Flow Chart NetMetering
Flow Chart NetMetering
Acknowledgement Stage
Installer Net Metering Cell Concernerd Authority NEPRA Billing CSO
1-1
Interconnection
Application
No
1-2 Add/Update
Info Or 1-4 Provisional Review
Documents
Yes
2.Screening
1-6 Concerned/
Competent Authority
SDO XEN SE P&E
Yes
2-2 Okay
Issue with Docs
Yes
3-1 Site Verification of DISCO
3. Technical Feasiblity
infrastructure
Re-Inspect Request a) Type of Xformer
b)Capcity of Xformer
Time Duration Reset
c) Capcity of Already Installed DG
d) Type of Meter and Conductor
The Installer
and Utility
3-2 Verify all Components installed
Agreement can
as per submitted documents.
P&I Dept to verify Grounding and be uploaded by
Safety either the SDO
or the Focal
Person
3-4 Update
Documents or DG No 3-3 Verified
installation.
Yes
sending to NEPRA
4-3 Vendor
Updates Issue to be
Documents . adressed by
Concerned Authority
4-2 Submit for
Issue with Docs DG License
Yes
5-2 License
Issued
(Meter Installation)
6. Commissioning
Yes
6-1 Remit and
Upload Paid copy No
of Demand
Notice
7. Billing Revenue Office Approval (CSO)
7-2 All
documents
verified
8. Billing Change
Yes
7-3 CSO will enter the
billing change in the
billing system.