Induction Voltage Regulator
Operation Manual
Ⅲ. Specification ---------------------------------------------------------------- 3
Ⅳ. Functions -------------------------------------------------------------------- 4
Ⅺ. Troubleshooting-----------------------------------------------------------17
Ⅻ. Maintenance ---------------------------------------------------------------18
Ⅰ. Safety Attentions
˙ Before the device is used, please read this manual, and follow the instructions and steps to operate.
˙ Please put the manual in the place where it safe and near the device for access at any time.
˙ Do not use non-original accessories proposed by the manufacturer in order to avoid danger.
˙ To keep the cooling effect and normal operation of the device itself, do not jam the vent of the cooling motor,
and keep the device back away from the wall at least 10 centimeters (four inches) to keep the vent unblocked.
˙ First determine the specification of the power supply before connecting the power cord with the power to
avoid the device to be damaged; when connecting the input and output terminals, the power cord must be
connected properly to prevent poor contact and to prevent the electric shock.
˙ There are different installation standards for the different capacities and input voltages; please select the
proper configuration mode in accordance with the capacity and input voltage, and pay attention to the wiring
˙ Do not put heavy items onto the power cord and a fix properly it to avoid stumbling pedestrians.
˙ Do not use the power cord with overload to prevent electric shock or to cause a fire hazard.
˙ Please handle it based on the exception handling procedure if there is abnormal phenomenon.
˙ Prevent any liquid and debris entering the inside of the device in order to prevent an electric shock or fire due
1. Please shut off the regulator if there is a good lightning protection measure when it is storm or lightning.
3. Please keep it away from the fire source and high temperature to prevent too high temperature of it.
E1+E
2
R
S θ
E2=E1cosθ 3
1 2 E1
Major mechanical components are the rotation part R and static part S (as shown in the diagram above). The winding
around the inside of rotation part R is the primary winding which is parallel with the power supply line, and the winding of
static part S is the secondary winding which is in series with the same load. When a certain primary voltage E1 is input into
3-4, the induced voltage by the secondary winding will change as the angle θ of this two windings changes, E2=E1cos
θ will change continuously; if 2-3 is connected together, the voltage between 1 ~ 4 terminal equals the voltage of
E1+E2=E1 (1+cosθ), two windings are parallel in the same direction, the terminal voltage among 1-4 is the largest and
is E1+E2. As for the perpendicular angle between two mutual windings, there is not the induced voltage in the secondary
winding, E2=0, and the terminal voltage equals to the supply voltage E1; If the rotation part again is switched to the angle
of greater than 90 °, there is also the induced voltage in the secondary winding. But the induced voltages E1 and E2 are
contrary, and the terminal voltages equal to the difference between E1 and E2.
From the above, according to the relative positions of the primary and secondary windings, when there is a load,
continuously also adjust the voltage under the changes of magnetic flux. This voltage regulator is a stationary device
without noise. The advantage lies in manufacturing capacity, strong instantaneous overload capability and low failure rate.
Introduction to Model
CLSK model: A current and voltage directive meter; detection alarm for too high input voltage, too low input voltage,
overload, under-phase and reverse phase and abnormal voltage; manual control of decreasing or increasing voltage; plus
The cabinet can also be beyond the control of distribution switches, power-off function to do to protect the load.
● Check whether there is some exterior damaged. Because regulators may be transported for the different modes of
transport and will suffer damage due to improper transportation, if there is failure, please do not input voltage, and
3. Nameplate Specification:
INDUCTION VOLTAGE REGULATOR
Example: CLS 500KVA
MODEL CLS----30500
MANUFACTURE No.
DELIVERY DATE
CAPACITY KV
500 400 KW
A
PHASE 3 Φ 4W FREQUENCY 50/60 Hz
INPUT VOLTAGE 380 V± 15 % RATED CURRENT 750 A
1 ENVIRONMENT <55
OUTPUT VOLTAGE 380 V± % ℃
TEMPERATURE
-6-
Ⅶ. Wiring and Installation
(1) Wiring attentions:
1. Before the voltage wire is input to the power supply, first determine the specification of the power supply, to avoid
2. The different installation standards are for the regulators with different capacities and input voltages; and follow the
capacity and the input voltage to choose an appropriate manner about wiring, and the particular attention should be
3. Pay attention to the input terminal of the regulator, which should be avoided to share the same switch with other
4. When connecting the input and output terminals, make sure that the power wire is connected properly, to prevent poor
5. Whether single-phase or three-phase series regulators, when wiring, the polarity of the voltage should be aware of.
6. For three-phase series regulators, particularly pay attention to the phase sequence wiring of input and output.
7. When wiring, please turn off the power, it is forbidden to operate with the live wire for safety.
8. Please refer to the electrician regulations or the current table of wire safety in page 9 to implement wiring.
9. Connect the input voltage of three-phase series regulators to one side of the voltage switch and connect the output
voltage of the voltage to the output connector. In addition, the neutral (N-water line) wires have clearly marked labels
(input and output will share the same terminal), please connect as required.
10. For the requirements of the grounding system, please refer to page 10.
Note: the diameter specifications listed in the table, as only reference. (The distance
between two points must be considered for wire).
2. Grounding line has a resistance of at least 8AmG or the line with the same size as the power line matches with the
3. Please make full use of the contact of the grounding rod or the contact within the switchboard as the grounding line.
4. Grounding types:
Manual function:
JP6
1. . Internal voltage regulator power to control the DIP switch plate JP6, Manual
Automatic
plate location in manually. (Such as the right)
2. Open the regulator input supply, operation, automatic operation, manual operation of lights.
3. Pressed on the control panel to manually step-up, step-down button, and observe the action whether it is
4. All normal, the internal voltage regulator electronic control panel automatically JP6 plate in position, at this
time, that is, for the normal work of the automatic voltage regulator.
Testing load
1. Connect the output line to the load.
2. Open the load and check whether the phase sequence is normal, when it is the reverse phase, replace any two
the factory prior to completion. If the pressure drop caused by load-line is too long, this feature is
adjustable to adjust the voltage up, a clockwise direction for the step-down, anti-clockwise for the
step-up.
☉Adjustment to explain
1, Adjusts VR3 generally, clockwise step-down, counterclockwise step-up. (VR3 output voltage upper
limit adjustment potentiometer)
2, Constant voltage precision adjustment, according to dials code switch hypothesis showing, the
hypothesis to dial the code switch (S9), then establishes the output voltage precision.
3, The hypothesis alarm current (inputs manostat nominal current) to adjust VR6 to cause the overflow
indicating lamp just to lighten.
4, The hypothesis high and low pressure warning, according to dials the code switch hypothesis to show,
the hypothesis dials the code switch (S7, S8), then establishes the warning voltage.
5, The hypothesis high and low pressure warning delay time, according to dials code switch hypothesis
showing to establish S6, then establishes the warning delay time.
If the machine is unattended, will come the electricity later to request the manostat automatic start, may
establish S5, 5th will be ON.(Power devices have to install autormatic.)
Constant voltage precision establishes (S9) Overtension excessively low warning delay
time to establish (S6)
Unit Unit
S9-1 S9-2 S9-3 S9-4 S6-1 S6-2 S6-3 S6-4
(+-%) ( second )
0 ON ON ON ON 0 ON ON ON ON
0.2 OFF ON ON ON 0.5 OFF ON ON ON
0.4 ON OFF ON ON 1 ON OFF ON ON
0.6 OFF OFF ON ON 1.5 OFF OFF ON ON
Leaving the 0.8 ON ON OFF ON 2 ON ON OFF ON
plant value 1 OFF ON OFF ON 2.5 OFF ON OFF ON
1.2 ON OFF OFF ON
3 ON OFF OFF ON
1.4 OFF OFF OFF ON
3.5 OFF OFF OFF ON
1.6 ON ON ON OFF
4 ON ON ON OFF
1.8 OFF ON ON OFF
Leaving 4.5 OFF ON ON OFF
2.1 ON OFF ON OFF the plant
5 ON OFF ON OFF
2.3 OFF OFF ON OFF value
2.5 ON ON OFF OFF 5.5 OFF OFF ON OFF
2.7 OFF ON OFF OFF 6 ON ON OFF OFF
9. If some failure happens in the regulator, it is unable to determine what the situation is, please contact our
company as soon as possible.
example: control of internal cleansing and clean up of the fan mouth, to prevent the humid dust of PCB
2. It's recommend to change the oil for transformer every five years at normal working condition. If it was
run at overloading working environment which may cause the oil easily aging, the oil will need to be
changed earlier.
3 In our company, the device has been strictly tested before delivering and more customer data are