Building Works at Hougang Town Daily Site Record: Thursday, March 19, 2020
Building Works at Hougang Town Daily Site Record: Thursday, March 19, 2020
Building Works at Hougang Town Daily Site Record: Thursday, March 19, 2020
DAILY SITE RECORD Thursday, March 19, 2020 DAILY SITE PHOTO
GROUT PILES
EXCAVATION TO PLATFORM LEVEL IN
total completed to date: 114 nos. PROGRESS
Total number of GROUT Piles 141 nos. 80.85%
14 PILE GROUT Today
Architectural
work
M & E Work
14 GROUT PILES DONE TODAY DRIVING SOLDIER PILES FOR ERSS WORKS
Weather
FAIR
Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 PILE CAP P40 REBAR INSTALLATION IN PILE CAP P41 REBAR INSTALLATION IN
PROGRESS PROGRESS
REMARKS :
PILE CAP P40 REBAR INSTALLATION IN PROGRESS
9CBP PILES HACKING DONE,5 HACKED USING BIG HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER, LEANCONCRETE DONE
2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
noise level reading: AT 10:25AM NOISE READING Exceeded, reading AT 91.6dB 9CBP PILES HACKING DONE,5 HACKED USING BIG 2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER,
LEANCONCRETE DONE