.474,20
CARRY FORWARD Road Alignement TU – Tunnel - CH 11.474,20
0...
CARRY FORWARD
- 98 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
2.804,69
2.804,69
2.836,62
2.795,42
5.632,04
- 99 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
480,50
480,50
CARRY FORWARD
- 100 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
845 - Waterproofing system
N. CODE
- 101 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
- 102 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
113 - Main Tunnel - section type 3 straight line (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
N. CODE
N. CODE
- 105 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
114 - Main Tunnel - section type 4 straight line (only excavation and lining)
810 - Pre-Support
N. CODE
274 NP.UW.03.01 AMOUNT CARRIED FORWARD 277.778,00
275 NP.UW.04.01 Armor whit steel ribs for underground works section type 4 3.043,88
276 NP.UW.04.02 HEB 180 - weigth 51.20 kg/m 5.234,30
277 NP.UW.05.05 91 * ((27,70+29,59)/2*51,20/1000) 11.131,12
133,460
278 NP.UW.06.01 plates & link chains - 45% 581,39
6
91 * ((27,70+29,59)/2*51,20*45%/1000)
60,0600
Total tonne
50 mm thick shotcreting with steel fibers for underground works section type 4
lining
91 * ((28,06+29,95)/2)
excavation face (50%) * 91 * 133,20 193,5206
Total sqm
100 mm thick shotcreting with steel fibers for underground works section type 4
excavation face
(50%) * 91 * 133,20
Total sqm 2.639,91
250 mm thick shotcreting for underground works section type 4 6.060,60
91 * ((27,62+29,51)/2)
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 4
91 * ((27,39+29,27)/2)
91 * ((28,02+29,90)/2) 8.700,51
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD Main Tunnel - section type 4 straight ...
CARRY FORWARD Main Tunnel
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD 6.060,60
6.060,60
2.599,87
2.599,87
2.578,03
2.635,36
5.213,39
- 106 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
114 - Main Tunnel - section type 4 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
184,4115
184,4115
- 107 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
114 - Main Tunnel - section type 4 straight line (only excavation and lining)
845 - Waterproofing system
N. CODE
- 108 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
114 - Main Tunnel - section type 4 straight line (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
- 109 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
114 - Main Tunnel - section type 4 straight line (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
N. CODE
N. CODE
- 112 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
115 - Main Tunnel - section type 5 straight line (only excavation and lining)
810 - Pre-Support
N. CODE
293 NP.UW.03.01 AMOUNT CARRIED FORWARD 277.778,00
294 NP.UW.04.01 Armor whit steel ribs for underground works section type 5 3.043,88
295 NP.UW.04.02 HEB 180 - weigth 51.20 kg/m 5.234,30
296 NP.UW.05.06 vault 13.357,34
297 NP.UW.06.01 164 * (29,08*51,20/1000) 244,179 581,39
invert 6
164 * (12,56*51,20/1000) 105,468
plates & link chains - 45% 4
164 * ((29,08+12,56)*51,20*45%/1000) 157,341
Total tonne 6
50 mm thick shotcreting with steel fibers for underground works section type 5
lining vault
164 * 29,50
lining invert 164 * 11,90
excavation face (50%) * 164 * 119,31
Total sqm 506,9896
100 mm thick shotcreting with steel fibers for underground works section type 5
excavation face
(50%) * 164 * 119,31
Total sqm
300 mm thick shotcreting for underground works section type 5
lining vault 4.838,00
164 * 28,96 1.951,60
lining invert 164 * 12,26 9.783,42
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 5
164 * (28,75+12,77)
164 * (29,42+12,33)
Total sqm Total 810 - Pre-Support NPR 16.573,02
CARRY FORWARD Main Tunnel - section type 5 straight ...
CARRY FORWARD Main Tunnel
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
9.783,42
9.783,42
4.749,44
2.010,64
6.760,08
6.809,28
6.847,00
13.656,28
- 113 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
115 - Main Tunnel - section type 5 straight line (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
- 116 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
115 - Main Tunnel - section type 5 straight line (only excavation and lining)
853 - Lining upper side
N. CODE
- 117 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
180 - Filling
N. CODE
306 12.01.00.a AMOUNT CARRIED FORWARD 1.996,
Providing and laying Granular Sub-Base Material - By Mechanical means section type 0 curve 11
section
54,5 * 16,10
Total cum Total 180 - Filling NPR
CARRY FORWARD Main Tunnel - section type 0 widened sec... 877,45
CARRY FORWARD Main Tunnel
877,45
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 118 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
800 - Tunnel excavation
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 119 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
810 - Pre-Support
N. CODE
1.438,84
1.438,84
CARRY FORWARD
- 120 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 121 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
845 - Waterproofing system
N. CODE
- 122 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
13,0000
13,0000 122.616,07
- 123 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
117 - Main Tunnel - section type 0 widened section (only excavation and lining)
853 - Lining upper side
N. CODE
54,6000 124.626,56
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 124 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
118 - Main Tunnel - section type 1 widened section (only excavation and lining)
180 - Filling
N. CODE
- 125 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
118 - Main Tunnel - section type 1 widened section (only excavation and lining)
800 - Tunnel excavation
N. CODE
321 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 1 curve 42
section
141 * 114,40
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 1 widened sec... 16.130,40
CARRY FORWARD Main Tunnel
16.130,40
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 126 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
118 - Main Tunnel - section type 1 widened section (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
3.924,03
3.924,03
- 127 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
118 - Main Tunnel - section type 1 widened section (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
35,2500
35,2500 122.616,07
0...
CARRY FORWARD
- 130 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
118 - Main Tunnel - section type 1 widened section (only excavation and lining)
853 - Lining upper side
N. CODE
148,0500 124.626,56
- 131 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
180 - Filling
N. CODE
- 132 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
800 - Tunnel excavation
N. CODE
335 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 2 curve 42
section
120 * 115,81
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 2 widened sec... 13.897,20
CARRY FORWARD Main Tunnel
13.897,20
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 133 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
3.330,00
3.330,00
3.358,80
3.320,40
6.679,20
- 134 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 135 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
845 - Waterproofing system
N. CODE
- 136 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
30,0000
30,0000 122.616,07
- 137 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
119 - Main Tunnel - section type 2 widened section (only excavation and lining)
853 - Lining upper side
N. CODE
126,0000 124.626,56
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 138 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
180 - Filling
N. CODE
- 139 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
800 - Tunnel excavation
N. CODE
352 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 3 - curve 42
section
66 * 117,51
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 3 widened sec... 7.755,66
CARRY FORWARD Main Tunnel
7.755,66
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 140 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
1.836,78
1.836,78
1.857,24
1.830,84
3.688,08
- 141 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
820 - Rock Reinforcement
N. CODE
307,89
307,89
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 142 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
845 - Waterproofing system
N. CODE
- 143 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
16,5000
16,5000 122.616,07
- 144 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
120 - Main Tunnel - section type 3 widened section (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
69,3000 124.626,56
- 145 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
122 - Main Tunnel - section type 0 lay-by (only excavation and lining)
180 - Filling
N. CODE
N. CODE
- 147 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
122 - Main Tunnel - section type 0 lay-by (only excavation and lining)
810 - Pre-Support
N. CODE
371 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
372 NP.UW.05.01 50 mm thick shotcreting with steel fibers for underground works section type 0 - lay by 2.652,95
373 NP.UW.06.01 17 * 30,74 581,39
Total sqm
50 mm thick shotcreting for underground works section type 0 - lay by
17 * 30,58
522,58
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 0 - lay by 522,58
17 * 30,66
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD Main Tunnel - section type 0 lay-by (only...
CARRY FORWARD Main Tunnel
CARRY FORWARD Road Alignement TU – Tunnel - CH 519,86
0... 519,86
CARRY FORWARD
521,22
521,22
- 148 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
122 - Main Tunnel - section type 0 lay-by (only excavation and lining)
820 - Rock Reinforcement
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 149 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
122 - Main Tunnel - section type 0 lay-by (only excavation and lining)
845 - Waterproofing system
N. CODE
N. CODE
7,6500
7,6500 122.616,07
0...
CARRY FORWARD
- 151 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
122 - Main Tunnel - section type 0 lay-by (only excavation and lining)
853 - Lining upper side
N. CODE
44,2481
73,1481 124.626,56
- 152 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
123 - Main Tunnel - section type 1 lay-by (only excavation and lining)
180 - Filling
N. CODE
- 153 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
123 - Main Tunnel - section type 1 lay-by (only excavation and lining)
800 - Tunnel excavation
N. CODE
384 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 1 - lay by 42
43 * 146,50
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 1 lay-by (only...
CARRY FORWARD Main Tunnel 6.299,50
CARRY FORWARD Road Alignement TU – Tunnel - CH 6.299,50
0...
CARRY FORWARD
- 154 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
123 - Main Tunnel - section type 1 lay-by (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
1.325,26
1.325,26
- 155 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
123 - Main Tunnel - section type 1 lay-by (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
19,3500
19,3500 122.616,07
0...
CARRY FORWARD
- 158 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
123 - Main Tunnel - section type 1 lay-by (only excavation and lining)
853 - Lining upper side
N. CODE
44,2481
117,3481 124.626,56
- 159 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
180 - Filling
N. CODE
- 160 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
800 - Tunnel excavation
N. CODE
398 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 2 - lay by 42
17 * 148,06
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 2 lay-by (only...
CARRY FORWARD Main Tunnel 2.517,02
CARRY FORWARD Road Alignement TU – Tunnel - CH 2.517,02
0...
CARRY FORWARD
- 161 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
522,58
522,58
526,
66
521,
22
1.047,88
- 162 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 163 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
845 - Waterproofing system
N. CODE
- 164 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
7,6500
7,6500 122.616,07
- 165 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
124 - Main Tunnel - section type 2 lay-by (only excavation and lining)
853 - Lining upper side
N. CODE
44,2481
73,1481 124.626,56
- 166 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
180 - Filling
N. CODE
- 167 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
800 - Tunnel excavation
N. CODE
415 NP.UW.02.02 AMOUNT CARRIED FORWARD 6.753,
Rock Excavations for underground works - with hammer or drill&blast section type 3 - lay by 42
9 * 151,56
Total cum Total 800 - Tunnel excavation NPR
CARRY FORWARD Main Tunnel - section type 3 lay-by (only...
CARRY FORWARD Main Tunnel 1.364,04
CARRY FORWARD Road Alignement TU – Tunnel - CH 1.364,04
0...
CARRY FORWARD
- 168 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
810 - Pre-Support
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
278,10
278,10
281,
61
276,
57
558,18
- 169 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
820 - Rock Reinforcement
N. CODE
- 170 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
845 - Waterproofing system
N. CODE
- 171 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
4,0500
4,0500 122.616,07
- 172 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
125 - Main Tunnel - section type 3 lay-by (only excavation and lining)
853 - Lining upper side
N. CODE
44,2481
59,5481 124.626,56
- 173 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
126 - Main Tunnel - Cut&Cover Stretch South
870 - Portal
N. CODE
16,2048
16,2048 122.616,07
438 NP.UW.23.01
306,01
30,12
336,13 19.445,72
439 NP.UW.24.01
47,0582
47,0582 124.626,56
- 174 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
126 - Main Tunnel - Cut&Cover Stretch South
870 - Portal
N. CODE
AMOUNT CARRIED FORWARD
Total 870 - Portal NPR
Total 126 - Main Tunnel - Cut&Cover Stretch South NPR
CARRY FORWARD Main Tunnel
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 175 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
127 - Main Tunnel - Cut&Cover Stretch North
870 - Portal
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
376,00
16,47
6,38
398,85
63,8160
63,8160
- 176 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
250 - Drenaggi
N. CODE
101,00
4,10
4,10
4,10
113,30
1.133,00
495,90
- 177 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
250 - Drenaggi
N. CODE
2.769,20
650,
00
735,
00
200,
00
100,
00
100,
00
1.785,00
1.126,00
- 178 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
250 - Drenaggi
N. CODE
- 179 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
700 - Marciapiedi e cordoli
N. CODE
2.253,20
2.253,20 1.950,00
- 180 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
1980 - Antincendio
N. CODE
1,00
1,00 12.000.000,00
468 NP.UW.32.03
1,00
1,00 10.000.000,00
- 181 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
1982 - Doors for by-pass and niches
N. CODE
N. CODE
- 183 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
1985 - Painting and internal surfaces finishing
N. CODE
472 NP.UW.35.01 AMOUNT CARRIED FORWARD 5.500,00
473 NP.UW.35.02 Painting and internal surface treatment of both sides of tunnel lining (up to 4 m above 110.000,00
474 NP.UW.35.03 walkways), accordingly to tender deisgn requirements, 220.000,00
9600
Total sqm
Painting and internal surface treatment around SOS niches, accordingly to tender deisgn 9.600,00
requirements, 9.600,00
9
Total no.
Painting and internal surface treatment around escape route tunnels entrance, 9,00
accordingly to tender deisgn requirements,
3
Total no. Total 1985 - Painting and internal surfaces finishing NPR 9,00
CARRY FORWARD Main Tunnel - Completation work
CARRY FORWARD Main Tunnel
CARRY FORWARD Road Alignement TU – Tunnel - CH 3,00
0...
CARRY FORWARD 3,00
- 184 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
2100 - Vie cavi
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
14.850,04
2.393,00
2.393,00
120,00
40,00
600,00
5.546,00
- 185 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
103 - Main Tunnel
130 - Main Tunnel - Completation work
2100 - Vie cavi
N. CODE
N. CODE
- 187 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
150 - By-Pass - section type 0 (only excavation and lining)
810 - Pre-Support
N. CODE
482 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
483 NP.UW.05.01 50 mm thick shotcreting with steel fibers for underground works section type 0 - by-pass 2.652,95
484 NP.UW.06.01 11,5 * 11,69 581,39
Total sqm
50 mm thick shotcreting for underground works section type 0 - by-pass
11,5 * 11,53
134,44
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 0 - by-pass 134,44
11,5 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 0 (only excavatio...
CARRY FORWARD By-Pass #1
CARRY FORWARD Road Alignement TU – Tunnel - CH 132,60
0... 132,60
CARRY FORWARD
133,52
133,52
- 188 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
150 - By-Pass - section type 0 (only excavation and lining)
820 - Rock Reinforcement
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 189 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
150 - By-Pass - section type 0 (only excavation and lining)
845 - Waterproofing system
N. CODE
N. CODE
13,74
13,74 14.258,95
- 191 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
150 - By-Pass - section type 0 (only excavation and lining)
853 - Lining upper side
N. CODE
2,8750 124.626,56
- 192 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
151 - By-Pass - section type 1 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 193 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
151 - By-Pass - section type 1 (only excavation and lining)
810 - Pre-Support
N. CODE
496 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
497 NP.UW.05.02 50 mm thick shotcreting with steel fibers for underground works section type 1 - by-pass 4.452,45
498 NP.UW.06.01 lining 581,39
34 * 11,85 402,
excavation face ((34)/2,50) * 19,22 90
Total sqm 261,
100 mm thick shotcreting for underground works section type 1 - by-pass 39
34 * 11,61
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 1 - by-pass
34 * 11,77 664,29
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 1 (only excavatio...
CARRY FORWARD By-Pass #1
CARRY FORWARD Road Alignement TU – Tunnel - CH
0... 394,74
CARRY FORWARD 394,74
400,18
400,18
- 194 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
151 - By-Pass - section type 1 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
40,63
40,63 14.258,95
- 197 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
151 - By-Pass - section type 1 (only excavation and lining)
853 - Lining upper side
N. CODE
8,5000 124.626,56
- 198 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
152 - By-Pass - section type 2 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 199 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
152 - By-Pass - section type 2 (only excavation and lining)
810 - Pre-Support
N. CODE
510 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
511 NP.UW.04.02 50 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass 5.234,30
512 NP.UW.05.01 lining 2.652,95
513 NP.UW.05.02 45,5 * 12,00 546, 4.452,45
514 NP.UW.06.01 excavation face 00 581,39
(50%) * ((45,5)/1,75) * 19,82 257,
Total sqm 66
100 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass
excavation face
(50%) * 45,5 * 19,82 * (1/1,75)
Total sqm 803,66
50 mm thick shotcreting for underground works section type 2 - by-pass
45,5 * 11,69
Total sqm
100 mm thick shotcreting for underground works section type 2 - by-pass
45,5 * 11,69
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 2 - by-pass 257,02
45,5 * 11,93
257,02
45,5 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 2 (only excavatio...
CARRY FORWARD By-Pass #1
CARRY FORWARD Road Alignement TU – Tunnel - CH 531,90
0... 531,90
CARRY FORWARD
531,90
531,90
542,
82
528,
26
1.071,08
- 200 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
152 - By-Pass - section type 2 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 202 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
152 - By-Pass - section type 2 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
54,37
54,37 14.258,95
- 203 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
152 - By-Pass - section type 2 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
11,3750 124.626,56
- 204 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
153 - By-Pass - section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
556,44
556,44
556,44
556,44
567,
87
552,
64
1.120,51
- 206 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
153 - By-Pass - section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 208 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
153 - By-Pass - section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
56,88
56,88 14.258,95
- 209 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
153 - By-Pass - section type 3 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
11,9000 124.626,56
- 210 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
126,95
135,43
178,68
537,29 5.234,30
548 NP.UW.05.01
94,12
132,47
226,59 2.652,95
549 NP.UW.05.02
- 212 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
810 - Pre-Support
N. CODE
- 213 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
34,64
48,75
83,39 11.800,00
- 214 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
845 - Waterproofing system
N. CODE
- 215 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
14,36
20,22
34,58 14.258,95
- 216 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
104 - By-Pass #1
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
853 - Lining upper side
N. CODE
7,6000
1,3310
14,3310 124.626,56
- 217 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
150 - By-Pass - section type 0 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 218 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
150 - By-Pass - section type 0 (only excavation and lining)
810 - Pre-Support
N. CODE
564 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
565 NP.UW.05.01 50 mm thick shotcreting with steel fibers for underground works section type 0 - by-pass 2.652,95
566 NP.UW.06.01 20,5 * 11,69 581,39
Total sqm
50 mm thick shotcreting for underground works section type 0 - by-pass
20,5 * 11,53
239,65
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 0 - by-pass 239,65
20,5 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 0 (only excavatio...
CARRY FORWARD By-Pass #2
CARRY FORWARD Road Alignement TU – Tunnel - CH 236,37
0... 236,37
CARRY FORWARD
238,01
238,01
- 219 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
150 - By-Pass - section type 0 (only excavation and lining)
820 - Rock Reinforcement
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 220 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
150 - By-Pass - section type 0 (only excavation and lining)
845 - Waterproofing system
N. CODE
N. CODE
24,50
24,50 14.258,95
- 222 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
150 - By-Pass - section type 0 (only excavation and lining)
853 - Lining upper side
N. CODE
5,1250 124.626,56
- 223 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
151 - By-Pass - section type 1 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 224 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
151 - By-Pass - section type 1 (only excavation and lining)
810 - Pre-Support
N. CODE
578 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
579 NP.UW.05.02 50 mm thick shotcreting with steel fibers for underground works section type 1 - by-pass 4.452,45
580 NP.UW.06.01 lining 581,39
51,5 * 11,85 610,
excavation face ((51,5)/2,50) * 19,22 28
Total sqm 395,
100 mm thick shotcreting for underground works section type 1 - by-pass 93
51,5 * 11,61
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 1 - by-pass
51,5 * 11,77 1.006,21
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 1 (only excavatio...
CARRY FORWARD By-Pass #2
CARRY FORWARD Road Alignement TU – Tunnel - CH
0... 597,92
CARRY FORWARD 597,92
606,16
606,16
- 225 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
151 - By-Pass - section type 1 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
61,54
61,54 14.258,95
- 228 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
151 - By-Pass - section type 1 (only excavation and lining)
853 - Lining upper side
N. CODE
12,8750 124.626,56
- 229 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
152 - By-Pass - section type 2 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 230 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
152 - By-Pass - section type 2 (only excavation and lining)
810 - Pre-Support
N. CODE
592 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
593 NP.UW.04.02 50 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass 5.234,30
594 NP.UW.05.01 lining 2.652,95
595 NP.UW.05.02 20,5 * 12,00 246, 4.452,45
596 NP.UW.06.01 excavation face 00 581,39
(50%) * ((20,5)/1,75) * 19,82 116,
Total sqm 05
100 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass
excavation face
(50%) * 20,5 * 19,82 * (1/1,75)
Total sqm 362,05
50 mm thick shotcreting for underground works section type 2 - by-pass
20,5 * 11,69
Total sqm
100 mm thick shotcreting for underground works section type 2 - by-pass
20,5 * 11,69
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 2 - by-pass 115,80
20,5 * 11,93
115,80
20,5 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 2 (only excavatio...
CARRY FORWARD By-Pass #2
CARRY FORWARD Road Alignement TU – Tunnel - CH 239,65
0... 239,65
CARRY FORWARD
239,65
239,65
244,
57
238,
01
482,58
- 231 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
152 - By-Pass - section type 2 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 233 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
152 - By-Pass - section type 2 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
24,50
24,50 14.258,95
- 234 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
152 - By-Pass - section type 2 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
5,1250 124.626,56
- 235 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
153 - By-Pass - section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
479,29
479,29
479,29
479,29
489,
13
476,
01
965,14
- 237 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
153 - By-Pass - section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 239 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
153 - By-Pass - section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
49,00
49,00 14.258,95
- 240 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
153 - By-Pass - section type 3 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
10,2500 124.626,56
- 241 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
126,95
135,43
178,68
537,29 5.234,30
630 NP.UW.05.01
94,12
132,47
226,59 2.652,95
631 NP.UW.05.02
- 243 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
810 - Pre-Support
N. CODE
- 244 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
34,64
48,75
83,39 11.800,00
- 245 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
845 - Waterproofing system
N. CODE
- 246 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
14,36
20,22
34,58 14.258,95
- 247 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
105 - By-Pass #2
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
853 - Lining upper side
N. CODE
7,6000
1,3310
14,3310 124.626,56
- 248 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
150 - By-Pass - section type 0 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 249 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
150 - By-Pass - section type 0 (only excavation and lining)
810 - Pre-Support
N. CODE
646 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
647 NP.UW.05.01 50 mm thick shotcreting with steel fibers for underground works section type 0 - by-pass 2.652,95
648 NP.UW.06.01 9 * 11,69 581,39
Total sqm
50 mm thick shotcreting for underground works section type 0 - by-pass
9 * 11,53
105,21
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 0 - by-pass 105,21
9 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 0 (only excavatio...
CARRY FORWARD By-Pass #3
CARRY FORWARD Road Alignement TU – Tunnel - CH 103,77
0... 103,77
CARRY FORWARD
104,49
104,49
- 250 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
150 - By-Pass - section type 0 (only excavation and lining)
820 - Rock Reinforcement
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 251 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
150 - By-Pass - section type 0 (only excavation and lining)
845 - Waterproofing system
N. CODE
N. CODE
10,76
10,76 14.258,95
- 253 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
150 - By-Pass - section type 0 (only excavation and lining)
853 - Lining upper side
N. CODE
2,2500 124.626,56
- 254 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
151 - By-Pass - section type 1 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 255 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
151 - By-Pass - section type 1 (only excavation and lining)
810 - Pre-Support
N. CODE
660 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
661 NP.UW.05.02 50 mm thick shotcreting with steel fibers for underground works section type 1 - by-pass 4.452,45
662 NP.UW.06.01 lining 581,39
26,5 * 11,85 314,
excavation face ((26,5)/2,50) * 19,22 03
Total sqm 203,
100 mm thick shotcreting for underground works section type 1 - by-pass 73
26,5 * 11,61
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 1 - by-pass
26,5 * 11,77 517,76
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 1 (only excavatio...
CARRY FORWARD By-Pass #3
CARRY FORWARD Road Alignement TU – Tunnel - CH
0... 307,67
CARRY FORWARD 307,67
311,91
311,91
- 256 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
151 - By-Pass - section type 1 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
N. CODE
31,67
31,67 14.258,95
- 259 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
151 - By-Pass - section type 1 (only excavation and lining)
853 - Lining upper side
N. CODE
6,6250 124.626,56
- 260 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
152 - By-Pass - section type 2 (only excavation and lining)
800 - Tunnel excavation
N. CODE
- 261 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
152 - By-Pass - section type 2 (only excavation and lining)
810 - Pre-Support
N. CODE
674 NP.UW.04.01 AMOUNT CARRIED FORWARD 3.043,88
675 NP.UW.04.02 50 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass 5.234,30
676 NP.UW.05.01 lining 2.652,95
677 NP.UW.05.02 35,5 * 12,00 426, 4.452,45
678 NP.UW.06.01 excavation face 00 581,39
(50%) * ((35,5)/1,75) * 19,82 201,
Total sqm 07
100 mm thick shotcreting with steel fibers for underground works section type 2 - by-pass
excavation face
(50%) * 35,5 * 19,82 * (1/1,75)
Total sqm 627,07
50 mm thick shotcreting for underground works section type 2 - by-pass
35,5 * 11,69
Total sqm
100 mm thick shotcreting for underground works section type 2 - by-pass
35,5 * 11,69
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works section type 2 - by-pass 200,53
35,5 * 11,93
200,53
35,5 * 11,61
Total sqm Total 810 - Pre-Support NPR
CARRY FORWARD By-Pass - section type 2 (only excavatio...
CARRY FORWARD By-Pass #3
CARRY FORWARD Road Alignement TU – Tunnel - CH 415,00
0... 415,00
CARRY FORWARD
415,00
415,00
423,
52
412,
16
835,68
- 262 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
152 - By-Pass - section type 2 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 264 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
152 - By-Pass - section type 2 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
42,42
42,42 14.258,95
- 265 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
152 - By-Pass - section type 2 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
8,8750 124.626,56
- 266 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
153 - By-Pass - section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
565,21
565,21
565,21
565,21
576,
82
561,
34
1.138,16
- 268 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
153 - By-Pass - section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
N. CODE
- 270 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
153 - By-Pass - section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
57,78
57,78 14.258,95
- 271 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
153 - By-Pass - section type 3 (only excavation and lining)
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
12,0875 124.626,56
- 272 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
800 - Tunnel excavation
N. CODE
N. CODE
126,95
135,43
178,68
537,29 5.234,30
712 NP.UW.05.01
94,12
132,47
226,59 2.652,95
713 NP.UW.05.02
- 274 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
810 - Pre-Support
N. CODE
- 275 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
820 - Rock Reinforcement
N. CODE
34,64
48,75
83,39 11.800,00
- 276 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
845 - Waterproofing system
N. CODE
- 277 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
850 - Lining bottom side / Inver
N. CODE
14,36
20,22
34,58 14.258,95
- 278 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
106 - By-Pass #3
154 - By-Pass - Air-Lock section type 3 (only excavation and lining)
853 - Lining upper side
N. CODE
7,6000
1,3310
14,3310 124.626,56
- 279 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
131 - Flushing niches
800 - Tunnel excavation
N. CODE
- 280 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
131 - Flushing niches
810 - Pre-Support
N. CODE
728 NP.UW.03.02 AMOUNT CARRIED FORWARD 108.379,99
729 NP.UW.04.01 Lattice Girders for underground works lattice girders - weigth 17.40 kg/m 3.043,88
730 NP.UW.05.01 32 * 3 * (1,42*17,40/1000) 2.652,95
731 NP.UW.05.02 Total tonne 4.452,45
732 NP.UW.06.01 50 mm thick shotcreting with steel fibers for underground works 32 * (1,56+1,56) * 4,69 581,39
32 * (2,14+(1,10/2)+(1,10/2)) * 1,46
2,3712
Total sqm
50 mm thick shotcreting for underground works 32 * (1,56+1,56) * 4,69 2,3712
32 * (2,14+(1,10/2)+(1,10/2)) * 1,46
468,
Total sqm
25
100 mm thick shotcreting for underground works 32 * (1,56+1,56) * 4,69
151,
32 * (2,14+(1,10/2)+(1,10/2)) * 1,46
37
Total sqm
Wire mesh ∅5mm/100x100 for Shotcrete - underground works 32 * 2 * (1,56+1,56) * 4,69 619,62
32 * 2 * (2,14+(1,10/2)+(1,10/2)) * 1,46
Total sqm Total 810 - Pre-Support NPR 468,
25
CARRY FORWARD Flushing niches
151,
CARRY FORWARD SOS niches
37
CARRY FORWARD Road Alignement TU – Tunnel - CH
619,62
0...
CARRY FORWARD 468,
25
151,
37
619,62
936,
50
302,
75
1.239,25
- 281 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
131 - Flushing niches
845 - Waterproofing system
N. CODE
N. CODE
- 283 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
131 - Flushing niches
853 - Lining upper side
N. CODE
735 NP.UW.17.01 AMOUNT CARRIED FORWARD 2.550,00
736 NP.UW.23.01 Form work for vault (Class F1 Finish) - Using steel 32 * (1,56+1,56) * 4,25 424, 19.445,72
737 NP.UW.24.01 32 * (2,14+(1,10/2)+(1,10/2)) * 1,36 32 124.626,56
Total sqm 141,
Reinforced/ Pre-stressed cement concrete in super-structure. RCC Grade M 40 - for 00
underground works (item 20.08.00.D.1q + NP.UW.01.00)
32 * (1,56+1,56) * 1,74 565,32
32 * (2,14+(1,10/2)+(1,10/2)) * 0,56
Total cum 173,
Providing and laying , fitting and placing HYSD bar reinforcement in super- structure - 72
for underground works (item 20.09.00.0 + NP.UW.01.00) 58,0
Steel ratio 94.60 kg/mc 32 * 7,24 * (94,60/1000) 6
Total tonne
Total 853 - Lining upper side NPR 231,78
Total 131 - Flushing niches NPR
CARRY FORWARD SOS niches
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
21,9169
21,9169
- 284 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
132 - Hydrant niches
800 - Tunnel excavation
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 285 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
132 - Hydrant niches
810 - Pre-Support
N. CODE
41,39
67,1
3
15,6
5
82,78
- 286 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
132 - Hydrant niches
845 - Waterproofing system
N. CODE
- 287 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
132 - Hydrant niches
850 - Lining bottom side / Inver
N. CODE
745 NP.UW.20.01 AMOUNT CARRIED FORWARD 10.981
Providing and laying of Plain Cement Concrete M 10 - for underground works (item ,24
20.01.00.0 + NP.UW.01.00)
6 * (1,82+(0,25/2)+(0,25/2)) * 0,84 * 0,10
Total cum Total 850 - Lining bottom side / Inver NPR
CARRY FORWARD Hydrant niches 1,04
CARRY FORWARD SOS niches 1,04
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 288 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
132 - Hydrant niches
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 289 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
133 - SOS / Hydrant niches
800 - Tunnel excavation
N. CODE
N. CODE
405,
11
411,
12
816,23
- 291 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
133 - SOS / Hydrant niches
845 - Waterproofing system
N. CODE
- 292 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
133 - SOS / Hydrant niches
850 - Lining bottom side / Inver
N. CODE
756 NP.UW.20.01 AMOUNT CARRIED FORWARD 10.981
Providing and laying of Plain Cement Concrete M 10 - for underground works (item ,24
20.01.00.0 + NP.UW.01.00)
9 * 2,60 * 2,95 * 0,10
Total cum Total 850 - Lining bottom side / Inver NPR
CARRY FORWARD SOS / Hydrant niches 6,90
CARRY FORWARD SOS niches 6,90
CARRY FORWARD Road Alignement TU – Tunnel - CH
0...
CARRY FORWARD
- 293 -
Priced Bill of Quantities
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034
115 - SOS niches
133 - SOS / Hydrant niches
853 - Lining upper side
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 294 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
026 - Culvert A3
1005 - culverts
N. CODE
N. CODE
- 296 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
028 - Culvert 7
1005 - culverts
N. CODE
- 297 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
029 - Culvert 8
1005 - culverts
N. CODE
- 298 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
030 - Culvert 9
1005 - culverts
N. CODE
N. CODE
- 300 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
032 - Culvert A4
1005 - culverts
N. CODE
- 301 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
033 - Culvert 11
1005 - culverts
N. CODE
- 302 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
006 - Hydraulic Works
034 - Culvert A5
1005 - culverts
N. CODE
20,27 16.220,39
- 303 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
067 - Wall CH 0+080 / CH 0+095
90 - Excavation
N. CODE
- 304 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
067 - Wall CH 0+080 / CH 0+095
560 - Structures
N. CODE
779 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
780 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
781 20.05.00.0 13,00 * 0,70 * 0,10 110.464,93
782 NP.CW.04.01 Total cum 7.780,00
783 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
784 NP.CW.16.01 reinforcement complete in foundation 0,91 16.220,39
785 NP.CW.18.01 steel rate 1,95 * 0,080 0,91 15.188,18
786 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
4,25 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 6 * 8,00 0,1560
Total m 0,1560
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 5 * 7,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
0,3400
20.04.00.H.0p + 7%)
wall 0,3400
13,00 * 1,00 * 0,30
protection cap
6 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 13,00 * 0,50 * 0,30
48,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 48,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
4 * 5,00
Total m
Total 560 - Structures NPR
Total 067 - Wall CH 0+080 / CH 0+095 NPR 37,50
CARRY FORWARD Civil Works
37,50
CARRY FORWARD Pedestrian Road Alignement PE
CARRY FORWARD
3,90
0,35
4,25
1,95
1,95
20,00
20,00
- 305 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
068 - Wall CH 0+900 / CH 0+920
90 - Excavation
N. CODE
N. CODE
3,11
40,00
40,00
- 307 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
069 - Wall CH 0+920 / CH 0+950
90 - Excavation
N. CODE
- 308 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
069 - Wall CH 0+920 / CH 0+950
560 - Structures
N. CODE
797 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
798 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
799 20.05.00.0 41,20 * 2,40 * 0,10 110.464,93
800 NP.CW.04.01 Total cum 7.780,00
801 NP.CW.04.05 Providing and laying , fitting and placing un-coated Mild steel / HYSD 20.140,00
802 NP.CW.16.01 reinforcement complete in foundation 9,89 16.220,39
803 NP.CW.18.01 steel rate 54,38 * 0,080 9,89 15.188,18
804 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
234,32 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 20 * 10,00 4,3504
16 * 10,00 4,3504
2 * 13 * 10,00
Total m
Providing and driving of 43 mm dia rock bolt steel nails by drilling holes of 120 mm dia using
cement grouting for fixing
vertical bolts 41 * 2 * 4,00
18,7456
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item 18,7456
20.04.00.H.0p + 7%)
wall 200,
41,20 * 8,00 * ((0,30+1,10)/2)
00
protection cap 160,
62 * ((0,70*0,70+0,30*0,30)/2) * 0,20
00
Total cum
260,
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
00
20.02.00.h + 7%) 41,20 * 2,20 * 0,60
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 620,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
36,00 * 5,00
Total m Total 560 - Structures NPR
CARRY FORWARD Civil Works
CARRY FORWARD Pedestrian Road Alignement PE 328,00
CARRY FORWARD
328,00
230,72
3,60
234,32
54,38
54,38
180,00
180,00
- 309 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
069 - Wall CH 0+920 / CH 0+950
560 - Structures
N. CODE
N. CODE
- 311 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
070 - Walls CH 0+110 / CH 0+890
560 - Structures
N. CODE
806 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
807 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
808 20.05.00.0 (35,00+80,00+5,00+20,00+15,00+25,00+30,00+5,00+20,00) * 0,70 * 0,10 110.464,93
809 NP.CW.04.01 20,00 * 2,20 * 0,10 7.780,00
810 NP.CW.04.03 Total cum 11.720,00
811 NP.CW.16.01 Providing and laying , fitting and placing un-coated Mild steel / HYSD 16,45 16.220,39
812 NP.CW.18.01 reinforcement complete in foundation 4,40 15.188,18
813 NP.CW.19.01 steel rate 59,25 * 0,080 20,85
Total tonne
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
310,62 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts (17+40+2+10+7+12+15+2+10) * 8,00 4,7400
10 * 10,00 4,7400
8 * 10,00
7 * 10,00
Total m
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts (23+53+3+13+10+16+20+3+13) * 7,50 24,8496
2 * 20 * 8,00 24,8496
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item 920,
20.04.00.H.0p + 7%) 00
wall 100,
(35,00+80,00+5,00+20,00+15,00+25,00+30,00+5,00+20,00) * 3,00 * 0,30 00
20,00 * 7,00 * ((0,30+1,00)/2) 80,0
protection cap 0
140 * ((0,70*0,70+0,30*0,30)/2) * 0,20 70,0
Total cum 0
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) (35,00+80,00+5,00+20,00+15,00+25,00+30,00+5,00+20,00) * 0,50 * 0,30 1.170,00
20,00 * 2,00 * 0,60
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped
CARRY FORWARD Structures
CARRY FORWARD Walls CH 0+110 / CH 0+890 1.155,00
CARRY FORWARD Civil Works 320,00
CARRY FORWARD Pedestrian Road Alignement PE 1.475,00
CARRY FORWARD
211,50
91,00
8,12
310,62
35,2
5
24,0
0
59,25
- 312 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
007 - Civil Works
070 - Walls CH 0+110 / CH 0+890
560 - Structures
N. CODE
N. CODE
10.693,20
10.693,20
- 314 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
201 - Exavation and Filling
90 - Excavation
N. CODE
- 315 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
201 - Exavation and Filling
175 - Embankment/Filling
N. CODE
AMOUNT CARRIED FORWARD
Construction of Embankment with Material Deposited from Roadway Cutting -
819 09.09.00.b
With machine pedestrian rockshed 761,05
square
842,90
Total cum
761,05
Providing suitable material and Back filling behind abutment, wing wall and return wall -
Granular Material
backfilling pedestrian rockshed 11290,70 842,90
Total cum
Total 175 - Embankment/Filling NPR 1.603,95 364,83
820 09.11.00.A Total 201 - Exavation and Filling NPR
CARRY FORWARD Pedestrain rockshed
CARRY FORWARD Pedestrian Road Alignement PE
CARRY FORWARD
11.290,70
11.290,70 1.500,45
- 316 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
204 - Consolidamento parete lungo il manufatto
160 - Protezione scavi
N. CODE
144,00
144,00
144,00
432,00 7.780,00
- 317 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
205 - Rockshed Section
280 - Foundation Slabs
N. CODE
2,25
3.058,22 13.966,07
826 20.03.00.0
501,8987
2,7077
504,6064 110.464,93
- 318 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
205 - Rockshed Section
300 - Vertical Elements
N. CODE
0,85
CARRY FORWARD Pedestrian Road Alignement PE
CARRY FORWARD
9,55
0,85
5,15
0,85
3.746,63 16.220,39
- 319 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
205 - Rockshed Section
574 - Impermeabilizzazioni
N. CODE
49,13
39,02
25,29
8.526,57 2.800,00
833 NP.CW.10.01
673,05
4,91
3,90
2,53
684,39 2.800,00
- 320 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
205 - Rockshed Section
680 - Slabs
N. CODE
7,48
4,03
2.587,60 17.501,69
- 321 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
206 - Road works and secondary civil works
1420 - Paving
N. CODE
780,00
780,00 33.500,00
- 322 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
202 - Pedestrain rockshed
207 - Cushion layer (Leca)
175 - Embankment/Filling
N. CODE
13.920,20 16.000,00
- 323 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
203 - ROADSIDE ROCK STABILIZATION
208 - Shotcrete + bolts
160 - Protezione scavi
N. CODE
1.290,00
1.290,00 3.000,00
- 324 -
Priced Bill of Quantities
03 - Pedestrian Road Alignement PE
204 - ROADSIDE ROCK EXCAVATION
208 - Shotcrete + bolts
160 - Protezione scavi
N. CODE
CH 0+040 - CH 0+070
30,00 * ((3,90+3,40)/2) 109,50
CH 0+110 - CH 0+140
30,00 * ((6,00+4,80)/2) 162,00
CH 0+170 - CH 0+200
30,00 * 9,00 270,00
CH 0+220 - CH 0+230
10,00 * 9,00 90,00
CH 0+260 - CH 0+280
20,00 * 4,50 90,00
CH 0+310 - CH 0+340
30,00 * ((5,50+4,20)/2) 145,50
CH 0+310 - CH 0+340
15,00 * 7,40 111,00
CH 0+540 - CH 0+560
40,00 * ((5,80+7,70)/2) 270,00
CH 0+580
7,00 * 6,60 46,20
CH 0+640 - CH 0+660
35,00 * 4,20 147,00
CH 0+720
5,00 * 5,40 27,00
CH 0+740
15,00 * 5,40 81,00
CH 0+780 - CH 0+830
50,00 * 4,00 200,00
CH 0+880
5,00 * 4,00 20,00
Total sqm 1.769,20 8.500,
00
848 NP.CW.02.02 Wire mesh D. 6/100/100 for Shotcrete - external areas
CH 0+040 - CH 0+070
30,00 * ((3,90+3,40)/2) 109,50
CH 0+110 - CH 0+140
30,00 * ((6,00+4,80)/2) 162,00
CH 0+170 - CH 0+200
30,00 * 9,00 270,00
CH 0+220 - CH 0+230
10,00 * 9,00 90,00
CH 0+260 - CH 0+280
20,00 * 4,50 90,00
CH 0+310 - CH 0+340
30,00 * ((5,50+4,20)/2) 145,50
CH 0+310 - CH 0+340
N. CODE
N. CODE
1.176,00
1.176,00 3.000,00
- 327 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
001 - Road Works
001 - Exavation, Filling and Paving
90 - Excavation
N. CODE
- 328 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
001 - Road Works
001 - Exavation, Filling and Paving
175 - Embankment/Filling
N. CODE
852 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
800,76
Total cum Total 175 - Embankment/Filling NPR
CARRY FORWARD Exavation, Filling and Paving 800,76
CARRY FORWARD Road Works 800,76
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 329 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
001 - Road Works
001 - Exavation, Filling and Paving
980 - Precast rectangular channeling
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 330 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
001 - Road Works
001 - Exavation, Filling and Paving
1420 - Paving
N. CODE
12.147,50
12.147,50
- 331 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
001 - Road Works
004 - Signaling
1610 - Signaling
N. CODE
- 332 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
002 - Rockside rock excavation
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
160 - Protezione scavi
N. CODE
CH 2+130 / CH 2+310
20,00 * 1,00 20,00
20,00 * 6,00 120,00
20,00 * 4,00 80,00
20,00 * 6,50 130,00
20,00 * 5,00 100,00
20,00 * 2,00 40,00
20,00 * 7,50 150,00
20,00 * 3,50 70,00
20,00 * 3,00 60,00
20,00 * 2,00 40,00
CH 2+350 / CH 2+590
20,00 * 1,00 20,00
20,00 * 4,00 80,00
20,00 * 2,50 50,00
20,00 * 1,00 20,00
20,00 * 5,00 100,00
20,00 * 1,00 20,00
20,00 * 5,50 110,00
20,00 * 3,50 70,00
20,00 * 2,00 40,00
20,00 * 2,00 40,00
20,00 * 1,00 20,00
20,00 * 1,50 30,00
20,00 * 1,00 20,00
Total sqm 1.430,00 8.500,
00
860 NP.CW.02.02 Wire mesh D. 6/100/100 for Shotcrete - external areas
CH 2+130 / CH 2+310
20,00 * 1,00 20,00
20,00 * 6,00 120,00
20,00 * 4,00 80,00
20,00 * 6,50 130,00
20,00 * 5,00 100,00
20,00 * 2,00 40,00
20,00 * 7,50 150,00
20,00 * 3,50 70,00
20,00 * 3,00 60,00
20,00 * 2,00 40,00
CH 2+350 / CH 2+590
20,00 * 1,00 20,00
20,00 * 4,00 80,00
20,00 * 2,50 50,00
20,00 * 1,00 20,00
N. CODE
AMOUNT CARRIED FORWARD
20,00 * 5,00 100,00
20,00 * 1,00 20,00
20,00 * 5,50 110,00
20,00 * 3,50 70,00
20,00 * 2,00 40,00
20,00 * 2,00 40,00
20,00 * 1,00 20,00
20,00 * 1,50 30,00
20,00 * 1,00 20,00
Total sqm 1.430,00 66
6,
861 NP.CW.04.01 Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110
05
mm dia using cement grouting for fixing
CH 2+130 / CH 2+310
10 * 5,00 50,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 8,00 80,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 8,00 80,00
(10*2) * 10,00 200,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 5,00 50,00
CH 2+350 / CH 2+590
10 * 5,00 50,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 5,00 50,00
10 * 6,00 60,00
10 * 5,00 50,00
10 * 5,00 50,00
N. CODE
948,00 3.000,00
- 335 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
003 - Rockfall Protection Measures
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
160 - Protezione scavi
N. CODE
2.654,40
4.795,20
3.777,60
11.227,20 11.720,00
867 NP.CW.06.01
2.765,00
4.995,00
3.935,00
11.695,00 6.000,00
- 336 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
003 - Rockfall Protection Measures
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450
160 - Protezione scavi
N. CODE
N. CODE
N. CODE
- 339 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
035 - Culvert 12
180 - Filling
N. CODE
872 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
13,79
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert 12 13,79
CARRY FORWARD Hydraulic Works 13,79
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 340 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
035 - Culvert 12
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
40,11
4,0110
4,0110
0,2500
0,2500
- 341 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
036 - Culvert A6
90 - Excavation
N. CODE
- 342 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
036 - Culvert A6
180 - Filling
N. CODE
880 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
32,06
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert A6 32,06
CARRY FORWARD Hydraulic Works 32,06
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 343 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
036 - Culvert A6
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
6,35
0,6350
0,6350
0,1500
0,1500
- 344 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
037 - Culvert 13
90 - Excavation
N. CODE
- 345 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
037 - Culvert 13
180 - Filling
N. CODE
889 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
32,32
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert 13 32,32
CARRY FORWARD Hydraulic Works 32,32
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 346 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
037 - Culvert 13
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
67,58
6,7580
6,7580
0,2500
0,2500
- 347 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
038 - Culvert A7
90 - Excavation
N. CODE
- 348 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
038 - Culvert A7
180 - Filling
N. CODE
897 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
34,56
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert A7 34,56
CARRY FORWARD Hydraulic Works 34,56
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 349 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
038 - Culvert A7
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
6,35
0,6350
0,6350
0,1500
0,1500
- 350 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
039 - Culvert 14
90 - Excavation
N. CODE
- 351 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
039 - Culvert 14
180 - Filling
N. CODE
906 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
35,55
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert 14 35,55
CARRY FORWARD Hydraulic Works 35,55
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 352 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
039 - Culvert 14
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
6,35
0,6350
0,6350
0,1500
0,1500
- 353 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
040 - Culvert 15
90 - Excavation
N. CODE
- 354 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
040 - Culvert 15
180 - Filling
N. CODE
915 09.09.00.b AMOUNT CARRIED FORWARD 36
Construction of Embankment with Material Deposited from Roadway Cutting - With 4,
machine 83
59,94
Total cum Total 180 - Filling NPR
CARRY FORWARD Culvert 15 59,94
CARRY FORWARD Hydraulic Works 59,94
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 355 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
006 - Hydraulic Works
040 - Culvert 15
1005 - culverts
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
45,68
4,5680
4,5680
0,2500
0,2500
- 356 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
059 - Wall CH 2+070 / CH 2+090
90 - Excavation
N. CODE
N. CODE
127,60
3,13
130,73
49,20
49,20
125,00
125,00
- 358 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
059 - Wall CH 2+070 / CH 2+090
560 - Structures
N. CODE
AMOUNT CARRIED FORWARD
Total 059 - Wall CH 2+070 / CH 2+090 NPR
CARRY FORWARD Civil Works
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
- 359 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
060 - Wall CH 2+110 / CH 2+130
90 - Excavation
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
- 360 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
060 - Wall CH 2+110 / CH 2+130
560 - Structures
N. CODE
18,81
6,00
6,00
65,00
65,00
- 361 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
061 - Wall CH 2+210
90 - Excavation
N. CODE
- 362 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
061 - Wall CH 2+210
560 - Structures
N. CODE
941 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
942 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
943 20.05.00.0 20,00 * 0,70 * 0,10 110.464,93
944 NP.CW.04.01 Total cum 7.780,00
945 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
946 NP.CW.16.01 reinforcement complete in foundation 1,40 16.220,39
947 NP.CW.18.01 steel rate 3,00 * 0,080 1,40 15.188,18
948 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
6,41 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 7 * 8,00 0,2400
Total m 0,2400
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 13 * 7,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
0,5128
20.04.00.H.0p + 7%)
wall 0,5128
20,00 * 1,00 * 0,30
protection cap
7 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 20,00 * 0,50 * 0,30
56,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 56,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
6 * 5,00
Total m
Total 560 - Structures NPR
Total 061 - Wall CH 2+210 NPR 97,50
CARRY FORWARD Civil Works
97,50
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
6,00
0,41
6,41
3,00
3,00
30,00
30,00
- 363 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
062 - Wall CH 2+270
90 - Excavation
N. CODE
N. CODE
6,00
0,41
6,41
3,00
3,00
30,00
30,00
- 365 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
063 - Wall CH 2+310
90 - Excavation
N. CODE
- 366 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
063 - Wall CH 2+310
560 - Structures
N. CODE
959 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
960 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
961 20.05.00.0 20,00 * 0,70 * 0,10 110.464,93
962 NP.CW.04.01 Total cum 7.780,00
963 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
964 NP.CW.16.01 reinforcement complete in foundation 1,40 16.220,39
965 NP.CW.18.01 steel rate 3,00 * 0,080 1,40 15.188,18
966 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
6,58 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 10 * 3,50 0,2400
Total m 0,2400
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 8 * 4,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
0,5264
20.04.00.H.0p + 7%)
wall 0,5264
20,00 * 1,00 * 0,30
protection cap
10 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 20,00 * 0,50 * 0,30
35,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 35,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
6 * 5,00
Total m
Total 560 - Structures NPR
Total 063 - Wall CH 2+310 NPR 36,00
CARRY FORWARD Civil Works
36,00
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
6,00
0,58
6,58
3,00
3,00
30,00
30,00
- 367 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
064 - Wall CH 2+410 / CH 2+430
90 - Excavation
N. CODE
N. CODE
12,00
1,16
13,16
6,00
6,00
65,00
65,00
- 369 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
065 - Wall CH 2+510 / CH 2+530
90 - Excavation
N. CODE
- 370 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
065 - Wall CH 2+510 / CH 2+530
560 - Structures
N. CODE
977 20.01.00.0 AMOUNT CARRIED FORWARD 9.893,01
978 20.03.00.0 Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation 110.464,93
979 20.05.00.0 40,00 * 0,70 * 0,10 110.464,93
980 NP.CW.04.01 Total cum 7.780,00
981 NP.CW.04.03 Providing and laying , fitting and placing un-coated Mild steel / HYSD 11.720,00
982 NP.CW.16.01 reinforcement complete in foundation 2,80 16.220,39
983 NP.CW.18.01 steel rate 6,00 * 0,080 2,80 15.188,18
984 NP.CW.19.01 Total tonne 2.900,00
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure steel ratio
13,16 * 0,080
Total tonne
Providing and driving of 25 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
sub-horizontal bolts 20 * 3,50 0,4800
Total m 0,4800
Providing and driving of 32 mm dia rock bolt steel nails by drilling holes of 110 mm dia using
cement grouting for fixing
vertical bolts 16 * 4,50
Total m
Plain/Reinforced cement concrete in sub-structure - RCC Grade M 40 (item
1,0528
20.04.00.H.0p + 7%)
wall 1,0528
40,00 * 1,00 * 0,30
protection cap
20 * ((0,70*0,70+0,30*0,30)/2) * 0,20
Total cum
Plain/Reinforced Cement Concrete in Foundation - RCC Grade M 40 (item
20.02.00.h + 7%) 40,00 * 0,50 * 0,30
70,00
Total cum
Drainage holes (weep holes f 100 mm) shall be provided in the walls every 3 m (longitudinal 70,00
step) and in multiple rows as indicated below, as well as a longitudinal drainage pipe f
100 mm shall be installed at the wall foot, wrapped into a geotextile
13 * 5,00
Total m
Total 560 - Structures NPR
Total 065 - Wall CH 2+510 / CH 2+530 NPR 72,00
CARRY FORWARD Civil Works
72,00
CARRY FORWARD Road Alignement MR2 - Mai...
CARRY FORWARD
12,00
1,16
13,16
6,00
6,00
65,00
65,00
- 371 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
066 - Wall CH 2+570 / CH 2+590
90 - Excavation
N. CODE
N. CODE
12,00
0,75
12,75
6,00
6,00
65,00
65,00
- 373 -
Priced Bill of Quantities
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587
007 - Civil Works
066 - Wall CH 2+570 / CH 2+590
560 - Structures
N. CODE
AMOUNT CARRIED FORWARD
Total 04 - Road Alignement MR2 - Main Road - North
Stretch - CH 2+034 to 2+587 NPR
CARRY FORWARD
- 374 -
Priced Bill of Quantities
05 - waste disposal
N. CODE
- 375 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
301 - Electrical Systems
301 - Energy supply
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 376 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
301 - Electrical Systems
302 - Lighting
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 377 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
301 - Electrical Systems
302 - Lighting
N. CODE
- 378 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
302 - Mechanical Systems
303 - Ventilation
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 379 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
302 - Mechanical Systems
313 - Engress tunnel ventilation
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 380 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
304 - Signage
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 381 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
304 - Signage
N. CODE
- 382 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
305 - Tunnel fire detection system
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 383 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
305 - Tunnel fire detection system
N. CODE
AMOUNT CARRIED FORWARD 396.000,00
Specifications. 1,00
1
Total amount
Total 305 - Tunnel fire detection system NPR 1,00
CARRY FORWARD Signage, Detection, Communication and Co...
CARRY FORWARD Main Tunnel - Electromechani...
CARRY FORWARD
- 384 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
306 - Videosurveillance system
ITEM DESCRIPTION OF WORKS AND SUPPLIES QUANTITY PRICE
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 385 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
306 - Videosurveillance system
N. CODE
1,00
- 386 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
307 - Communication network
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 387 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
308 - Tunnel control system
N. CODE
6,00
1,00
1,00
1,00
1,00
1,00
1,00
10,00
10,00
10,00
10,00
1,00
1,00
- 388 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
308 - Tunnel control system
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
- 389 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
309 - Radio diffusion in tunnel
N. CODE
300,00
300,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 390 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
309 - Radio diffusion in tunnel
N. CODE
1,00
CARRY FORWARD Main Tunnel - Electromechani...
CARRY FORWARD
- 391 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
310 - Emergency telephone system
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 392 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
310 - Emergency telephone system
N. CODE
- 393 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
311 - Cabling system
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 394 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
304 - Signage, Detection, Communication and Control Systems
311 - Cabling system
N. CODE
N. CODE
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
1,00
- 396 -
Priced Bill of Quantities
07 - Main Tunnel - Electromechanical Equipment
305 - Secondary systems
312 - Secondary installations
N. CODE
AMOUNT CARRIED FORWARD
Total 07 - Main Tunnel - Electromechanical Equipment
NPR
Jobs amount NPR
- 397 -
TOTAL AMOUNT OF WORK
A) WORKS
01 - Road Alignement MR1 - Main Road - South Stretch - CH 0+000 to 0+904 462.984.316,2
1
001 - Road Works 36.116.491,12
001 - Exavation, Filling and Paving 34.617.691,79
90 - Excavation 2.703.232,51
175 - Embankment/Filling 228.503,97
980 - Precast rectangular channeling 4.410.000,00
1420 - Paving 27.275.955,31
004 - Signaling 1.498.799,33
1610 - Signaling 1.498.799,33
002 - Rockside rock excavation 69.747.367,00
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350 69.747.367,00
160 - Protezione scavi 69.747.367,00
003 - Rockfall Protection Measures 304.477.591,60
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450 191.114.391,60
160 - Protezione scavi 191.114.391,60
009 - ROCKFALL BARRIER 84.819.500,00
160 - Protezione scavi 84.819.500,00
010 - Scaling of unstable blocks 28.543.700,00
160 - Protezione scavi 28.543.700,00
006 - Hydraulic Works 8.171.761,30
019 - Culvert 1 525.546,12
90 - Excavation 7.393,68
180 - Filling 10.528,99
1005 - culverts 507.623,45
020 - Culvert 2 1.393.006,17
90 - Excavation 20.901,40
180 - Filling 18.620,92
1005 - culverts 1.353.483,85
021 - Culvert A1 673.324,07
90 - Excavation 10.934,02
180 - Filling 13.049,97
1005 - culverts 649.340,08
022 - Culvert 3 739.628,57
90 - Excavation 12.340,80
180 - Filling 18.788,75
1005 - culverts 708.499,02
023 - Culvert A2 1.374.898,66
90 - Excavation 22.781,90
180 - Filling 11.944,53
1005 - culverts 1.340.172,23
024 - Culvert 4 2.382.544,31
90 - Excavation 15.121,97
180 - Filling 21.371,74
1005 - culverts 2.346.050,60
025 - Culvert 5 1.082.813,40
90 - Excavation 9.249,00
1005 - culverts 1.073.564,40
007 - Civil Works 44.471.105,19
050 - Wall CH 0+050 / CH 0+110 3.932.383,57
90 - Excavation 46.565,79
560 - Structures 3.885.817,78
051 - Wall CH 0+150 / CH 0+250 8.588.437,99
90 - Excavation 84.384,51
560 - Structures 8.504.053,48
052 - Wall CH 0+350 1.920.652,20
90 - Excavation 11.641,45
560 - Structures 1.909.010,75
053 - Wall CH 0+390 2.161.812,40
90 - Excavation 11.641,45
560 - Structures 2.150.170,95
- 398 -
TOTAL AMOUNT OF WORK
A) WORKS
054 - Wall CH 0+450 1.488.326,69
90 - Excavation 11.641,45
560 - Structures 1.476.685,24
055 - Wall CH 0+530 / CH 0+550 4.249.974,25
90 - Excavation 23.282,90
560 - Structures 4.226.691,35
056 - Wall CH 0+630 / CH 0+650 4.249.974,25
90 - Excavation 23.282,90
560 - Structures 4.226.691,35
057 - Wall CH 0+790 1.043.666,69
90 - Excavation 11.641,45
560 - Structures 1.032.025,24
058 - Wall CH 0+870 / CH 0+890 16.835.877,15
90 - Excavation 224.513,64
560 - Structures 16.611.363,51
02 - Road Alignement TU – Tunnel - CH 0+904 to 2+034 4.042.251.071,
06
001 - Road Works 24.934.578,82
001 - Exavation, Filling and Paving 23.013.083,42
1420 - Paving 23.013.083,42
004 - Signaling 1.921.495,40
1610 - Signaling 1.921.495,40
101 - Main Tunnel - South portal -Technological Building 151.558.736,59
005 - Tecco Mesh and Shotcrete CH 28+200 / CH 28+350 125.537.408,65
90 - Excavation 3.450.896,12
175 - Embankment/Filling 5.411.903,89
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi 116.674.608,64
102 - Technological Building South 26.021.327,94
280 - Foundation Slabs 3.537.735,67
300 - Vertical Elements 6.840.429,02
680 - Slabs 5.918.163,25
685 - Completion work 9.725.000,00
102 - Main Tunnel - North portal -Technological Building 124.030.036,00
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450 107.971.857,09
90 - Excavation 2.885.639,53
175 - Embankment/Filling 5.974.001,55
600 - Protezione imbocchi in ingresso gallerie in presenza di marciapiedi 99.112.216,01
103 - Technological Building North 16.058.178,91
280 - Foundation Slabs 4.385.473,04
300 - Vertical Elements 6.039.736,07
680 - Slabs 3.482.969,80
685 - Completion work 2.150.000,00
103 - Main Tunnel 3.399.993.377,39
110 - Main Tunnel - section type 0 straight line (only excavation and lining) 73.658.776,41
180 - Filling 1.616.589,61
800 - Tunnel excavation 39.382.568,73
810 - Pre-Support 9.265.520,58
820 - Rock Reinforcement 400.703,62
845 - Waterproofing system 6.975.349,27
850 - Lining bottom side / Inver 1.739.417,53
853 - Lining upper side 14.278.627,07
111 - Main Tunnel - section type 1 straight line (only excavation and lining) 216.141.826,13
180 - Filling 1.616.589,61
800 - Tunnel excavation 100.256.680,99
810 - Pre-Support 48.143.937,10
820 - Rock Reinforcement 8.325.150,75
845 - Waterproofing system 17.534.364,22
850 - Lining bottom side / Inver 4.372.285,33
853 - Lining upper side 35.892.818,13
112 - Main Tunnel - section type 2 straight line (only excavation and lining) 159.874.101,31
180 - Filling 1.616.589,61
800 - Tunnel excavation 55.954.583,47
- 399 -
TOTAL AMOUNT OF WORK
A) WORKS
810 - Pre-Support 42.833.410,81
820 - Rock Reinforcement 15.892.667,52
845 - Waterproofing system 9.663.098,53
850 - Lining bottom side / Inver 4.724.000,18
853 - Lining upper side 29.189.751,19
113 - Main Tunnel - section type 3 straight line (only excavation and lining) 267.656.895,58
180 - Filling 1.616.589,61
800 - Tunnel excavation 77.490.091,76
810 - Pre-Support 92.055.359,97
820 - Rock Reinforcement 37.045.880,51
845 - Waterproofing system 13.182.770,18
850 - Lining bottom side / Inver 6.444.556,43
853 - Lining upper side 39.821.647,12
114 - Main Tunnel - section type 4 straight line (only excavation and lining) 389.742.328,62
180 - Filling 1.616.589,61
800 - Tunnel excavation 76.500.580,67
810 - Pre-Support 143.932.549,95
820 - Rock Reinforcement 103.183.941,77
845 - Waterproofing system 11.839.378,46
850 - Lining bottom side / Inver 8.473.661,34
853 - Lining upper side 44.195.626,82
115 - Main Tunnel - section type 5 straight line (only excavation and lining) 891.513.136,76
180 - Filling 2.390.082,23
800 - Tunnel excavation 150.727.960,16
810 - Pre-Support 340.722.508,16
820 - Rock Reinforcement 232.224.000,00
845 - Waterproofing system 21.978.961,84
850 - Lining bottom side / Inver 49.456.583,83
853 - Lining upper side 94.013.040,54
117 - Main Tunnel - section type 0 widened section (only excavation and lining) 81.655.350,99
180 - Filling 1.751.486,72
800 - Tunnel excavation 39.683.095,92
810 - Pre-Support 9.036.359,87
820 - Rock Reinforcement 382.322,72
845 - Waterproofing system 6.798.119,12
850 - Lining bottom side / Inver 3.253.562,47
853 - Lining upper side 20.750.404,17
118 - Main Tunnel - section type 1 widened section (only excavation and lining) 254.342.234,61
180 - Filling 1.751.486,72
800 - Tunnel excavation 108.935.365,97
810 - Pre-Support 51.270.704,08
820 - Rock Reinforcement 8.863.637,60
845 - Waterproofing system 18.433.361,46
850 - Lining bottom side / Inver 8.822.159,78
853 - Lining upper side 56.265.519,00
119 - Main Tunnel - section type 2 widened section (only excavation and lining) 263.204.564,17
180 - Filling 1.751.486,72
800 - Tunnel excavation 93.853.628,42
810 - Pre-Support 70.614.577,23
820 - Rock Reinforcement 25.903.135,44
845 - Waterproofing system 15.687.967,20
850 - Lining bottom side / Inver 7.508.221,08
853 - Lining upper side 47.885.548,08
120 - Main Tunnel - section type 3 widened section (only excavation and lining) 177.211.446,06
180 - Filling 1.751.486,72
800 - Tunnel excavation 52.377.229,36
810 - Pre-Support 61.310.120,19
820 - Rock Reinforcement 22.677.654,78
845 - Waterproofing system 8.628.381,96
850 - Lining bottom side / Inver 4.129.521,60
853 - Lining upper side 26.337.051,45
122 - Main Tunnel - section type 0 lay-by (only excavation and lining) 49.915.641,98
180 - Filling 2.221.450,86
- 400 -
TOTAL AMOUNT OF WORK
A) WORKS
800 - Tunnel excavation 16.642.587,97
810 - Pre-Support 3.272.865,50
820 - Rock Reinforcement 124.990,12
845 - Waterproofing system 2.451.962,02
850 - Lining bottom side / Inver 1.633.261,99
853 - Lining upper side 23.568.523,52
123 - Main Tunnel - section type 1 lay-by (only excavation and lining) 127.048.103,95
180 - Filling 2.221.450,86
800 - Tunnel excavation 42.543.169,29
810 - Pre-Support 29.489.855,74
820 - Rock Reinforcement 3.812.786,85
845 - Waterproofing system 6.202.021,58
850 - Lining bottom side / Inver 4.131.192,07
853 - Lining upper side 38.647.627,56
124 - Main Tunnel - section type 2 lay-by (only excavation and lining) 62.962.577,59
180 - Filling 2.221.450,86
800 - Tunnel excavation 16.998.493,21
810 - Pre-Support 11.872.453,77
820 - Rock Reinforcement 4.216.432,22
845 - Waterproofing system 2.451.962,02
850 - Lining bottom side / Inver 1.633.261,99
853 - Lining upper side 23.568.523,52
125 - Main Tunnel - section type 3 lay-by (only excavation and lining) 45.878.039,88
180 - Filling 2.221.450,86
800 - Tunnel excavation 9.211.935,02
810 - Pre-Support 10.688.516,25
820 - Rock Reinforcement 2.664.572,90
845 - Waterproofing system 1.298.097,54
850 - Lining bottom side / Inver 864.668,10
853 - Lining upper side 18.928.799,21
126 - Main Tunnel - Cut&Cover Stretch South 18.369.618,41
870 - Portal 18.369.618,41
127 - Main Tunnel - Cut&Cover Stretch North 21.783.716,45
870 - Portal 21.783.716,45
130 - Main Tunnel - Completation work 299.035.018,49
250 - Drenaggi 57.622.922,94
700 - Marciapiedi e cordoli 59.793.195,64
1980 - Antincendio 56.526.950,00
1982 - Doors for by-pass and niches 21.600.000,00
1983 - Metallic horizontal support for traffic lights 11.000.000,00
1985 - Painting and internal surfaces finishing 54.450.000,00
2100 - Vie cavi 38.041.949,91
104 - By-Pass #1 107.239.423,50
150 - By-Pass - section type 0 (only excavation and lining) 5.039.434,35
800 - Tunnel excavation 1.446.920,24
810 - Pre-Support 838.627,59
820 - Rock Reinforcement 84.552,14
845 - Waterproofing system 685.262,69
850 - Lining bottom side / Inver 647.784,43
853 - Lining upper side 1.336.287,26
151 - By-Pass - section type 1 (only excavation and lining) 17.941.899,34
800 - Tunnel excavation 4.413.224,90
810 - Pre-Support 4.012.239,81
820 - Rock Reinforcement 1.624.871,56
845 - Waterproofing system 2.025.994,04
850 - Lining bottom side / Inver 1.915.131,84
853 - Lining upper side 3.950.437,19
152 - By-Pass - section type 2 (only excavation and lining) 27.852.012,13
800 - Tunnel excavation 6.090.301,69
810 - Pre-Support 8.193.641,86
820 - Rock Reinforcement 3.007.171,13
845 - Waterproofing system 2.711.256,73
850 - Lining bottom side / Inver 2.562.916,26
- 401 -
TOTAL AMOUNT OF WORK
A) WORKS
853 - Lining upper side 5.286.724,46
153 - By-Pass - section type 3 (only excavation and lining) 35.401.973,11
800 - Tunnel excavation 6.371.379,03
810 - Pre-Support 10.420.308,24
820 - Rock Reinforcement 7.561.937,07
845 - Waterproofing system 2.836.391,66
850 - Lining bottom side / Inver 2.681.262,16
853 - Lining upper side 5.530.694,95
154 - By-Pass - Air-Lock section type 3 (only excavation and lining) 21.004.104,57
800 - Tunnel excavation 4.128.095,51
810 - Pre-Support 6.946.388,92
820 - Rock Reinforcement 3.899.700,11
845 - Waterproofing system 1.101.659,78
850 - Lining bottom side / Inver 1.185.006,12
853 - Lining upper side 3.743.254,13
105 - By-Pass #2 100.230.084,47
150 - By-Pass - section type 0 (only excavation and lining) 8.983.258,67
800 - Tunnel excavation 2.579.266,17
810 - Pre-Support 1.494.920,26
820 - Rock Reinforcement 150.723,38
845 - Waterproofing system 1.221.555,23
850 - Lining bottom side / Inver 1.154.802,40
853 - Lining upper side 2.381.991,23
151 - By-Pass - section type 1 (only excavation and lining) 27.176.873,20
800 - Tunnel excavation 6.684.737,72
810 - Pre-Support 6.077.406,75
820 - Rock Reinforcement 2.461.202,51
845 - Waterproofing system 3.068.785,09
850 - Lining bottom side / Inver 2.900.880,70
853 - Lining upper side 5.983.860,43
152 - By-Pass - section type 2 (only excavation and lining) 12.548.817,43
800 - Tunnel excavation 2.743.982,08
810 - Pre-Support 3.691.544,99
820 - Rock Reinforcement 1.354.941,50
845 - Waterproofing system 1.221.555,23
850 - Lining bottom side / Inver 1.154.802,40
853 - Lining upper side 2.381.991,23
153 - By-Pass - section type 3 (only excavation and lining) 30.517.030,60
800 - Tunnel excavation 5.487.964,16
810 - Pre-Support 8.999.245,00
820 - Rock Reinforcement 6.513.453,52
845 - Waterproofing system 2.443.110,46
850 - Lining bottom side / Inver 2.309.494,96
853 - Lining upper side 4.763.762,50
154 - By-Pass - Air-Lock section type 3 (only excavation and lining) 21.004.104,57
800 - Tunnel excavation 4.128.095,51
810 - Pre-Support 6.946.388,92
820 - Rock Reinforcement 3.899.700,11
845 - Waterproofing system 1.101.659,78
850 - Lining bottom side / Inver 1.185.006,12
853 - Lining upper side 3.743.254,13
106 - By-Pass #3 96.620.130,74
150 - By-Pass - section type 0 (only excavation and lining) 3.943.824,30
800 - Tunnel excavation 1.132.345,93
810 - Pre-Support 656.292,67
820 - Rock Reinforcement 66.171,24
845 - Waterproofing system 536.292,54
850 - Lining bottom side / Inver 507.017,96
853 - Lining upper side 1.045.703,96
151 - By-Pass - section type 1 (only excavation and lining) 13.984.366,99
800 - Tunnel excavation 3.439.719,41
810 - Pre-Support 3.127.225,95
820 - Rock Reinforcement 1.266.444,01
- 402 -
TOTAL AMOUNT OF WORK
A) WORKS
845 - Waterproofing system 1.579.083,59
850 - Lining bottom side / Inver 1.492.766,83
853 - Lining upper side 3.079.127,20
152 - By-Pass - section type 2 (only excavation and lining) 21.730.843,21
800 - Tunnel excavation 4.751.773,85
810 - Pre-Support 6.392.957,01
820 - Rock Reinforcement 2.346.262,86
845 - Waterproofing system 2.115.376,13
850 - Lining bottom side / Inver 1.999.642,19
853 - Lining upper side 4.124.831,17
153 - By-Pass - section type 3 (only excavation and lining) 35.956.991,67
800 - Tunnel excavation 6.471.802,39
810 - Pre-Support 10.581.785,92
820 - Rock Reinforcement 7.681.115,11
845 - Waterproofing system 2.881.105,20
850 - Lining bottom side / Inver 2.723.401,09
853 - Lining upper side 5.617.781,96
154 - By-Pass - Air-Lock section type 3 (only excavation and lining) 21.004.104,57
800 - Tunnel excavation 4.128.095,51
810 - Pre-Support 6.946.388,92
820 - Rock Reinforcement 3.899.700,11
845 - Waterproofing system 1.101.659,78
850 - Lining bottom side / Inver 1.185.006,12
853 - Lining upper side 3.743.254,13
115 - SOS niches 37.644.703,55
131 - Flushing niches 22.870.110,54
800 - Tunnel excavation 3.753.010,56
810 - Pre-Support 7.266.175,07
845 - Waterproofing system 2.920.320,00
850 - Lining bottom side / Inver 250.482,08
853 - Lining upper side 8.680.122,83
132 - Hydrant niches 1.433.597,88
800 - Tunnel excavation 200.441,51
810 - Pre-Support 488.885,06
845 - Waterproofing system 197.820,00
850 - Lining bottom side / Inver 11.420,49
853 - Lining upper side 535.030,82
133 - SOS / Hydrant niches 13.340.995,13
800 - Tunnel excavation 2.436.296,27
810 - Pre-Support 4.975.417,07
845 - Waterproofing system 925.020,00
850 - Lining bottom side / Inver 75.770,56
853 - Lining upper side 4.928.491,23
03 - Pedestrian Road Alignement PE 928.318.891,2
2
006 - Hydraulic Works 6.162.042,91
026 - Culvert A3 400.823,18
1005 - culverts 400.823,18
027 - Culvert 6 570.968,53
1005 - culverts 570.968,53
028 - Culvert 7 508.800,04
1005 - culverts 508.800,04
029 - Culvert 8 1.182.837,39
1005 - culverts 1.182.837,39
030 - Culvert 9 711.120,31
1005 - culverts 711.120,31
031 - Culvert 10 955.158,91
1005 - culverts 955.158,91
032 - Culvert A4 604.506,80
1005 - culverts 604.506,80
033 - Culvert 11 675.128,03
1005 - culverts 675.128,03
- 403 -
TOTAL AMOUNT OF WORK
A) WORKS
034 - Culvert A5 552.699,72
1005 - culverts 552.699,72
007 - Civil Works 59.975.388,31
067 - Wall CH 0+080 / CH 0+095 1.040.853,80
90 - Excavation 7.566,94
560 - Structures 1.033.286,86
068 - Wall CH 0+900 / CH 0+920 2.137.047,95
90 - Excavation 16.685,01
560 - Structures 2.120.362,94
069 - Wall CH 0+920 / CH 0+950 19.285.069,62
90 - Excavation 57.714,72
560 - Structures 19.227.354,90
070 - Walls CH 0+110 / CH 0+890 37.512.416,94
90 - Excavation 303.157,38
560 - Structures 37.209.259,56
202 - Pedestrain rockshed 723.175.479,44
001 - Exavation, Filling and Paving 8.078.985,31
1420 - Paving 8.078.985,31
201 - Exavation and Filling 21.590.408,04
90 - Excavation 4.064.108,14
175 - Embankment/Filling 17.526.299,90
204 - Consolidamento parete lungo il manufatto 6.652.095,08
160 - Protezione scavi 6.652.095,08
205 - Rockshed Section 418.743.167,36
280 - Foundation Slabs 103.034.177,11
300 - Vertical Elements 139.257.861,62
574 - Impermeabilizzazioni 71.630.164,44
680 - Slabs 104.820.964,19
206 - Road works and secondary civil works 40.991.587,06
1420 - Paving 40.991.587,06
207 - Cushion layer (Leca) 227.119.236,59
175 - Embankment/Filling 227.119.236,59
203 - ROADSIDE ROCK STABILIZATION 89.703.564,90
208 - Shotcrete + bolts 89.703.564,90
160 - Protezione scavi 89.703.564,90
204 - ROADSIDE ROCK EXCAVATION 49.302.415,66
208 - Shotcrete + bolts 49.302.415,66
160 - Protezione scavi 49.302.415,66
04 - Road Alignement MR2 - Main Road - North Stretch - CH 2+034 to 2+587 516.094.456,2
6
001 - Road Works 28.566.828,53
001 - Exavation, Filling and Paving 27.617.242,75
90 - Excavation 1.621.468,58
175 - Embankment/Filling 292.141,27
980 - Precast rectangular channeling 2.695.000,00
1420 - Paving 23.008.632,90
004 - Signaling 949.585,78
1610 - Signaling 949.585,78
002 - Rockside rock excavation 37.735.451,50
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450 37.735.451,50
160 - Protezione scavi 37.735.451,50
003 - Rockfall Protection Measures 407.919.515,90
006 - Tecco Mesh and Shotcrete CH 30+250 / CH 30+450 319.510.515,90
160 - Protezione scavi 319.510.515,90
009 - ROCKFALL BARRIER 88.409.000,00
160 - Protezione scavi 88.409.000,00
006 - Hydraulic Works 7.957.147,38
035 - Culvert 12 1.885.194,96
90 - Excavation 9.563,22
180 - Filling 5.031,01
1005 - culverts 1.870.600,73
- 404 -
TOTAL AMOUNT OF WORK
A) WORKS
036 - Culvert A6 539.316,91
90 - Excavation 7.861,41
180 - Filling 11.696,45
1005 - culverts 519.759,05
037 - Culvert 13 2.648.943,97
90 - Excavation 37.492,52
180 - Filling 11.791,31
1005 - culverts 2.599.660,14
038 - Culvert A7 584.693,80
90 - Excavation 8.746,49
180 - Filling 12.608,52
1005 - culverts 563.338,79
039 - Culvert 14 575.047,34
90 - Excavation 8.563,00
180 - Filling 12.969,71
1005 - culverts 553.514,63
040 - Culvert 15 1.723.950,40
90 - Excavation 21.158,05
180 - Filling 21.867,91
1005 - culverts 1.680.924,44
007 - Civil Works 33.915.512,95
059 - Wall CH 2+070 / CH 2+090 16.835.877,15
90 - Excavation 224.513,64
560 - Structures 16.611.363,51
060 - Wall CH 2+110 / CH 2+130 4.099.628,75
90 - Excavation 23.282,90
560 - Structures 4.076.345,85
061 - Wall CH 2+210 1.923.566,90
90 - Excavation 11.641,45
560 - Structures 1.911.925,45
062 - Wall CH 2+270 1.923.566,90
90 - Excavation 11.641,45
560 - Structures 1.911.925,45
063 - Wall CH 2+310 1.043.666,69
90 - Excavation 11.641,45
560 - Structures 1.032.025,24
064 - Wall CH 2+410 / CH 2+430 2.101.833,39
90 - Excavation 23.282,90
560 - Structures 2.078.550,49
065 - Wall CH 2+510 / CH 2+530 2.101.833,39
90 - Excavation 23.282,90
560 - Structures 2.078.550,49
066 - Wall CH 2+570 / CH 2+590 3.885.539,78
90 - Excavation 23.282,90
560 - Structures 3.862.256,88
05 - waste disposal 11.655.853,73
07 - Main Tunnel - Electromechanical Equipment 630.418.800,0
0
301 - Electrical Systems 132.000.000,00
301 - Energy supply 57.288.000,00
302 - Lighting 74.712.000,00
302 - Mechanical Systems 182.292.000,00
303 - Ventilation 103.356.000,00
313 - Engress tunnel ventilation 78.936.000,00
304 - Signage, Detection, Communication and Control Systems 304.378.800,00
304 - Signage 30.360.000,00
305 - Tunnel fire detection system 32.604.000,00
306 - Videosurveillance system 17.278.800,00
307 - Communication network 15.180.000,00
- 405 -
TOTAL AMOUNT OF WORK
A) WORKS
308 - Tunnel control system 63.624.000,00
309 - Radio diffusion in tunnel 33.792.000,00
310 - Emergency telephone system 33.396.000,00
311 - Cabling system 78.144.000,00
305 - Secondary systems 11.748.000,00
312 - Secondary installations 11.748.000,00
B) AVAILABLE AMOUNTS
ON OF
0.DOC
Approved
MUB
oQ
................ 4
................ 5
Page 2
oQ
9
9
soft
copy.
.pdf
Page 3
oQ
oQ
38
3,
49
2.703.232,51
2.703.232,51
2.703.232,51
2.703.232,51
2.703.232,5
2.703.232,51
PRICE AMOUNT
36 2.703.232,51
4, 228.503,97
83
4,
83
228.503,97
2.931.736,48
2.931.736,48
2.931.736,4
2.931.736,48
PRICE AMOUNT
4.900, 2.931.736,48
00 4.410.000,00
4.410.000,00
7.341.736,48
7.341.736,48
7.341.736,4
7.341.736,48
PRICE AMOUNT
1.996,11 7.341.736,48
12.172,63 3.979.165,44
9.577,26 18.313.721,84
73,42 3.602.294,80
1.380.773,23
27.275.955,31
34.617.691,7
9
34.617.691,79
34.617.691,
34.617.691,79
PRICE AMOUNT
34.617.691,79
1.745, 1.498.799,33
53
1.498.799,33
1.498.799,33
36.116.491,12
36.116.491,
36.116.491,12
PRICE AMOUNT
36.116.491,12
8.500, 21.590.000,00
00
21.590.000,00
21.590.000,0
21.590.000,00
57.706.491,
57.706.491,12
PRICE AMOUNT
57.706.491,12
66 1.691.767,00
6,
05
23.281.767,00
23.281.767,0
23.281.767,00
59.398.258,
59.398.258,12
PRICE AMOUNT
59.398.258,12
23.281.767,00
23.281.767,0
23.281.767,00
59.398.258,
59.398.258,12
PRICE AMOUNT
59.398.258,12
7.780,00 41.389.600,00
3.000,00 5.076.000,00
69.747.367,00
69.747.367,0
0
69.747.367,00
105.863.858
105.863.858,12
PRICE AMOUNT
105.863.858,12
8.500,00 27.132.000,00
666,05 2.126.031,60
9.350,00 44.767.800,00
74.025.831,60
74.025.831,6
74.025.831,60
179.889.689
179.889.689,72
PRICE AMOUNT
179.889.689,72
8.200,00 62.818.560,00
6.000,00 47.880.000,00
3.000,00 6.390.000,00
191.114.391,60
191.114.391,
60
191.114.391,60
296.978.249
296.978.249,72
PRICE AMOUNT
PRICE AMOUNT
296.978.249,72
34.500,00 17.112.000,00
53.000,00 67.707.500,00
84.819.500,00
84.819.500,0
0
275.933.891,60
381.797.749
381.797.749,72
PRICE AMOUNT
1.900, 381.797.749,72
00 28.543.700,00
28.543.700,00
28.543.700,0
0
304.477.591,60
410.341.449
410.341.449,72
PRICE AMOUNT
11 410.341.449,72
9, 7.393,68
93
7.393,68
7.393,68
7.393,68
410.348.843
410.348.843,40
PRICE AMOUNT
36 410.348.843,40
4, 10.528,99
83
4,
83
10.528,99
17.922,67
17.922,67
410.359.372
410.359.372,39
PRICE AMOUNT
16.857,39 410.359.372,39
11.539,20 197.231,46
13.966,07 47.426,11
110.464,93 18.435,21
14.843,16 14.581,37
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
507.623,45
525.546,12
525.546,12
410.866.995
410.866.995,84
PRICE AMOUNT
11 410.866.995,84
9, 20.901,40
93
20.901,40
20.901,40
546.447,52
410.887.897
410.887.897,24
PRICE AMOUNT
36 410.887.897,24
4, 18.620,92
83
4,
83
18.620,92
39.522,32
565.068,44
410.906.518
410.906.518,16
PRICE AMOUNT
11.539,20 410.906.518,16
13.966,07 47.656,90
110.464,93 144.967,81
14.843,16 114.662,60
110.464,93 537.173,96
437.000,00 399.772,58
109.250,00
1.353.483,85
1.393.006,17
1.918.552,29
412.260.002
412.260.002,01
PRICE AMOUNT
11 412.260.002,01
9, 10.934,02
93
10.934,02
10.934,02
1.929.486,31
412.270.936
412.270.936,03
PRICE AMOUNT
36 412.270.936,03
4, 13.049,97
83
4,
83
13.049,97
23.983,99
1.942.536,28
412.283.986
412.283.986,00
PRICE AMOUNT
21.807,99 412.283.986,00
11.539,20 316.215,86
13.966,07 70.158,34
110.464,93 18.435,21
14.843,16 14.581,37
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
649.340,08
673.324,07
2.591.876,36
412.933.326
412.933.326,08
PRICE AMOUNT
11 412.933.326,08
9, 12.340,80
93
12.340,80
12.340,80
2.604.217,16
412.945.666
412.945.666,88
PRICE AMOUNT
36 412.945.666,88
4, 18.788,75
83
4,
83
18.788,75
31.129,55
2.623.005,91
412.964.455
412.964.455,63
PRICE AMOUNT
21.807,99 412.964.455,63
11.539,20 366.374,23
13.966,07 79.158,91
110.464,93 18.435,21
14.843,16 14.581,37
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
708.499,02
739.628,57
3.331.504,93
413.672.954
413.672.954,65
PRICE AMOUNT
11 413.672.954,65
9, 22.781,90
93
22.781,90
22.781,90
3.354.286,83
413.695.736
413.695.736,55
PRICE AMOUNT
36 413.695.736,55
4, 11.944,53
83
4,
83
11.944,53
34.726,43
3.366.231,36
413.707.681
413.707.681,08
PRICE AMOUNT
11.539,20 413.707.681,08
13.966,07 53.195,71
110.464,93 164.799,63
14.843,16 130.348,62
110.464,93 506.003,32
437.000,00 376.574,95
109.250,00
1.340.172,23
1.374.898,66
4.706.403,59
415.047.853
415.047.853,31
PRICE AMOUNT
11 415.047.853,31
9, 15.121,97
93
15.121,97
15.121,97
4.721.525,56
415.062.975
415.062.975,28
PRICE AMOUNT
36 415.062.975,28
4, 21.371,74
83
4,
83
21.371,74
36.493,71
4.742.897,30
415.084.347
415.084.347,02
PRICE AMOUNT
11.539,20 415.084.347,02
13.966,07 88.505,66
110.464,93 293.147,81
14.843,16 231.865,89
110.464,93 930.666,13
437.000,00 692.615,11
109.250,00
2.346.050,60
2.382.544,31
7.088.947,90
417.430.397
417.430.397,62
PRICE AMOUNT
11 417.430.397,62
9, 9.249,00
93
9.249,00
9.249,00
7.098.196,90
417.439.646
417.439.646,62
PRICE AMOUNT
11.539,20 417.439.646,62
13.966,07 41.541,12
110.464,93 122.622,09
14.843,16 96.988,21
110.464,93 403.140,23
437.000,00 300.022,75
109.250,00
1.073.564,40
1.082.813,40
8.171.761,30
418.513.211
418.513.211,02
PRICE AMOUNT
31 418.513.211,02
9, 46.565,79
82
9,
82
46.565,79
46.565,79
46.565,79
418.559.776
418.559.776,81
PRICE AMOUNT
9.893,01 418.559.776,81
110.464,93 55.400,86
110.464,93 106.046,33
7.780,00 225.967,06
11.720,00 735.210,00
16.220,39 1.687.680,00
15.188,18 414.755,37
2.900,00 182.258,16
478.500,00
3.885.817,78
3.932.383,57
3.932.383,57
422.445.594
422.445.594,59
PRICE AMOUNT
422.445.594,59
31 84.384,51
9,
82 84.384,51
84.384,51
4.016.768,08
422.529.979
422.529.979,10
PRICE AMOUNT
422.529.979,10
9.893,01 83.101,28
110.464,93 159.069,50
110.464,93 560.985,10
7.780,00 1.633.800,00
11.720,00 4.184.040,00
16.220,39 1.029.670,36
15.188,18 273.387,24
2.900,00 580.000,00
12.520.821,56
431.034.032
431.034.032,58
PRICE AMOUNT
431.034.032,58
8.504.053,48
8.588.437,99
12.520.821,56
431.034.032
431.034.032,58
PRICE AMOUNT
31 431.034.032,58
9, 11.641,45
82
11.641,45
11.641,45
12.532.463,01
431.045.674
431.045.674,03
PRICE AMOUNT
9.893,01 431.045.674,03
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 111.171,91
11.720,00 272.300,00
16.220,39 1.148.560,00
15.188,18 204.052,51
2.900,00 45.564,54
87.000,00
1.909.010,75
1.920.652,20
14.441.473,76
432.954.684
432.954.684,78
PRICE AMOUNT
31 432.954.684,78
9, 11.641,45
82
9,
82
11.641,45
11.641,45
14.453.115,21
432.966.326
432.966.326,23
PRICE AMOUNT
9.893,01 432.966.326,23
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 109.669,58
11.720,00 435.680,00
16.220,39 1.230.600,00
15.188,18 201.295,04
2.900,00 45.564,54
87.000,00
2.150.170,95
2.161.812,40
16.603.286,16
435.116.497
435.116.497,18
PRICE AMOUNT
31 435.116.497,18
9, 11.641,45
82
11.641,45
11.641,45
16.614.927,61
435.128.138
435.128.138,63
PRICE AMOUNT
9.893,01 435.128.138,63
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 58.148,74
11.720,00 435.680,00
16.220,39 703.200,00
15.188,18 106.730,17
2.900,00 45.564,54
87.000,00
1.476.685,24
1.488.326,69
18.091.612,85
436.604.823
436.604.823,87
PRICE AMOUNT
31 436.604.823,87
9, 23.282,90
82
9,
82
23.282,90
23.282,90
18.114.895,75
436.628.106
436.628.106,77
PRICE AMOUNT
9.893,01 436.628.106,77
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 219.250,79
11.720,00 871.360,00
16.220,39 2.373.300,00
15.188,18 402.427,88
2.900,00 91.129,08
188.500,00
4.226.691,35
4.249.974,25
22.341.587,10
440.854.798
440.854.798,12
PRICE AMOUNT
31 440.854.798,12
9, 23.282,90
82
23.282,90
23.282,90
22.364.870,00
440.878.081
440.878.081,02
PRICE AMOUNT
9.893,01 440.878.081,02
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 219.250,79
11.720,00 871.360,00
16.220,39 2.373.300,00
15.188,18 402.427,88
2.900,00 91.129,08
188.500,00
4.226.691,35
4.249.974,25
26.591.561,35
445.104.772
445.104.772,37
PRICE AMOUNT
31 445.104.772,37
9, 11.641,45
82
9,
82
11.641,45
11.641,45
26.603.202,80
445.116.413
445.116.413,82
PRICE AMOUNT
9.893,01 445.116.413,82
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 58.148,74
11.720,00 272.300,00
16.220,39 421.920,00
15.188,18 106.730,17
2.900,00 45.564,54
87.000,00
1.032.025,24
1.043.666,69
27.635.228,04
446.148.439
446.148.439,06
PRICE AMOUNT
31 446.148.439,06
9, 224.513,64
82
224.513,64
224.513,64
27.859.741,68
446.372.952
446.372.952,70
PRICE AMOUNT
9.893,01 446.372.952,70
110.464,93 89.037,09
110.464,93 434.789,96
7.780,00 1.155.286,42
11.720,00 4.201.200,00
16.220,39 7.500.800,00
15.188,18 2.120.491,58
2.900,00 747.258,46
362.500,00
16.611.363,51
462.984.316,21
PRICE AMOUNT
462.984.316,21
16.835.877,1
5
44.471.105,19
462.984.316
,21
462.984.316,21
PRICE AMOUNT
12.172,63 462.984.316,21
9.577,26 16.900.601,22
73,42 4.418.756,22
1.693.725,98
23.013.083,42
23.013.083,4
2
23.013.083,42
23.013.083,
485.997.399,63
PRICE AMOUNT
485.997.399,63
1.745,53 1.786.375,40
600,00 135.120,00
1.921.495,40
1.921.495,40
24.934.578,82
24.934.578,
487.918.895,03
PRICE AMOUNT
38 487.918.895,03
3, 3.450.896,12
49
3,
49
3.450.896,12
3.450.896,12
3.450.896,12
28.385.474,
491.369.791,15
PRICE AMOUNT
491.369.791,15
1.500,45 4.076.347,54
9.893,01 1.335.556,35
5.411.903,89
8.862.800,01
8.862.800,01
33.797.378,
496.781.695,04
PRICE AMOUNT
496.781.695,04
110.464,93 293.682,06
1.272,98 1.438.467,40
11.300,00 20.426.445,00
22.158.594,46
31.021.394,4
31.021.394,47
55.955.973,
518.940.289,50
PRICE AMOUNT
518.940.289,50
1.494,15 5.401.800,50
11.990,00 54.242.760,00
81.803.154,96
90.665.954,9
90.665.954,97
115.600.533
578.584.850,00
PRICE AMOUNT
578.584.850,00
20.140,00 21.694.606,60
15.000,00 12.600.000,00
15.188,18 576.847,08
116.674.608,64
125.537.408,
65
125.537.408,65
150.471.987
613.456.303,68
PRICE AMOUNT
613.456.303,68
9.893,01 462.003,57
110.464,93 1.037.630,23
15.188,18 2.038.101,87
3.537.735,67
3.537.735,67
129.075.144,32
154.009.723
616.994.039,35
PRICE AMOUNT
616.994.039,35
110.464,93 2.735.697,13
2.735.697,13
6.273.432,80
131.810.841,45
156.745.420
619.729.736,48
PRICE AMOUNT
619.729.736,48
16.220 4.104.731,89
,39
6.840.429,02
10.378.164,6
135.915.573,34
160.850.152
623.834.468,37
PRICE AMOUNT
623.834.468,37
112.276,18 2.415.375,01
17.501,69 3.502.788,24
5.918.163,25
16.296.327,9
141.833.736,59
166.768.315
629.752.631,62
PRICE AMOUNT
629.752.631,62
5.000.000,00 5.000.000,00
4.400.000,00 4.400.000,00
50.000,00 200.000,00
25.000,00 125.000,00
9.725.000,00
26.021.327,9
4
151.558.736,59
176.493.315
639.477.631,62
PRICE AMOUNT
38 639.477.631,62
3, 2.885.639,53
49
2.885.639,53
2.885.639,53
2.885.639,53
179.378.954
642.363.271,15
PRICE AMOUNT
642.363.271,15
1.500,45 3.698.609,25
9.893,01 2.275.392,30
5.974.001,55
8.859.641,08
8.859.641,08
185.352.956
648.337.272,70
PRICE AMOUNT
648.337.272,70
13.966,07 133.515,63
110.464,93 73.923,13
1.272,98 1.069.303,20
11.300,00 15.262.797,00
19.425.713,81
28.285.354,8
28.285.354,89
204.778.670
667.762.986,51
PRICE AMOUNT
667.762.986,51
1.494,15 2.886.174,85
1.958,27 1.507.300,00
11.990,00 34.120.902,20
20.140,00 37.158.300,00
92.212.216,01
101.071.857,
101.071.857,09
277.565.172
740.549.488,71
PRICE AMOUNT
15.000 740.549.488,71
,00 6.900.000,00
15.000
,00
99.112.216,01
107.971.857,
09
107.971.857,09
284.465.172
747.449.488,71
PRICE AMOUNT
9.893,01 747.449.488,71
110.464,93 224.670,26
15.188,18 1.700.165,74
2.460.637,04
4.385.473,04
4.385.473,04
112.357.330,13
288.850.645
751.834.961,75
PRICE AMOUNT
751.834.961,75
110.464,93 2.317.156,56
2.317.156,56
6.702.629,60
114.674.486,69
291.167.802
754.152.118,31
PRICE AMOUNT
754.152.118,31
16.220 3.722.579,51
,39
6.039.736,07
10.425.209,1
118.397.066,20
294.890.381
757.874.697,82
PRICE AMOUNT
757.874.697,82
112.276,18 1.318.885,83
17.501,69 2.164.083,97
3.482.969,80
13.908.178,9
121.880.036,00
298.373.351
761.357.667,62
PRICE AMOUNT
761.357.667,62
2.000.000,00 2.000.000,00
50.000,00 150.000,00
2.150.000,00
16.058.178,9
1
124.030.036,00
300.523.351
763.507.667,62
PRICE AMOUNT
1.996, 763.507.667,62
11 1.616.589,61
1.616.589,61
1.616.589,61
1.616.589,61
302.139.941
765.124.257,23
PRICE AMOUNT
6.753, 765.124.257,23
42 39.382.568,73
39.382.568,73
40.999.158,3
40.999.158,34
341.522.509
804.506.825,96
PRICE AMOUNT
3.043,88 804.506.825,96
2.652,95 4.503.968,36
581,39 3.903.815,93
857.736,29
9.265.520,58
50.264.678,9
50.264.678,92
350.788.030
813.772.346,54
PRICE AMOUNT
7.352, 813.772.346,54
36 400.703,62
36
400.703,62
50.665.382,5
50.665.382,54
351.188.733
814.173.050,16
PRICE AMOUNT
814.173.050,16
4.500,00 6.646.275,00
3.019,03 329.074,27
6.975.349,27
57.640.731,8
57.640.731,81
358.164.083
821.148.399,43
PRICE AMOUNT
821.148.399,43
10.981,24 239.391,03
15.549,15 1.500.026,50
122.616,07 0,00
1.739.417,53
59.380.149,3
59.380.149,34
359.903.500
822.887.816,96
PRICE AMOUNT
822.887.816,96
2.550,00 3.352.077,00
19.445,72 10.926.550,07
124.626,56 0,00
14.278.627,07
73.658.776,4
1
73.658.776,41
374.182.127
837.166.444,03
PRICE AMOUNT
1.996, 837.166.444,03
11 1.616.589,61
11
1.616.589,61
1.616.589,61
75.275.366,02
375.798.717
838.783.033,64
PRICE AMOUNT
6.753, 838.783.033,64
42 100.256.680,99
100.256.680,99
101.873.270,
175.532.047,01
476.055.398
939.039.714,63
PRICE AMOUNT
3.043,88 939.039.714,63
4.452,45 29.463.540,85
581,39 16.512.311,55
2.168.084,70
48.143.937,10
150.017.207,
223.675.984,11
524.199.335
987.183.651,73
PRICE AMOUNT
7.352, 987.183.651,73
36 8.325.150,75
8.325.150,75
158.342.358,
232.001.134,86
532.524.486
995.508.802,48
PRICE AMOUNT
995.508.802,48
4.500,00 16.707.150,00
3.019,03 827.214,22
17.534.364,22
175.876.722,
249.535.499,08
550.058.850
1.013.043.166,70
PRICE AMOUNT
1.013.043.166,70
10.981,24 601.771,95
15.549,15 3.770.513,38
122.616,07 0,00
4.372.285,33
180.249.008,
253.907.784,41
554.431.135
1.017.415.452,03
PRICE AMOUNT
1.017.415.452,03
2.550,00 8.426.322,00
19.445,72 27.466.496,13
124.626,56 0,00
35.892.818,13
216.141.826,
13
289.800.602,54
590.323.953
1.053.308.270,16
PRICE AMOUNT
1.996, 1.053.308.270,16
11 1.616.589,61
1.996, 1.053.308.270,16
11 1.616.589,61
1.616.589,61
1.616.589,61
291.417.192,15
591.940.543
1.054.924.859,77
PRICE AMOUNT
6.753, 1.054.924.859,77
42 55.954.583,47
55.954.583,47
57.571.173,0
347.371.775,62
647.895.127
1.110.879.443,24
PRICE AMOUNT
3.043,88 1.110.879.443,24
5.234,30 13.518.114,59
2.652,95 12.359.909,62
4.452,45 5.438.096,50
581,39 9.126.765,58
2.390.524,52
42.833.410,81
100.404.583,
390.205.186,43
690.728.537
1.153.712.854,05
PRICE AMOUNT
1.153.712.854,05
16.001,24 11.736.589,52
11.800,00 4.156.078,00
15.892.667,52
116.297.251,
406.097.853,95
706.621.205
1.169.605.521,57
PRICE AMOUNT
1.169.605.521,57
4.500,00 9.207.225,00
3.019,03 455.873,53
9.663.098,53
125.960.349,
415.760.952,48
716.284.303
1.179.268.620,10
PRICE AMOUNT
1.179.268.620,10
10.981,24 331.633,45
15.549,15 2.077.988,41
122.616,07 2.314.378,32
4.724.000,18
130.684.350,
420.484.952,66
721.008.304
1.183.992.620,28
PRICE AMOUNT
1.183.992.620,28
2.550,00 4.643.703,00
19.445,72 15.136.742,91
124.626,56 9.409.305,28
29.189.751,19
159.874.101,
31
449.674.703,85
750.198.055
1.213.182.371,47
PRICE AMOUNT
1.996, 1.213.182.371,47
11 1.616.589,61
11
1.616.589,61
1.616.589,61
451.291.293,46
751.814.644
1.214.798.961,08
PRICE AMOUNT
6.753, 1.214.798.961,08
42 77.490.091,76
77.490.091,76
79.106.681,3
528.781.385,22
829.304.736
1.292.289.052,84
PRICE AMOUNT
108.379,99 1.292.289.052,84
3.043,88 7.700.333,26
5.234,30 26.075.428,46
8.904,90 30.029.702,53
581,39 24.975.483,98
3.274.411,74
92.055.359,97
171.162.041,
620.836.745,19
921.360.096
1.384.344.412,81
PRICE AMOUNT
11.721 1.384.344.412,81
,36 2.414.600,16
8.033, 28.961.380,35
67 5.669.900,00
11.800
,00
37.045.880,51
208.207.921,
657.882.625,70
958.405.977
1.421.390.293,32
PRICE AMOUNT
1.421.390.293,32
4.500,00 12.560.850,00
3.019,03 621.920,18
13.182.770,18
221.390.692,
671.065.395,88
971.588.747
1.434.573.063,50
PRICE AMOUNT
1.434.573.063,50
10.981,24 452.427,09
15.549,15 2.834.765,54
122.616,07 3.157.363,80
6.444.556,43
227.835.248,
677.509.952,31
978.033.303
1.441.017.619,93
PRICE AMOUNT
1.441.017.619,93
2.550,00 6.335.118,00
19.445,72 20.649.993,44
124.626,56 12.836.535,68
39.821.647,12
267.656.895,
58
717.331.599,43
1.017.854.9
1.480.839.267,05
PRICE AMOUNT
1.996, 1.480.839.267,05
11 1.616.589,61
1.616.589,61
1.616.589,61
718.948.189,04
1.019.471.5
1.482.455.856,66
PRICE AMOUNT
6.753, 1.482.455.856,66
42 76.500.580,67
42
76.500.580,67
78.117.170,2
795.448.769,71
1.095.972.1
1.558.956.437,33
PRICE AMOUNT
277.778,00 1.558.956.437,33
3.043,88 53.755.765,23
5.234,30 26.483.308,38
11.131,12 31.722.998,58
581,39 28.939.464,95
3.031.012,81
143.932.549,95
222.049.720,
939.381.319,66
1.239.904.6
1.702.888.987,28
PRICE AMOUNT
3.229,18 1.702.888.987,28
16.466,26 15.427.407,45
11.800,00 2.996.859,32
250.000,00 38.656.800,00
46.102.875,00
103.183.941,77
325.233.662,
1.042.565.261,
1.343.088.6
1.806.072.929,05
PRICE AMOUNT
1.806.072.929,05
4.500,00 11.289.915,00
3.019,03 549.463,46
11.839.378,46
337.073.040,
1.054.404.639,
1.354.927.9
1.817.912.307,51
PRICE AMOUNT
1.817.912.307,51
15.549,15 622.587,97
15.549,15 2.829.945,30
122.616,07 5.021.128,07
8.473.661,34
345.546.701,
1.062.878.301,
1.363.401.6
1.826.385.968,85
PRICE AMOUNT
1.826.385.968,85
2.550,00 5.597.046,00
19.445,72 22.721.157,08
124.626,56 15.877.423,74
44.195.626,82
389.742.328,
62
1.107.073.928,
1.407.597.2
1.870.581.595,67
PRICE AMOUNT
1.996, 1.870.581.595,67
11 2.390.082,23
2.390.082,23
2.390.082,23
1.109.464.010,
1.409.987.3
1.872.971.677,90
PRICE AMOUNT
6.753, 1.872.971.677,90
42 150.727.960,16
42
150.727.960,16
153.118.042,
1.260.191.970,
1.560.715.3
2.023.699.638,06
PRICE AMOUNT
277.778,00 2.023.699.638,06
3.043,88 140.830.557,11
5.234,30 50.446.284,12
13.357,34 51.209.355,31
581,39 90.296.686,99
7.939.624,63
340.722.508,16
493.840.550,
1.600.914.478,
1.901.437.8
2.364.422.146,22
PRICE AMOUNT
11.800 2.364.422.146,22
,00 232.224.000,00
232.224.000,00
726.064.550,
1.833.138.478,
2.133.661.8
2.596.646.146,22
PRICE AMOUNT
2.596.646.146,22
4.500,00 20.988.720,00
3.019,03 990.241,84
21.978.961,84
748.043.512,
1.855.117.440,
2.155.640.7
2.618.625.108,06
PRICE AMOUNT
2.618.625.108,06
15.549,15 20.298.482,38
122.616,07 29.158.101,45
49.456.583,83
797.500.096,
1.904.574.024,
2.205.097.3
2.668.081.691,89
PRICE AMOUNT
2.668.081.691,89
2.550,00 10.086.984,00
19.445,72 46.114.358,24
124.626,56 37.811.698,30
94.013.040,54
891.513.136,
76
1.998.587.064,
2.299.110.4
2.762.094.732,43
PRICE AMOUNT
1.996, 2.762.094.732,43
11 1.751.486,72
1.751.486,72
1.751.486,72
2.000.338.551,
2.300.861.9
2.763.846.219,15
PRICE AMOUNT
6.753, 2.763.846.219,15
42 39.683.095,92
39.683.095,92
41.434.582,6
2.040.021.647,
2.340.544.9
2.803.529.315,07
PRICE AMOUNT
3.043,88 2.803.529.315,07
2.652,95 4.392.318,84
581,39 3.807.513,84
836.527,19
9.036.359,87
50.470.942,5
2.049.058.007,
2.349.581.3
2.812.565.674,94
PRICE AMOUNT
7.352, 2.812.565.674,94
36 382.322,72
36
382.322,72
50.853.265,2
2.049.440.330,
2.349.963.6
2.812.947.997,66
PRICE AMOUNT
2.812.947.997,66
4.500,00 6.484.140,00
3.019,03 313.979,12
6.798.119,12
57.651.384,3
2.056.238.449,
2.356.761.8
2.819.746.116,78
PRICE AMOUNT
2.819.746.116,78
10.981,24 228.409,79
15.549,15 1.431.143,77
122.616,07 1.594.008,91
3.253.562,47
60.904.946,8
2.059.492.011,
2.360.015.3
2.822.999.679,25
PRICE AMOUNT
2.822.999.679,25
2.550,00 3.277.872,00
19.445,72 10.667.921,99
124.626,56 6.804.610,18
20.750.404,17
81.655.350,9
9
2.080.242.415,
2.380.765.7
2.843.750.083,42
PRICE AMOUNT
1.996, 2.843.750.083,42
11 1.751.486,72
11
1.751.486,72
1.751.486,72
2.081.993.902,
2.382.517.2
2.845.501.570,14
PRICE AMOUNT
6.753, 2.845.501.570,14
42 108.935.365,97
108.935.365,97
110.686.852,
2.190.929.268,
2.491.452.6
2.954.436.936,11
PRICE AMOUNT
3.043,88 2.954.436.936,11
4.452,45 31.618.212,18
581,39 17.371.100,10
2.281.391,80
51.270.704,08
161.957.556,
2.242.199.972,
2.542.723.3
3.005.707.640,19
PRICE AMOUNT
7.352, 3.005.707.640,19
36 8.863.637,60
8.863.637,60
170.821.194,
2.251.063.610,
2.551.586.9
3.014.571.277,79
PRICE AMOUNT
3.014.571.277,79
4.500,00 17.581.995,00
3.019,03 851.366,46
18.433.361,46
189.254.555,
2.269.496.971,
2.570.020.3
3.033.004.639,25
PRICE AMOUNT
3.033.004.639,25
10.981,24 619.341,94
15.549,15 3.880.601,37
122.616,07 4.322.216,47
8.822.159,78
198.076.715,
2.278.319.131,
2.578.842.4
3.041.826.799,03
PRICE AMOUNT
3.041.826.799,03
2.550,00 8.888.076,00
19.445,72 28.926.480,79
124.626,56 18.450.962,21
56.265.519,00
254.342.234,
61
2.334.584.650,
2.635.108.0
3.098.092.318,03
PRICE AMOUNT
1.996, 3.098.092.318,03
11 1.751.486,72
1.996, 3.098.092.318,03
11 1.751.486,72
1.751.486,72
1.751.486,72
2.336.336.137,
2.636.859.4
3.099.843.804,75
PRICE AMOUNT
6.753, 3.099.843.804,75
42 93.853.628,42
93.853.628,42
95.605.115,1
2.430.189.765,
2.730.713.1
3.193.697.433,17
PRICE AMOUNT
3.043,88 3.193.697.433,17
5.234,30 22.338.883,13
2.652,95 20.731.492,01
4.452,45 8.834.323,50
581,39 14.826.658,50
3.883.220,09
70.614.577,23
166.219.692,
2.500.804.342,
2.801.327.6
3.264.312.010,40
PRICE AMOUNT
3.264.312.010,40
16.001,24 19.297.495,44
11.800,00 6.605.640,00
25.903.135,44
192.122.827,
2.526.707.478,
2.827.230.8
3.290.215.145,84
PRICE AMOUNT
3.290.215.145,84
4.500,00 14.963.400,00
3.019,03 724.567,20
15.687.967,20
207.810.795,
2.542.395.445,
2.842.918.7
3.305.903.113,04
PRICE AMOUNT
3.305.903.113,04
10.981,24 527.099,52
15.549,15 3.302.639,46
122.616,07 3.678.482,10
7.508.221,08
215.319.016,
2.549.903.666,
2.850.427.0
3.313.411.334,12
PRICE AMOUNT
3.313.411.334,12
2.550,00 7.564.320,00
19.445,72 24.618.281,52
124.626,56 15.702.946,56
47.885.548,08
263.204.564,
17
2.597.789.214,
2.898.312.5
3.361.296.882,20
PRICE AMOUNT
1.996, 3.361.296.882,20
11 1.751.486,72
11
1.751.486,72
1.751.486,72
2.599.540.701,
2.900.064.0
3.363.048.368,92
PRICE AMOUNT
6.753, 3.363.048.368,92
42 52.377.229,36
52.377.229,36
54.128.716,0
2.651.917.930,
2.952.441.2
3.415.425.598,28
PRICE AMOUNT
108.379,99 3.415.425.598,28
3.043,88 5.042.920,93
5.234,30 17.468.918,64
8.904,90 20.297.725,57
581,39 16.356.342,22
2.144.212,83
61.310.120,19
115.438.836,
2.713.228.050,
3.013.751.4
3.476.735.718,47
PRICE AMOUNT
11.721 3.476.735.718,47
,36 1.547.219,52
8.033, 17.497.333,26
67 3.633.102,00
11.800
,00
22.677.654,78
138.116.491,
2.735.905.705,
3.036.429.0
3.499.413.373,25
PRICE AMOUNT
3.499.413.373,25
4.500,00 8.229.870,00
3.019,03 398.511,96
8.628.381,96
146.744.873,
2.744.534.087,
3.045.057.4
3.508.041.755,21
PRICE AMOUNT
3.508.041.755,21
10.981,24 289.904,74
15.549,15 1.816.451,70
122.616,07 2.023.165,16
4.129.521,60
150.874.394,
2.748.663.609,
3.049.186.9
3.512.171.276,81
PRICE AMOUNT
3.512.171.276,81
2.550,00 4.160.376,00
19.445,72 13.540.054,84
124.626,56 8.636.620,61
26.337.051,45
177.211.446,
06
2.775.000.660,
3.075.524.0
3.538.508.328,26
PRICE AMOUNT
1.996, 3.538.508.328,26
11 2.221.450,86
2.221.450,86
2.221.450,86
2.777.222.111,
3.077.745.4
3.540.729.779,12
PRICE AMOUNT
6.753, 3.540.729.779,12
42 16.642.587,97
42
16.642.587,97
18.864.038,8
2.793.864.699,
3.094.388.0
3.557.372.367,09
PRICE AMOUNT
3.043,88 3.557.372.367,09
2.652,95 1.590.670,81
581,39 1.379.162,59
303.032,10
3.272.865,50
22.136.904,3
2.797.137.564,
3.097.660.9
3.560.645.232,59
PRICE AMOUNT
7.352, 3.560.645.232,59
36 124.990,12
124.990,12
22.261.894,4
2.797.262.555,
3.097.785.9
3.560.770.222,71
PRICE AMOUNT
3.560.770.222,71
4.500,00 2.349.315,00
3.019,03 102.647,02
2.451.962,02
24.713.856,4
2.799.714.517,
3.100.237.8
3.563.222.184,73
PRICE AMOUNT
3.563.222.184,73
10.981,24 95.207,35
15.549,15 600.041,70
122.616,07 938.012,94
1.633.261,99
26.347.118,4
2.801.347.779,
3.101.871.1
3.564.855.446,72
PRICE AMOUNT
3.564.855.446,72
2.550,00 1.189.957,50
19.445,72 13.262.369,95
124.626,56 9.116.196,07
23.568.523,52
49.915.641,9
8
2.824.916.302,
3.125.439.6
3.588.423.970,24
PRICE AMOUNT
1.996, 3.588.423.970,24
11 2.221.450,86
1.996, 3.588.423.970,24
11 2.221.450,86
2.221.450,86
2.221.450,86
2.827.137.753,
3.127.661.1
3.590.645.421,10
PRICE AMOUNT
6.753, 3.590.645.421,10
42 42.543.169,29
42.543.169,29
44.764.620,1
2.869.680.922,
3.170.204.2
3.633.188.590,39
PRICE AMOUNT
3.043,88 3.633.188.590,39
4.452,45 22.849.341,80
581,39 5.870.021,03
770.492,91
29.489.855,74
74.254.475,8
2.899.170.778,
3.199.694.1
3.662.678.446,13
PRICE AMOUNT
7.352, 3.662.678.446,13
36 3.812.786,85
3.812.786,85
78.067.262,7
2.902.983.565,
3.203.506.9
3.666.491.232,98
PRICE AMOUNT
3.666.491.232,98
4.500,00 5.942.385,00
3.019,03 259.636,58
6.202.021,58
84.269.284,3
2.909.185.586,
3.209.708.9
3.672.693.254,56
PRICE AMOUNT
3.672.693.254,56
10.981,24 240.818,59
15.549,15 1.517.752,53
122.616,07 2.372.620,95
4.131.192,07
88.400.476,3
2.913.316.779,
3.213.840.1
3.676.824.446,63
PRICE AMOUNT
3.676.824.446,63
2.550,00 3.009.892,50
19.445,72 21.013.045,03
124.626,56 14.624.690,03
38.647.627,56
127.048.103,
95
2.951.964.406,
3.252.487.7
3.715.472.074,19
PRICE AMOUNT
1.996, 3.715.472.074,19
11 2.221.450,86
1.996, 3.715.472.074,19
11 2.221.450,86
2.221.450,86
2.221.450,86
2.954.185.857,
3.254.709.2
3.717.693.525,05
PRICE AMOUNT
6.753, 3.717.693.525,05
42 16.998.493,21
16.998.493,21
19.219.944,0
2.971.184.350,
3.271.707.7
3.734.692.018,26
PRICE AMOUNT
3.043,88 3.734.692.018,26
5.234,30 3.795.261,78
2.652,95 3.754.825,11
4.452,45 1.386.378,61
581,39 2.326.761,32
609.226,95
11.872.453,77
31.092.397,8
2.983.056.804,
3.283.580.1
3.746.564.472,03
PRICE AMOUNT
3.746.564.472,03
16.001,24 3.280.574,22
11.800,00 935.858,00
4.216.432,22
35.308.830,0
2.987.273.236,
3.287.796.5
3.750.780.904,25
PRICE AMOUNT
3.750.780.904,25
4.500,00 2.349.315,00
3.019,03 102.647,02
2.451.962,02
37.760.792,0
2.989.725.198,
3.290.248.5
3.753.232.866,27
PRICE AMOUNT
3.753.232.866,27
10.981,24 95.207,35
15.549,15 600.041,70
122.616,07 938.012,94
1.633.261,99
39.394.054,0
2.991.358.460,
3.291.881.8
3.754.866.128,26
PRICE AMOUNT
3.754.866.128,26
2.550,00 1.189.957,50
19.445,72 13.262.369,95
124.626,56 9.116.196,07
23.568.523,52
62.962.577,5
9
3.014.926.984,
3.315.450.3
3.778.434.651,78
PRICE AMOUNT
1.996, 3.778.434.651,78
11 2.221.450,86
11
2.221.450,86
2.221.450,86
3.017.148.435,
3.317.671.7
3.780.656.102,64
PRICE AMOUNT
6.753, 3.780.656.102,64
42 9.211.935,02
9.211.935,02
11.433.385,8
3.026.360.370,
3.326.883.7
3.789.868.037,66
PRICE AMOUNT
108.379,99 3.789.868.037,66
3.043,88 763.168,54
5.234,30 2.935.365,68
11.131,12 3.569.897,29
581,39 3.095.564,47
324.520,27
10.688.516,25
22.121.902,1
3.037.048.886,
3.337.572.2
3.800.556.553,91
PRICE AMOUNT
3.800.556.553,91
8.033,67 2.169.090,90
11.800,00 495.482,00
2.664.572,90
24.786.475,0
3.039.713.459,
3.340.236.8
3.803.221.126,81
PRICE AMOUNT
3.803.221.126,81
4.500,00 1.243.755,00
3.019,03 54.342,54
1.298.097,54
26.084.572,5
3.041.011.556,
3.341.534.9
3.804.519.224,35
PRICE AMOUNT
3.804.519.224,35
10.981,24 50.403,89
15.549,15 317.669,13
122.616,07 496.595,08
864.668,10
26.949.240,6
3.041.876.224,
3.342.399.5
3.805.383.892,45
PRICE AMOUNT
3.805.383.892,45
2.550,00 629.977,50
19.445,72 10.877.546,85
124.626,56 7.421.274,86
18.928.799,21
45.878.039,8
8
3.060.805.024,
3.361.328.3
3.824.312.691,66
PRICE AMOUNT
3.824.312.691,66
16.967,86 805.973,35
112.276,18 1.039.958,12
2.550,00 1.000.084,50
10.981,24 82.139,68
10.981,24 3.623,81
15.549,15 1.049.878,61
122.616,07 1.986.968,89
19.445,72 6.536.289,86
124.626,56 5.864.701,59
3.079.174.642,
3.379.697.9
3.842.682.310,07
PRICE AMOUNT
3.842.682.310,07
18.369.618,41
18.369.618,4
1
3.079.174.642,
3.379.697.9
3.842.682.310,07
PRICE AMOUNT
16.967,86 3.842.682.310,07
112.276,18 431.832,04
2.550,00 657.208,62
10.981,24 1.230.120,00
15.549,15 98.831,16
122.616,07 1.264.145,90
19.445,72 2.392.484,76
124.626,56 7.755.925,42
7.953.168,55
21.783.716,45
21.783.716,4
5
3.100.958.358,
3.401.481.7
3.864.466.026,52
PRICE AMOUNT
114.300,00 3.864.466.026,52
139.000,00 1.828.800,00
80.600,00 2.224.000,00
46.000,00 2.337.400,00
200.000,00 828.000,00
150.000,00 200.000,00
1.618,68 150.000,00
183.396,44
7.751.596,44
7.751.596,44
3.108.709.955,
3.409.233.3
3.872.217.622,96
PRICE AMOUNT
3.872.217.622,96
5.800.973,20
15.855.940,74
15.837.198,30
57.311.372,94
57.311.372,9
3.158.269.731,
3.458.793.0
3.921.777.399,46
2.549,
15
5.725,
82
2.549,
15
5.725,
82
8.872,
38
PRICE AMOUNT
3.921.777.399,46
10.715,51 12.065.664,26
33.500,00 311.550,00
57.622.922,94
57.622.922,9
3.158.581.281,
3.459.104.6
3.922.088.949,46
PRICE AMOUNT
3.922.088.949,46
12.463,60 55.399.455,64
1.950,00 4.393.740,00
59.793.195,64
117.416.118,
3.218.374.477,
3.518.897.8
3.981.882.145,10
PRICE AMOUNT
3.981.882.145,10
40.300,00 282.100,00
47.650,00 428.850,00
20.000,00 27.516.000,00
10.000,00 700.000,00
280.000,00 5.600.000,00
12.000.000,00 12.000.000,00
10.000.000,00 10.000.000,00
56.526.950,00
173.943.068,
3.274.901.427,
3.575.424.7
4.038.409.095,10
PRICE AMOUNT
4.038.409.095,10
1.900.000,00 17.100.000,00
500.000,00 4.500.000,00
21.600.000,00
195.543.068,
3.296.501.427,
3.597.024.7
4.060.009.095,10
PRICE AMOUNT
5.500.000,00 4.060.009.095,10
11.000.000,00
11.000.000,00
206.543.068,
3.307.501.427,
3.608.024.7
4.071.009.095,10
PRICE AMOUNT
5.500,00 4.071.009.095,10
110.000,00 52.800.000,00
220.000,00 990.000,00
660.000,00
54.450.000,00
260.993.068,
3.361.951.427,
3.662.474.7
4.125.459.095,10
PRICE AMOUNT
21.900,00 4.125.459.095,10
1.000.000,00 43.800,00
1.601,34 2.000.000,00
1.890,91 23.779.963,05
10.486.986,86
36.310.749,91
297.303.818,
3.398.262.177,
3.698.785.5
4.161.769.845,01
PRICE AMOUNT
4.161.769.845,01
48.000,00 1.584.000,00
73.600,00 147.200,00
38.041.949,91
299.035.018,
49
3.399.993.377,
39
3.700.516.7
4.163.501.045,01
PRICE AMOUNT
6.753, 4.163.501.045,01
42 1.446.920,24
42
1.446.920,24
1.446.920,24
1.446.920,24
3.701.963.6
4.164.947.965,25
PRICE AMOUNT
3.043,88 4.164.947.965,25
2.652,95 409.219,23
581,39 351.781,17
77.627,19
838.627,59
2.285.547,83
2.285.547,83
3.702.802.2
4.165.786.592,84
PRICE AMOUNT
7.352, 4.165.786.592,84
36 84.552,14
84.552,14
2.370.099,97
2.370.099,97
3.702.886.8
4.165.871.144,98
PRICE AMOUNT
4.165.871.144,98
4.500,00 615.825,00
3.019,03 69.437,69
685.262,69
3.055.362,66
3.055.362,66
3.703.572.0
4.166.556.407,67
PRICE AMOUNT
4.166.556.407,67
10.981,24 51.831,45
15.549,15 118.018,05
122.616,07 282.016,96
14.258,95 195.917,97
647.784,43
3.703.147,09
3.703.147,09
3.704.219.8
4.167.204.192,10
PRICE AMOUNT
4.167.204.192,10
2.550,00 282.412,50
19.445,72 695.573,40
124.626,56 358.301,36
1.336.287,26
5.039.434,35
5.039.434,35
3.705.556.1
4.168.540.479,36
PRICE AMOUNT
6.753, 4.168.540.479,36
42 4.413.224,90
42
4.413.224,90
4.413.224,90
9.452.659,25
3.709.969.3
4.172.953.704,26
PRICE AMOUNT
3.043,88 4.172.953.704,26
4.452,45 2.022.019,05
581,39 1.757.560,11
232.660,65
4.012.239,81
8.425.464,71
13.464.899,06
3.713.981.6
4.176.965.944,07
PRICE AMOUNT
7.352, 4.176.965.944,07
36 1.624.871,56
1.624.871,56
10.050.336,2
15.089.770,62
3.715.606.4
4.178.590.815,63
PRICE AMOUNT
4.178.590.815,63
4.500,00 1.820.700,00
3.019,03 205.294,04
2.025.994,04
12.076.330,3
17.115.764,66
3.717.632.4
4.180.616.809,67
PRICE AMOUNT
4.180.616.809,67
10.981,24 153.078,49
15.549,15 348.922,93
122.616,07 833.789,28
14.258,95 579.341,14
1.915.131,84
13.991.462,1
19.030.896,50
3.719.547.6
4.182.531.941,51
PRICE AMOUNT
4.182.531.941,51
2.550,00 834.921,00
19.445,72 2.056.190,43
124.626,56 1.059.325,76
3.950.437,19
17.941.899,3
4
22.981.333,69
3.723.498.0
4.186.482.378,70
PRICE AMOUNT
6.753, 4.186.482.378,70
42 6.090.301,69
42
6.090.301,69
6.090.301,69
29.071.635,38
3.729.588.3
4.192.572.680,39
PRICE AMOUNT
3.043,88 4.192.572.680,39
5.234,30 2.446.244,60
2.652,95 1.345.319,79
4.452,45 1.411.104,11
581,39 2.368.258,16
622.715,20
8.193.641,86
14.283.943,5
37.265.277,24
3.737.782.0
4.200.766.322,25
PRICE AMOUNT
4.200.766.322,25
8.212,36 1.627.279,13
11.800,00 1.379.892,00
3.007.171,13
17.291.114,6
40.272.448,37
3.740.789.1
4.203.773.493,38
PRICE AMOUNT
4.203.773.493,38
4.500,00 2.436.525,00
3.019,03 274.731,73
2.711.256,73
20.002.371,4
42.983.705,10
3.743.500.4
4.206.484.750,11
PRICE AMOUNT
4.206.484.750,11
10.981,24 204.909,94
15.549,15 466.940,97
122.616,07 1.115.806,24
14.258,95 775.259,11
2.562.916,26
22.565.287,6
45.546.621,36
3.746.063.3
4.209.047.666,37
PRICE AMOUNT
4.209.047.666,37
2.550,00 1.117.333,50
19.445,72 2.751.763,84
124.626,56 1.417.627,12
5.286.724,46
27.852.012,1
3
50.833.345,82
3.751.350.0
4.214.334.390,83
PRICE AMOUNT
6.753, 4.214.334.390,83
42 6.371.379,03
6.371.379,03
6.371.379,03
57.204.724,85
3.757.721.4
4.220.705.769,86
PRICE AMOUNT
108.379,99 4.220.705.769,86
3.043,88 171.478,82
5.234,30 3.174.523,33
2.652,95 2.469.124,00
4.452,45 1.476.207,50
581,39 2.477.521,28
651.453,31
10.420.308,24
16.791.687,2
67.625.033,09
3.768.141.7
4.231.126.078,10
PRICE AMOUNT
4.231.126.078,10
8.033,67 6.118.443,07
11.800,00 1.443.494,00
7.561.937,07
24.353.624,3
75.186.970,16
3.775.703.6
4.238.688.015,17
PRICE AMOUNT
4.238.688.015,17
4.500,00 2.548.980,00
3.019,03 287.411,66
2.836.391,66
27.190.016,0
78.023.361,82
3.778.540.0
4.241.524.406,83
PRICE AMOUNT
4.241.524.406,83
10.981,24 214.353,80
15.549,15 488.554,29
122.616,07 1.167.304,99
14.258,95 811.049,08
2.681.262,16
29.871.278,1
80.704.623,98
3.781.221.3
4.244.205.668,99
PRICE AMOUNT
4.244.205.668,99
2.550,00 1.168.894,50
19.445,72 2.878.744,39
124.626,56 1.483.056,06
5.530.694,95
35.401.973,1
1
86.235.318,93
3.786.752.0
4.249.736.363,94
PRICE AMOUNT
4.249.736.363,94
6.753, 4.128.095,51
42
4.128.095,51
4.128.095,51
90.363.414,44
3.790.880.1
4.253.864.459,45
PRICE AMOUNT
4.253.864.459,45
108.379,99 623.455,89
3.043,88 1.635.446,29
5.234,30 2.812.337,05
2.652,95 601.131,94
5.672.371,17
9.800.466,68
96.035.785,61
3.796.552.5
4.259.536.830,62
PRICE AMOUNT
4.259.536.830,62
4.452,45 1.008.880,65
581,39 265.137,10
6.946.388,92
11.074.484,4
97.309.803,36
3.797.826.5
4.260.810.848,37
PRICE AMOUNT
4.260.810.848,37
11.721,36 304.755,36
8.033,67 2.610.942,75
11.800,00 984.002,00
3.899.700,11
14.974.184,5
101.209.503,47
3.801.726.2
4.264.710.548,48
PRICE AMOUNT
4.264.710.548,48
4.500,00 1.023.165,00
3.019,03 78.494,78
1.101.659,78
16.075.844,3
102.311.163,25
3.802.827.8
4.265.812.208,26
PRICE AMOUNT
4.265.812.208,26
10.981,24 109.482,96
15.549,15 183.946,44
122.616,07 398.502,23
14.258,95 493.074,49
1.185.006,12
17.260.850,4
103.496.169,37
3.804.012.8
4.266.997.214,38
PRICE AMOUNT
4.266.997.214,38
2.550,00 502.885,50
19.445,72 1.454.345,40
124.626,56 1.786.023,23
3.743.254,13
21.004.104,5
7
107.239.423,50
3.807.756.1
4.270.740.468,51
PRICE AMOUNT
6.753, 4.270.740.468,51
42 2.579.266,17
42
2.579.266,17
2.579.266,17
2.579.266,17
3.810.335.4
4.273.319.734,68
PRICE AMOUNT
3.043,88 4.273.319.734,68
2.652,95 729.465,84
581,39 627.077,79
138.376,63
1.494.920,26
4.074.186,43
4.074.186,43
3.811.830.3
4.274.814.654,94
PRICE AMOUNT
7.352, 4.274.814.654,94
36 150.723,38
150.723,38
4.224.909,81
4.224.909,81
3.811.981.0
4.274.965.378,32
PRICE AMOUNT
4.274.965.378,32
4.500,00 1.097.775,00
3.019,03 123.780,23
1.221.555,23
5.446.465,04
5.446.465,04
3.813.202.6
4.276.186.933,55
PRICE AMOUNT
4.276.186.933,55
10.981,24 92.352,23
15.549,15 210.380,00
122.616,07 502.725,89
14.258,95 349.344,28
1.154.802,40
6.601.267,44
6.601.267,44
3.814.357.4
4.277.341.735,95
PRICE AMOUNT
4.277.341.735,95
2.550,00 503.421,00
19.445,72 1.239.859,11
124.626,56 638.711,12
2.381.991,23
8.983.258,67
8.983.258,67
3.816.739.4
4.279.723.727,18
PRICE AMOUNT
6.753, 4.279.723.727,18
42 6.684.737,72
42
6.684.737,72
6.684.737,72
15.667.996,39
3.823.424.1
4.286.408.464,90
PRICE AMOUNT
3.043,88 4.286.408.464,90
4.452,45 3.062.782,49
581,39 2.662.208,90
352.415,36
6.077.406,75
12.762.144,4
21.745.403,14
3.829.501.5
4.292.485.871,65
PRICE AMOUNT
7.352, 4.292.485.871,65
36 2.461.202,51
2.461.202,51
15.223.346,9
24.206.605,65
3.831.962.7
4.294.947.074,16
PRICE AMOUNT
4.294.947.074,16
4.500,00 2.757.825,00
3.019,03 310.960,09
3.068.785,09
18.292.132,0
27.275.390,74
3.835.031.5
4.298.015.859,25
PRICE AMOUNT
4.298.015.859,25
10.981,24 231.923,79
15.549,15 528.515,61
122.616,07 1.262.945,52
14.258,95 877.495,78
2.900.880,70
21.193.012,7
30.176.271,44
3.837.932.4
4.300.916.739,95
PRICE AMOUNT
4.300.916.739,95
2.550,00 1.264.672,50
19.445,72 3.114.620,97
124.626,56 1.604.566,96
5.983.860,43
27.176.873,2
0
36.160.131,87
3.843.916.2
4.306.900.600,38
PRICE AMOUNT
6.753, 4.306.900.600,38
42 2.743.982,08
42
2.743.982,08
2.743.982,08
38.904.113,95
3.846.660.2
4.309.644.582,46
PRICE AMOUNT
3.043,88 4.309.644.582,46
5.234,30 1.102.036,75
2.652,95 606.131,94
4.452,45 635.779,47
581,39 1.067.029,64
280.567,19
3.691.544,99
6.435.527,07
42.595.658,94
3.850.351.8
4.313.336.127,45
PRICE AMOUNT
4.313.336.127,45
8.212,36 733.199,50
11.800,00 621.742,00
1.354.941,50
7.790.468,57
43.950.600,44
3.851.706.7
4.314.691.068,95
PRICE AMOUNT
4.314.691.068,95
4.500,00 1.097.775,00
3.019,03 123.780,23
1.221.555,23
9.012.023,80
45.172.155,67
3.852.928.3
4.315.912.624,18
PRICE AMOUNT
4.315.912.624,18
10.981,24 92.352,23
15.549,15 210.380,00
122.616,07 502.725,89
14.258,95 349.344,28
1.154.802,40
10.166.826,2
46.326.958,07
3.854.083.1
4.317.067.426,58
PRICE AMOUNT
4.317.067.426,58
2.550,00 503.421,00
19.445,72 1.239.859,11
124.626,56 638.711,12
2.381.991,23
12.548.817,4
3
48.708.949,30
3.856.465.1
4.319.449.417,81
PRICE AMOUNT
6.753, 4.319.449.417,81
42 5.487.964,16
5.487.964,16
5.487.964,16
54.196.913,46
3.861.953.0
4.324.937.381,97
PRICE AMOUNT
108.379,99 4.324.937.381,97
3.043,88 171.478,82
5.234,30 2.734.347,84
2.652,95 2.126.748,43
4.452,45 1.271.532,41
581,39 2.134.014,76
561.122,74
8.999.245,00
14.487.209,1
63.196.158,46
3.870.952.3
4.333.936.626,97
PRICE AMOUNT
4.333.936.626,97
8.033,67 5.270.087,52
11.800,00 1.243.366,00
6.513.453,52
21.000.662,6
69.709.611,98
3.877.465.7
4.340.450.080,49
PRICE AMOUNT
4.340.450.080,49
4.500,00 2.195.550,00
3.019,03 247.560,46
2.443.110,46
23.443.773,1
72.152.722,44
3.879.908.8
4.342.893.190,95
PRICE AMOUNT
4.342.893.190,95
10.981,24 184.594,64
15.549,15 420.760,00
122.616,07 1.005.451,77
14.258,95 698.688,55
2.309.494,96
25.753.268,1
74.462.217,40
3.882.218.3
4.345.202.685,91
PRICE AMOUNT
4.345.202.685,91
2.550,00 1.006.816,50
19.445,72 2.479.523,76
124.626,56 1.277.422,24
4.763.762,50
30.517.030,6
0
79.225.979,90
3.886.982.1
4.349.966.448,41
PRICE AMOUNT
4.349.966.448,41
6.753, 4.128.095,51
42
4.128.095,51
4.128.095,51
83.354.075,41
3.891.110.2
4.354.094.543,92
PRICE AMOUNT
4.354.094.543,92
108.379,99 623.455,89
3.043,88 1.635.446,29
5.234,30 2.812.337,05
2.652,95 601.131,94
5.672.371,17
9.800.466,68
89.026.446,58
3.896.782.5
4.359.766.915,09
PRICE AMOUNT
4.359.766.915,09
4.452,45 1.008.880,65
581,39 265.137,10
6.946.388,92
11.074.484,4
90.300.464,33
3.898.056.6
4.361.040.932,84
PRICE AMOUNT
4.361.040.932,84
11.721,36 304.755,36
8.033,67 2.610.942,75
11.800,00 984.002,00
3.899.700,11
14.974.184,5
94.200.164,44
3.901.956.3
4.364.940.632,95
PRICE AMOUNT
4.364.940.632,95
4.500,00 1.023.165,00
3.019,03 78.494,78
1.101.659,78
16.075.844,3
95.301.824,22
3.903.057.9
4.366.042.292,73
PRICE AMOUNT
4.366.042.292,73
10.981,24 109.482,96
15.549,15 183.946,44
122.616,07 398.502,23
14.258,95 493.074,49
1.185.006,12
17.260.850,4
96.486.830,34
3.904.242.9
4.367.227.298,85
PRICE AMOUNT
4.367.227.298,85
2.550,00 502.885,50
19.445,72 1.454.345,40
124.626,56 1.786.023,23
3.743.254,13
21.004.104,5
7
100.230.084,47
3.907.986.2
4.370.970.552,98
PRICE AMOUNT
6.753, 4.370.970.552,98
42 1.132.345,93
42
1.132.345,93
1.132.345,93
1.132.345,93
3.909.118.5
4.372.102.898,91
PRICE AMOUNT
3.043,88 4.372.102.898,91
2.652,95 320.246,61
581,39 275.296,62
60.749,44
656.292,67
1.788.638,60
1.788.638,60
3.909.774.8
4.372.759.191,58
PRICE AMOUNT
7.352, 4.372.759.191,58
36 66.171,24
66.171,24
1.854.809,84
1.854.809,84
3.909.841.0
4.372.825.362,82
PRICE AMOUNT
4.372.825.362,82
4.500,00 481.950,00
3.019,03 54.342,54
536.292,54
2.391.102,38
2.391.102,38
3.910.377.3
4.373.361.655,36
PRICE AMOUNT
4.373.361.655,36
10.981,24 40.520,78
15.549,15 92.361,95
122.616,07 220.708,93
14.258,95 153.426,30
507.017,96
2.898.120,34
2.898.120,34
3.910.884.3
4.373.868.673,32
PRICE AMOUNT
4.373.868.673,32
2.550,00 221.008,50
19.445,72 544.285,70
124.626,56 280.409,76
1.045.703,96
3.943.824,30
3.943.824,30
3.911.930.0
4.374.914.377,28
PRICE AMOUNT
6.753, 4.374.914.377,28
42 3.439.719,41
42
3.439.719,41
3.439.719,41
7.383.543,71
3.915.369.7
4.378.354.096,69
PRICE AMOUNT
3.043,88 4.378.354.096,69
4.452,45 1.575.999,31
581,39 1.369.885,29
181.341,35
3.127.225,95
6.566.945,36
10.510.769,66
3.918.497.0
4.381.481.322,64
PRICE AMOUNT
7.352, 4.381.481.322,64
36 1.266.444,01
1.266.444,01
7.833.389,37
11.777.213,67
3.919.763.4
4.382.747.766,65
PRICE AMOUNT
4.382.747.766,65
4.500,00 1.419.075,00
3.019,03 160.008,59
1.579.083,59
9.412.472,96
13.356.297,26
3.921.342.5
4.384.326.850,24
PRICE AMOUNT
4.384.326.850,24
10.981,24 119.366,08
15.549,15 271.954,63
122.616,07 649.865,17
14.258,95 451.580,95
1.492.766,83
10.905.239,7
14.849.064,09
3.922.835.3
4.385.819.617,07
PRICE AMOUNT
4.385.819.617,07
2.550,00 650.760,00
19.445,72 1.602.716,24
124.626,56 825.650,96
3.079.127,20
13.984.366,9
9
17.928.191,29
3.925.914.4
4.388.898.744,27
PRICE AMOUNT
6.753, 4.388.898.744,27
42 4.751.773,85
42
4.751.773,85
4.751.773,85
22.679.965,14
3.930.666.2
4.393.650.518,12
PRICE AMOUNT
3.043,88 4.393.650.518,12
5.234,30 1.908.725,83
2.652,95 1.049.634,18
4.452,45 1.100.974,25
581,39 1.847.766,75
485.856,00
6.392.957,01
11.144.730,8
29.072.922,15
3.937.059.1
4.400.043.475,13
PRICE AMOUNT
4.400.043.475,13
8.212,36 1.269.630,86
11.800,00 1.076.632,00
2.346.262,86
13.490.993,7
31.419.185,01
3.939.405.4
4.402.389.737,99
PRICE AMOUNT
4.402.389.737,99
4.500,00 1.901.025,00
3.019,03 214.351,13
2.115.376,13
15.606.369,8
33.534.561,14
3.941.520.7
4.404.505.114,12
PRICE AMOUNT
4.404.505.114,12
10.981,24 159.886,85
15.549,15 364.316,58
122.616,07 870.574,10
14.258,95 604.864,66
1.999.642,19
17.606.012,0
35.534.203,33
3.943.520.4
4.406.504.756,31
PRICE AMOUNT
4.406.504.756,31
2.550,00 871.768,50
19.445,72 2.147.001,95
124.626,56 1.106.060,72
4.124.831,17
21.730.843,2
1
39.659.034,50
3.947.645.2
4.410.629.587,48
PRICE AMOUNT
6.753, 4.410.629.587,48
42 6.471.802,39
6.471.802,39
6.471.802,39
46.130.836,89
3.954.117.0
4.417.101.389,87
PRICE AMOUNT
108.379,99 4.417.101.389,87
3.043,88 171.478,82
5.234,30 3.224.534,28
2.652,95 2.508.014,85
4.452,45 1.499.473,87
581,39 2.516.569,26
661.714,84
10.581.785,92
17.053.588,3
56.712.622,81
3.964.698.8
4.427.683.175,79
PRICE AMOUNT
4.427.683.175,79
8.033,67 6.214.847,11
11.800,00 1.466.268,00
7.681.115,11
24.734.703,4
64.393.737,92
3.972.379.9
4.435.364.290,90
PRICE AMOUNT
4.435.364.290,90
4.500,00 2.589.165,00
3.019,03 291.940,20
2.881.105,20
27.615.808,6
67.274.843,12
3.975.261.0
4.438.245.396,10
PRICE AMOUNT
4.438.245.396,10
10.981,24 217.648,18
15.549,15 496.173,38
122.616,07 1.185.697,40
14.258,95 823.882,13
2.723.401,09
30.339.209,7
69.998.244,21
3.977.984.4
4.440.968.797,19
PRICE AMOUNT
4.440.968.797,19
2.550,00 1.187.305,50
19.445,72 2.924.052,92
124.626,56 1.506.423,54
5.617.781,96
35.956.991,6
7
75.616.026,17
3.983.602.2
4.446.586.579,15
PRICE AMOUNT
4.446.586.579,15
6.753, 4.128.095,51
42
4.128.095,51
4.128.095,51
79.744.121,68
3.987.730.3
4.450.714.674,66
PRICE AMOUNT
4.450.714.674,66
108.379,99 623.455,89
3.043,88 1.635.446,29
5.234,30 2.812.337,05
2.652,95 601.131,94
5.672.371,17
9.800.466,68
85.416.492,85
3.993.402.7
4.456.387.045,83
PRICE AMOUNT
4.456.387.045,83
4.452,45 1.008.880,65
581,39 265.137,10
6.946.388,92
11.074.484,4
86.690.510,60
3.994.676.7
4.457.661.063,58
PRICE AMOUNT
4.457.661.063,58
11.721,36 304.755,36
8.033,67 2.610.942,75
11.800,00 984.002,00
3.899.700,11
14.974.184,5
90.590.210,71
3.998.576.4
4.461.560.763,69
PRICE AMOUNT
4.461.560.763,69
4.500,00 1.023.165,00
3.019,03 78.494,78
1.101.659,78
16.075.844,3
91.691.870,49
3.999.678.1
4.462.662.423,47
PRICE AMOUNT
4.462.662.423,47
10.981,24 109.482,96
15.549,15 183.946,44
122.616,07 398.502,23
14.258,95 493.074,49
1.185.006,12
17.260.850,4
92.876.876,61
4.000.863.1
4.463.847.429,59
PRICE AMOUNT
4.463.847.429,59
2.550,00 502.885,50
19.445,72 1.454.345,40
124.626,56 1.786.023,23
3.743.254,13
21.004.104,5
7
96.620.130,74
4.004.606.3
4.467.590.683,72
PRICE AMOUNT
6.753, 4.467.590.683,72
42 3.753.010,56
6.753,
42
3.753.010,56
3.753.010,56
3.753.010,56
4.008.359.3
4.471.343.694,28
PRICE AMOUNT
108.379,99 4.471.343.694,28
3.043,88 256.990,63
2.652,95 1.886.048,93
4.452,45 1.643.820,88
581,39 2.758.827,07
720.487,56
7.266.175,07
11.019.185,6
11.019.185,63
4.015.625.5
4.478.609.869,35
PRICE AMOUNT
4.500, 4.478.609.869,35
00 2.920.320,00
2.920.320,00
13.939.505,6
13.939.505,63
4.018.545.8
4.481.530.189,35
PRICE AMOUNT
10.981 4.481.530.189,35
,24 250.482,08
,24
250.482,08
14.189.987,7
14.189.987,71
4.018.796.3
4.481.780.671,43
PRICE AMOUNT
2.550,00 4.481.780.671,43
19.445,72 1.441.566,00
124.626,56 4.507.128,98
2.731.427,85
8.680.122,83
22.870.110,5
4
22.870.110,54
4.027.476.4
4.490.460.794,26
PRICE AMOUNT
6.753, 4.490.460.794,26
42 200.441,51
200.441,51
200.441,51
23.070.552,05
4.027.676.9
4.490.661.235,77
PRICE AMOUNT
108.379,99 4.490.661.235,77
3.043,88 20.678,90
2.652,95 125.986,19
4.452,45 109.805,60
581,39 184.286,91
48.127,46
488.885,06
689.326,57
23.559.437,11
4.028.165.8
4.491.150.120,83
PRICE AMOUNT
4.500, 4.491.150.120,83
00 197.820,00
00
197.820,00
887.146,57
23.757.257,11
4.028.363.6
4.491.347.940,83
PRICE AMOUNT
10.981 4.491.347.940,83
,24 11.420,49
11.420,49
898.567,06
23.768.677,60
4.028.375.0
4.491.359.361,32
PRICE AMOUNT
2.550,00 4.491.359.361,32
19.445,72 83.563,50
124.626,56 280.990,65
170.476,67
535.030,82
1.433.597,88
24.303.708,42
4.028.910.0
4.491.894.392,14
PRICE AMOUNT
6.753, 4.491.894.392,14
42 2.436.296,27
2.436.296,27
2.436.296,27
26.740.004,69
4.031.346.3
4.494.330.688,41
PRICE AMOUNT
108.379,99 4.494.330.688,41
3.043,88 357.881,56
2.652,95 1.254.139,44
4.452,45 1.084.181,08
581,39 1.804.667,03
474.547,96
4.975.417,07
7.411.713,34
31.715.421,76
4.036.321.7
4.499.306.105,48
PRICE AMOUNT
4.500, 4.499.306.105,48
00 925.020,00
00
925.020,00
8.336.733,34
32.640.441,76
4.037.246.8
4.500.231.125,48
PRICE AMOUNT
10.981 4.500.231.125,48
,24 75.770,56
75.770,56
8.412.503,90
32.716.212,32
4.037.322.5
4.500.306.896,04
PRICE AMOUNT
2.550,00 4.500.306.896,04
19.445,72 715.300,50
124.626,56 2.622.644,26
1.590.546,47
4.928.491,23
13.340.995,1
3
37.644.703,55
4.042.251.0
71,06
4.505.235.387,27
PRICE AMOUNT
4.505.235.387,27
110.464,93 162.383,45
16.220,39 238.439,73
400.823,18
400.823,18
400.823,18
400.823,18
4.505.636.210,45
PRICE AMOUNT
4.505.636.210,45
110.464,93 231.313,56
16.220,39 339.654,97
570.968,53
570.968,53
971.791,71
971.791,71
4.506.207.178,98
PRICE AMOUNT
4.506.207.178,98
110.464,93 206.127,56
16.220,39 302.672,48
508.800,04
508.800,04
1.480.591,75
1.480.591,7
4.506.715.979,02
PRICE AMOUNT
PRICE AMOUNT
4.506.715.979,02
110.464,93 479.196,87
16.220,39 703.640,52
1.182.837,39
1.182.837,39
2.663.429,14
2.663.429,1
4.507.898.816,41
PRICE AMOUNT
4.507.898.816,41
110.464,93 288.092,54
16.220,39 423.027,77
711.120,31
711.120,31
3.374.549,45
3.374.549,4
4.508.609.936,72
PRICE AMOUNT
4.508.609.936,72
110.464,93 386.958,65
16.220,39 568.200,26
955.158,91
955.158,91
4.329.708,36
4.329.708,3
4.509.565.095,63
PRICE AMOUNT
4.509.565.095,63
110.464,93 244.900,75
16.220,39 359.606,05
604.506,80
604.506,80
4.934.215,16
4.934.215,1
4.510.169.602,43
PRICE AMOUNT
PRICE AMOUNT
4.510.169.602,43
110.464,93 273.511,17
16.220,39 401.616,86
675.128,03
675.128,03
5.609.343,19
5.609.343,1
4.510.844.730,46
PRICE AMOUNT
4.510.844.730,46
110.464,93 223.912,41
16.220,39 328.787,31
552.699,72
552.699,72
6.162.042,91
6.162.042,9
4.511.397.430,18
PRICE AMOUNT
31 4.511.397.430,18
9, 7.566,94
82
9,
82
7.566,94
7.566,94
7.566,94
6.169.609,8
4.511.404.997,12
PRICE AMOUNT
9.893,01 4.511.404.997,12
110.464,93 9.002,64
110.464,93 17.232,53
7.780,00 37.558,08
11.720,00 373.440,00
16.220,39 439.500,00
15.188,18 68.936,66
2.900,00 29.616,95
58.000,00
1.033.286,86
1.040.853,80
1.040.853,80
7.202.896,7
4.512.438.283,98
PRICE AMOUNT
31 4.512.438.283,98
9, 16.685,01
82
16.685,01
16.685,01
1.057.538,81
7.219.581,7
4.512.454.968,99
PRICE AMOUNT
9.893,01 4.512.454.968,99
110.464,93 14.344,86
110.464,93 27.483,67
7.780,00 114.971,90
11.720,00 622.400,00
16.220,39 966.900,00
15.188,18 211.027,27
2.900,00 47.235,24
116.000,00
2.120.362,94
2.137.047,95
3.177.901,75
9.339.944,6
4.514.575.331,93
PRICE AMOUNT
31 4.514.575.331,93
9, 57.714,72
82
9,
82
57.714,72
57.714,72
3.235.616,47
9.397.659,3
4.514.633.046,65
PRICE AMOUNT
9.893,01 4.514.633.046,65
110.464,93 97.841,87
110.464,93 480.566,63
7.780,00 2.070.731,39
20.140,00 4.823.600,00
16.220,39 6.605.920,00
15.188,18 3.800.761,78
2.900,00 825.933,23
522.000,00
19.227.354,90
22.462.971,37
28.625.014,
4.533.860.401,55
PRICE AMOUNT
4.533.860.401,55
19.285.069,6
2
22.462.971,37
28.625.014,
4.533.860.401,55
PRICE AMOUNT
31 4.533.860.401,55
9, 303.157,38
82
303.157,38
303.157,38
22.766.128,75
28.928.171,
4.534.163.558,93
PRICE AMOUNT
9.893,01 4.534.163.558,93
110.464,93 206.269,26
110.464,93 523.603,77
7.780,00 2.745.009,32
11.720,00 9.102.600,00
16.220,39 17.287.000,00
15.188,18 5.038.377,54
899.899,67
35.802.759,56
36.105.916,9
58.568.888,31
64.730.931,
4.569.966.318,49
PRICE AMOUNT
2.900, 4.569.966.318,49
00 1.406.500,00
37.209.259,56
37.512.416,9
4
59.975.388,31
66.137.431,
4.571.372.818,49
PRICE AMOUNT
1.996,11 4.571.372.818,49
12.172,63 2.109.309,40
9.577,26 4.331.630,39
73,42 852.950,78
785.094,74
8.078.985,31
8.078.985,31
8.078.985,31
74.216.416,
4.579.451.803,80
PRICE AMOUNT
4.579.451.803,80
38 4.064.108,14
3,
49
4.064.108,14
4.064.108,14
12.143.093,45
78.280.524,
4.583.515.911,94
PRICE AMOUNT
4.583.515.911,94
364,83 585.169,08
1.500,45 16.941.130,82
17.526.299,90
21.590.408,0
4
29.669.393,35
95.806.824,
4.601.042.211,84
PRICE AMOUNT
4.601.042.211,84
8.500,00 3.101.055,00
521,01 190.080,08
7.780,00 3.360.960,00
6.652.095,08
6.652.095,08
36.321.488,43
102.458.919
4.607.694.306,92
PRICE AMOUNT
4.607.694.306,92
9.893,01 4.581.551,86
13.966,07 42.711.314,60
110.464,93 55.741.310,65
103.034.177,11
103.034.177,
139.355.665,54
205.493.096
4.710.728.484,03
PRICE AMOUNT
4.710.728.484,03
110.464,93 78.486.061,83
16.220,39 60.771.799,79
139.257.861,62
242.292.038,
278.613.527,16
344.750.958
4.849.986.345,65
PRICE AMOUNT
4.849.986.345,65
24.081,94 40.520.994,70
666,05 4.558.406,24
1.464,50 760.075,50
2.800,00 23.874.396,00
2.800,00 1.916.292,00
71.630.164,44
313.922.203,
350.243.691,60
416.381.122
4.921.616.510,09
PRICE AMOUNT
4.921.616.510,09
112.276,18 59.533.591,15
17.501,69 45.287.373,04
104.820.964,19
418.743.167,
36
455.064.655,79
521.202.087
5.026.437.474,28
PRICE AMOUNT
5.026.437.474,28
5.116,63 11.972.914,20
1.996,11 1.145.846,98
13.966,07 1.742.825,88
33.500,00 26.130.000,00
40.991.587,06
40.991.587,0
6
496.056.242,85
562.193.674
5.067.429.061,34
PRICE AMOUNT
5.067.429.061,34
1.500,45 2.307.962,18
114,66 2.088.074,41
16.000,00 222.723.200,00
227.119.236,59
227.119.236,
59
723.175.479,44
789.312.910
5.294.548.297,93
PRICE AMOUNT
5.294.548.297,93
8.500,00 16.473.000,00
666,05 1.290.804,90
11.720,00 68.069.760,00
3.000,00 3.870.000,00
89.703.564,90
89.703.564,9
0
89.703.564,90
879.016.475
5.384.251.862,83
PRICE AMOUNT
5.384.251.862,83
8.500, 15.038.200,00
00
15.038.200,00
15.038.200,0
15.038.200,00
894.054.675
5.399.290.062,83
PRICE AMOUNT
5.399.290.062,83
66 1.178.375,66
6,
05
16.216.575,66
16.216.575,6
16.216.575,66
895.233.051
5.400.468.438,49
PRICE AMOUNT
5.400.468.438,49
11.720,00 29.557.840,00
3.000,00 3.528.000,00
49.302.415,66
49.302.415,6
6
49.302.415,66
928.318.891
,22
5.433.554.278,49
PRICE AMOUNT
38 5.433.554.278,49
3, 1.621.468,58
49
3,
49
1.621.468,58
1.621.468,58
1.621.468,58
1.621.468,5
5.435.175.747,07
PRICE AMOUNT
36 5.435.175.747,07
4, 292.141,27
83
292.141,27
1.913.609,85
1.913.609,85
1.913.609,8
5.435.467.888,34
PRICE AMOUNT
4.900, 5.435.467.888,34
00 2.695.000,00
2.695.000,00
4.608.609,85
4.608.609,85
4.608.609,8
5.438.162.888,34
PRICE AMOUNT
1.996,11 5.438.162.888,34
12.172,63 8.106.921,31
9.577,26 11.683.046,82
73,42 2.326.795,32
891.869,45
23.008.632,90
27.617.242,7
5
27.617.242,75
27.617.242,
5.461.171.521,24
PRICE AMOUNT
5.461.171.521,24
1.745, 949.585,78
53
949.585,78
949.585,78
28.566.828,53
28.566.828,
5.462.121.107,02
PRICE AMOUNT
5.462.121.107,02
8.500, 12.155.000,00
00
12.155.000,00
12.155.000,0
12.155.000,00
40.721.828,
5.474.276.107,02
PRICE AMOUNT
5.474.276.107,02
66 952.451,50
6,
05
13.107.451,50
13.107.451,5
13.107.451,50
41.674.280,
5.475.228.558,52
PRICE AMOUNT
5.475.228.558,52
7.780,00 21.784.000,00
3.000,00 2.844.000,00
37.735.451,50
37.735.451,5
0
37.735.451,50
66.302.280,
5.499.856.558,52
PRICE AMOUNT
5.499.856.558,52
8.500,00 39.763.000,00
666,05 3.115.781,90
9.350,00 65.608.950,00
11.720,00 131.582.784,00
6.000,00 70.170.000,00
310.240.515,90
310.240.515,
310.240.515,90
376.542.795
5.810.097.074,42
PRICE AMOUNT
3.000, 5.810.097.074,42
00 9.270.000,00
319.510.515,90
319.510.515,
90
319.510.515,90
385.812.795
5.819.367.074,42
PRICE AMOUNT
5.819.367.074,42
40.400,00 26.664.000,00
53.000,00 61.745.000,00
88.409.000,00
88.409.000,0
0
407.919.515,90
474.221.795
5.907.776.074,42
PRICE AMOUNT
11 5.907.776.074,42
9, 9.563,22
93
9,
93
9.563,22
9.563,22
9.563,22
474.231.359
5.907.785.637,64
PRICE AMOUNT
36 5.907.785.637,64
4, 5.031,01
83
5.031,01
14.594,23
14.594,23
474.236.390
5.907.790.668,65
PRICE AMOUNT
11.539,20 5.907.790.668,65
13.966,07 53.080,32
110.464,93 374.011,35
14.843,16 295.825,08
110.464,93 595.359,15
437.000,00 443.074,83
109.250,00
1.870.600,73
1.885.194,96
1.885.194,96
476.106.990
5.909.661.269,38
PRICE AMOUNT
11 5.909.661.269,38
9, 7.861,41
93
93
7.861,41
7.861,41
1.893.056,37
476.114.852
5.909.669.130,79
PRICE AMOUNT
36 5.909.669.130,79
4, 11.696,45
83
11.696,45
19.557,86
1.904.752,82
476.126.548
5.909.680.827,24
PRICE AMOUNT
16.857,39 5.909.680.827,24
11.539,20 211.391,67
13.966,07 51.234,05
110.464,93 18.435,21
14.843,16 8.748,82
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
519.759,05
539.316,91
2.424.511,87
476.646.307
5.910.200.586,29
PRICE AMOUNT
11 5.910.200.586,29
9, 37.492,52
93
9,
93
37.492,52
37.492,52
2.462.004,39
476.683.800
5.910.238.078,81
PRICE AMOUNT
36 5.910.238.078,81
4, 11.791,31
83
11.791,31
49.283,83
2.473.795,70
476.695.591
5.910.249.870,12
PRICE AMOUNT
11.539,20 5.910.249.870,12
13.966,07 105.468,29
110.464,93 354.738,18
14.843,16 280.580,92
110.464,93 1.003.100,75
437.000,00 746.522,00
109.250,00
2.599.660,14
2.648.943,97
5.073.455,84
479.295.251
5.912.849.530,26
PRICE AMOUNT
11 5.912.849.530,26
9, 8.746,49
93
93
8.746,49
8.746,49
5.082.202,33
479.303.998
5.912.858.276,75
PRICE AMOUNT
36 5.912.858.276,75
4, 12.608,52
83
12.608,52
21.355,01
5.094.810,85
479.316.606
5.912.870.885,27
PRICE AMOUNT
18.507,00 5.912.870.885,27
11.539,20 244.292,40
13.966,07 56.080,51
110.464,93 18.435,21
14.843,16 14.581,37
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
563.338,79
584.693,80
5.658.149,64
479.879.945
5.913.434.224,06
PRICE AMOUNT
11 5.913.434.224,06
9, 8.563,00
93
93
8.563,00
8.563,00
5.666.712,64
479.888.508
5.913.442.787,06
PRICE AMOUNT
36 5.913.442.787,06
4, 12.969,71
83
12.969,71
21.532,71
5.679.682,35
479.901.478
5.913.455.756,77
PRICE AMOUNT
16.857,39 5.913.455.756,77
11.539,20 235.160,59
13.966,07 55.388,16
110.464,93 18.435,21
14.843,16 14.581,37
110.464,93 94.254,07
437.000,00 70.145,23
65.550,00
553.514,63
575.047,34
6.233.196,98
480.454.992
5.914.009.271,40
PRICE AMOUNT
11 5.914.009.271,40
9, 21.158,05
93
9,
93
21.158,05
21.158,05
6.254.355,03
480.476.150
5.914.030.429,45
PRICE AMOUNT
36 5.914.030.429,45
4, 21.867,91
83
21.867,91
43.025,96
6.276.222,94
480.498.018
5.914.052.297,36
PRICE AMOUNT
11.539,20 5.914.052.297,36
13.966,07 58.619,14
110.464,93 184.491,78
14.843,16 145.924,17
110.464,93 678.035,55
437.000,00 504.603,80
109.250,00
1.680.924,44
1.723.950,40
7.957.147,38
482.178.943
5.915.733.221,80
PRICE AMOUNT
31 5.915.733.221,80
9, 224.513,64
82
224.513,64
224.513,64
224.513,64
482.403.456
5.915.957.735,44
PRICE AMOUNT
9.893,01 5.915.957.735,44
110.464,93 89.037,09
110.464,93 434.789,96
7.780,00 1.155.286,42
11.720,00 4.201.200,00
16.220,39 7.500.800,00
15.188,18 2.120.491,58
2.900,00 747.258,46
362.500,00
16.611.363,51
16.835.877,15
499.014.820
5.932.569.098,95
PRICE AMOUNT
5.932.569.098,95
16.835.877,1
5
16.835.877,15
499.014.820
5.932.569.098,95
PRICE AMOUNT
31 5.932.569.098,95
9, 23.282,90
82
23.282,90
23.282,90
16.859.160,05
499.038.103
5.932.592.381,85
PRICE AMOUNT
9.893,01 5.932.592.381,85
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 166.227,63
11.720,00 871.360,00
16.220,39 2.373.300,00
15.188,18 305.105,54
2.900,00 91.129,08
188.500,00
4.076.345,85
4.099.628,75
20.935.505,90
503.114.449
5.936.668.727,70
PRICE AMOUNT
31 5.936.668.727,70
9, 11.641,45
82
9,
82
11.641,45
11.641,45
20.947.147,35
503.126.090
5.936.680.369,15
PRICE AMOUNT
9.893,01 5.936.680.369,15
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 56.646,42
11.720,00 435.680,00
16.220,39 1.142.700,00
15.188,18 103.972,70
2.900,00 45.564,54
87.000,00
1.911.925,45
1.923.566,90
22.859.072,80
505.038.016
5.938.592.294,60
PRICE AMOUNT
31 5.938.592.294,60
9, 11.641,45
82
11.641,45
11.641,45
22.870.714,25
505.049.657
5.938.603.936,05
PRICE AMOUNT
9.893,01 5.938.603.936,05
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 56.646,42
11.720,00 435.680,00
16.220,39 1.142.700,00
15.188,18 103.972,70
2.900,00 45.564,54
87.000,00
1.911.925,45
1.923.566,90
24.782.639,70
506.961.583
5.940.515.861,50
PRICE AMOUNT
31 5.940.515.861,50
9, 11.641,45
82
9,
82
11.641,45
11.641,45
24.794.281,15
506.973.224
5.940.527.502,95
PRICE AMOUNT
9.893,01 5.940.527.502,95
110.464,93 13.850,21
110.464,93 26.511,58
7.780,00 58.148,74
11.720,00 272.300,00
16.220,39 421.920,00
15.188,18 106.730,17
2.900,00 45.564,54
87.000,00
1.032.025,24
1.043.666,69
25.826.306,39
508.005.249
5.941.559.528,19
PRICE AMOUNT
31 5.941.559.528,19
9, 23.282,90
82
23.282,90
23.282,90
25.849.589,29
508.028.532
5.941.582.811,09
PRICE AMOUNT
9.893,01 5.941.582.811,09
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 116.297,48
11.720,00 544.600,00
16.220,39 843.840,00
15.188,18 213.460,33
2.900,00 91.129,08
188.500,00
2.078.550,49
2.101.833,39
27.928.139,78
510.107.083
5.943.661.361,58
PRICE AMOUNT
31 5.943.661.361,58
9, 23.282,90
82
9,
82
23.282,90
23.282,90
27.951.422,68
510.130.365
5.943.684.644,48
PRICE AMOUNT
9.893,01 5.943.684.644,48
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 116.297,48
11.720,00 544.600,00
16.220,39 843.840,00
15.188,18 213.460,33
2.900,00 91.129,08
188.500,00
2.078.550,49
2.101.833,39
30.029.973,17
512.208.916
5.945.763.194,97
PRICE AMOUNT
31 5.945.763.194,97
9, 23.282,90
82
23.282,90
23.282,90
30.053.256,07
512.232.199
5.945.786.477,87
PRICE AMOUNT
9.893,01 5.945.786.477,87
110.464,93 27.700,43
110.464,93 53.023,17
7.780,00 112.674,23
11.720,00 809.120,00
16.220,39 2.373.300,00
15.188,18 206.809,97
2.900,00 91.129,08
188.500,00
3.862.256,88
3.885.539,78
33.915.512,95
5.949.648.734,75
PRICE AMOUNT
5.949.648.734,75
516.094.456
,26
5.949.648.734,75
PRICE AMOUNT
PRICE AMOUNT
69 5.949.648.734,75
,5 11.655.853,73
8
11.655.853,
73
5.961.304.588,48
PRICE AMOUNT
29.700.000,00 5.961.304.588,48
11.880.000,00 29.700.000,00
132.000,00 11.880.000,00
1.320.000,00 132.000,00
2.508.000,00 1.320.000,00
10.560.000,00 2.508.000,00
264.000,00 10.560.000,00
132.000,00 264.000,00
660.000,00 132.000,00
132.000,00 660.000,00
132.000,00
57.288.000,0
0
57.288.000,00
57.288.000,
6.018.592.588,48
PRICE AMOUNT
15.972.000,00 6.018.592.588,48
13.200.000,00 15.972.000,00
2.376.000,00 13.200.000,00
10.560.000,00 2.376.000,00
3.036.000,00 10.560.000,00
5.148.000,00 3.036.000,00
1.584.000,00 5.148.000,00
132.000,00 1.584.000,00
1.980.000,00 132.000,00
264.000,00 1.980.000,00
16.500.000,00 264.000,00
132.000,00 16.500.000,00
528.000,00 132.000,00
528.000,00
71.412.000,00
71.412.000,0
128.700.000,00
128.700.000
6.090.004.588,48
PRICE AMOUNT
2.640.000,00 6.090.004.588,48
660.000,00 2.640.000,00
660.000,00
74.712.000,0
0
132.000.000,00
132.000.000
6.093.304.588,48
PRICE AMOUNT
4.488.000,00 6.093.304.588,48
1.848.000,00 67.320.000,00
2.244.000,00 3.696.000,00
396.000,00 13.464.000,00
3.960.000,00 396.000,00
3.300.000,00 3.960.000,00
4.620.000,00 3.300.000,00
396.000,00 4.620.000,00
924.000,00 396.000,00
3.960.000,00 924.000,00
1.320.000,00 3.960.000,00
1.320.000,00
4.488.000,00 6.093.304.588,48
1.848.000,00 67.320.000,00
2.244.000,00 3.696.000,00
396.000,00 13.464.000,00
3.960.000,00 396.000,00
3.300.000,00 3.960.000,00
4.620.000,00 3.300.000,00
396.000,00 4.620.000,00
924.000,00 396.000,00
3.960.000,00 924.000,00
1.320.000,00 3.960.000,00
1.320.000,00
103.356.000,
00
103.356.000,00
235.356.000
6.196.660.588,48
PRICE AMOUNT
PRICE AMOUNT
15.840.000,00 6.196.660.588,48
264.000,00 63.360.000,00
3.300.000,00 264.000,00
2.772.000,00 3.300.000,00
3.696.000,00 2.772.000,00
396.000,00 3.696.000,00
792.000,00 396.000,00
3.300.000,00 792.000,00
1.056.000,00 3.300.000,00
1.056.000,00
78.936.000,0
0
182.292.000,00
314.292.000
6.275.596.588,48
PRICE AMOUNT
1.056.000,00 6.275.596.588,48
330.000,00 1.056.000,00
1.056.000,00 1.320.000,00
528.000,00 7.392.000,00
132.000,00 2.112.000,00
2.640.000,00 4.752.000,00
3.960.000,00 2.640.000,00
132.000,00 3.960.000,00
660.000,00 132.000,00
1.980.000,00 660.000,00
1.584.000,00 1.980.000,00
132.000,00 1.584.000,00
528.000,00 132.000,00
528.000,00
28.248.000,00
28.248.000,0
28.248.000,00
342.540.000
6.303.844.588,48
PRICE AMOUNT
1.320.000,00 6.303.844.588,48
792.000,00 1.320.000,00
792.000,00
30.360.000,0
0
30.360.000,00
344.652.000
6.305.956.588,48
PRICE AMOUNT
4.620.000,00 6.305.956.588,48
1.320.000,00 9.240.000,00
1.980,00 2.640.000,00
594.000,00 2.772.000,00
1.320.000,00 7.128.000,00
660.000,00 1.320.000,00
132.000,00 660.000,00
924.000,00 132.000,00
1.980.000,00 924.000,00
3.960.000,00 1.980.000,00
132.000,00 3.960.000,00
264.000,00 132.000,00
1.056.000,00 264.000,00
1.056.000,00
4.620.000,00 6.305.956.588,48
1.320.000,00 9.240.000,00
1.980,00 2.640.000,00
594.000,00 2.772.000,00
1.320.000,00 7.128.000,00
660.000,00 1.320.000,00
132.000,00 660.000,00
924.000,00 132.000,00
1.980.000,00 924.000,00
3.960.000,00 1.980.000,00
132.000,00 3.960.000,00
264.000,00 132.000,00
1.056.000,00 264.000,00
1.056.000,00
32.208.000,00
32.208.000,0
62.568.000,00
376.860.000
6.338.164.588,48
PRICE AMOUNT
396.000,00 6.338.164.588,48
396.000,00
32.604.000,0
0
62.964.000,00
377.256.000
6.338.560.588,48
PRICE AMOUNT
1.320.000,00 6.338.560.588,48
924.000,00 1.320.000,00
237.600,00 924.000,00
264.000,00 3.088.800,00
396.000,00 792.000,00
1.320.000,00 792.000,00
1.584.000,00 1.320.000,00
264.000,00 1.584.000,00
132.000,00 264.000,00
924.000,00 132.000,00
1.320.000,00 924.000,00
3.300.000,00 1.320.000,00
3.300.000,00
15.760.800,00
15.760.800,0
78.724.800,00
393.016.800
6.354.321.388,48
PRICE AMOUNT
132.000,00 6.354.321.388,48
198.000,00 132.000,00
792.000,00 198.000,00
396.000,00 792.000,00
396.000,00
17.278.800,0
0
80.242.800,00
394.534.800
6.355.839.388,48
PRICE AMOUNT
2.244.000,00 6.355.839.388,48
3.300.000,00 6.732.000,00
660.000,00 3.300.000,00
528.000,00 660.000,00
132.000,00 528.000,00
660.000,00 132.000,00
1.056.000,00 660.000,00
1.320.000,00 1.056.000,00
132.000,00 1.320.000,00
264.000,00 132.000,00
132.000,00 264.000,00
264.000,00 132.000,00
264.000,00
15.180.000,0
0
95.422.800,00
409.714.800
6.371.019.388,48
PRICE AMOUNT
396.000,00 6.371.019.388,48
660.000,00 792.000,00
1.320.000,00 1.320.000,00
198.000,00 13.200.000,00
1.584.000,00 2.376.000,00
1.056.000,00 1.584.000,00
66.000,00 5.280.000,00
264.000,00 396.000,00
1.320.000,00 264.000,00
9.900.000,00 1.320.000,00
528.000,00 9.900.000,00
198.000,00 5.280.000,00
1.056.000,00 1.980.000,00
1.056.000,00
44.748.000,00
44.748.000,0
140.170.800,00
454.462.800
6.415.767.388,48
PRICE AMOUNT
396.000,00 6.415.767.388,48
5.280.000,00 396.000,00
3.960.000,00 5.280.000,00
3.300.000,00 3.960.000,00
660.000,00 3.300.000,00
1.980.000,00 660.000,00
2.640.000,00 1.980.000,00
660.000,00 2.640.000,00
660.000,00
63.624.000,0
0
159.046.800,00
473.338.800
6.434.643.388,48
PRICE AMOUNT
10.824.000,00 6.434.643.388,48
4.884.000,00 10.824.000,00
1.782.000,00 9.768.000,00
1.320,00 1.782.000,00
528,00 1.320.000,00
132.000,00 528.000,00
660,00 132.000,00
264.000,00 198.000,00
2.970.000,00 264.000,00
132.000,00 2.970.000,00
792.000,00 132.000,00
594.000,00 792.000,00
2.970.000,00 594.000,00
2.970.000,00
32.274.000,00
32.274.000,0
191.320.800,00
505.612.800
6.466.917.388,48
PRICE AMOUNT
330.000,00 6.466.917.388,48
264.000,00 330.000,00
528.000,00 264.000,00
396.000,00 528.000,00
396.000,00
33.792.000,0
0
192.838.800,00
507.130.800
6.468.435.388,48
PRICE AMOUNT
1.716.000,00 6.468.435.388,48
2.640.000,00 18.876.000,00
660.000,00 2.640.000,00
2.640.000,00 660.000,00
396.000,00 2.640.000,00
132.000,00 396.000,00
660.000,00 132.000,00
1.980.000,00 660.000,00
2.640.000,00 1.980.000,00
132.000,00 2.640.000,00
396.000,00 132.000,00
1.980.000,00 396.000,00
1.980.000,00
226.234.800,00
540.526.800
6.501.831.388,48
132.000,00 2.640.000,00
396.000,00 132.000,00
1.980.000,00 396.000,00
1.980.000,00
226.234.800,00
540.526.800
6.501.831.388,48
PRICE AMOUNT
264.000,00 6.501.831.388,48
264.000,00
264.000,00
33.396.000,0
0
226.234.800,00
540.526.800
6.501.831.388,48
PRICE AMOUNT
PRICE AMOUNT
5.940.000,00 6.501.831.388,48
3.960.000,00 5.940.000,00
1.584.000,00 3.960.000,00
44.220.000,00 1.584.000,00
132.000,00 44.220.000,00
2.640.000,00 132.000,00
1.320.000,00 2.640.000,00
15.840.000,00 1.320.000,00
132.000,00 15.840.000,00
264.000,00 132.000,00
1.980.000,00 264.000,00
132.000,00 1.980.000,00
132.000,00
78.144.000,0
0
618.670.800
6.579.975.388,48
PRICE AMOUNT
6.579.975.388,48
304.378.800,00
618.670.800
6.579.975.388,48
PRICE AMOUNT
3.300.000,00 6.579.975.388,48
990.000,00 3.300.000,00
528.000,00 1.980.000,00
264.000,00 528.000,00
132.000,00 264.000,00
1.320.000,00 132.000,00
528.000,00 1.320.000,00
1.980.000,00 528.000,00
132.000,00 1.980.000,00
528.000,00 132.000,00
660.000,00 528.000,00
396.000,00 660.000,00
396.000,00
11.748.000,0
0
11.748.000,00
6.591.723.388,48
PRICE AMOUNT
6.591.723.388,48
630.418.800
,00
6.591.723.388,
48
1.488.326,69
11.641,45
1.476.685,24
4.249.974,25
23.282,90
4.226.691,35
4.249.974,25
23.282,90
4.226.691,35
1.043.666,69
11.641,45
1.032.025,24
16.835.877,15
224.513,64
16.611.363,51
4.042.251.071,
06
24.934.578,82
23.013.083,42
23.013.083,42
1.921.495,40
1.921.495,40
151.558.736,59
125.537.408,65
3.450.896,12
5.411.903,89
116.674.608,64
26.021.327,94
3.537.735,67
6.840.429,02
5.918.163,25
9.725.000,00
124.030.036,00
107.971.857,09
2.885.639,53
5.974.001,55
99.112.216,01
16.058.178,91
4.385.473,04
6.039.736,07
3.482.969,80
2.150.000,00
3.399.993.377,39
73.658.776,41
1.616.589,61
39.382.568,73
9.265.520,58
400.703,62
6.975.349,27
1.739.417,53
14.278.627,07
216.141.826,13
1.616.589,61
100.256.680,99
48.143.937,10
8.325.150,75
17.534.364,22
4.372.285,33
35.892.818,13
159.874.101,31
1.616.589,61
55.954.583,47
42.833.410,81
15.892.667,52
9.663.098,53
4.724.000,18
29.189.751,19
267.656.895,58
1.616.589,61
77.490.091,76
92.055.359,97
37.045.880,51
13.182.770,18
6.444.556,43
39.821.647,12
389.742.328,62
1.616.589,61
76.500.580,67
143.932.549,95
103.183.941,77
11.839.378,46
8.473.661,34
44.195.626,82
891.513.136,76
2.390.082,23
150.727.960,16
340.722.508,16
232.224.000,00
21.978.961,84
49.456.583,83
94.013.040,54
81.655.350,99
1.751.486,72
39.683.095,92
9.036.359,87
382.322,72
6.798.119,12
3.253.562,47
20.750.404,17
254.342.234,61
1.751.486,72
108.935.365,97
51.270.704,08
8.863.637,60
18.433.361,46
8.822.159,78
56.265.519,00
263.204.564,17
1.751.486,72
93.853.628,42
70.614.577,23
25.903.135,44
15.687.967,20
7.508.221,08
47.885.548,08
177.211.446,06
1.751.486,72
52.377.229,36
61.310.120,19
22.677.654,78
8.628.381,96
4.129.521,60
26.337.051,45
49.915.641,98
2.221.450,86
16.642.587,97
3.272.865,50
124.990,12
2.451.962,02
1.633.261,99
23.568.523,52
127.048.103,95
2.221.450,86
42.543.169,29
29.489.855,74
3.812.786,85
6.202.021,58
4.131.192,07
38.647.627,56
62.962.577,59
2.221.450,86
16.998.493,21
11.872.453,77
4.216.432,22
2.451.962,02
1.633.261,99
23.568.523,52
45.878.039,88
2.221.450,86
9.211.935,02
10.688.516,25
2.664.572,90
1.298.097,54
864.668,10
18.928.799,21
18.369.618,41
18.369.618,41
21.783.716,45
21.783.716,45
299.035.018,49
57.622.922,94
59.793.195,64
56.526.950,00
21.600.000,00
11.000.000,00
54.450.000,00
38.041.949,91
107.239.423,50
5.039.434,35
1.446.920,24
838.627,59
84.552,14
685.262,69
647.784,43
1.336.287,26
17.941.899,34
4.413.224,90
4.012.239,81
1.624.871,56
2.025.994,04
1.915.131,84
3.950.437,19
27.852.012,13
6.090.301,69
8.193.641,86
3.007.171,13
2.711.256,73
2.562.916,26
5.286.724,46
35.401.973,11
6.371.379,03
10.420.308,24
7.561.937,07
2.836.391,66
2.681.262,16
5.530.694,95
21.004.104,57
4.128.095,51
6.946.388,92
3.899.700,11
1.101.659,78
1.185.006,12
3.743.254,13
100.230.084,47
8.983.258,67
2.579.266,17
1.494.920,26
150.723,38
1.221.555,23
1.154.802,40
2.381.991,23
27.176.873,20
6.684.737,72
6.077.406,75
2.461.202,51
3.068.785,09
2.900.880,70
5.983.860,43
12.548.817,43
2.743.982,08
3.691.544,99
1.354.941,50
1.221.555,23
1.154.802,40
2.381.991,23
30.517.030,60
5.487.964,16
8.999.245,00
6.513.453,52
2.443.110,46
2.309.494,96
4.763.762,50
21.004.104,57
4.128.095,51
6.946.388,92
3.899.700,11
1.101.659,78
1.185.006,12
3.743.254,13
96.620.130,74
3.943.824,30
1.132.345,93
656.292,67
66.171,24
536.292,54
507.017,96
1.045.703,96
13.984.366,99
3.439.719,41
3.127.225,95
1.266.444,01
1.579.083,59
1.492.766,83
3.079.127,20
21.730.843,21
4.751.773,85
6.392.957,01
2.346.262,86
2.115.376,13
1.999.642,19
4.124.831,17
35.956.991,67
6.471.802,39
10.581.785,92
7.681.115,11
2.881.105,20
2.723.401,09
5.617.781,96
21.004.104,57
4.128.095,51
6.946.388,92
3.899.700,11
1.101.659,78
1.185.006,12
3.743.254,13
37.644.703,55
22.870.110,54
3.753.010,56
7.266.175,07
2.920.320,00
250.482,08
8.680.122,83
1.433.597,88
200.441,51
488.885,06
197.820,00
11.420,49
535.030,82
13.340.995,13
2.436.296,27
4.975.417,07
925.020,00
75.770,56
4.928.491,23
928.318.891,2
2
6.162.042,91
400.823,18
400.823,18
570.968,53
570.968,53
508.800,04
508.800,04
1.182.837,39
1.182.837,39
711.120,31
711.120,31
955.158,91
955.158,91
604.506,80
604.506,80
675.128,03
675.128,03
552.699,72
552.699,72
59.975.388,31
1.040.853,80
7.566,94
1.033.286,86
2.137.047,95
16.685,01
2.120.362,94
19.285.069,62
57.714,72
19.227.354,90
37.512.416,94
303.157,38
37.209.259,56
723.175.479,44
8.078.985,31
8.078.985,31
21.590.408,04
4.064.108,14
17.526.299,90
6.652.095,08
6.652.095,08
418.743.167,36
103.034.177,11
139.257.861,62
71.630.164,44
104.820.964,19
40.991.587,06
40.991.587,06
227.119.236,59
227.119.236,59
89.703.564,90
89.703.564,90
89.703.564,90
49.302.415,66
49.302.415,66
49.302.415,66
516.094.456,2
6
28.566.828,53
27.617.242,75
1.621.468,58
292.141,27
2.695.000,00
23.008.632,90
949.585,78
949.585,78
37.735.451,50
37.735.451,50
37.735.451,50
407.919.515,90
319.510.515,90
319.510.515,90
88.409.000,00
88.409.000,00
7.957.147,38
1.885.194,96
9.563,22
5.031,01
1.870.600,73
539.316,91
7.861,41
11.696,45
519.759,05
2.648.943,97
37.492,52
11.791,31
2.599.660,14
584.693,80
8.746,49
12.608,52
563.338,79
575.047,34
8.563,00
12.969,71
553.514,63
1.723.950,40
21.158,05
21.867,91
1.680.924,44
33.915.512,95
16.835.877,15
224.513,64
16.611.363,51
4.099.628,75
23.282,90
4.076.345,85
1.923.566,90
11.641,45
1.911.925,45
1.923.566,90
11.641,45
1.911.925,45
1.043.666,69
11.641,45
1.032.025,24
2.101.833,39
23.282,90
2.078.550,49
2.101.833,39
23.282,90
2.078.550,49
3.885.539,78
23.282,90
3.862.256,88
11.655.853,73
630.418.800,0
0
132.000.000,00
57.288.000,00
74.712.000,00
182.292.000,00
103.356.000,00
78.936.000,00
304.378.800,00
30.360.000,00
32.604.000,00
17.278.800,00
15.180.000,00
63.624.000,00
33.792.000,00
33.396.000,00
78.144.000,00
11.748.000,00
11.748.000,00
6.591.723.388,48
6.591.723.388,48