PACKAGE A1 OLEFINS

PRESERVATION CHECKSHEET
JOB CARD : HEPL-01-STD - Plate Heat Exchangers JOB PLAN TYPE : 1-INITIAL PRESERVATION

TAG : 10-E-2100C Description: QUENCH WATER COOLER Schedule Week : 39 2020

Subcontractor : PTSC Technician : Supervisor : Location : Site Work

NR STEP FREQUENCY ACTIVITY DUE DATE EXECUTED


1 IN_1 IN ITEM SHALL BE DELIVERED COMPLETELY ASSEMBLED AND PACKED, 9/22/2020 9/23/2020
UNDER NITROGEN PRESERVATION (0.5 BARG OR 0.2 BARG BY THE
DESIGN PRESSURE WHICHEVER IS SMALLER)
2 IN_2 IN ITEM SHALL BE LEFT IN SHIPPING PACKAGE UNTIL INSTALLATION. 9/22/2020 9/23/2020

3 IN_3 IN PACKAGE SHALL BE STORED IN WAREHOUSE OR UNDER SHELTER, 9/22/2020 9/23/2020


KEPT AWAY FROM WATER, HUMIDITY AND SUN.
4 IN_4 IN PACKAGE SHALL BE CHECKED FOR ANY DAMAGE OR WEAR. 9/22/2020 9/23/2020

5 IN_5 IN NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/23/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
6 IN_6 IN IF THE EXCHANGER HAS BEEN REMOVED FROM PACKAGE OR 9/22/2020 9/23/2020
PACKAGE HAS BEEN DAMAGED PERFORM THE FOLLOWING
CHECKS/ACTIVITIES:
7 IN_7 IN FOR ALL FLANGES: CHECK ANTI-RUST PROTECTION ON SEAL 9/22/2020 9/23/2020
SURFACES PROVIDED BY SUPPLIER/MANUFACTURER AND RENEW
ANY DAMAGED PROTECTION BY APPLYING A COAT OF PROTECTION
PRODUCT (DRY LAYER FOR EXTERNAL PARTS) AND PROTECT WITH
PLASTIC SHEETS OR WOODEN COVERS.
8 IN_8 IN WHERE A SPOT CHECK REVEALS SOME RUST FORMATION, PROVIDE 9/22/2020 9/23/2020
FOR THE FOLLOWING OPERATIONS DEPENDING BY THE PART
INVOLVED: - REMOVE ALL FLANGE COVERS OF THE NOZZLES,
CLEAN THE FLANGE FACES FROM RUST BRUSH AND AFTER WITH
SOLVENT AND APPLY RUST PREVENTIVE PRODUCT. - REMOVE RUST
BY MECHANICAL OR MANUAL BRUSH AND RESTORE PAINTING
ACCORDING TO PAINTING PROCEDURE.
9 IN_9 IN CHECK THAT ALL OPENINGS AND CONNECTIONS ARE TIGHTLY 9/22/2020 9/23/2020
CLOSED.
10 IN_10 IN ITEM SHALL BE PROTECTED FROM DUST, SAND, LIGHT, HUMIDITY 9/22/2020 9/23/2020
AND WEATHER CONDITIONS
11 IN_11 IN COAT WITH HEAVY GREASE OR PROTECTIVE PRODUCT 9/22/2020 9/23/2020
BOLTS/THREADED CONNECTIONS AND FLANGES AND ALL
EXPOSED MACHINED SURFACE.
12 IN_12 IN NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/23/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
13 IN_13 IN ANCHOR BOLTS THAT ARE NOT OTHERWISE PROTECTED WHEN 9/22/2020 9/23/2020
RECEIVED AT JOB SITE, SHALL BE CLEANED FROM RUST, AND SHALL
BE COATED WITH RUST PREVENTATIVE (DRY LAYER AND SOFT
LAYER FOR EXTERNAL OR INTERNAL PARTS).
14 IN_14 IN REMOVE AND STORE FRAGILE ACCESSORIES/INSTRUMENTS. 9/22/2020 9/23/2020

15 MP_1 4W PACKAGE SHALL BE CHECKED FOR ANY DAMAGE OR WEAR. 9/22/2020 9/23/2020

16 MP_2 4W NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/22/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
PACKAGE A1 OLEFINS

PRESERVATION CHECKSHEET
JOB CARD : HEPL-01-STD - Plate Heat Exchangers JOB PLAN TYPE : 1-INITIAL PRESERVATION

TAG : 10-E-2100C Description: QUENCH WATER COOLER Schedule Week : 39 2020

Subcontractor : PTSC Technician : Supervisor : Location : Site Work

NR STEP FREQUENCY ACTIVITY DUE DATE EXECUTED


17 MP_3 4W ANY WATER DEPOSIT SHALL BE REMOVED 9/22/2020 9/23/2020

18 MP_4 4W IF THE EXCHANGER HAS BEEN INSTALLED OR REMOVED FROM 9/22/2020 9/22/2020
PACKAGE PERFORM THE FOLLOWING CHECKS/ACTIVITIES:
19 MP_5 4W CHECK THAT ALL OPENINGS AND CONNECTIONS ARE TIGHTLY 9/22/2020 9/23/2020
CLOSED.
20 MP_6 4W CHECK LEAKAGES ON CONNECTIONS. TIGHTEN COUPLINGS AND 9/22/2020 9/22/2020
FLANGES IF NECESSARY.
21 MP_7 4W NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/22/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
22 MP_8 4W CHECK PAINTING AND IF NECESSARY REPAINT. 9/22/2020 9/23/2020

23 MP_9 4W CHECK INSULATION AND IF NECESSARY REPAIR. 9/22/2020 9/22/2020

24 MP_10 4W CHECK AND DRAIN CONDENSATE FROM LOW POINTS. 9/22/2020 9/22/2020

25 MP_11 4W CHECK GREASE/PROTECTIVE PRODUCT COATING AND, IF 9/22/2020 9/22/2020


NECESSARY, REFURBISH ON BOLTS/THREADED CONNECTIONS,
FLANGES AND ALL EXPOSED MACHINED SURFACES.
26 MP_12 4W ITEM SHALL BE PROTECTED FROM DUST, SAND, LIGHT, HUMIDITY 9/22/2020 9/23/2020
AND WEATHER CONDITIONS
27 MP_13 4W CHECK STATUS OF TARPAULINS COVERING THE EQUIPMENT (IF 9/22/2020 9/22/2020
ANY). REPAIR IF TEARS FOUND.

REMARKS
Accepted by Supervisor CONTRACTOR/CLIENT
Accepted by Supervisor SUBCONTRACTOR
W □ M □ R □
Entered in
Name: Name:
Database

Signature: Signature: □
Date: Date: