Professional Documents
Culture Documents
HFHP Construction Tool and Templates v1
HFHP Construction Tool and Templates v1
HFHP Construction Tool and Templates v1
Procurement
document of HFHP
Construction
Tabulated bids from all bidders tallying bid and Quality
price of each bidder per material and other Assurance
Canvass Tally relevant information of the bidder like on- Procurement
COO/SMT Yes
Sheet going projects with HFHP, other ongoing and Unit Accreditation
past projects, construction duration and list , Bids and
of submittals provided by the bidder. Awards
Committee
Pre-construction
Consolidated
Construction
Progress Summary of progress/ accomplishment rates Operations
and Quality COO No
Monitoring of all HFHP projects updated weekly Manager
Assurance
Report
Project
Manager
Operation
Request for payment for approved Site
Progress Billing Manager
percentage of work completed by the IP Engineer Yes
Request
Implementing Partner with attached photos
COO
Construction
and Quality
Assurance
Construction
Request document for substitution of IP and Quality
Request for
materials with required specification, Project Assurance
Approval/ Yes
including but not limited to color, brand, Site Engineer Manager
Substitution
make, etc. (Hubs) Design and
Innovation
Construction
and Quality
Request document for further information or
Request for Site Engineer Project Assurance
provision of shop drawings to clarify Yes
Information (Hubs) Manager
particular details in the plans
Design and
Innovation
Project
Request Document for item of works not Operation
Change Order Manager
identified during the bidding/procurement Site Engineer Manager
Request-with No
stage but is critical to the completion of the (Hubs)
cost implication Project
project and has budgetary implication COO
Manager
Possible cases:
Construction
Site Engineer Project
Site Instruction and Quality No
1. Improper or non-use of Personal (Hubs) Manager
Assurance
Protective Equipment(PPE)
2. Cleanliness of construction site
3. Non-compliance to the construction site
policies
4. Other construction work specific
instruction
a. Flood test
b. Pressure Test Construction
Certificate of Project
c. Megger and other electrical test IP and Quality Yes
Tests completed Manager
d. Gas line test Assurance
e. Plumbing test for toilet fixture
Construction
and Quality
Certificate of Certification of completion of 100% of Site Engineer Project Assurance
Yes
Completion required work (Hubs) Manager
Operation
Manager
Construction
Document detailing items needing Operations
Punchlist Report and Quality COO Yes
rectification/repair Manager
Assurance
Pr ogram Developmen t
Social Due
Diligence
Operations
Technical Due
E Diligence Report
Conceptual
Conduct technical Review and Design and BOQ
E
due diligence
Finalize
Proposal
Engineering
study needed?
Request for
engineering F
study
Quality Assurance
Construction and
Review
Conceptual Plan
and BOQ
Technical Core Team
No Submit to RD for
Review Project Proposal
Yes Resource
SMT/ BOT
Proposal aaproved?
Mobilization
Procurement
Project
approved for
Human Settlement and Housing
funding
Finalize BOQ
and prepare Bid Analysis Report
bidding
document
Finance
Construction and
Prepare
Operations
Conduct Pre-
Purchase
bidding
Requisition
activity
Form
Project
SMT/ BOT
Send Invitation
Send Notice of
to accredited Receive Bids Tabulate Bids
Award
Finance
bidders
Canvass Tally
Sheet
Accreditation, Bids and Awards
Committee
Pre-construction
Project awarded
to Implementing
Partner Pre-construction
deck
Operations
Conduct of Pre
Issuance of Notice Request release of
Start Construction
to Proceed downpayment
Meeting
Design and Innovations
QA/QC Tools
Prepare Quality
Assurance
Quality Assurance
Progress Billing
guidelines and Progress billing Process
templates orientation Downpayment
Finance
Prepare
Legal
Construction
Agreement
Implementing Partner
Attend pre-
construction
meeting and Mobilization
Process Surety
Bond
Ensure signing of
Lead trial build
Request updating construction
with Provide IP with
Start of Construction agreement
Implementing updated plans
agreement addendum/
partner
revisions
Construction and Quality Assurance
Recommend
Validation and
possible
Finalization of
adjustment to the
BOQ
design
Design
Finalized BOQ
Recommendation
Design and Innovation
Update
construction
agreement
Implementing Partner
Prepare
Proceed with Prepare and
Implementing Partner
Yes
No
Holdpoint Checklist Validate report
B With issues?
Operations
Holdpoints
Sign hold point
requirements Yes
met?
checklist
No
Approve IP report
A Prepare MRF
As part of
sweat equity?
HOA Member
Update
Frequency of Progress Billing check Consolidated Site Validation of
via Site Validation?
Project Progress Billing Report accura te?
60% and 100% billing c/o
Construction QA? Monitoring Report
30% and 90% c/o Operations(Site Template
Engineer)
Consolidated Progress
Monitoring Report
Yes
Office of the COO/ Program Support Officer
No
Ensure
completeness of Endorse for
Report accurate? Yes
documents and payment
accuracy of figures
Finance
Request for
Implementing Partner
Information
No
C
Site Engineer / Project Manager
Submit RFI/RFA/
Request/s valid? Yes
RFS Inform IP
No
No
Construction and Quality Assurance
RFA/RFS/EFI and SI
Database
Design and Innovations Unit
Yes
Validate and
approve/
C
disapprove
request
Yes
Operations Manager
Validate and
approve/ Approve
Yes/No C
disapprove request?
request
Yes
Prepare contract
Legal
Yes
addendum
Certificate of
Completed Tests
Punch list
Flood Test for Drains/Floor
Accomplishment
Report
Implementing Partner
Slope
Approved 100%
Pressure Test for Water line
Start Accomplishment Rectify/Correct Process Warranty
Report punch list Bond
Waterproofing Tests
No
Other applicable Tests
D
Certificate of No Certificate of
Punchlist Report
Completion Acceptance
Operations
Validates and
Issue Certificate of Provide IP with Punch list Sign Certificate of
approve punch list Yes
Completion Punchlist Report approve? Acceptance
Report
Request Release
of retention
Conduct Punch
listing activity
Prepare Punchlist
Construction and Quality Assurance
Report
IP Performance Report No
D
Office of the COO
Approve request
Finance
Process and
Release Payment
Accreditation and Bids and
Awards Committee
IP Database