BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Thursday, March 19, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks

PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 2 nos.
total Number OF Pile Caps 57 nos. 3.51%

MSCP PILES 100.00%


Structural work

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES
EXCAVATION TO PLATFORM LEVEL IN
total completed to date: 114 nos. PROGRESS
Total number of GROUT Piles 141 nos. 80.85%
14 PILE GROUT Today
Architectural
work
M & E Work

14 GROUT PILES DONE TODAY DRIVING SOLDIER PILES FOR ERSS WORKS

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator BIG BREAKER 1
Site engineer 1 Safety office 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 grout machine 1

Weather

FAIR

Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 PILE CAP P40 REBAR INSTALLATION IN PILE CAP P41 REBAR INSTALLATION IN
PROGRESS PROGRESS

Housekeeping work inprogress,

14 GROUT PILES DONE TODAY

DRIVING SOLDIER PILES FOR ERSS WORKS

REMARKS :
PILE CAP P40 REBAR INSTALLATION IN PROGRESS

PILE CAP P41 REBAR INSTALLATION IN PROGRESS

9CBP PILES HACKING DONE,5 HACKED USING BIG HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER, LEANCONCRETE DONE
2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS

noise level reading: AT 10:25AM NOISE READING Exceeded, reading AT 91.6dB 9CBP PILES HACKING DONE,5 HACKED USING BIG 2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER,
LEANCONCRETE DONE