CM4 Little THD TDD Calculation

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

If you know the thd and “true” RMS currents, you can derive ha, hb, and hc necessary to

calculate TDD.

Thus, for phase A


thdA = sqrt(H2A2 + H2A3 + H2A4 + ….)/I RMS, A1 * 100%

ha = (thdA * I RMS, A1 )/100%

For phase B
thdB = sqrt(H2B2 + H2B3 + H2B4 + ….)/I RMS,B1 * 100%

hb = (thdB * I RMS,B1 )/100%

For phase C
thdC = sqrt(H2C2 + H2C3 + H2C4 + ….)/I RMS,C1 * 100%

hc = (thdC * I RMS,C1 )/100%

Where
 I RMS, A1 is the “true” current for phase A
 I RMS,B1 is the “true” current for phase B
 I RMS,C1 is the “true” current for phase C

From that point,

You can multiply TDD by 100% get obtain a percentage.

You might also like