Bar – Boljare Highway,

Section Smokovac – Uvač – Mateševo


Bridge / Most Suvovara
Expert’s Witness Report on Unforeseeable
Physical Condition - Cavern under the Sub-
Clauses 4.12 and 13.9 / Stručni nalaz o
nepredvidivim fizičkim uslovima – kaverni
prema potklauzulama 4.12 i 13.9

August 2020
Rev00
Supervision of Design and Works
Nadzor nad Projektovanjem i Izgradnjom
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Document Control Sheet

Client: Ministry of Transport and Maritime Affairs

Project: Supervision of Design and Works on the Bar - – Boljare Highway


Section Smokovac – Uvač – Mateševo

Title: Suvovara Bridge Expert’s Witness Report on Unforeseeable Physical Condition -


Cavern under the Sub-Clauses 4.12 and 13.9 – Rev01 August 2020 / Most Suvovara -
Stručni nalaz o nepredvidivim fizičkim uslovima – kaverni, prema potklauzulama 4.12 i
13.9 – Rev01

Revision History

Prepared by Checked by Approved by

ORIGINAL Darko Muza Jan Lorange Jan Lorange

SIGNATURE

DATE 15 August 2020 15 August 2020 15 August 2020

1
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

LIST OF CONTENTS

1. INTRODUCTION / UVOD................................................................................................................................3
2. CLAIM EVENT / DOGAĐAJ POTRAŽIVANJA.......................................................................................... 3
2.1. CLAIM EVENT NO. 054 / DOGAĐAJ POTRAŽIVANJA BR 054.............................................................. 3
2.2. CLAIM EVENT NO. 054-2 / DOGAĐAJ POTRAŽIVANJA BR 054-2 .................................................... 13
3. TECHNICAL REVIEW OF CONTRACTOR’S DOCUMENTATION / TEHNIČKI PREGLED
DOKUMENTACIJE IZVOĐAČA RADOVA .................................................................................................. 19
3.1. GENERAL COMMENTS / OPŠTI KOMENTARI....................................................................................... 19
3.2. TECHNICAL COMMENTS / TEHNIČKI KOMENTARI............................................................................ 19
3.3. TECHNICAL CONCLUSION / TEHNIČKI ZAKLJUČAK......................................................................... 22
4. GENERAL DESCRIPTION / OPŠTI OPIS...................................................................................................23
5. PRELIMINARY DESIGN / IDEJNI PROJEKAT....................................................................................... 24
6. CONCLUSION ON PRELIMINARY DESIGN / ZAKLJUČAK O IDEJNOM PROJEKTU................ 29
7. CONTRACTOR’S CLAIM ANALIZY / ANALIZA POTRAŽIVANJA IZVOĐAČA RADOVA..........30
8. FINAL CONCLUSION / KONAČAN ZAKLJUČAK................................................................................. 31

2
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

1. INTRODUCTION 1. UVOD
Due to Contractor's claims for unforeseeable Zbog Izvođačevih potraživanja za nepredvidive
geological conditions in occasions of caverns geološke uslove u slučaju kaverni uočenih
observed during foundation pit excavation, tokom iskopa temeljne jame, Inženjer dostavlja
herewith the Engineer is providing our expert svoje stručno mišljenje kako slijedi. U ovom
witness opinion below. This particular Report konkretnom Izvještaju dajemo mišljenje o
shows our opinion on the Contractor's Claim No. Izvođačevom potraživanju br. 054 i 054/2, koje
054 & 054/2, described in chapter 2. of this je opisano u poglavlju 2. ovog Izvještaja; i
Report; and related to Suvovara bridge. odnosi se na most Suvovara.
2. CLAIM EVENTS No. 054 and 054/2 2. DOGAĐAJI POTRAŽIVANJA br. 054 i
054/2
Herewith, please find bellow description of the
Claim Event as follow: U nastavku dajemo opis događaja potraživanja:
 2.1 Claim Event No. 054  2.1 Događaj Potraživanja br. 054

Foundation pits S2 L, S4 L and S5 L were
 Temeljne jame S2 L, S4 L i S5 L iskopane su
excavated at the designed elevation. Due to the
na projektovanoj koti. Uslijed činjenice da u
fact that no geotechnical environment suitable
dijelovima temeljnih jama nije nađena
for shallow foundation geotechnical category D
geotehnička sredina pogodna za plitko
was found in parts of the foundation pits, the
fundiranje geotehnička kategorija D, Izvođač je
Contractor asked the Designer to check the type
zatražio od Projektanta provjeru tipa fundiranja
of foundation in accordance with the actual
u skladu sa stvarnom zatečenom geotehničkom
existing geotechnical environment. Also,
sredinom. Takođe, izvedena su prospekcijska
prospective drilling was performed in order to
bušenja u svrhu potvrđivanja stvarne
confirm the actual geotechnical environment of
geotehničke sredine temeljnog tla, a na osnovu
the foundation soil, and based on the obtained
dobivenih rezultata i sukladno Izjavama
results and in accordance with the Designers'
Projektanata sa dna temeljnih jama uklonjeni su
Statements, parts of poorer rock mass were
dijelovi lošije stijenske mase do zahtjevane
removed from the bottom of the foundation pit
geotehničke sredine, te su iste stepenasto
to the required geotechnical environment, and
zapunjene betonom marke MB30.
these are gradually filled with MB30 concrete.

U priloženom Izvođačevom detaljnom
In Contractor’s filly detailed Claim No. 054; Potraživanju br. 054; u poglavlju Događaji
in the chapter The Events giving rise to Claim koji su doveli do potraživanja (Analiza
(Factual-Matter Analysis); Background, it is činjenićnog stanja); Pozadina, navedeno je
stated: “ On construction site of Subsection 3.1, slijedeće: “Na gradilištu podsekcije 3.1 Izvođač
the Contractor encounter a change in the se susreo sa promjenom geoloških uslova na
geological conditions at the bridge #6 Suvovara mostu br. 6 Suvovara, temelji stubova S2L, S4L
at the bottom of the foundation of piers P2L, i S5L.
P4L and P5L.
Izvođač smatra da su ovi nepovoljni fizički
The Contractor consider this adverse physical uslovi Nepredvidivi, stoga u skladu sa PK 4.12
conditions to have been Unforeseeable, Ugovora o projektovanju i izgradnji autoputa
therefore in accordance with SC 4.12 of the Bar – Boljare, Izvođač je obavijestio Inženjera
Design and Built Contract for Bar – Boljare dopisom RB-BBH/4737/CD-P3 datiranim
Highway, the Contractor informed the Engineer 30.11.2017. godine (Prilog 2) da smo se susreli

3
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

that we encountered unforeseeable physical sa nepredvidivim fizičkim uslovima na


conditions on the construction site via letter RB- gradilištu.
BBH/4737/CD-P3 dated on 30.11.2017
Imajući u vidu da su svi ovi promjenjeni
(Enclosure 2).
geološki uslovi doveli do varijacije obima
Having in mind that this changed geological radova, stoga je u skladu sa Podklauzulom 13.9
conditions led to a variation to the scope of Nepredvidivi radovi. Izvođač je zatražio od
Works, therefore pursuant to Sub-clause 13.9 Inženjera da primjeni neophodnu Proceduru o
Unforeseeable Works, the Contractor asked the varijaciji u skladu sa Podklauzulama 13.1 i
Engineer to apply the required Variation 13.3 Ugovora.
procedure in accordance to Contract Sub-
clauses 13.1 and 13.3.
Gorenavedeni Nepredvidivi fizički uslovi su
The above mentioned Unforeseeable Physical
evidentirani u slijedećim dokumentima:
Conditions are all recorded in the following
documents:
Statement regarding foundation conditions Mišljenje u vezi uslova temeljenja (Prilog 4)
(Enclosure 4)
Međutim, Inženjer je odbio zahtjev Izvođača
However, the Engineer rejected Contractor’s putem dopisa IG/5659/VM datiranog
request via its letter IG/5659/VM dated on 14.12.2017. godine (prilog 3), smatrajući da
04.12.2017 (Enclosure 3) on the bases that the geološki uslovi koje je konstatovao Izvođač bez
geological conditions reported by the sumnje ne predstavljaju nepredvidive radove u
Contractor are undoubtedly not unforeseeable skladu sa Podklauzulom 13.9
works under Sub-clause 13.9.
Izvođač se ne slaže s ovim mišljenjem i podnio
The Contractor disagrees with this opinion and je Obaviještenje o potraživanju za vrijeme i
submitted a notice of claim for time and cost via troškove preko svog dopisa RB-BBH/4911/CD-
its letter RB-BBH/4911/CD-P3 dated on P3 datiranog 14.12.2017 godine.“
14.12.2017.
In the chapter Cost (Damage) Analyses the
Contractor states as follow: U poglavlju Analiza troškova (Štete) Izvođač
navodi slijedeće:
“Due to the allocation of additional resources,
in order to complete Unforeseeable works, the „Za raspoređivanja dodatnih sredstava za
Contractor is entitled to the following costs: kompletiranje Nepredvidljivih radova, Izvođač
ima pravo na sledeće troškove:

4
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

No. Position Item Quantity Unit price Amount

1 S2L Additional excavation 37,924 20,55 779,34


2 Additional concrete 37,924 246,60 9.352,06
3 S4L Additional excavation 20,424 20,55 419,71
4 Additional concrete 20,424 246,60 5.036,56
5 S5L Additional excavation 130,424 20,55 2.680,21
6 Additional concrete 130,424 246,60 32.162,56
7 Management cost 10% 5.043,04
TOTAL AMOUNT 55.473,48

Contractor also attached Opinion about Izvođač je takođe priložio Mišljenje u vezi
foundation conditions, and below are the uslova temeljenja, a u nastavko donosimo
statements from the Geological Reports on the navode iz Geoloških izvještaja o kartiranju
mapping of foundation pits, as well as their temeljnih jama, kao i njihove anekse, kako
annexes, as follows: slijedi:
Foundation pit S2 L
In related Geological Report, Geologist in charge Temeljna jama S2L
states as follows:
U vezanom Geološkom izvještaju, odgovorni
“By geological mapping of foundation pit of pier Geolog Izvođača navodi slijedeće:
S2 L, it has been found that the lithological
„Geološkim kartiranjem temeljnog iskopa stuba
composition and engineering-geological
S2 L utvrđeno je da litološki sastav i
characteristics correspond to the present in the
inženjersko-geološke karakteristike odgovaraju
Geotechnics Design for bridge Suvovara.
napisanom u Geotehničkom elaboratu za most
Excavation was done mechanically and mining,
Suvovara. Iskop je rađen mašinski sve do
mechanical excavation of floor feet height of 2,4
dubine od 2,4 m....
m…
Dno temeljne jame uglavnom izgrađuju
Bottom of foundation pit is mostly build of fine
sitnozrni pješčari sa kalcitnim žicama i manjim
sandstones with calcite wires and smaller
proslojcima alevrolita 2cIG2(abc)1,sa izuzetkom
interbeds of alevrolite 2cIG2(abc)1,with the
istočne kosine, gdje preovlađuju prašinaste
exception oof the eastern slope where dominate
gline i pjeskovito-glinovite prašine sa
powder clay and sandy-clay powder with
sadržajem šljunkovite komponente koje
contains gravel component which intake 1,5 to
zahvataju i 1,5 do 2,0 m temeljnog dna...
2,0 of foundation bottom…
It is noticed smaller tectonical activity followed
by appearance of joints. Zapaža se manja tektonska aktivnost koju prate
pojave pukotina.
Six prospecting studied boreholes were drilled,
which determinated the geological structure of Urađeno je 6 prospekcijskih bušotina, kojima je
5
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

the terrain bellow the bottom of foundation of utvrđena geološka građa terena ispod
pier S2 L. The drilling results showed favourable temeljnog dna stuba S2 L. Rezultati bušotina
engineering-geological characteristics of the pokazali su povoljne inženjersko-geološke
foundation site at the very bottom of the karakteristike terena za fundiranje u samom
foundation, excluding the zone around the drill dnu temelja, izuzimajući zonu oko bušotina B-1
hole B-1 and B-2, which was build from a worse i B-2, koja je izgrađena od lošije stijenske
rock mass. mase.
Due to the characteristic of the rock mass that is
represented on the eastern side of the slope and
Zbog karakteristika stijenske mase koja je
the bottom of the foundation pit, it is
zastupljena na istočnoj strani kosine i podnom
neededadditional Designer’s opinion for the
dijelu temeljne jame potrebno je dodatno
condition of the foundation of pier S2 L.”
mišljenje Projektanta za uslove fundiranja
In the Annex to the same Geological Report, the stuba S2 L.“
responsible Geologist states:
“After completion of the excavation and the
U Aneksu istog Geološkog izvještaja odgovorni
completed prospective boreholes in the
Geolog navodi:
foundation pit of the pier S2 L, due to a poor
engineering-geological conditions in the part of „Nakon završetka iskopa i urađenih
the foundation pit of funding of pier, the prospekcijskih bušotina u temeljnoj jami stuba
Designer’s opinion on the method of pier S2 L, a zbog lošijih inženjersko-geoloških
foundation was requested. uslova fundiranja stuba u jednom dijelu
temeljne jame, zatraženo je mišljenje
Following the recommendation of the
Projektanta o načinu fundiranja stuba.
Responsible Designers for the bridge Suvovara,
whose statement is attached as an annex, the Po preporuci odgovornih Projektanata za most
bottom of the eastern part of the foundation pit Suvovara, čiju izjavu prilažemo kao prilog uz
of pier S2 L was cleaned to the solid rock mass. ovaj aneks, izvršeno je čišćenje dna stuba S2 L
After cleaning the foundation pit, a replacement u istočnom dijelu do čvrste stijenske mase.
of the material was made with concrete MB 30 Nakon čišćenja temeljne jame izvršena je
to the level of the foundation.” zamjena materijala sa betonom MB 30 do kote
fundiranja.“
In attached Opinion Regarding Foundation
Conditions at Pier S2 L on Suvovara Bridge U priloženom Mišljenju u vezi uslova
at Smokovac – Uvač – Mateševo, authors temeljenja stubova S2 L mosta Suvovara
Kenan Imširpašić and Enes Lakota – bridge autoputa Smokovac – Uvač – Mateševo,
Designers for Suvovara bridge it states: autora Kenana Imširpašića i Enesa Lakote –
Projektanata mosta Suvovara navedeno je:
“By email dated on 25 August 2017 You have
submitted to us Report About Engineering- „Putem elektronske pošte ste nam 25. avgusta
Geological Mapping at Foundation Pit S2-L at 2017 dostavili Izvještaj o inženjersko-
Suvovara Bridge and asked for opinion. geološkom kartiranju temeljne jame stuba S2-L
mosta Suvovara, te zatražili mišljenje.
We have reviewed mentioned Report as well as
bedding stresses for foundation S2-L. Pogledali smo pomenuti izvještaj, kao i
naprezanja temeljne stope S2-L.
Prema našem mišljenju radi se o povoljnim
According to our opinion there are good
uslovima za temeljenje. Izuzetak je jedino
conditions for foundation. Exception is only

6
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

eastern part of construction pit. istočna strana temeljne jame.


Considering that foundation pit is dry and S obzirom da je temeljna jama suha i stabilna,
stable, where risk of loss stability is not te da nije registrovana opasnost od gubitka
registered, we suggest keeping foundation of stabilnosti, predlažemo zadržavanje temeljne
pier S2-L with position and dimensiones as in stope S2-L sa položajem i dimenzijama prema
Main Design, with construction of replacement Glavnom projektu, uz izradu zamjenskog
materials on eastern part of pit. materijala do geološki povoljnih slojeva ispod
istočnog dijela stope.
Zamjena lošeg materijala se može vršiti sa
Weaker materials could be replaced with
podložnim betonom ili na većim dubinama špar
blinding concrete, or thicker layers with spar
betonom.“
concrete.”

U nastavku Aneksa priložena je Izjava o


The Annex is accompanied by a Statement on
geotehničkim uslovima fundiranja stubova
the geotechnical conditions for the foundation
S2L, S4L i S5L mosta Suvovara, autora
of the S2L, S4L and S5L piers of the
odgovornog Projektanta Peng Tingjia i geologa
Suvovara Bridge, authored by the responsible
Saše Cupaća, u kojoj je navedeno:
Designer Peng Tingjia and geologist Saša Cupać,
which states: „Nakon završetka temeljnih jama za stubove
S2L, S4L i S5L, dobili smo dopis podizvođača
“After the excavation of foundation pitsfor piers
preduzeća Bemax koji su upućeni Glavnom
S2L, S4L and S5L was finished, we received
Izvođaču. U dopisima je priloženo mišljenje
letter from Subcontractor, company Bemax,
Projektanatavg-dina Kenana Imširpašića i g-
which were sent to the Main Contractor. In
dina Enesa Lakote. Takođe, dostavljeni su nam
letter, opinion of designers Mr Kenan Imširpašić
Izvještaji o inženjersko-geološkom kartiranju
and Mr Enes Lakota was submitted. The Reports
temeljnih iskopa koje je izradio inženjer
of engineering-geological mapping foundation
geologije Radovan Čvorović. Nakon uvida u
pits, done by geology engineer Radovan
dostavljenu dokumentaciju konstatovano je
Čvorović, were also submitted. After the insight
slijedeće:
into this letter, we make the following
conclusion. Geološkim kartiranjem temeljnih iskopa svih
stubova utvrđeno je da litološki sastav i IG
By geological mapping of foundation pits of all
karakteristike odgovaraju Geotehničkom
piers, it has been found that the lithological
elaboratu za most Suvovara.
composition and EG characteristics correspond
to the Geotechnical Report for Suvovara bridge.
Pier S2L Stub S2L
Bottom of the foundation pit is mostly built of Dno temeljne jame uglavnom izgrađuju
fine grain sandstone with calcite wires and sitnozrni pješčari sa kalcitnim žicama i manjim
smaller interbeds of alevrolite2cIG2(abc)1 of proslojcima alevrolita 2cIG 2(abc)1 geotehničke
geotechnical category D, with the exception of kategorije D, sa izuzetkom istočne kosine, gdje
the eastern slope where silty clay and sandy clay preovlađuju prašinaste gline i pjeskovito-
silt dominate, with content of gravel component glinovite prašine sa sadržajem šljunkovite
which intake 1,5 to 2 meter soft foundation komponente koje zahvataju i 1,5 do 2,0 m
bottom. Excavation is stabile, there is no temeljnog dna. Iskop je stabilan i nema pojave
occurrence of underground water. Six podzemnih voda. Urađeno je 6 prospekcijskih

7
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

prospecting studied boreholes were drilled, bušotina ispod temeljnog dna stuba. Rezultati
which determinated the geological structure of su pokazali da je manji dio temeljnog dna
the terrain bellow the foundation bottom. The (prospekcijske bušotine B1 i B2)izgrađen od
drilling results showed unfavourable rock mass lošije stijenske mase.
in a smaller part of foundation bottom
(boreholes B1 and B2).
Pier S4L
Stub S4L
Bottom of foundation pit is built from flysch
sediments represented by sandy limestones, Dno temeljne jame izgrađuju flišni sedimenti
marls, sandstone and alevrolites. Excavation is predstavljeni pjeskovitim krečnjacima,
stable, there is no occurence of underground laporcima, pješčarima i alevrolitima. Iskop je
water. Nine prospective boreholes were drilled. stabilan i nema pojave podzemnih voda.
Drilling results showed unfavourable rock mass Urađeno je 9 prospekcijskih bušotina ispod
in a smaller part of foundation bottom in the temeljnog dna stuba. Rezultati su pokazali da je
area of the borehole B5, due to which four manja zona oko bušotine B5 izgrađena od
additional boreholes were done in order to lošije stijenske mase, zbog čega su izvedene 4
determinate a distribution zone. The rest of the dodatne bušotine (B6, B7, B8 i B9), kako bi se
foundation bottom is built from flysch sediments odredilo njeno rasprostiranje. Ostali dio dna
of geotechnical category D. temelja je izgrađen od flišnih sedimenata
kategorije D.
Pier S5L
Stub S5L
Terrain under the foundation pier is dominantly
built from heterogenious dilluvial material, Teren ispod temelja stuba većim dijelom
mostly sandy-silty clay with large sandstone, izgrađuje deluvijum heterogenog sastava;
marly limestone and alevrolite particles. The dominira pjeskovito prašinasta glina sa
western slope is built from marly limestone. krupnim odlomcima pješčara, laporovitog
Excavation is stable, there is no occurence of krečnjaka i alevrolita. Zapadnu kosinu grade
underground water. Six prospective boreholes laporoviti krečnjaci. Iskop je stabilan, nema
were performed bellow the foundation bottom. pojave podzemne vode. Urađeno je 6
Results showed that in the western part of prospekcijskih bušotina ispod temeljnog dna
foundation pit, rock mass with geotechnical stuba. Rezultati su pokazali da se u zapadnom
category D is located at 1 m and in the eastern dijelu stijenska masa geotehničke kategorije D
part at -3,5 m deep from the foundation bottom. nalazi na dubini od 1 m, a u istočnom dijelu na
dubini od 3,5 m od dna temeljne jame.
Due to the unfourable EG characteristics of the
rock mass in foundation pits, the Contractor Zbog nepovoljnih IG karakteristika stijenske
asked additional Designer's opinion for the mase u temeljnim iskopima, zatraženo je od
conditions for foundations of piers. strane Izvođača dodatno mišljenje Projektanta
za uslove fundiranja stubova.
1. It is necessary to replace material bellow
foundation level of Suvovara bridge piers 1. Potrebno je izvršiti zamjenu materijala
S2L, S4L and S5L, where soil and weak rock ispod kote fundiranja temelja stubova S2L,
mass are identify by prospective boreholes. S4L i S5L mosta Suvovara, gdje je
Replacement shall be made untill the prospekcijskim bušotinama konstatovano
appearance of the favourable rock mass of tlo i loša stijenska masa. Zamjenu tla
geotechnical category D. Foundation izvršiti do pojave povoljne stijenske mase
bottoms should be stepped after replacement. geotehničke kategorije D. Dno temeljnih

8
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

2. Based on information from the terrain and iskopa nakon zamjene treba formirati
annexes of geological mapping reports, as stepenasto.
well as consultations with the Engineer and 2. Na osnovu informacija sa terena, uvidu u
the Contractor. Contractor is required after anekse geoloških izvještaja o kartiranju,
remooving unfavourable material to fill kao i konsultacija sa Nadzorom i
foundation pit with concrete MB30, or in Izvođačem, od Izvođača se traži da nakon
deeper layers with concrete MB30 combined što je uklonio loš materijal, zapuni temeljni
with crushed solid limestone (spar concrete). iskop betonom marke MB30, ili na većim
Filling shall be performed up to the dubinama betonom MB30 u kombinaciji sa
foundation level. Afterwards, it can be lomljenim kamenom od svježe krečnjačke
continued with next stages of foundation stijene (špar beton). Zapunjavanje izvesti
construction, do kote fundiranja. Nakon toga, može da se
nastavi sa slijedećim fazama izgradnje
Foundation pit S4L
temelja.“
In the related Geological Report, the responsible
Temeljna jama S4L
Contractor's Geologist states the following:
U vezanom Geološkom izvještaju, odgovorni
„By geological mapping of foundation pit of pier
Geolog Izvođača navodi slijedeće:
S4L, it has been found that the lithological
composition and engineering-geological „Geološkim kartiranjem temeljnog iskopa stuba
characteristics correspond to the present in the S4 L utvrđeno je da litološki sastav i
Geotechnical Design for bridge Suvovara. inženjersko-geološke karakteristike odgovaraju
Excavation was done mechanically and mining, napisanom u Geotehničkom elaboratu za most
mechanical excavation of floor feet height of 2,4 Suvovara. Iskop je rađen mašinski sve do
m... dubine od 2,4 m....
Bottom of foundation pit construct flysch
sediments represented by sandy limestones,
Dno temeljne jame izgrađuju flišni sedimenti
marls, sandstones and alevrolites. Sandy
predstavljeni pjeskovitim krečnjacima,
limestones are lightly gray, plating to layered
laporcima, pješčarima i alevrolitima. Pjeskoviti
structure, with a thickness of 5-10 cm...Zones
krečnjaci su svjetlo sive boje, pločaste do
present in the easern part was built from the
slojevite strukture, sa debljinom slojeva od 5 do
rock mass of the worse physical-mechanical
10 cm...U istočnom dijelu prisutna je zona
characteristics that need to be cleaned and to
izgrađena od stijenske mase lošijih fizičko-
replace the substrate with the blinding layer of
mehaničkih karakteristika, koju je potrebno
concrete MB30.
iščistiti i izvršiti zamjenu materijala sa
It is noticed smaller tectonic activity followed by podložnim betonom marke MB30.
appearance of joints.
Zapaža se manja tektonska aktivnost koju prate
9 prospective boreholes were drilled, which pojave pukotina.
determined the geological structure of the
Urađeno je 9 prospekcijskih bušotina kojima je
terrain, showed a favourable conditions for the
utvrđena geološka građa terena, što je
foundation of the bottom of the pier S4L.
pokazalo povoljne uslove za fundiranje stuba
Excluding the narrow zone arround the B5
S4L, izuzimajući usku zonu oko bušotine B5,
borehole, which was built from the worse rock
koja je izgrađena od lošije stijenske mase, zbog
mass, due to which additional boreholes were
čega su i urađene dodatne bušotine (B6, B7,
made (B6, B7, B8, B9), to determine a
B9, B9), kako bi se utvrdilanjena zona
propagation zone. The foundation of the bottom

9
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

of the pier S4L will be carried out on flysch prostiranja.


sediments in geotechnical environment D, as
what is shown in the Geotechnical Elaborate for
bridge Suvovara. Fundiranje dna temelja stuba S4L će se izvoditi
na flišnim sedimentima, u geotehničkoj sredini
Both Designer's Statements attached to
D, kao što je prikazano u Geotehničkom
foundation pit S2 L are also apply to the
elaboratu za most Suvovara.
foundation pit S4 L
Foundation pit S5 L
Obije Izjave Projektanta priložene uz temeljnu
In the related Geological Report, the responsible
jamu S2 L odnose se i na temeljnu jamu S4 L
Contractor's Geologist states the following:
Temeljna jama S5 L
„By geological mapping of foundation pit of pier
S5L, it has been found that the lithological U vezanom Geološkom izvještaju, odgovorni
composition and engineering-geological Geolog Izvođača navodi slijedeće:
characteristics correspond to the present in the
Geotechnical Design for bridge Suvovara.
Excavation was done mechanically and mining, „Geološkim kartiranjem temeljnog iskopa stuba
mechanical excavation of floor feet height of 1,4 S5L utvrđeno je da litološki sastav i
m... inženjersko-geološke karakteristike odgovaraju
Terrain under the foundation pit of pier S5L napisanom u Geotehničkom elaboratu za most
dominantly construct river drift heterogenious Suvovara. Iskop je rađen mašinski sve do
lithological composition mostly dominated dubine od 1,4m...
sandy-powder clays with large sections of
sandstones, marly limestone and alevrolites.
West slope is represented by marly limestones Teren ispod temelja stuba S5L velikim dijelom
Ep 90/46... izgrađuje deluvijum heterogenog litološkog
sastava, uglavnom dominira pjeskovito
It is noticed smaller tectonic activity followed by prašinasta glina sa krupnijim odlomcima
appearance of joints. pješčara, laporovitog krečnjaka i alevrolita. Na
Six prospective boreholes were drilled, which zapadnoj kosini zastupljeni su laporoviti
determined the geological structure of the krečnjaci Ep 90/46...
terrain below the bottom of foundation of tpier Zapaža se manja tektonska aktivnost koju prate
S5L. In the western part of the foundation pit pojave pukotina.
hard rock mass is located at a depth of 1,o m
from the bottom of the foundation pit, and at the Urađeno je 6 prospekcijskih bušotina kojima je
east part at a depth ≈ 3,5 m. utvrđena geološka građa terena ispod
temeljnog stuba S5L., U zapadnom dijelu
Due to the characteristics of the rock mass that temeljne jame čvrsta stijenska masa nalazi se
is represented at the designed depth it is needed na dubini od 1,0 m od dna temeljne jame, a u
additional Designer's opinion for the conditions istočnom dijelu na dubini od ≈ 3,5 m.
of foundation of pier S5 L.
In the Annex to the same Geological Report, the
responsible Geologist states: Zbog karakteristika stijenske mase koja je
zastupljena na projektovanoj dubini potrebno
“After the completion of the excavation and the je dodatno mišljenje Projektanta za uslove
completed prospecting boreholes in the

10
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

foundation pit of the pier S5 L, due to a poor fundiranja stuba S5 L.


engineering-geological conditions in the part of
U Aneksu istog Geološkog izvještaja odgovorni
the foundation pit of funding of pier, the
Geolog navodi:
Designer’s opinion on the method of pier
foundation was requested. „Nakon završetka iskopa i urađenih
prospekcijskih bušotina u temeljnoj jami stuba
Following the recommendation of the
S5 L, a zbog lošijih inženjersko-geoloških
Responsible Designers for the bridge Suvovara,
uslova fundiranja stuba u jednom dijelu
whose statement is attached as an annex, the
temeljne jame, zatraženo je mišljenje
bottom of the eastern part of the foundation pit
Projektanta o načinu fundiranja stuba.
of pier S5 L was cleaned to the solid rock mass.
After cleaning the foundation pit, a replacement Po preporuci odgovornih Projektanata za most
of the material was made with concrete MB 30 Suvovara, čiju izjavu prilažemo kao prilog uz
to the level of the foundation.” ovaj aneks, izvršeno je čišćenje dna temelja
stuba S5 L do čvrste stijenske mase. Nakon
Both Designer's Statements attached to
čišćenja temeljne jame izvršena je zamjena
foundation pit S2 L are also apply to the
materijala sa betonom MB 30 do kote
foundation pit S5 L
fundiranja.“
Obije Izjave Projektanta priložene uz temeljnu
Additional costs calculation – 55.473,48 € jamu S2 L odnose se i na temeljnu jamu S5 L
Contractor didn’t claimed any EoT
Proračun dodatnih troškova – 55.473,48 €
Izvođač ne potražuje produženje roka;

11
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 1: Main Design – Engineering-geological map


Slika 1: Glavni projekt – Inženjersko-geološka karta

Picture 2: Main Design – Suvovara bridge – left axis - Longitudinal EG section


Slika 2: Glavni projekt –most Suvovara – lijeva osa – podužni IG presjek

 2.2 Claim Event No. 054/2  2.2 Događaj Potraživanja br. 054/2

12
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Foundation pit of the abutment O1 L was


excavated at the designed elevation. Due to the

fact that no geotechnical environment suitable Temeljna jama oporca O1 L iskopana je na
for shallow foundation geotechnical category D projektovanoj koti. Uslijed činjenice da u
was found in the south part of the foundation južnom dijelu temeljne jame nije nađena
pit, as well as the fact that the cavern of geotehnička sredina pogodna za plitko
dimensions 2x0,7x3 m (length x width x depth) fundiranje; geotehnička kategorija D, kao i
was found in the south-western part of the činjenica da je u jugozapadnom dijelu iskopa
excavation, the Contractor asked the Designer prisutna kaverna dimenzija 2x0,7x3 m (dužina x
to check the type of foundation in accordance širina x dubina), Izvođač je zatražio od
with the actual existing geotechnical Projektanta provjeru tipa fundiranja u skladu sa
environment. Also, prospective drilling was stvarnom zatečenom geotehničkom sredinom.
performed in order to confirm the actual Takođe, izvedena su prospekcijska bušenja u
geotechnical environment of the foundation soil, svrhu potvrđivanja stvarne geotehničke sredine
and based on the obtained results and in temeljnog tla, a na osnovu dobivenih rezultata i
accordance with the Designers' Statements, sukladno Izjavama Projektanata sa dna temeljne
parts of poorer rock mass was removed from the jame uklonjeni su dijelovi lošije stijenske mase
bottom of the foundation pit to the required do zahtjevane geotehničke sredine, te su iste
geotechnical environment, and these are stepenasto zapunjene betonom marke MB30;
gradually filled with MB30 concrete, the same jednako kao i kaverna.
as the cavern.
In Contractor’s filly detailed Claim No.
054/2; in the chapter The Events giving rise to U priloženom Izvođačevom detaljnom
Claim (Factual-Matter Analysis); Potraživanju br. 054/2; u poglavlju Događaji
Background, it is stated: “ On construction site koji su doveli do potraživanja (Analiza
of Subsection 3.1, the Contractor encounter a činjenićnog stanja); Pozadina, navedeno je
change in the geological conditions at the slijedeće: “Na gradilištu podsekcije 3.1 Izvođač
bridge #6 Suvovara at the bottom of the se susreo sa promjenom geoloških uslova na
foundation of abutment A1L. mostu br. 6 Suvovara, temelj oporca O1L.

The Contractor consider this adverse physical Izvođač smatra da su ovi nepovoljni fizički
conditions to have been Unforeseeable, uslovi Nepredvidivi, stoga u skladu sa PK 4.12
therefore in accordance with SC 4.12 of the Ugovora o projektovanju i izgradnji autoputa
Design and Built Contract for Bar – Boljare Bar – Boljare, Izvođač je obavijestio Inženjera
Highway, the Contractor informed the Engineer dopisom RB-BBH/1387/CD-P3 datiranim
that we encountered unforeseeable physical 05.04.2018. godine (Prilog 2) da smo se susreli
conditions on the construction site via letter sa nepredvidivim fizičkim uslovima na
RB-BBH/1387/CD-P3 dated on 05.04.2018 gradilištu.
(Enclosure 2). Imajući u vidu da su svi ovi promjenjeni
Having in mind that this changed geological geološki uslovi doveli do varijacije obima
conditions led to a variation to the scope of Radova, stoga je u skladu sa Podklauzulom 13.9
Works, therefore pursuant to Sub-clause 13.9 Nepredvidivi radovi. Izvođač je zatražio od
Unforeseeable Works, the Contractor asked the Inženjera da primjeni neophodnu Proceduru o
Engineer to apply the required Variation varijaciji u skladu sa Podklauzulama 13.1 i 13.3
procedure in accordance to Contract Sub- Ugovora.
clauses 13.1 and 13.3.
The above mentioned Unforeseeable Physical

13
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Conditions are all recorded in the following Gorenavedeni Nepredvidivi fizički uslovi su
documents: evidentirani u slijedećim dokumentima:
Statement regarding foundation conditions at Mišljenje u vezi uslova temeljenja oporca O1L
Abutment A1L (Enclosure 4) (Prilog 4)
However, the Engineer rejected Contractor’s
request via its letter IG/6816/VM dated on
Međutim, Inženjer je odbio zahtjev Izvođača
11.04.2018 (Enclosure 3) on the bases that the
putem dopisa IG/6816/VM datiranog
geological conditions reported by the
11.04.2018. godine (Prilog 3), smatrajući da
Contractor are undoubtedly not unforeseeable
geološki uslovi koje je konstatovao Izvođač bez
works under Sub-clause 13.9.
sumnje ne predstavljaju nepredvidive radove u
The Contractor disagrees with this opinion and skladu sa Podklauzulom 13.9
submitted a notice of claim for time and cost via
Izvođač se ne slaže s ovim mišljenjem i podnio
its letter RB-BBH/1447/CD dated on
je Obaviještenje o potraživanju za vrijeme i
16.04.2018.
troškove preko svog dopisa RB-BBH/1447/CD
In the chapter Cost (Damage) Analyses the datiranog 16.04.2018. godine.“
Contractor states as follow:
U poglavlju Analiza troškova (Štete) Izvođač
“Due to the allocation of additional resources, navodi slijedeće:
in order to complete Unforeseeable works, the
„Za raspoređivanja dodatnih sredstava za
Contractor is entitled to the following costs:
kompletiranje Nepredvidljivih radova, Izvođač
ima pravo na sledeće troškove:

No. Position Item Quantity Unit price Amount

1 A1L Additional excavation 68,299 20,55 1.403,54


2 Additional concrete 68,299 246,60 16.842,53
3 Management cost 10% 1.824,61
TOTAL AMOUNT 20.070,68

Contractor also attached Opinion about Izvođač je takođe priložio Mišljenje u vezi
foundation conditions, and below are the uslova temeljenja, a u nastavku donosimo
statements from the Geological Reports on the navode iz Geološkog izvještaja o kartiranju
mapping of foundation pits, as well as their temeljne jame, kao i njegovog aneksa, kako
annexes, as follows: slijedi:

Foundation pit O1 L Temeljna jama O1 L


In related Geological Report, Geologist in charge U vezanom Geološkom izvještaju, odgovorni
states as follows: Geolog Izvođača navodi slijedeće:
“By geological mapping of foundation pit of „Geološkim kartiranjem temeljnog oporca O1

14
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

abutment O1 L, it has been found that the L utvrđeno je da litološki sastav i inženjersko-
lithological composition and engineering- geološke karakteristike odgovaraju napisanom
geological characteristics correspond to the u Geotehničkom elaboratu za most Suvovara.
present in the Geotechnical Design for bridge Iskop je rađen mašinski do projektovane kote....
Suvovara. Excavation was done mechanically to
designed level…
Veći dio temeljnog iskopa izgrađuju flišni
Most od excavation of foundation pit contracts
sedimenti predstavljeni pjeskovitim
flysch sediments, while the southern side of the
krečnjacima i pješčarima, dok je južna strana
excavation was build from decay of sandstone
iskopa izgrađena od raspadine pješčara i
and sandy limestone with the content of the
pjeskovitih krečnjaka sa sadržajem prašinasto-
dusty-clay component…
glinovite komponente...
It is noticed smaller tectonical activity followed
Zapaža se manja tektonska aktivnost koju prate
by appearance of joints with the falling element
pojave pukotina sa elementima pada F3 56/68 i
F3 56/68 and 155/42. In the south-western part
155/42. U jugozapadnom dijelu iskopa prisutna
of the excavation there is a cavern of dimensions
je kaverna dimenzija 2x0,7x3 m (dužina x širina
2x0,7x3 m (length x width x depth)
x dubina).
Eignt prospecting studied boreholes were drilled,
Urađeno je 8 prospekcijskih bušotina, kojima je
which determinated the geological structure of
utvrđena geološka građa terena ispod
the terrain bellow the bottom of foundation of
temeljnog dna oporca O1 L.
pier O1 L.
Rezultati bušenja pokazali su povoljne
The drilling results showed favourable
inženjersko-geološke karakteristike u
engineering-geological characteristics in the
sjevernom dijelu temelja do kaverne, dok je
northern part of the foundation to the cavern,
drugi dio koji se pruža od kaverne ka jugu,
while the other part flows from the cavern to the
zapadu i istoku zbog prisustva diskontinuiteta u
south, the west and the esat due to a presence of
stijenskoj masi i inženjersko-geoloških
discontinuity in the rock mass and the
svojstava stijenske mase nepovoljan za
engineering-geological properties of the rock
fundiranje.
mass are unfavourable for the foundation.
Zbog karakteristika stijenske mase koja je
Due to the characteristic of the rock mass that is
zastupljena na južnoj i dijelu zapadne i istočne
present on the eouth and part of the western side
strane oporca, potrebno je dodatno mišljenje
of the abutment, it is needed additional
Projektanta za uslove fundiranja temeljnog
Designer’s opinion for the conditions of
oporca O1 L.“
foundation of abutment O1 L.”
In the Annex to the same Geological Report, the
responsible Geologist states: U Aneksu istog Geološkog izvještaja odgovorni
Geolog navodi:
“After completion of the excavation and the
completed prospective boreholes of the „Nakon završetka iskopa i urađenih
abutment O1 L, due to a poor engineering- prospekcijskih bušotina u temeljnom iskopu
geological conditions in one part of the oporca O1 L, a zbog lošijih inženjersko-
foundation pit of funding of abutment, the geoloških uslova fundiranja stuba u jednom
Designer’s opinion on the method of abutment dijelu iskopa, zatraženo je mišljenje
foundation was requested. Projektanta o načinu fundiranja stuba.
Following the recommendation of the Po preporuci odgovornih Projektanata za most

15
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Responsible Designers for the bridge Suvovara, Suvovara, čiju izjavu prilažemo kao prilog uz
whose statement is attached as an annex to this ovaj aneks, izvršeno je produbljenje i čišćenje u
annex, deeping was done and the bottom of the južnom, zapadnom i istočnom dijelu do čvrste
southern, wastern and eastern part of the stijenske mase. Nakon čišćenja temeljnog
foundation pit of abutment O1 L was cleaned iskopa izvršena je zamjena materijala sa
untill the solid rock mass. After cleaning the betonom MB 30 do kote fundiranja.“
foundation pit, a replacement of the material
was made with concrete MB 30 to the level of
the foundation.”
In attached Opinion Regarding Foundation
Conditions at Abutment O1 L on Suvovara
Bridge at Smokovac – Uvač – Mateševo U priloženom Mišljenju u vezi uslova
Motorway Section, authors Kenan Imširpašić temeljenja oporca O1 L mosta Suvovara
and Enes Lakota – bridge Designers for autoputa Smokovac – Uvač – Mateševo,
Suvovara bridge it states: autora Kenana Imširpašića i Enesa Lakote –
Projektanata mosta Suvovara navedeno je:
“By email dated on 29 January 2018 You have
submitted to us Report About Engineering- „Putem elektronske pošte ste nam 29. januara
Geological Mapping at Foundation Pit of 2018 dostavili Izvještaj o inženjersko-
abutment O1-L at Suvovara Bridge and asked geološkom kartiranju temeljne jame oporca
for opinion. O1-L mosta Suvovara, te zatražili mišljenje.

We have reviewed mentioned Report as well as Pogledali smo pomenuti izvještaj, kao i
bedding stresses for abutment foundation O1-L. naprezanja temeljne stope oporca O1-L.

According to our opinion there are good Prema našem mišljenju za veći dio temeljne
conditions for bigger part of foundation. stope radi se o povoljnim uslovima za
Exception is only south part of construction pit, temeljenje. Izuzetak je južna strana temeljne
as well as registered cavern (dimensions jame, te dio oko registrovane kaverne
according to your report 2x0,7x3 m) Maximal (dimenzija prema Vašem izvještaju 2x0,7x3
bedding stresses for whole foundation are up to m).Maksimalna naprezanja cijelog temelja su
520 kPa in additional and seismic load do 520 kPa u dopunskim i izuzetnim
combinations. Permissible loads for abutment kombinacijama opterećenja. Dozvoljena
O1-L according to Geotechnical final report for opterećenja tla prema Geotehničkom elaboratu
Suvovara bridge are much higher than za oporac O1-L mosta Suvovara su znatno viša
mentioned values. od pomenutih vrijednosti.

Considering that foundation pit is dry and S obzirom da je temeljna jama suha i stabilna,
stable, we suggest keeping foundation of predlažemo zadržavanje temeljne stope O1-L
abutment O1-L with position and dimensiones as sa položajem i dimenzijama prema Glavnom
in Main Design, with construction of projektu, uz izradu zamjenskog materijala do
replacement materials on south part of pit, down geološki povoljnih slojeva ispod južnog dijela
to geologically favourable layers, as well as stope, kao i ispunu registrovane kaverne
concrete filling of registered cavern. betonom.

Weaker materials could be replaced with Zamjena lošeg materijala ispod temeljne stope
blinding concrete, or thicker layers with spar se može vršiti sa podložnim betonom ili na
concrete.” većim dubinama špar betonom.“

16
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

The Annex is accompanied by a Statement on U nastavku Aneksa priložena je Izjava o


the geotechnical conditions for the foundation geotehničkim uslovima fundiranja oporca
of the Suvovara Bridge abutment O1L, O1L mosta Suvovara, autora odgovornog
authored by the responsible Designer Peng Projektanta Peng Tingjia i geologa Saše
Tingjia and geologist Saša Cupać, which states: Cupaća, u kojoj je navedeno:

“After the excavation of foundation pits for „Nakon završetka temeljnih jama za oporac
abutment O1L was finished, we received letter O1L, dobili smo dopis podizvođača preduzeća
from Subcontractor, company Bemax, which was Bemax koji su upućeni Glavnom Izvođaču. U
sent to the Main Contractor. In letter, opinion of dopisima je priloženo mišljenje Projektanta g-
designers Mr Kenan Imširpašić and Mr Enes dina Kenana Imširpašića i g-dina Enesa
Lakota was submitted. The Report of Lakote. Takođe, dostavljen nam je Izvještaj o
engineering-geological mapping foundation pit, inženjersko-geološkom kartiranju temeljnog
done by geology engineer Radovan Čvorović, iskopa koje je izradio inženjer geologije
was also submitted. After the insight into this Radovan Čvorović. Nakon uvida u dostavljenu
letter, we make the following conclusion. dokumentaciju konstatovano je slijedeće:

By geological mapping of foundation pit of Geološkim kartiranjem temeljnog iskopa


abutment, it has been found that the lithological oporca utvrđeno je da je litološki sastav i IG
composition and EG characteristics correspond karakteristike odgovaraju Geotehničkom
to the Geotechnical Report for Suvovara bridge. elaboratu za most Suvovara.

Foundation pit is made of flysch sediments Temeljni iskop izgrađuju flišni sedimenti
presented by sandy limestones and sandstones, predstavljeni pjeskovitim krečnjacima i
while the southern side of the excavation was pješčarima, dok je južna strana iskopa
built from the decay of sandstone and sandy izgrađena od raspadine pješčara i pjeskovitih
limestone with content of the dusty-clay krečnjaka sa sadržajem prašinasto-glinovite
component. Compatibility is clearly visible with komponente. Slojevitost je jasno vidljiva sa
the fall towards north-east. padom prema sjeveroistoku.

Excavation is stabile, dry, excluding the western Iskop je stabilan i suv, izuzimajući zapadnu
side of the slope where is a leak of water. stranu kosine gdje je prisutno curenje vode.

In the south-western part of the excavation there U jugozapadnom dijelu iskopa prisutna je
is a cavern of dimensions 2x0,7x3 m (length x kaverna dimenzija 2x0,7x3 m (dužina x širina x
width x depth). dubina).

Eight prospecting studied boreholes were Urađeno je 8 prospekcijskih bušotina, kojima


drilled, which determinated the geological je utvrđena geološka građa terena ispod
structure of the terrain bellow the bottom of temeljnog dna oporca. Rezultati bušenja su
foundation of abutment. The drilling results pokazali nepovoljne IG karakteristike
showed unfavourable EG characterictics (degradirana stijena) u južnom dijelu temeljnog
(degradated rock) at the south part of dna i zoni kaverne.
foundation bottom and cavern area.
Due to the unfavourable EG characteristics of
Zbog nepovoljnih IG karakteristika stijenske
the rock mass in part of foundation pit, the
mase u dijelu temeljnog iskopa, zatraženo je od
Contractor asked an additional Designer’s
strane Izvođača dodatno mišljenje Projektanta
opinion for the conditions of foundation of

17
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

abutment. za uslove fundiranja oporca.


There are good conditions for bigger part of Veći dio temeljne stope izvodi se u povoljnim
foundation. Exception is only the south part of uslovima za temeljenje. Izuzetak je južna strana
construction pit, as well as registered cavern. temeljne jame, te dio oko registrovane kaverne.
Maximal bedding stresses for the whole Maksimalna naprezanja cijelog temelja su do
foundation are up to 520 kPa in additional and 520 kPa u dopunskim i izuzetnim
seismic load combinations. Permissible loads for kombinacijama opterećenja. Dozvoljena
abutment O1-L according to Geotechnical final opterećenja tla prema Geotehničkom elaboratu
report for Suvovara bridge are much higher. za oporac O1-L mosta Suvovara su znatno viša.
It is necessary to replace material below Potrebno je izvršiti zamjenu materijala ispod
foundation level of Suvovara bridge abutment kote fundiranja temelja oporca O1L mosta
O1L, where unfavourable rock mass is identified Suvovara, gdje je prospekcijskim bušotinama
by prospective boreholes. Replacement shall konstatovana nepovoljna stijenska masa.
made until the appearance of the favourable Zamjenu izvršiti do pojave povoljne stijenske
rock mass. Foundation bottom should be stepped mase. Dno temeljnih iskopa nakon zamjene
after replacement. treba formirati stepenasto.
Registered cavern shall be cleaned and filled Registrovanu kavernu treba očistiti i ispuniti
with concrete… betonom...
In the case of significant inflow of water into the U slučaju značajnijeg priliva vode u iskop
excavation (west slope), it must be removed. (zapadna kosina) istu ukloniti.
After removing unfavourable material, the Nakon uklanjanja nepovoljnog materijala,
foundation pit shall be filled with concrete temeljni iskop zapuniti betonom marke MB30
MB30 or in deeper layers with concrete MB30 ili na većim dubinama betonom MB30 u
combined with crushed solid limestone (spar kombinaciji sa lomljenim kamenom od svježe
concrete). krečnjačke stijene (spar beton).
Filling shall be performed up to the foundation Zapunjavanje izvesti do kote fundiranja. Nakon
level. Afterwards, it can be continued with toga, može se nastaviti sa slijedećim fazama
following stages of foundation construction. izgradnje temelja.“

18
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

3. TECHNICAL REVIEW OF 3. TEHNIČKI PREGLED


CONTRACTOR'S DOCUMENTATION DOKUMENTACIJE IZVOĐAČA
RADOVA
3.1. General comments
3.1. Opšti komentari
Both Claim Events; No. 054 and 054/2 are
related to existence of unfavourable material in Oba događaja potraživanja; br. 054 i 054/2
the parts of the bottom of the foundation pits for odnose se na postojanje nepovoljnog materijala
piers S2 L, S4 L, S5 L and abutment O1 L, with u dijelovima temeljnog dna temeljnih jama
appearance of the cavern in the zone of stubova S2 L, S4 L i S5 L i oporca O1 L,
foundation soil for abutment O1 L; described in zajedno sa pojavom kaverne u zoni temeljnog
the Claim Event 054/2. tla oporca O1 L; opisane u Događaju
Potraživanja 054/2.

3.2. Technical comments


3.2. Tehnički komentari

In all of attached Geological Reports related to


foundation pits described in the frame of the U svim priloženim Geološkim izvještajima
Claim Events No. 054 and 054/2, Contractor’s vezanim za temeljne jame opisane u okviru
Geologist in charge is stating: Događaja Potraživanja br. 054 i 054/2,
Izvođačev odgovorni Geolog izjavljuje:
“By geological mapping of foundation pit, it has
been found that the lithological composition and
„Geološkim kartiranjem temeljnoe jame
engineering-geological characteristics
utvrđeno je da litološki sastav i inženjersko-
correspond to the present in the Geotechnical
geološke karakteristike odgovaraju napisanom
Design for bridge Suvovara.
u Geotehničkom elaboratu za most Suvovara
In the statement for the foundation S2 L, Bridge
Designer stated: U Izjavi za temelj S2 L, Projektant mosta
navodi:
“…According to our opinion there are good
conditions for foundation. Exception is only
eastern part of construction pit.
„.Prema našem mišljenju radi se o povoljnim
Considering that foundation pit is dry and uslovima za temeljenje. Izuzetak je jedino
stable, where risk of loss stability is not istočna strana temeljne jame.
registered, we suggest keeping foundation of
S obzirom da je temeljna jama suha i stabilna,
pier S2-L with position and dimensiones as in
te da nije registrovana opasnost od gubitka
Main Design, with construction of replacement
stabilnosti, predlažemo zadržavanje temeljne
materials on eastern part of pit.
stope S2-L sa položajem i dimenzijama prema
Glavnom projektu, uz izradu zamjenskog
materijala do geološki povoljnih slojeva ispod
Weaker materials could be replaced with istočnog dijela stope.
blinding concrete, or thicker layers with spar
concrete.” Zamjena lošeg materijala se može vršiti sa
podložnim betonom ili na većim dubinama špar
Similar conclusion was done by the same authors betonom.“
on the issue of the foundation pit of abutment A1 Sličan zaključak donesen je od strane istih

19
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

L. autora po pitanju temeljne jame oporca O1 L.


Also, conclusion from Geotechnical Designers
Takođe, zaključak iz izjave geotehničkih
statement, related to the same foundation pits is:
Projektanata, vezan za iste temeljne jame je:
1. It is necessary to replace material
bellow foundation level of Suvovara bridge piers 1. Potrebno je izvršiti zamjenu materijala
S2L, S4L and S5L, where soil and weak rock ispod kote fundiranja temelja stubova S2L, S4L
mass are identify by prospective boreholes. i S5L mosta Suvovara, gdje je prospekcijskim
Replacement shall be made untill the bušotinama konstatovano tlo i loša stijenska
appearance of the favourable rock mass of masa. Zamjenu tla izvršiti do pojave povoljne
geotechnical category D. Foundation bottoms stijenske mase geotehničke kategorije D. Dno
should be stepped after replacement. temeljnih iskopa nakon zamjene treba formirati
stepenasto.
2. Based on information from the terrain 2. Na osnovu informacija sa terena, uvidu
and annexes of geological mapping reports, as u anekse geoloških izvještaja o kartiranju, kao i
well as consultations with the Engineer and the konsultacija sa Nadzorom i Izvođačem, od
Contractor. Contractor is required after Izvođača se traži da nakon što je uklonio loš
remooving unfavourable material to fill materijal, zapuni temeljni iskop betonom marke
foundation pit with concrete MB30, or in deeper MB30, ili na većim dubinama betonom MB30 u
layers with concrete MB30 combined with kombinaciji sa lomljenim kamenom od svježe
crushed solid limestone (spar concrete). Filling krečnjačke stijene (špar beton). Zapunjavanje
shall be performed up to the foundation level. izvesti do kote fundiranja. Nakon toga, može da
Afterwards, it can be continued with next stages se nastavi sa slijedećim fazama izgradnje
of foundation construction. temelja.“
Similar conclusion was done by the same
authors on the issue of the foundation pit of Sličan zaključak donesen je od strane istih
abutment A1 L. autora po pitanju temeljne jame oporca O1 L.

Also, we are referring to the Geotechnical Final Pozivamo se na Elaborat o detaljnim


Report for Main Design for the Suvovara geotehničkim istraživanjima za nivo glavnog
Bridge; chapter 7 CONCLUSION, where is građevinskog projekta za most Suvovara;
stated as follow: poglavlje 7 ZAKLJUČAK, gdje je izjavljeno
slijedeće:
Geotechnical Final Report for bridge Suvovara
has been made according to the Design of Geotehnički elaborat za most Suvovara, urađen
detailed geotechnical investigations, and is a je shodno Projektu detaljnih geotehničkih
synthesis of the research results from this phase, istraživanja, i kao takav predstavlja sintezu
previous phases and analysis of available fund rezultata istraživanja iz ove faze, prethodnih
documentation from similar projects in the faza i analize razpoložljive fondovske
flysch terrains. dokumentacije sličnih projekata na flišnim
terenima.
Based on the investigation results, we have
defined the geological, hydrogeological, Na osnovu rezultata istraživanja definisali smo
engineering-geological and geotechnical geološke, hidrogeološke, inženjerskogeološke i
conditions for construction of the bridge. We geotehničke uslove izgradnje mosta. Takođe
have also defined the necessary scope of smo definisali potreban obim geotehničkog
geotechnical monitoring and supervision over monitoringa i nadzora izrade mosta s kojim če
bridgeconstruction with which conditions for se moći optimizovati uslovi izgradnje. U cjelini
construction will be optimized. Taken as a gledano, geotehnički uslovi gradnje mosta

20
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

whole, geotechnical conditions of construction Suvovara su relativno povoljni na lijevoj traci i


of bridge Suvovara are relatively favourable on nešto manje povoljni na desnoj traci.
the left lane and somewhat less favourable on
Proračuni koje smo napravili ukazuju na to da
the right lane.
se može fundiranje na obje trake izvesti plitko
However, the results of the calculations have ili duboko fundiranje.
shown that bridge can be founded both; on
Ali pritom je potrebno uzeti u obzir da kod
shallow or deep foundations.
iskopa građevinske jame može doći (u
However, we have to take into account the hidrološkom maksimumu) do povećanih dotoka
possibility of increased groundwater discharges podzemne ili površinske vode u jamu, što može
in the hydrogeological maximums into dovesti do degradacije fliša i njegovog
construction pits and the support locations. This slabljenja u smislu nosivosti i slijeganja. To
can lead to degradation of the flysch and partial pogotovo važi za zonu desne trake gdje se
loss of bearing capacity and higher settlrements. javlja slabiji fliš. Stoga smatramo, da je barem
This is especially relevant to the right lane, za desnu traku primjerenije fundiranje na
where weaker flysch was found. Therefore, we šipovima.
are recommended that deep foundation is
Konačnu odluku o vrsti fundiranja prepuštamo
considered at least for the right lane.
projektantu, koji će izabrati način fundiranja
The final choice should certainly be made by na osnovu tehničko-ekonomske analize.
designer on the bases of a technical and
economic analysis.

3.3. Technical conclusion 3.3. Tehnički zaključak

21
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

In supporting documents for the Claim Events


No. 054 and 054/2, Contractor explained
unforeseeable geological conditions as a U pratećim dokumentima Događaja
consequences of: Potraživanja br. 054 i 054/2, Izvođač je
objasnio nepredvidive geološke uslove kao
“On construction site of Subsection 3.1, the poslijedice:
Contractor encounter a change in the geological
conditions at the bridge #6 Suvovara at the „Na gradilištu podsekcije 3.1 Izvođač se susreo
bottom of the foundation of piers P2L, P4L and sa promjenom geoloških uslova na mostu br. 6
P5L.” Suvovara, temelji stubova S2L, S4L i S5L i
temelj oporca O1L.“
We are referring to the Preliminary Design for
Suvovara bridge, where was stated: “Deluvial Pozivamo se na Idejni projekt za most
deposits are variable thicknesses from 1 to 3 m. Suvovara u kojem je navedeno: „Deluvijalne
Certainly, the greater thickness of deluvial naslage su promjenjive debljine od 1 do 3
deposits is not excluded locally, in the form of m. Svakako, da se lokalno ne isključuje, u
pockets.” vidu džepova, i veća debljina deluvijalnih
naslaga.“
From our point of view, weaker materials
replacement with blinding concrete, or in thicker
layers with spar concrete, cannot be taken into Sa naše tačke gledišta, zamjena lošeg
consideration as any kind of Unforeseeable materijala koja se vrši sa podložnim betonom ili
Works taking into account Sub-Clause 13.9 of na većim dubinama špar betonom se ne može
Particular Conditions, where Unforeseeable uzeti u obzir kao bilo koja vrsta nepredvidivih
works are the works that relate to variation of radova, uzimajući u obzir podklauzulu 13.9
the scope of work due to changed geological, Posebnih uslova, gde su nepredvidivi radovi
hydrogeological and ecological conditions in radovi koji se odnose na izmjene u opsegu
relation to the delivered Preliminary Design. radova zbog promijenjenih geoloških,
hidrogeoloških i ekoloških uslova u odnosu na
dostavljeni Idejni projekat.

4. GENERAL DESCRIPTION 4. OPŠTI OPIS

22
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Along the terrain of the Bar-Boljari highway,


section UVAČ-MATEŠEVO, through which the
designed Suvovara bridge is to be constructed, Duž terena autoputa Bar-Boljari, dionica
the terrain is geologically built by: SMOKOVAC - UVAČ, kroz koji se treba izvesti
projektovani most Suvovara teren geološki
Upper Cretaceous (K23F) izgrađuje:
The basic rock mass is represented by flysch Gornja kreda(K23F)
sediments that occur in the facies of siltstones,
sandstones and packets of limestone. Deluvial Osnovnu stijensku masu predstavljaju flišni
deposits are of variable thickness from 1 to 2 m. sedimenti koji se javljaju u faciji alevrolita,
They are heterogeneous in composition. The pješčara i paketa krečnjaka. Deluvijalne
dusty-sandy fraction with variable crumb naslage su promjenljive debljine od 1 do 2 m.
content (marl siltstones) dominates. Due to the Heterogenog su sastava. Dominira prašinasto
dusty-sandy fraction, they are generally of low pjeskovita frakcija sa promjenljivim sadržajem
plasticity and hard consistency (Ic> 1). Due to drobine (laporci alevroliti). Zbog prašinasto
the relatively small transport, the pieces are pjeskovite frakcije generalno su niske
semi-rounded, ie with rare grains of gravel. plastičnosti i tvrde konzistencije (Ic>1).U
They are mostly water-saturated, medium- koritu potoka je puliciklična facija – mješavina
consolidated and medium-compressible. aluvijalnih deluvijalnih naslaga. Zbog
relativno malog transporta, komadi su
poluzaobljeni, odnosno sa rijetkim zrnima
šljunka. Uglavnom su vodozasićene, srednje
konsolidovane i srednje stišljive.

5. PRELIMINARY DESIGN 5. IDEJNI PROJEKAT

23
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

We refer to the Elaborate on detailed


geotechnical investigations (bases for the level
of preliminary construction design) - Section Pozivamo se na Elaborat o detaljnim
Uvac - Matesevo, where in the Separate for geotehničkim istraživanjima (podloge za
bridges - Bridge No. 6 SUVOVARA (CH. km nivo idejnog građevinskog projekta) –
22+749,98 to km 22+991,41 right lane dionica Uvač – Mateševo, gdje je Separatu za
L=241,43) (ch. km 22+742,02 do km mostove – MOST 6 SUVOVARA (st. km
22+925,46 left lane L=183,44), chapter 2. 22+749,98 do km 22+991,41 desna traka
TYPES AND SCOPE OF PERFORMED L=241,43) (st. km 22+742,02 do km
WORKS was stated: 22+925,46 lijeva traka L=183,44), u poglavlju
2. VRSTE I OBIM IZVEDENIH RADOVA
““The following investigation works were navedeno:
carried out at the location of the Suvovaar
Bridge:
-Three trial pits: J-20; J-21 and J-25 (Appendix “Na lokaciji mosta Suvovara izvedeni su
No. 6.4); sljedeći istražni radovi:

"Two geoelectric sondes GS63 and GS64 ." -Tri istražne jame: J-20; J-21 i J-25 (prilog br.
6.4.);
In Chapter 3. GEOTECHNICAL
CONDITIONS OF BRIDGE -Dvije geoelektrične sonde GS63 i GS64..”
CONSTRUCTION; subchapter 3.1. The U poglavlju 3. GEOTEHNIČKI USLOVI
morphological properties of the terrain stated: IZGRADNJE MOSTA; potpoglavlje 3.1.
“The valley sides are extremely asymmetrical. Morfološka svojstva terena navedeno je:
The right side up to 25⁰, and the left valley side “Dolinske strane su izrazito asimetrične.
has a much milder slope. They were formed Desna strana do 25⁰, a lijeva dolinska strana
within the flysch sediment and Cretaceous- je znatno blažeg nagiba. Formirane su u
Paleogene age, on the sides of which, due to the okviru sedimenta fliša i kredno-paleogene
disintegration of rock masses and planned starosti, po čijim stranama su
leaching, deluvial sediment is deposited. ” dezintegracijom stijenskih masa i planiranim
In Chapter 3.7. Analysis of geotechnical spiranjem, deponovanja deluvijalni sediment.”
conditions for bridge construction; subchapter U poglavlju 3.7. Analiza geotehničkih uslova
3.7.1. Analysis of funding conditions states: izgradnje mosta; potpoglavlju 3.7.1. Analiza
“All piers should be funded in the basic rock uslova fundiranja navedeno je:
mass. The criterion of the depth of the “Sva stubna mjesta treba fundirati u
foundation pit to enter the basic rock mass is osnovnoj stijenskoj masi. Kriterijum dubina
min. 2.5 to 3.0 m. Resistant and deformable temeljne jame da se u osnovnu stijensku
characteristics of the relatively weakest, in the masu uđ|e min. 2,5 do 3,0 m. Otporne i
mechanical sense, lithological members - clays deformabilne karakteristike i relativno
and siltstones are in such a range that the najslabijih, u mehaničkom smislu, litoloških
occurrence of uneven subsidence and exceeding članova – glinaca i alevrolita su u
the allowable load capacity is excluded. The takvom rasponu da se isključuju pojave
minimum value of the permissible load is 0.4 neravnomjernog slijeganja i prekoračenja
MPa. The resistance of rock masses to dozvoljene nosivosti. Minimalna vrijednost
excavation is small, so the excavation can be dozvoljene nosivosti iznosi 0,4 MPa.
performed completely mechanically. Temporary Otpornost stijenskih masa prema iskopu je
protection of the foundation excavation can be mala pa se iskop u potpunosti može izvesti

24
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

provided by a wide excavation with a slope mehanizovano. Privremena zaštita temeljnog


inclination of 1.5: 1.0. Only in the central part of iskopa može se obezbijediti širokim iskopom
the designed bridge, in the closestzone of the sa nagibom kosina 1,5:1,0. Samo u
stream, smaller occurrences of groundwater are centralnom dijelu projektovanog mosta, u
expected. Groundwater can be easily evacuated neposrednoj zoni potoka, očekuju se manje
from drainage pits by sludge pumps. Provision pojave podzemne vode. Iz drenažnih jama
should be made for a leveling layer (tampon) of podzemna voda se može lako evakuisati
lean concrete up to 0.1 m thick. If possible, the muljnim pumpama. Treba predvidjeti
piers should be placed outside the influence of izradu izravnavajućeg sloja (tampona) od
the stream in order to make the foundation pits mršavog betona debljine do 0,1 m. Ukoliko je
execution in dry. ” moguće stubna mjesta postaviti izvan uticaja
potoka kako bi se temeljne jame izvele u
In Chapter 4 CONCLUSION states: “The
suvom.”
terrain in the bridge zone is built mainly of
flysch sediments represented by claystones, U poglavlju 4. ZAKLJUČAK navedeno je:
thin-layered marls, sandstones and sandy “Teren u zoni mosta izgrađuju u osnovi
limestones, while in the surface parts deluvial- flišni sedimenti predstavljeni glincima,
eluvial sediments of small thickness are tankoslojevitim laporcima, pješčarima i
present. These are relatively well-bearing rock pjeskovitim krečnjacima, dok su u površinskim
masses and represent a favorable geotechnical djelovima zastupljeni deluvijalno-eluvijalni
environment for the foundation of bridge piers. sedimenti male debljine. Radi se o relativno
It is recommended that the bridge piers be dobro nosivim stijenskim masama i
founded in the basic rock mass - flysch at a predstavljaju povoljnu geotehničku sredinu za
depth of min. 2.5 - 3 m. fundiranje mostovskih stubova. Preporučuje se
da se mostovski stubovi fundiraju u osnovnoj
In the Partial Report on geotechnical
stijenskoj masi – flišu na dubini min. 2,5 – 3 m.
investigations of the terrain, within the
corridor of the designed route of the highway U Parcijalnom Izvještauj o geotehničkim
Bar - Boljari, section Podgorica - Veruša, istraživanjima terena, unutar koridora
part Veternik - Čestograzst. km 19 + 625 to projektovane trase autoputa Bar – Boljari,
km 32 + 743; Chapter 2 ANALYSIS OF dionica Podgorica – Veruša, dio Veternik
GEOTECHNICAL CONDITIONS OF -Čestograzst. km 19+625 do st. km
HIGHWAY CONSTRUCTION states the 32+743; u poglavlju 2. ANALIZA
following: GEOTEHNIČKIH USLOVA GRAĐENJA
AUTOPUTA navedeno je slijedeće:
Zone 43- bridge km 22 + 744– km 22 + 928
(Suvovara M-6 bridge)
The Suvovara Bridge is designed over a wide Zona 43- most st. km 22+744– st. km 22+928
valley, ie it bridges a stream with a permanent (most Suvovara M-6)
watercourse along which the road to Močila
Most Suvovara projektovan je preko široke
and Ptić goes. The valley sides are
doline, odnosno premošćuje potok sa stalnim
asymmetrical, the right side is steeper up to
vodotokom duž kojeg ide put za Močila i
25⁰, and the left valley side has a much milder
Ptić. Dolinske strane su asimetrične, desna je
slope - 10⁰. The basic rock mass is represented
strmija do 25⁰, a leva dolinska strana je
by flysch sediments that occur in the facies of
siltstones, sandstones and packets of limestone. znatno blažeg nagiba - 10⁰. Osnovnu stensku
The bridge is of great length - 390 m. The masu predstavljaju flišni sedimenti koji se
maximum height of the bridge is about 20 m. javljaju u faciji alevrolita, peščara i paketa
Deluvial deposits are variable thicknesses from krečnjaka. Most je velike dužine – 390 m.

25
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

1 to 3 m. Certainly, the greater thickness of Maksimalna visina mosta je oko 20 m.


deluvial deposits is not excluded locally, in the Deluvijalne naslage su promenljive debljine
form of pockets. The thickness of alluvial od 1 do 3 m. Svakako, da se lokalno ne
deluvial deposits up to 3.0 m thick is expected isključuje, u vidu džepova, i veća debljina
in the stream bed. In any case, the piers should deluvijalnih naslaga. U koritu potoka očekuje
be funded in the basic rock mass, which would se debljina aluvijalno deluvijalnih naslaga
go at least 1.5 to 2.0 m deep. The estimated debljine do 3,0m. U svakom slučaju stubna
depth would be about 4-5 m. The resistant and mesta treba fundirati u osnovnoj stenskoj
deformable characteristics of even the weakest, masi, u koju bi se zašlo min 1,5 do 2,0 m.
in the mechanical sense lithological members - Procenjena dubina bi bila oko 4-5m.
clays and claystones - are in such a range that Otporne i deformabilne karakteristike i
the phenomena of uneven subsidence and relativno najslabijih, u mehaničkom smislu
exceeding the allowed bearing capacity are litoloških članova –glinaca i alevrolita su u
excluded. The minimum value of the takvom rasponu da se isključuju pojave
permissible load is 400 kPa. The resistance of neravnomernog sleganja i prekoračenja
rock masses to excavation is small and can be dozvoljene nosivosti. Minimalna vrednost
executed completely mechanically. Temporary dozvoljene nosivosti iznosi 400 kPa.
protection of the excavation of the foundation Otpornost stenskih masa prema iskopu je
pits can be provided by a wide excavation with mala i u potpunosti se može izvesti
a slope of 1.5: 1.0. Only in the central part of mehanizovano. Privremena zaštita temeljnog
the designed bridge, in the close zone of the iskopa može se obezbediti širokim iskopom sa
stream, smaller occurrences of groundwater nagibom kosina 1,5:1,0. Samo u centralnom
are expected. Groundwater can be easily delu projektovanog mosta, u neposrednoj
evacuated from drainage pits with sludge zoni potoka, očekuju se manje pojave
pumps. It should be planned to make a leveling podzemne vode. Iz drenažnih jama muljnim
layer (tampon) from lean concrete up to 0.1 m pumpama podzemna voda se može lako
thick.” evakuisati. Treba predvideti izradu
izravnavajućeg sloja (tampona) od mršavog
betona debljine do 0,1 m.“

26
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 3: FINAL GEOTECHNICAL REPORT for preparation of the Preliminary Design for Bar-
Boljare Highway, section: Podgorica - Veruša – Engineering-Geological map for location of the Suvovara
bridge
Slika 3: ELABORAT DETALJNIH GEOTEHNIČKIH ISTRAŽIVANJA za izradu Idejnog projekta
autoputa Bar-Boljare, deonica: Podgorica - Veruša – Inženjerskogeološka karta na lokaciji mosta
Suvovara

27
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 4: FINAL GEOTECHNICAL REPORT for preparation of the Preliminary Design for Bar-
Boljare Highway, section: Podgorica - Veruša – Longitudinal EG section for location of the Suvovara
bridge
Slika 4: ELABORAT DETALJNIH GEOTEHNIČKIH ISTRAŽIVANJA za izradu Idejnog projekta
autoputa Bar-Boljare, deonica: Podgorica - Veruša – Podužni IG profil na lokaciji mosta Suvovara

6. CONCLUSION ON PRELIMINARY 6. ZAKLJUČAK U VEZI SA IDEJNIM

28
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

DESIGN PROJEKTOM
Taking into account main purpose of the Uzimajući u obzir glavnu svrhu Idejnog
Preliminary Design to provide an input data to projekta da obezbijedi ulazne podatke za
Design-and- Built Contractor; by relatively low, izvođača radova na projektovanju i izgradnji;
but sufficient level of geotechnical relativno niskim, ali dovoljnim nivoom
investigations, foundation soil with higher geotehničkih istraživanja, temeljno tlo sa većom
thickness of dilluvial deposits, as well as debljinom deluvijalnih naslaga, kao i lokalna
forming of the pockets was forecasted in related mogućnost pojave džepova predviđena je u
Geotechnical Report and Partial Report. All vezanom Geotehničkom elaboratu i Parcijalnom
mentioned documents were available to the izvještaju. Svi navedeni dokumenti bili su
Contractor in the tendering stage of the Project. dostupni Izvođaču u tenderskoj fazi Projekta.
Also, the general geotechnical model of the Takođe, generalni geotehnički model terena
terrain observed during the foundation pits zatečen iskopom temeljnih jama (veći dio
excavation (most of excavation of foundation pit temeljnog iskopa izgrađuju flišni sedimenti
contracts flysch sediments, represented by sandy predstavljeni pjeskovitim krečnjacima i
limestones and sandstones, while smaller of the pješčarima, dok je manji dio iskopa izgrađen od
excavation was build from decay of sandstone raspadine pješčara i pjeskovitih krečnjaka sa
and sandy limestone with the content of the sadržajem prašinasto-glinovite komponente) u
dusty-clay component) match in total potpunosti odgovara opisima iz geotehničke
descriptions from geotechnical documents from dokumentacije Idejnog projekta.
Preliminary Design.
Bearing in mind all above mentioned, as well as
Imajući u vidu sve gore navedeno, kao i
the fact that mentioned information is considered
činjenicu da se pomenute informacije smatraju
as sufficient for the level of Preliminary Design,
dovoljnim za nivo Idejnog projekta, kao i
as well as the fact that Design and Built
činjenicu da je Izvođač radova na projektovanju
Contractor is experienced and worldwide
i izgradnji iskusan i svjetski priznat Izvođač, sa
recognized Contractor, with previous knowledge
prethodnim poznavanjem sličnih radova u
of similar Works in similar environment, the
sličnom okruženju, mišljenje Nadzornog organa
Engineer's opinion is that mentioned phenomena
je da se pomenuti fenomen ne može tretirati kao
cannot be treated as Unforeseeable Geological
nepredvidivi geološki uslovi.
Conditions.

7. CONTRACTOR'S CLAIM ANALIZY 7. ANALIZA POTRAŽIVANJA

29
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

In this Expert's Witness Report we have also IZVOĐAČA RADOVA


analysed Contractor's Claims No. 054 and 054/2
U ovom Izvještaju eksperta smo takođe
for Additional Payment (under SC 20.1). Our
analizirali Potraživanja izvođača br. 054 i 054/2
clarification is follow:
za dopunsko plaćanje (pod SC 20.1). Naše
Description of Employer's risk event: pojašnjenje je sljedeće:
Unforeseeable difficulties caused by changes
Opis slučaja rizika za poslodavca:
in geological conditions
nepredvidive teškoće izazvane promjenama
The Contractor is making a claim in accordance u geološkim uslovima
with Sub-Clause 4.12 and Sub-Clause 13.9. The
Izvođač radova potražuje prema p.kl. 4.12 i
Engineer understands and they are concluding
p.kl. 13.9. Nadzorni organ razumije i zaključuje
the following:
sljedeće:
The Engineer took into account actual physical
Nadzorni organ je uzeo u obzir stvarne fizičke
conditions observed on the site during the events
uslove uočene na lokaciji tokom događaja
described in this Contractor's Claim, as well as
opisanih u ovom potraživanju Izvođača, kao i
the evidences of the physical conditions which
dokaze o fizičkim uslovima koje Izvođač može
may be foreseen by the Contractor when
predvidjeti prilikom podnošenja ponude – na
submitting the Tender - available to the
raspolaganju Izvođaču.
Contractor.
Po mišljenju Nadzornog organa, idejni projekat
As per the Engineer's opinion, Preliminary
- svi gore navedeni djelovi koji se odnose na
Design – all the above mentioned parts related to
Most br. 6 – most Suvovara su validni
the Bridge No. 6 - Suvovara bridge are valid
dokumenti, poznati izvođaču radova prilikom
documents, familiar to the Contractor when
dostavljanja ponude.
submitting the tender.
Navedena Dokumentacija, koja je dio Idejnog
The mentioned Documentation, which is a part
projekta, na osnovu izvedenih Geotehničkih
of the Preliminary Design, on the basis of the
istraživanja (GI) za okvir Idejnog projekta daje
executed Geotechnical explorations for the scope
preliminarne ulazne geološke i geotehničke
of the Preliminary Design, provides for input
podatke Izvođaču definisanjem opštih
geological and geotechnical data to the
predviđenih geoloških uslova, pa donosimo
Contractor by defining general foreseen
slijedeći konačan zaključak:
geological conditions, so we are making the
following final conclusion:

8. FINAL CONCLUSION 8. KONAČAN ZAKLJUČAK

30
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Engineer's conclusion on Preliminary Design


facts is following:
Zaključak Nadzornog organa o činjenicama u
 Mentioned Geotechnical elaborate was vezi sa Idejnim projektom je sljedeći:
done for the purpose of providing an
elementary Geotechnical data for the stage  Navedeni Geotehnički elaborat je urađen u
of the Preliminary Design; cilju obezbjeđivanja elementarnih
geotehničkih podataka za fazu idejnog
 Data were based on detailed Engineering –
projekta;
geological mapping of the area, trial pits
execution and geoelectrical sondage of the  Podaci su zasnovani na detaljnom
area – as per the Engineer's point of view inženjersko - geološkom istraživanju
sufficient for the stage of the Preliminary područja, istražnim raskopima i
Design; geoelektričnom sondairanju terena – prema
Nadzornom organu dovoljnoj za fazu
 An unambiguous geological description of
Idejnog projekta;
the terrain is given, with a defined
possibility of encountering lots of softer  Dat je nedvosmisleni geološki opis terena,
material, which needs to be removed and sa definisanom mogućnosti nailaska na
gradually replaced with blinding concrete: partije mekšeg materijala, kojeg je
Deluvial deposits are variable thicknesses potrebno ukloniti i stepenasto zamijeniti
from 1 to 3 m. Certainly, the greater podložnim betonom: Deluvijalne naslage
thickness of deluvial deposits is not su promenljive debljine od 1 do 3 m.
excluded locally, in the form of pockets. Svakako, da se lokalno ne isključuje, u
Clarification: in the Preliminary design vidu džepova, i veća debljina deluvijalnih
that the same type of geological sediments naslaga. Pojašnjenje: Idejnim projektom
will be encountered as the ones encountered naglašeno da će se naići na isti tip
by the Contractor during the execution of geoloških sedimenata na koje je i Izvođač
the excavation (flysch sediments), the naišao tokom izvođenja iskopa (flišni
difference is only in the degree of the sedimenti) razlika je samo u stepenu
surface decomposition of these sediments površinskog raspadanja ovih sedimenata i
and that is not the case throughout the entire to ne na cijelim površinama temeljnih jama
surface of the foundation pits, but along the već duž mikrolokacija gdje su površinski
micro-location where the surface flysch flišni sedimenti više raspadnuti. Sa naše
sediments are more decomposed. From our tačke gledišta, zamjena lošeg materijala
point of view, replacement of weaker koja se vrši sa podložnim betonom ili na
materials with blinding concrete, or in većim dubinama špar betonom se ne može
thicker layers with spar concrete, cannot be uzeti u obzir kao bilo koja vrsta
taken into consideration as any kind of nepredvidivih radova.
Unforeseeable works. Poređenjem gore navedenih zaključaka
By comparison of above mentioned Engineer's Nadzornog organa sa podtačkom 1.1.6.8.
conclusions with Sub-Clause 1.1.6.8. Nepredvidivo predstavlja nešto što iskusni
“Unforeseeable” means not reasonably Izvođač razumno nije mogao da predvidi do
foreseeable by an experienced Contractor by the vremena podnošenja Ponude; Inženjer
date for submission of the Tender; the Engineer podrazumijeva da nastale fizičke uslove
considers that incurred physical conditions nabrojene u ovom Izvještaju treba tretirati kao
encountered under these report are foreseeable predvidive fizičke uslove od strane Iskusnog
physical conditions by experienced contractor Izvođača (Rizični Događaji po Izvođača) prema
(Contractor’s Risk Events) under the Terms of Ugovornim Uslovima, bazirano na osnovu
the Contract based on available documents by raspoložive dokumentacije dostupne do datuma

31
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

the time of the tender. Accordingly, all costs za podnošenje ponude. Sukladno, svi troškovi
attributable for dealing with these events in the koji se mogu pripisati suočavanju s tim
stage od design, build and remedy of defects are događajima u fazi projektovanja, izgradnje i
included in the Accepted Contract Amount. otklanjanja nedostataka uključeni su u
Design-and-Built Contractor wasn’t limitated in prihvaćeni Ugovorni Iznos. Izvođač na
choosing of type and quantity of geotechnical projektovanju i izgradnji ničim nije bio
investigations; in order to get accurate data on limitiran u odabiru vrsta i količine geotehničkih
geotechnical environment of foundation soil and istraživanja; a u svrhu dobivanja što preciznijih
founding type of the bridge. podataka o geotehničkoj sredini u kojoj se
nalazi temeljno tlo i tipu fundiranja mosta.
Nadzorni organ konstatuje da se pomenuti
The Engineer is hereby establishing that the radovi ne mogu tretirati kao nepredvidivi
mentioned works may not be treated as radovi, uz obrazloženje da radovi mogu biti
Unforeseeable works, with an explanation that predviđeni od strane iskusnog izvođača radova
the works may be foreseen by the experienced iz dostavljenog Idejnog projekta.
Contractor from the delivered Preliminary
Design. Prema mišljenju Inženjera, riječ je o relativno
plitkim zonama deluvijalnog materijala
According to the Engineer, these are relatively rasprostranjenog na manjim površinama
shallow zones of deluvial material spread over temeljnih stopa, a što bi trebalo biti predvidivo
smaller areas of the foundation feet, which od strane Iskusnog Izvođača.
should be foreseen by an Experienced
Contractor. Imajući na umu činjenicu da je Podizvođač
izvodio izgradnju mosta Suvovara, sa
Bearing in mind the fact that Suvovara bridge Ugovorom baziranim na jediničnim količinama
construction was executed by the Sub- izvedenih radova, a ne Projektovanje i
Contractor; with the Contract based on unit izgradnja, kao Ugovor Glavnog Izvođača,
quantities of executed works, not Design-and- prema mišljenju Inženjera, ovo potraživanje
Built, as the Contract of the Main Contractor, as nema činjenično ni ugovorno utemeljenje u
per the Engineer’s opinion, this claim is neither Ugovoru sa Investitorom.
factually nor contractually founded in the
Contract with the Employer. Imajući na umu sve gore navedeno, mišljenje
Inženjera je da potraživanja Izvođača nisu
So, bearing in mind all above mentioned, the opravdana.
Engineer’s opinion is that Contractor’s claims
should be treated as unjustified.