Professional Documents
Culture Documents
AZ ABS 00 BG01 004016 - Rev01
AZ ABS 00 BG01 004016 - Rev01
AZ ABS 00 BG01 004016 - Rev01
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 3 of 25
TABLE OF REVISIONS
Revision Modification
00 First issue
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 4 of 25
TABLE OF CONTENT
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 5 of 25
7 ATTACHMENTS..................................................................................................................................... 16
7.1 Attachment 1 – MRR (Material Receipt Report) ................................................................................... 17
7.2 Attachment 2 – Material Request / Issue Voucher ............................................................................... 18
7.3 Attachment 3 – OSDR (Over/Short/Damage Report) ........................................................................... 19
7.4 Attachment 4 – Material Return ........................................................................................................... 20
7.5 Attachment 5 – Vehicle Pass for Cargo Transportation ........................................................................ 21
7.6 Attachment 6 – Spare Parts Register ................................................................................................... 22
7.7 Attachment 7 – Special Tools Register ................................................................................................ 23
7.8 Attachment 8 – Stock Verification Report ............................................................................................. 24
7.9 Attachment 9 – Field Damage / Loss Report ........................................................................................ 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 6 of 25
This document is applicable to all CONTRACTOR’s scope of work for the ABSHERON EPS project: onshore
in Baku Deepwater Jackets Factory and offshore during installation and Hook-up phases of work.
2 REFERENCE DOCUMENTS
2.1 COMPANY PROJECT Documents
Reference Title
ABS-J1860-JO01-BG01-
Die Stamping
LET-000060
Reference Title
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 7 of 25
Reference Title
ABS-J1860-BG01-JO01-
HARD STAMPING
LET-000051
Reference Title
Over Short & Damage Document giving details of overages, shortages & damages to materials
Report received at site.
Material Request Form Document giving details of materials requested for a work.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 8 of 25
Material Issue Voucher Document giving details of materials issued for a work.
For the other definitions related to quality refer to ISO 9000:2015 “Quality management systems -
Fundamentals and vocabulary”.
3.2 Abbreviations
COM Commissioning Manager
BOSS BOS Shelf
WS Warehouse Superintendent
4 RESPONSIBILITIES
4.1 Site Material Controller
The Site Material Controller shall be responsible for the following:
a) Ensure that marking required for traceability order exists when materials are received on site and also
before returning any surplus to stock.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 9 of 25
b) Ensure that materials are properly segregated (correctly identified and not mixed up with other projects
materials).
c) Advises the applicable Discipline Managers that the materials have arrived on site and ascertains that
he has carried out quantitative and qualitative inspection before proceeding with storage of the
material.
d) Carry out a quantitative and qualitative reception inspection of materials arriving on the site.
e) Store materials under appropriate conditions in a suitable environment.
f) Prepare and keep up to date a journal of the material stocks on the material file of the AS400 database.
g) Put aside those materials which are non-conforming or in quarantine.
h) Document and tracking of receiving deficiencies.
i) Issue materials only upon presentation of a Material Request Form and a Material Release Note and
prepare the Materials Issue Voucher.
j) Manage the surplus and waste of materials and ensure the follow-up of quantities and continuity of
identification.
k) Set aside materials damaged on arrival on the site and raise an OSDR and copy to the procurement
department logistics officer who takes up the issue with the carrier.
l) Implement all measures necessary to ensure health of personnel and safety and protection of the
environment.
m) Prepare and maintain an inventory and the reconciliation of materials received on site.
n) When material arrives begin material preservation activities that will include documentation.
o) Raise OSD report for any non-complying items.
It is the responsibility of the Site Material Controller to ensure that this procedure is read and understood and
to keep the procedure current by issuing new or revised parts.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 10 of 25
5 PROCEDURE
5.1 Applicability
This procedure applies to all personnel involved in site material receipt and control activities, including
SUBCONTRACTORS. The procedure covers all material receipt and control activities from arrival of materials
at site until material reconciliation.
5.2 Receipt
All items will be checked against the Bill of Loading on receipt at work lay down area, but in cases like
containers and items inside wooden boxes, inspection will be done as soon as items arrive at the storage site.
All VENDOR certification shall be received on site as per Purchase Order. Material Controller will ensure that
the documents are available on site where required.
For receiving of COMPANY ITEMS refer to document AZ-ABS-00-BG01-004034.
5.3 Inspection
5.3.1 Procured materials
All materials procured to be used by BOS Shelf are subjected to the following checks and reports. This does
not apply to materials directly procured by SUBCONTRACTORS as part of their sub-contracts – those activities
are detailed in SUBCONTRACTORS material control procedures as part of their process controls. Preserved
materials shall in no case be de-preserved for receiving inspection purpose.
Quantitative check (Material Controller): To check on arrival at the storage area the quantities received against
quantities shown on the packing list and ascertain delivery status of the Purchase Order in the presence of
Company Representative.
Quality check (Material QC Inspector): This check comprises of a visual inspection for damage. An inspection
of the conformity of the identification marking and verification /confirmation with the material mill certificates
and the purchase order. Verification of material mill certificates and conformity check with the applicable project
specifications. For Welding Consumables the check will be performed by Welding Engineer while for
painting/coating consumables by the Coating Engineer.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 11 of 25
Delivery note: After checking the quantities, the delivery note should be signed by an authorized person as per
the warehouse procedure ref. GP-BOSS-QUAL-304.
Material Receipt Report: On completion of inspection this report will be prepared immediately by feeding the
received item data into a database. All MRR output from the database will be in a sequential order and will be
duly signed at goods receipt inspection by the Material Controller and Material QC Inspector, refer to
Attachment 1.
All signed originals of MRR will be retained and sequentially filed by the Material Controller or delegate at site.
Any material / equipment not clearing inspection will be held in a quarantined area under the responsibility of
the Site Material Controller and returned to the VENDOR after detailed investigation and findings if required.
5.4.2 Storage and Handling of Flat Plates, Pre-formed Plates and Beams
All plates will be stored in a horizontal position, on firm ground and kept above any standing water. Supports
will be provided to minimize distortion or water accumulation.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 12 of 25
They will be stored away from areas where they are not liable to contamination from grease, oil, paint or other
harmful substances. Measures will be put in place to prevent damage when handling plates that have been
primed or galvanized.
Precautions shall be enforced to minimize distortion during handling. Off cuts will be marked for traceability
with relevant Heat/Cast numbers and stored adjacent to new stocks.
5.4.5 Mechanical
In general, major mechanical equipment will be stored in secure areas and in accordance with manufacturer’s
instructions and approved maintenance and preservation procedures. Vessels etc. will be stored in designated
outdoor areas.
5.4.8 Preservation
To be performed in accordance with each manufacturer requirements and according to CONTRACTOR’s
document: AZ-ABS-00-BG01-004017, Storage and Preservation Procedure.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 13 of 25
Description
Order No.
Item no.
Equip /Tag no.
All special tools in use for the project will be assigned movable number and controlled by means of a Special
Tools Register (Attachment 7) indicating the position of the tool at any time.
5.4.10 Storage and Handling of Austenitic and Inconel materials
All Austenitic stainless steel and Inconel materials will be segregated and stored away from carbon steel or
any other materials that could potentially contaminate them.
All SUBCONTRACTOR material requests shall be of sequential numbering and signed and stamped by the
SUBCONTRACTOR site leader and duly approved by Contractor Discipline Superintendent/Coordinator, a
letter of attorney and a copy of the passport shall be attached. The “user” maintains a copy of this form in his
file.
For issue of steel plate, tubular or sections, the material identification will be requested as per the applicable
nesting drawing.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 14 of 25
Where material is to be taken off site after collection, the SUBCONTRACTOR shall ensure the required “Pass”
for cargo transportation (Attachment 5) is obtained from Material Controller/HSES. HSES shall ensure that the
relevant Material Issued is detailed on the Pass.
Checked stock control records shall be entered with stock check details and countersigned by Site Material
Controller.
5.6.2 Traceability
Where required full traceability will be maintained throughout the life of the material. The Site Material
Controller / QC Inspector will be responsible to ensure that traceability marking is properly carried out (see
5.2.1). Superintendents are responsible for the material identification and transfer subsequent to construction
and during fabrication / erection activities in accordance with procedure AZ-ABS-00-BG01-004022, Process
Control.
CONTRACTOR shall not use die stamping for material traceability marking. This was agreed with COMPANY
and recorded in CONTRACTOR Letter ABS-J1860-BG01-JO01-LET-000051 and answered in COMPANY
letter ABS-J1860-JO01-BG01-LET-000060.
It is a function of Project Quality Control Department to ensure traceability markings and proper identification
marks are carried out. The Quality Control Inspector shall ensure that all sections cut from a piece are marked
in a manner that assures permanent cross-reference with the source identification.
Fabrication superintendents are also responsible to ensure that all off-cuts deemed to be returned back to
stock for future use will be duly marked with traceability marking of the parent item (see 5.2.1 ) by paint marker
and returned to stock yard as per section 5.6.4.
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 15 of 25
Site Materials controller is responsible to ensure that all off-cuts carry the traceability marking when items are
returned back to stock from fabrication yard.
5.6.3 Identification
Identification and recording of cut structural steel (plates, shapes, tubulars and pipes) shall be carried out so
that any particular item of steel can be identifiable by reference to drawings and material records.
Upon return of any surplus material, the stock-card for the item will be updated immediately and the current
stock level entered into the materials database.
Allowance will be granted for materials at levels to be mutually agreed during the course of the WORK between
the CONTRACTOR and the COMPANY.
A separate reconciliation may be carried out for each Purchase Order item purchased by BOS Shelf. The
format will be the same as that noted above.
6 FLOW CHARTS
N/A
7 ATTACHMENTS
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 17 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 18 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 19 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 20 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 21 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 22 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 23 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 24 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document Number
MATERIAL CONTROL PROCEDURE AZ-ABS-00-BG01-004016
Revision: 01 Status: AFC
Document Type: PRC System: NN Family Equip.: NA Discipline: QUA Class: 1 Date: 09-Nov-2019
ORIGINATOR Reference: NA Page 25 of 25
This document is the property of JOCAP. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.