Pipe Calculation

Pipe ID=1 peak


Pipe data: length=95.935m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>76.2827/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =76.2827/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.007819m/m
Head loss, HL =S*L =0.007819*95.94
=0.750113m
Total Head loss, HL total =0.750113
Pipe Calculation
Pipe ID=1 average
Pipe data: length=95.935m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>36.6157/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =36.6157/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002008m/m
Head loss, HL =S*L =0.002008*95.94
=0.192678m
Total Head loss, HL total =0.192678
Pipe Calculation
Pipe ID=2 peak
Pipe data: length=70.015m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*70.02
=0.129391m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=2 average
Pipe data: length=70.015m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*70.02
=0.033260m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=3 peak
Pipe data: length=25.973m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*25.97
=0.065123m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=3 average
Pipe data: length=25.973m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*25.97
=0.016717m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=4 peak
Pipe data: length=24.333m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*24.33
=0.044968m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=4 average
Pipe data: length=24.333m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*24.33
=0.011559m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=5 peak
Pipe data: length=34.291m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*34.29
=0.085979m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=5 average
Pipe data: length=34.291m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*34.29
=0.022071m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=6 peak
Pipe data: length=37.621m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*37.62
=0.069525m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=6 average
Pipe data: length=37.621m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*37.62
=0.017872m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=7 peak
Pipe data: length=49.893m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*49.89
=0.125098m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=7 average
Pipe data: length=49.893m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*49.89
=0.032113m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=8 peak
Pipe data: length=51.974m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*51.97
=0.096050m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=8 average
Pipe data: length=51.974m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*51.97
=0.024690m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=9 peak
Pipe data: length=34.148m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*34.15
=0.085620m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=9 average
Pipe data: length=34.148m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*34.15
=0.021979m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=10 peak
Pipe data: length=32.05m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*32.05
=0.080360m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=10 average
Pipe data: length=32.05m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.0650.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*32.05
=0.020629m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=11 peak
Pipe data: length=45.284m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>41.2761/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =41.2761/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.002507m/m
Head loss, HL =S*L =0.002507*45.28
=0.113542m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=11 average
Pipe data: length=45.284m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>19.8058/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =19.8058/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000644m/m
Head loss, HL =S*L =0.000644*45.28
=0.029147m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=12 peak
Pipe data: length=46.509m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*46.51
=0.085950m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=12 average
Pipe data: length=46.509m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*46.51
=0.022094m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=13 peak
Pipe data: length=37.172m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*37.17
=0.068695m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=13 average
Pipe data: length=37.172m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*37.17
=0.017658m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=14 peak
Pipe data: length=33.084m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =-0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>35.0066/0.05 =0.8492*130*-0.0650.63S0.54/1000
=>S0.54 =35.0066/0.05*1/(0.8492*130*-0.0650.63)/1000
=>S =0.001848m/m
Head loss, HL =S*L =0.001848*33.08
=0.061141m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=14 average
Pipe data: length=33.084m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =-0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>16.8098/0.05 =0.8492*130*-0.0650.63S0.54/1000
=>S0.54 =16.8098/0.05*1/(0.8492*130*-0.0650.63)/1000
=>S =0.000475m/m
Head loss, HL =S*L =0.000475*33.08
=0.015716m
Total Head loss, HL total =0.000000
Pipe Calculation
Pipe ID=15 peak
Pipe data: length=20.338m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>28.9352/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =28.9352/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.001299m/m
Head loss, HL =S*L =0.001299*20.34
=0.026414m
Total Head loss, HL total =0.026414
Pipe Calculation
Pipe ID=15 average
Pipe data: length=20.338m, diameter=260mm, C=130
Area,A =22/7*diameter2/4=0.0531m2
Hydraulic radius, R =Area/perimeter =0.065m
Flow, Q =Area*Velocity
=>Q/A =Velocity
Velocity,V =0.8492*C*R0.63S0.54(m/s)
=>Q/A =0.8492*C*R0.63S0.54
=>13.8889/0.05 =0.8492*130*0.0650.63S0.54/1000
=>S0.54 =13.8889/0.05*1/(0.8492*130*0.065 0.63)/1000
=>S =0.000334m/m
Head loss, HL =S*L =0.000334*20.34
=0.006785m
Total Head loss, HL total =0.006785