For Estimation - Gabion - RTW

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 45

GOVERNMENT OF NEPAL

MINISTRY OF URBAN DEVELOPMENT


1 of 45
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
BABARMAHAL,KATHMANDU

-n=;=_ -n=;=_

SUMMARY OF COST

S.N. Description of works Amount (NRs) Remarks


A
a. Earthwork 2,289,560.10
b. River Bank Protection Works 101,681,584.34
Sub-Total (A) 103,971,144.44

B. General Items
a. Third Party Insurance (0.15 % of A) 155,956.72
b. Insurance of the work(0.15 % of A) 155,956.72
Insurance against accident of the worksman (0.15 %
c. 155,956.72
of A)
d. As built drawing preparation(0.05 % of A) 51,985.57
e. Commission of the performance bond (0.05 % of A) 51,985.57
f. Lab Test Work (0.05 % of A) 51,985.57
Sub-Total (B) 623,826.87

C. Miscellaneous Items
a. Environmental Protection (1% of A) 1039711.4444
b. Institutional Development(1% of A) 1039711.4444
Sub-Total (C) 2079422.8888

D Other Expenditure
a Work Charge (2.5% of A) 2,599,278.61
b Other Minor Expenses (0.5% of A) 519,855.72
c Physical Contingency (5% of A) 5,198,557.22

Prepared by: Checked by: Approved by


GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
2 of 45
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
BABARMAHAL,KATHMANDU

d Price Escalation Contingency (5% of A) 5,198,557.22


e VAT ( 13% of A+B+C) 13,867,671.25
Sub-Total (D) 27,383,920.02

Grand Total (A+B+C+D) 134,058,314.22

Prepared by: Checked by: Approved by


3 of 45

-n=;=_ -n=;=_

ABSTRACT OF COST

S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks

C Earthwork

Structure foundation excavation for all types of soil/rock


by both manual and mechanical means as per drawing
3.2 SS DOR 905 and technical specification, including removal of stumps m3 - 314.85 -
and other deleterious matter, with all lifts and lead as
drawing and instruction of engineer.

Construction of embankments with material deposited


from Roadway Cutting: Providing, laying, spreading and
SS DOR
3.4 compacting embankment with roadway cutting material m3 - 703.04 -
909,910
and compact to the required density as per drawing and
Tech, specification.

Providing suitable material and backfilling behind


abutment, wingwall, return wall and other retaining
3.5 SS DOR 908 m3 4,042.74 566.34 2,289,560.10
structures complete as per drawing and technical
specification
Sub - Total (C) 2,289,560.10
E River Bank Protection Works
SS DOR
Providing and laying of dry stone masonry works as per
5.1 2602, 2603, m3 - 5,593.65 -
drawing and technical specification
2608

Providing and laying of Random rubble stone masonry


SS DOR works in cement mortar 1:4 in foundation and in structure
5.1 m3 - 12,435.95 -
2600,2607 as per drawing and technical specification (assuming ratio
of foundation work and Structure works to be 25% :75%)

Providing and placing machine mixed M20/20 cement m3


concrete for the foundation, drain walls and footing etc.
5.1.2 [SS2000] including compaction,curing,testing all complete as per - 16,226.15 -
specification and drawing
Providing, Preparing and Installing formwork including m2
necessary supports and removing after completion for
5.1.3 vertical plain surface [class F2 finish] all complete as per - 778.57 -
standard specification. [SS 1804 1805}*
Providing and Laying of 110mm HDPE Pipes (4 Kg/Cm2) m
5.1.6 - 115.00 -

Ref: Clause
Providing and laying of hand packed stone solling with
1006 of SS
150 to 200 mm thick stones and packing with smaller
#REF! DoR & m3 - 6,899.45 -
stones on prepared surface as per drawing and technical
S.N.24.15 A
specifications
of Norms DoR

Providing mechanically woven double twisted crates /


mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm,
lacing wire 2.40 mm ) including rolling cutting and with
#REF! SS DOR 2402 m3 18,092.11 5,547.55 100,366,968.29
lacing wire and binding wire and filling stone/boulder in
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification

Providing mechanically woven double twisted crates /


mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40 mm,
lacing wire 2.20 mm ) including rolling cutting and with
5.10 SS DOR 2402 m3 - 5,436.69 -
lacing wire and binding wire and filling stone/boulder in
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification

Providing and laying of PCC M: 10 (or 1:3:6 for nominal


#REF! SS DOR 2000 mix) in foundation complete as per Drawing and Technical m3 - 11,164.65 -
Specification
Providing and laying of Plain /Reinforced cement concrete
#REF! SS DOR 2000 in foundation complete as per Drawing and Technical m3 - 11,725.29 -
Specification : PCC Grade M 15
Providing and Laying of a Geo-Textile filter/geo
SS DOR membrane between pitching and embankment
5.12 sqm 7,945.86 165.45 1,314,616.05
2403,2404 slopes,behind earth retaining structures as per drawing
and Technical specification

Providing and laying of stone pitching on slopes laid over


prepared filter media including boulder apron laid dry in
5.19 SS DOR 2416 cum - 7,180.05 -
front of toe of embankment complete as per drawing and
technical specification
Sub - Total (E) 101,681,584.34
H Day Works
Supply of labour as required as per preamble and as
8.1 0
instructed by the Engineer.
0 Unskilled labour Nos - 750.00 -
0 skilled labour Nos - 1,030.00 -
Supply of excavator for maintenance of road or else as
8.2 required and instructed by engineer including operator and Hrs - 2,187.00 -
other charges
8.3 Provide Built up Drawing as completed Nos 3.00 15,000.00 45,000.00
Sub - Total (H) 45,000.00

Base Cost (A+B+C+D+E+F+G+H+I) 104,016,144.44 I


4 of 45

DETAIL QUANTITY CALCULATION OF ALL ITEM OF WORKS

SPEC
S No. Description Unit Gabion Wall Total
REF
3 Earthwork
3.2 SS DOR 905 Structure foundation excavation for all types of soil/rock
by both manual and mechanical means as per drawing and
technical specification, including removal of stumps and m3
other deleterious matter, with all lifts and lead as drawing
and instruction of engineer.
13475.811828 -
3.4 SS DOR Construction of embankments with material deposited from
909,910 Roadway Cutting: Providing, laying, spreading and
compacting embankment with roadway cutting material m3
and compact to the required density as per drawing and
Tech, specification.
-
3.5 SS DOR 908 Providing suitable material and backfilling behind abutment,
wingwall, return wall and other retaining structures m3
complete as per drawing and technical specification 4,042.74 4,042.74
5 River Bank Protection Works
5.1 SS DOR Providing and laying of dry stone masonry works as per
2602, 2603, drawing and technical specification
2608
m3

-
5.1 SS DOR Providing and laying of Random rubble stone masonry
2600,2607 works in cement mortar 1:4 in foundation and in structure
as per drawing and technical specification (assuming ratio
of foundation work and Structure works to be 25% :75%) m3

-
[SS2000] Providing and placing machine mixed M20/20 cement m3
concrete for the foundation, drain walls and footing etc.
5.1.2 including compaction,curing,testing all complete as per
specification and drawing
-

Prepared By: Checked By: Approved By:


5 of 45
Providing, Preparing and Installing formwork including m2
necessary supports and removing after completion for
5.1.3 vertical plain surface [class F2 finish] all complete as per
standard specification. [SS 1804 1805}*
-
Providing and Laying of 110mm HDPE Pipes (4 Kg/Cm2) m
5.1.6
-
5.6 Ref: Clause Providing and laying of hand packed stone solling with 150
1006 of SS to 200 mm thick stones and packing with smaller stones on
DoR & prepared surface as per drawing and technical
S.N.24.15 A specifications
of Norms m3
DoR

-
5.7 SS DOR Providing mechanically woven double twisted crates /
2402 mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm,
lacing wire 2.40 mm ) including rolling cutting and with
lacing wire and binding wire and filling stone/boulder in m3
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification
18,092.11 18,092.11
5.10 SS DOR Providing mechanically woven double twisted crates /
2402 mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40 mm,
lacing wire 2.20 mm ) including rolling cutting and with
lacing wire and binding wire and filling stone/boulder in m3
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification
-
5.9 SS DOR Providing and laying of PCC M: 10 (or 1:3:6 for nominal
2000 mix) in foundation complete as per Drawing and Technical m3
Specification -
#REF! SS DOR Providing and laying of Plain /Reinforced cement concrete
2000 in foundation complete as per Drawing and Technical m3
Specification : PCC Grade M 15 - -
5.1 SS DOR Providing and laying of Reinforced/prestressed cement
2000 concrete in superstructure as per Drawing and Technical
Specification : PCC Grade M 20

m3

- -
5.12 SS DOR Providing and Laying of a Geo-Textile filter/geo
2403,2404 membrane between pitching and embankment
slopes,behind earth retaining structures as per drawing and sqm
Technical specification
7945.86 7,945.86
5.19 SS DOR Providing and laying of stone pitching on slopes laid over
2416 prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and cum
technical specification
-
8 DAY WORKS
8.1 Supply of labour as required as per preamble and as
instructed by the Engineer.
Unskilled labour Nos -
skilled labour Nos -
8.2 Supply of excavator for maintenance of road or else as
required and instructed by engineer including operator and Hrs
other charges -
8.3 Provide Built up Drawing as completed Nos 3 3.00

Prepared By: Checked By: Approved By:


Page 6

Item Unit Rates

Pay SPEC
S. No. Description Unit Rate Remarks
Item No. REF
1 General
Insurance of works, plants, materials, loss and damage to
1 1.1 GCC 13 equipments, Contractor's workmen and employees and third PS 1750000
party insurance against damage to other persons and property.

Provide and maintain Site Office on rental basis (two rooms


Size (3mx4m)) at location acceptable to the project manager
2 1.2 SCC - with in the Contract package with accomadation facilities for Mths 50,000
the Supervision Team as per Project Manager instruction (As Per
Special Provision)
Carry out additional tests for material and works as required and
3 1.3 GCC 33.1
instructed by the Project Manager. PS 100,000

Reallocation of services and minor infrastructures as per


4 1.4 111 DoR
specification and as instructed by the Project Manager. PS 200,000

Provide and maintain traffic safety, Occupation Health and


Safety (OHS) as per special provision,control measures and
5 1.5 104 DoR
temporary diversions during construction as instructed by the LS 500,000
Engineer.

Provide and installation of project information board of size


1.80 m X 1.2 m along with iron posts including excavation,
6 1.6 110 (b) DoR
concreting,backfillingetc all complete as per DoR Standard Nos. 10,000
Specifixcation for Road and Bridge Works.
Environmental Mitigation Works as instructed by the Project
7 1.7
Manager. PS 100,000

Social Compliuance and Safeguards as Instructed by gthe Project


8 1.8
Manager PS 100,000

Providing and establishing the camp with mobilization and


demobilization for contractor's labour and staffs and
9 1.9 111 DoR
demobilization after completion of works as per the specification Months 15,000
and as instructed by Project Manager
Carry out maintenance of the existing road to keep the road Km-
10 1.10 111 DoR serviceable throughout the contract period as per the specification 3,000
and as instructed by the Project Manager month
Control dust nuissance by sprinkling water as required and
11 1.11
instructed by Engineer LS 100,000

12 2.0 Site Clearance

Clearing and grubbing road land including uprooting rank


vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
13 disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead of
1000 meters including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

(A) In area of light jungle (less than 15 number per 100


14 2.1 SS DOR201 Sqm 20.81
sqm)

(B) In area of Thorny jungle (more than 15 number per 100


15 2.2 SS DOR201 Sqm 29.43
sqm)

(C) Felling and uprooting of bamboo clearing the area,


16 2.3 SS DOR201 cum 2,080.83
stacking of bamboo and disposing of wastes

Prepared by: Checked by: Approved by:


Page 7
3.0 Earthworks

Roadway excavation in all types of soil/rock by both manual and


SS DOR mechanical means as per drawing and technical specification,
17 3.1 m3 189.37
905 including removal of stumps and other deleterious matter, with all
lifts and lead as drawing and instruction of engineer.

Structure foundation excavation for all types of soil/rock by both


manual and mechanical means as per drawing and technical
SS DOR
18 3.2 specification, including removal of stumps and other deleterious m3 315
905
matter, with all lifts and lead as drawing and instruction of
engineer.

Construction of embankments with material deposited from


SS DOR Roadway Cutting: Providing, laying, spreading and compacting
19 3.3 m3 703
909,910 embankment with roadway cutting material and compact to the
required density as per drawing and Tech, specification.
Providing suitable material and backfilling behind abutment,
20 3.4 SS DOR 908 wingwall, return wall and other retaining structures complete as m3 566
per drawing and technical specification
Removal of unserviceable Soil with Disposal upto 1000 meters
21 3.5 SS DOR 905 (Removal of unserviceable soil including excavation, loading and m3 130
disposal upto 1000 meters lead.)
4 Pavement Works
Scarifying the existing road surface to a depth of 50 mm and
SS DOR
disposal of scarified Material with in all lifts and lead as per m2 22
1003
Drawing and Technical Specifications
Construction of subgrade and earthen shoulders with approved
SS DOR
14 4.1 material (capping layer) obtained from borrow pits with with all m3 51
1004
lifts & leads lead as per drawing and technical spacification
Providing and laying granular Sub base material by mechanical
SS DoR means on prepared surface, mixing at OMC, and compacting to
15 4.2 m3 4,388
1201 achieve the desired density, complete as per Drawing and
Technical Specifications

Providing laying , spreading and compacting graded stone


aggregate to wet mix macadam specification including premixing
SS DoR
16 4.3 the material with water at OMC laying in uniform layers in sub- m3 3,869
1208
base on well prepared surface and compacting to achieve requiered
density as oer drawing and technical specification

Providing and laying crusher run macadam on a prepared surface,


SS DOR spreading and mixing, watering and compacting to form a layer of
17 4.4 m3 4,739
1204 sub base/base course as per drawing and technical specifications.
(by mix in place method)

Providing and applying prime coat with hot bitumen(including


SS DOR Cutter) on prepared surface of grannular base including cleaning
18 4.5 Ltr 117
1302 of road surface and spraying by mechanical means as per technical
specification
Providing and applying tack coat with hot bitumen at specified
SS DOR
19 4.6 rate on the prepared non-bituminous surfaces including cleaning as Ltr 107
1302
per technical specification
SS DOR Providing and mixing of Bitumen cutter as per design/direction of
20 4.7 Ltr 104
1300 Engineer
SS DOR Providing and mixing of Anti-Stripping agent as per
21 4.8 Kg 391
1300 design/direction of Engineer
Providing and laying surface dressing as wearing course in single
coat using gravel of specified size on a recently applied layer of
22 4.9 1303
bituminour binder on prepared surface as per Drawing and
Technical Specifications.
Case I 19 mm nominal chipping size Sqm 76
Case II 13mm nominal chipping size Sqm 53
Case III 10 mm nominal chipping size Sqm 37
Case IV 6 mm nominal chipping size Sqm 25

Previous
Providing and Laying sand spreading over newly primed surface
22 4.10 DOR Norms Sqm 68
(1301,1305)
(13.01,1305)

Prepared by: Checked by: Approved by:


Page 8
Providing and laying bituminous concrete/asphalt concrete using
SS DOR
19 4.11 crushed aggregate of specified grading, premixed with bituminous cum 12,211
1309
binder and filler as per drawing and technical specification

5.0 Structural/ Side Drain/ Cross Drainage Works


SS DOR
Providing and laying of dry stone masonry works as per drawing
20 5.1 2602, 2603,
and technical specification m3 5,594
2608
Providing and laying of Random rubble stone masonry works in
SS DOR cement mortar 1:4 in foundation and in structure as per drawing
21 5.2
2600,2607 and technical specification (assuming ratio of foundation work and m3 12,436
Structure works to be 25% :75%)

Providing and laying of stone pitching on slopes laid over


SS DOR prepared filter media including boulder apron laid dry in front of
22 5.3
2416 toe of embankment complete as per drawing and technical m3 7,180
specification
SS DOR Providing and pointing with cement mortar on masonry work in
23 5.4
2600 structuire as per technical specification (cement mortar- 1:3) m2 266
Ref: Clause
1006 of SS
Providing and laying of hand packed stone solling with 150 to
DoR &
24 5.5
S.N.24.15 A
200 mm thick stones and packing with smaller stones on prepared m3 6,899
surface as per drawing and technical specifications
of Norms
DoR
Providing mechanically woven double twisted crates /
mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm,
mesh wire 3 mm, selvedge wire 3.90 mm, lacing wire 2.40 mm )
SS DOR
24 5.6 including rolling cutting and with lacing wire and binding wire m3 5,548
2402
and filling stone/boulder in gabion boxes/mattress etc. including
dressing, bedding, bonding all complete as per drawing and
technical specification

Providing mechanically woven double twisted crates /


mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm,
mesh wire 2.7 mm, selvedge wire 3.40 mm, lacing wire 2.20
SS DOR
5.7 mm ) including rolling cutting and with lacing wire and binding m3 5,437
2402
wire and filling stone/boulder in gabion boxes/mattress etc.
including dressing, bedding, bonding all complete as per drawing
and technical specification

Providing, preparing and installing form work including necessary


SS DOR supports and removing after completion for walls/structures.
25 5.8
1804,1805 (Class F2 Finish), vertical plain surface; Using timber soft wood. m2 779
(Height upto 3 m)
Providing and laying, fitting and placing HYSD bar reinforcement
SS DOR
26 5.9 in superstructure complete as per drawing and technical Kg 122
2014
specification
SS DOR Providing and laying of PCC M: 10 (or 1:3:6 for nominal mix) in
27 5.10 m3 11,165
2000 foundation complete as per Drawing and Technical Specification
SSTB Hand
28 5.11 book of Plum Concrete (1:3:6+40% Broken Stone) m3 10,698
DoLIDAR
Providing and laying of Plain /Reinforced cement concrete in
SS DOR
29 5.12 foundation complete as per Drawing and Technical Specification : m3 11,725
2000
PCC Grade M 15
Providing and laying of Reinforced/prestressed cement concrete
SS DOR
30 5.13 in superstructure as per Drawing and Technical Specification : m3 16,226
2000
PCC Grade M 20

Providing and laying Reinforced Cement Concrete NP3


39 5.14 SS DOR 701 Flush jointed pipe for culverts including fixing with cement
mortar 1:2 as per Drawing and Technical Specification

A 300 mm internal dia m 5,226


B 450 mm internal dia m 7,054
C 600 mm internal dia m 9,272
D 900 mm internal dia m 16,407
E 1000 mm internal dia m 18,349
F 1200 mm internal dia m 22,272

Prepared by: Checked by: Approved by:


Page 9
Providing and Laying of a Geo-Textile filter/geo
SS DOR membrane between pitching and embankment
5.15 sqm 165
2403,2404 slopes,behind earth retaining structures as per drawing and
Technical specification

Providing and laying of stone pitching on slopes laid over


SS DOR prepared filter media including boulder apron laid dry in
5.16 cum 7,180
2416 front of toe of embankment complete as per drawing and
technical specification

Providing suitable material and backfilling behind


abutment, wingwall, return wall and other retaining
5.17 SS DOR 908 cum 566
structures complete as per drawing and technical
specification
12 Bio-engineering Work

Planting rooted grass slips on the slopes 45-60 deg


including preparation of slips on site. A max of 5cm depth
SS DOR
31 12.1
2807
with metal rod or Operation includes digging, planting hole sqm 310
to hard-wood peg, depending on the nature of the soil. The
planting drills should be space

13 Miscellaneous Work

Providing and fixing non reflective warning mandatory and


informatory sign board of two mm thick MS sheet with
back support frame fixed on heavy 50mm tube or channel
SS DOR
34 13.1
1501
section of 75mm*40mm firmly fixed to the ground by the Nos. 4,966
means of properly designed foundation with M10/40 grade
cement concrete 300mm*300mm*300mm, as per drawing
and technical specification/DOR Publication

SS
36 13.2 Supply and place one kilometer stone Nos. 5,557
DOR1506
SS DOR
37 13.3 Supply and place 5th kilometer stone. Nos. 11,027
1506

Providing and installation of 150mm * 1.5 m long


delineators (roadway indicator, hazard markers, object
SS DOR markers) 80-100cm above ground level painted black and
38 13.4 Nos. 1,694
1507 white in 20cm wide strips, burried or pressed into the
ground and confirming to the drawings and technical
specifications.

Provide and erecting "W" metal beam crashbarrier


comprising of 3.43mm thick corrugated sheet metal beam
rail, 70cm above road/ground level,fixed on ISMC serises
channel vertical post, 150*75*5 mm spaced 2m c/c,1.8m
13.8 high,1.1m below ground/road level,all steel paetsand rm 7,374
fitment to be galvanized by hot dip process,all fittings to
confirm to IS 1367 and IS 1364,metal beam rail to be fixed
on the vertical post with a spacer of chaneel section
150*75*5mm 330mm long, all complete

14
40
41 14.1 SP G -15 Labour
b) Skilled labour day 1,030
c) Unskilled labour day 750

Prepared by: Checked by: Approved by:


Page 10

RATE ANALYSIS (FY 2075/076)


Skilled 1030.00
I. SITE CLEARANCE Unskilled 750.00
ITEM Cutting of trees including cutting of trunks, branches and removal stumps root stacking of seviceable material with all lifts and upto a lead of 1000 m and
earth filling in the depression pit.
(A) Girth from 30 cm. to 60 cm.
UNIT Nos. For 30 nos
Ref: Clause 201 of SS DoR & S.N. 2.2 (i) of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 0.83 M/D 750.00 625.00 625.00
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.2 Hr 1016.00 203.20 203.20
Actual Rate 828.20
Overhead @ 15 % 124.23
Sub Total 952.43
Rate per no. 952.43

(B) Girth above 60 cm. to 90 cm


UNIT Nos. For 10 nos
S.N. Ref: Clause 201 of SS DoR & S.N. 2.2 (ii) of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00 0.00
Labour
b) Unskilled 2.50 M/D 750.00 1875.00 1875.00
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.6 Hr 1016.00 609.60 609.60
Actual Rate 2484.60
Overhead @ 15 % 372.69
Sub Total 2857.29
Rate per no. 2857.29

ITEM
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal
and disposal of top organic soil not exceeding 150 mm in thickness.
(A) In area of light jungle (less than 15 number per 100 sqm)
UNIT Sqm For 10000 Sqm
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 0.0225 M/D 750.00 16.88 16.88
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.0012 Hr 1016.00 1.22 1.22
Actual Rate 18.09
Overhead @ 15 % 2.71
Sub Total 20.81
Rate per Sqm. 20.81

(B) In area of Thorny jungle (more than 15 number per 100 sqm)
UNIT Sqm For 10000 Sqm
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 0.0325 M/D 750.00 24.38 24.38
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.0012 Hr 1016.00 1.22 1.22
Actual Rate 25.59
Overhead @ 15 % 3.84
Sub Total 29.43
Rate per Sqm. 29.43

(C) Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing of wastes
UNIT cum For 100 cum
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 2.2500 M/D 750.00 1687.50 1687.50
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.12 Hr 1016.00 121.92 121.92
Actual Rate 1809.42
Overhead @ 15 % 271.41
Sub Total 2080.83
Rate per cum. 2080.83

Pay Item No.


ITEM Roadway excavation in all types of soil by manual means as per drawing and technical specification, including removal of stumps and other deleterious matter,
with all lifts and lead as drawing and instruction of engineer.

UNIT cu. m. For 12 cu.m

Prepared by: Checked by: Approved by:


Page 11
Ref: Clause 905 of SS DoR & S.N. 9.1 I A of Norms DoR
Source Type Quantity Unit Rate Amount Total (Rs.)
Skilled 0.08 m-day 1030.00 85.83 85.83
Labor
Unskilled 0.67 m-day 750.00 500.00 500.00
Actual Cost 585.83
Tools ,Plants & Equipments @ 3% 17.58
Overhead @ 15 % 87.88
Sub Total 691.28
Rate per cum. 691.28

Roadway excavation in all types of soil by mechanical means as per drawing and technical specification, including removal of stumps and other deleterious
matter, with all lifts and lead as drawing and instruction of engineer.

Unit Cu m For 360 cu.m


Ref: Clause 905 of SS DoR & S.N. 9.1 I B of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00277778 M/D 1030.00 2.86 2.86
Labour b) Unskilled 0.00833333 M/D 750.00 6.25 6.25
c)Operator 0 M/D 0.00
Material Disel 0 Lit 82.30 0.00 0.00
Lubricant (1 % of Fuel) 0.00
Equipment Hudraulic excavator 0.01666667 Hr 2787.00 46.45 46.45
Actual cost 55.56
Overhead @ 15 % 8.33
Sub Total 63.90
Rate per cum. 63.90

Road way and drain excavation for all types of soil with combination of Manual and Mechanical means
Unit Cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (20%) 0.2 Cum 691.28 138.26 138.26
Machine Excavation (80%) 0.8 Cum 63.90 51.12 51.12
Actual Cost 189.37
Total Rate 189.37

Structure foundation excavation for all types of soil with combination of Manual and Mechanical means
Unit Cu,m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (40%) 0.4 Cum 691.28 276.51 276.51
Machine Excavation (60%) 0.6 Cum 63.90 38.34 38.34
Actual Cost 314.85
Total Rate 314.85

Roadway and drain excavation in ordinary rock by manual means as per drawing and technical specification, including all lift and all lift as per
drawing and instruction of the engineer
Ref: Clause 905 of SS DoR & S.N. 9.1 II A of Norms DoR
Unit: Cu.m For 60 cum
Source Type Quantity Unit Rate Amount Remarks
Skilled 0.05 md 1,030.00 51.50
Skilled 0.83 750.00 625.00
Actul Rate 676.50
Tools, Plants & Equipment @3% 20.30
Overhead @ 15 % 101.48
Total 798.27
Unit Rate 798.27

Roadway and drain excavation in ordinary rock by mechanical means as per drawing and technical specification, including all lift and all lift as per
drawing and instruction of the engineer

Ref: Clause 905 of SS DoR & S.N. 9.1 II B of Norms DoR


Unit: Cu.m For 120 cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00833333 M/D 1030.00 8.58 8.58
Labour
b) Unskilled 0.025 M/D 750.00 18.75 18.75
Material Disel 0 Lit 82.30 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Hydraulic Excavator 0.05 Hr 2787.00 139.35 139.35
Actual cost 166.68
Overhead @ 15 % 20.9025
Total 187.59
Unit Rate 187.59

Road way and drain excavation for ordinary rock with combination of Manual and Mechanical means

Description Particular Quantity Unit Rate Amount Total


Manual Excavation (20%) 0.2 Cum 798.27 159.65 159.65
Machine Excavation (80%) 0.8 Cum 187.59 150.07 150.07
Actual Cost 309.72

Prepared by: Checked by: Approved by:


Page 12
Total Rate 309.72

Earthwork in exacavation in foundation for structure for ordinary rock with a combination of Machine and Mechanical means

Description Particular Quantity Unit Rate Amount Total


Manual Excavation (40%) 0.4 Cum 798.27 319.31 319.31
Machine Excavation (60%) 0.6 Cum 187.59 112.55 112.55
Actual Cost 431.86
Total Rate 431.86

Roadway excavation in hard rock manually chiselling including breaking rocks, lifts and lead for disposal as per drawing and technical specification

Ref: Clause 905 of SS DoR & S.N. 9.1 IV B of Norms DoR


Unit: Cu. M For 16 cum
Source Type Quantity Unit Rate Amount Total Rs
Labour Skilled 0.1250 md 1,030.00 128.75
Unskilled 3.63 md 750.00 2718.75
Blacksmith 0.06 md 1,030.00 64.38
Actul Rate 2911.88
Tools, Plants & Equipment @3% 87.36
Overhead @ 15 % 436.78
Total 3436.01
Unit Rate 3436.01

Road way excavation in hard rock with rock breakers, including breaking rock lifts and lead for disposal as per drawing and technical specificationa;
mechanical lead upto 30 m
Ref: Clause 905 of SS DoR & S.N. 9.1 IV A of Norms DoR
Unit: Cu. M For 16 cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.0625 M/D 1030.00 64.38 64.38
Labour b) Unskilled 0.625 M/D 750.00 468.75 468.75
c)Operator 0 M/D 1030.00 0.00 0.00
Material Disel Lit 82.30 0.00 0.00

Prepared by: Checked by: Approved by:


Page 13
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Excavator + Breaker 0.375 Hr 3087.00 1157.63 1157.63
Actual cost 1690.75
Overhead @ 15 % 253.61
Total Rate 1944.36

Road way and drain excavation in hard rock with combination of Manual and Mechanical means
Unit: cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (20%) 0.2 Cum 3436.01 687.20 687.20
Machine Excavation (80%) 0.8 Cum 1944.36 1555.49 1555.49
Actual Cost 2242.69
Total Rate 2242.69

Earthwork in excavation in foundation of structure with a combination of Manual and Mechanical means
Unit: cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (40%) 0.4 Cum 3436.01 1374.41 1374.41
Machine Excavation (60%) 0.6 Cum 1944.36 1166.62 1166.62
Actual Cost 2541.02
Total Rate 2541.02

Construction of embankments with material deposited from Roadway Cutting: Providing, laying, spreading and compacting embankment with
roadway cutting material and compact to the required density as per drawing and Tech, specification.

Ref: Clause 909,910 of SS DoR & S.N. 9.9 A of Norms DoR


UNIT cu. m. For 100 cu.m

Source Type Quantity Unit Rate Amount, Rs Remarks


Labor Skilled 0.02 m-day 1030.00 20.60
Unskilled 0.50 m-day 750.00 375.00
Material Water 240.00 ltr 0.25 60.00
Equipment Vibratory Rollers 0.06 Hrs. 2939.00 176.34
Actual Rate 611.34
Sub total 611.34
Overhead 15% 91.70
Rate per m³ 703.04

Prepared by: Checked by: Approved by:


Page 14

Removal of unserviceable Soil with Disposal upto 1000 meters (Removal of unserviceable soil including excavation, loading and disposal upto 1000
meters lead.)
Ref: Clause 905 of SS DoR & S.N. 9.2 of Norms DoR
UNIT cu. m. For 360 cu.m

Source Type Quantity Unit Rate Amount, Rs Remarks


Skilled 0.0028 m-day 1030.00 2.86
Labor
Unskilled 0.0111 m-day 750.00 8.33
Excavator 0.02 ltr 2787.00 46.45
Equipment
Tipper 0.05 Hrs. 1166.00 58.30
Actual Rate 113.08
Sub total 113.08
Overhead 15% 16.96

Rate per m³ 130.05

Scarifying the existing road surface to a depth of 50 mmand disposal of scarified Material with in all lifts and lead as per Drawing and Technical
Specifications.
Ref: Clause 1003 of SS DoR & S.N.10.2 of Norms DoR
UNIT Cu m For 600 Sqm
Source Type Quantity Unit Rate Amount Remarks
Skill 0.00166667 md 1,030.00 1.72
Labour
Unskill 0.01 md 750.00 7.50
Water - ltr 0.25 0.00
Material
Caping layer material - cum 150.00 0.00
Equipment Tractor with ripper 0.01 hr 1,016.00 10.16
Actul Rate 19.38
Overhead @ 15 % 2.91
Unit Rate per m2 22.28

Construction of subgrade and earthen shoulders with approved material (capping layer) obtained from borrow pits with with all lifts & leads lead as
per drawing and technical spacification

Ref: Clause 1004 of SS DoR & S.N.10.3 of Norms DoR


UNIT Cu m For 600 Cum
Source Type Quantity Unit Rate Amount Remarks
Skill 0.00166667 md 1,030.00 1.72
Labour
Unskill 0.01 md 750.00 7.50
Water 120.00 ltr 0.25 30.00
Material
Caping layer material 1.25 cum 150.00 187.50
Equipment Motor grader 0.01 hr 3,998.00 39.98
Vibratory Roller 0.01 hr 2939.00 29.39
Actul Rate 296.09
Overhead @ 15 % 44.41
Unit Rate per m3 340.50
Unit Rate per m2 for 15 cm depth 51.07

Providing and laying granular Sub base material by mechanical means on prepared surface, mixing at OMC, and compacting to achieve the desired
density, complete as per Drawing and Technical Specifications
Ref: Clause 1201 of SS DoR & S.N.12.1 A of Norms DoR
Unit: cum For 300 cum
m3 Ref: 26-A-a
Source Type Quantity Unit Rate Amount Total
Labour Skilled 0.007 m-day 1,030.00 6.87 6.87
Unskilled 0.04 m-day 750.00 30.00 30.00

Materials Sub base material S1 or S2 type 1.28 cu.m. 2,754.5 3525.82 3,525.82
Water 60.00 ltr. 0.25 15.00 15.00
Motor Grader 0.020 hr. 3,998.0 79.96 79.96
Equipment Vibratory Roller 0.040 hr. 2,939.00 117.56 117.56
Tractor/Loader 0.040 hr. 1,016.0 40.64 40.64
Actual Rate 3815.85
Overhead @ 15 % 572.38
Sub Total 4388.23
Rate per m3 4388.23

Providing laying , spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at
0OMC laying in uniform layers in sub-base on well preparedRef:
surface and0 compacting to
Clause 0 achieve requiered density as oer drawing
0.00 0 and technical
UNIT m3 For 225.00 cu/m 0.00 0
Source Type Quantity Unit Rate Amount Total
Skilled 0.013 m-day 1,030.00 13.73 13.73
Labour
Unskilled 0.04 m-day 750.00 33.33 33.33
Crushed stone 1.03 cu.m. 3,001.75 3091.80 3,091.80
Material
Water 80.00 ltr. 0.25 20.00 20.00
mixer 0.04 0 325 13.00 13.00
Equipment
Grader 0.027 hr. 2,798.00 74.61 74.61
Vibratory Roller 0.040 hr. 2,939.00 117.56 117.56
Actual RateAc 3364.04
Overhead @ 15% 504.61
Rate per m3 3868.65

Prepared by: Checked by: Approved by:


Page 15

Providing and laying crusher run macadam on a prepared surface, spreading and mixing, watering and compacting to form a layer of sub base/base
course as per drawing and technical specifications. (by mix in place method)
Ref: Clause 1204 of SS DoR & S.N.12.7 A of Norms DoR
UNIT m3 For 360.00 cu/m
Source Type Quantity Unit Rate Amount Total
Skilled 0.008 m-day 1,030.00 8.58 8.58
Labour
Unskilled 0.04 m-day 750.00 29.17 29.17
Crushed stone 1.32 cu.m. 3,001.8 3962.31 3,962.31
Material
Water 100.00 ltr. 0.25 25.00 25.00
Grader 0.017 hr. 2,798.0 46.63 46.63
Equipment
Vibratory Roller 0.017 hr. 2,939.0 48.98 48.98
Actual RateAc 4120.68
Overhead @ 15% 618.10
Rate per m3 4738.78

Providing and pointing with cement mortar on masonry work in structuire as per technical specification (cement mortar- 1:3)
S.N. Ref: Clause 2600 of SS DoR & S.N.26.7 A of Norms DoR
unit sqm For 100 sqm
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled labour 0.09 m-day 1030.00 92.70 92.70
Unskilled labour 0.09 m-day 750.00 67.50 67.50
Cement 3.10 kg 16.50 51.15 51.15
Material Collection of sand 0.01 cu.m. 3175.20 20.00 20.00
Water 0.50 ltr 0.25 0.13 0.13
Actual Rate 231.35
Overhead @ 15 % 34.70
Total 266.06
Rate per m2 266.06

Providing and laying of dry stone masonry works as per drawing and technical specification

Ref: Clause 2602, 2603, 2608 of SS DoR & S.N.26.1 of Norms DoR
UNIT m3 For 5 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.8 m-day 1030.00 824.00 824
Unskilled 1.60 m-day 750.00 1200.00 1200
material Collection of Stone 1.15 cu.m. 2469.60 2840.04 2840.04
Actual Rate 4864.04
Overhead @ 15 % 729.61
Sub Total 5593.65
Rate per m³ 5593.65

Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in foundation as per drawing and technical specification

Ref: Clause 2602, 2603, 2607 of SS DoR & S.N.26.3 B of Norms DoR
UNIT m4 For 5 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 1.400 m-day 1030.00 1442.00 1442.00
Unskilled 2.800 m-day 750.00 2100.00 2100.00
Rubble 1.15 cu.m. 2469.60 2840.04 2840.04
Material Cement 158.0 kg. 16.50 2607.00 2607.00
Sand 0.326 cu.m. 3175.20 1035.12 1035.12
Actual Rate 10024.16
Overhead @ 15 % 1503.62
Sub Total 11527.78
Rate per m3 11527.78

Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in Structure as per drawing and technical specification

Ref: Clause 2600,2607 of SS DoR & S.N.26.5 A of Norms DoR


UNIT m4 For 5 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 1.400 m-day 1030.00 1442.00 1442.00
Unskilled 4.000 m-day 750.00 3000.00 3000.00
Construction Rubble 1.15 cu.m. 2469.60 2840.04 2840.04
Cement 132.0 kg. 16.50 2178.00 2178.00
Materials Sand 0.370 cu.m. 3175.20 1174.82 1174.82
Water 200.000 ltr 0.25 50.00 50.00

Add 5% of cost of labour & material for scaffolding 392.24


Actual Rate 11077.11
Overhead @ 15 % 1661.57
Sub Total 12738.67
Rate per m3 12738.67

Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in foundation and in structure as per drawing and technical
specification (assuming ratio of foundation work and Structure works to be 25% :75%)
Ref: Clause 2600,2607 of SS DoR & S.N.26.5 A of Norms DoR

Prepared by: Checked by: Approved by:


Page 16
UNIT m3 For 5 cu m
Description Particular Quantity Unit Rate Amount Total
Random rubble stone masonry (1:4) in foundation (0.07) 0.25 Cum 11527.78 2881.94 2881.94
Random rubble stone masonry (1:4) in foundation (0.93) 0.75 Cum 12738.67 9554.00 9554.00
Actual Cost 12435.95
Total Rate 12435.95

Stone pitching
Providing and laying of stone pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as
per drawing and technical specification

Ref: Clause 2416 of SS DoR & S.N.24.15 A of Norms DoR


UNIT m3 For 1 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Skilled 1.00 m-day 1030.00 1030.00 1030.00
Labor
Unskilled 3.00 m-day 750.00 2250.00 2250.00
Stone weighing >40kg 1.00 cu.m. 2469.60 2469.60 2469.60
material
Stone spalls (minimum 25 mm size) 0.20 cu.m. 2469.60 493.92 493.92
Actual Rate 6243.52
Overhead @ 15 % 936.53
Sub Total 7180.05
Rate per m³ 7180.05

Providing mechanically woven double twisted crates / mattress including rolling cutting and with lacing wire and binding wire as per specification.

Ref: Clause 2402 of SS DoR & S.N.24.2 A of Norms DoR


Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm, lacing wire 2.40 mm

Rate per m2
270

Ref: Clause 2402 of SS DoR & S.N.24.2 B of Norms DoR


Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40 mm, lacing wire 2.20 mm

Rate per m2
250

Assembling mechanical woven Gabion boxes/mattresses, placing in position including stretching; forming compartrments;
tying the sides and diaphragm with binding wire in each mesh; tying with bracing wires and tie wirews; and tying down the
lid complete as per specification (stone filling not included)

Ref: Clause 2402 of SS DoR & S.N.24.3 A of Norms DoR

UNIT sq. m For 160 sq.m


Source Type Quantity Unit Rate Amount Total (Rs.)
Skilled 0.0125 m-day 1030.00 12.88 12.88
Labor
Unskilled 0.06 m-day 750.00 46.88 46.88
Material Binding Wire 0.00 Kg. 92.00 0.00 0.00
Actual Rate 59.75
Overhead @ 15 % 8.96
Sub Total 68.71
Rate per m³ 68.71

Providing and filling stone boulders in Gabion boxes/mattresses etc. including dressing ,, bedding, bonding all complete as
per drawing and technical specification

Ref: Clause 2402 of SS DoR & S.N.24.4 of Norms DoR

UNIT cu. m For 10 sq.m

Source Type Quantity Unit Rate Amount Total (Rs.)

Labor Skilled 0.2 m-day 1030.00 206.00 206.00

Unskilled 0.80 m-day 750.00 600.00 600.00

Construction Boulder 1.10 cu.m. 2469.60 2716.56 2716.56

Actual Rate 3522.56

Overhead @ 15 % 528.38

Sub Total 4050.94

Rate per m³ 4050.94

Prepared by: Checked by: Approved by:


Page 17
FORMWORK
Providing, preparing and installing form work including necessary supports and removing after completion for walls/structures. (Class F2 Finish), vertical
plain surface; Using timber soft wood. (Height upto 3 m)

Ref: Clause 1804, 1805 of SS DoR & S.N. 18.2 a. i. of Norms DoR
UNIT m2 For 10 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.22 m-day 1030.00 226.60 226.60
Unskilled 0.22 m-day 750.00 165.00 165.00
Materials Ply woods 9 mm thick 1.10 m³ 82.50 90.75 90.75
Struts ballies 0.04 cum 4166.67 166.67 166.67
Nails, Spikes etc. 0.25 k.g 112.00 28.00 28.00
Actual Rate per 10m² 677.02
Overhead @ 15 % 101.55
Sub Total 778.57
Actual rate per m² 778.57

Providing and laying of PCC M: 10 (or 1:3:6 for nominal mix) in foundation complete as per Drawing and Technical
Concrete Specification

Ref: Clause 2000 of SS DoR & S.N. 20.1. of Norms DoR


UNIT m3 For 15 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.13 m-day 1030.00 137.33 137.33
Unskilled 1.47 m-day 750.00 1100.00 1100.00
Construction Cement 230 kg 16.50 3795.00 3795.00
Materials Aggregrate 40 mm 0.9 cu.m. 3316.32 2984.69 2984.69
Coarse Sand 0.45 cu.m. 3175.20 1428.84 1428.84
Water 133.33 ltr 0.25 33.33 33.33
Concrete mixer 0.40 hr 573.00 229.20 229.20
Equipment
Generator 0.40 hr 305.00 122.00 122.00
Actual Rate 9708.39
Overhead @ 15 % 1456.26
Sub Total 11164.65
Rate per m³ 11164.65

Prepared by: Checked by: Approved by:


Page 18
Providing and laying of Plain /Reinforced cement concrete in foundation complete as per Drawing and Technical
Specification : PCC Grade M 15

Ref: Clause 2000 of SS DoR & S.N. 20.2. A. of Norms DoR


UNIT m3 For 15 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.20 m-day 1030.00 206.00 206.00
Unskilled 2.00 m-day 750.00 1500.00 1500.00
Cement 275.33 kg 16.50 4543.00 4543.00
Aggregrate 40 mm 0.54 cu.m. 3316.32 1790.81 1790.81
Material
Coarse Sand 0.45 cu.m. 3175.20 1428.84 1428.84
Water 133.33 ltr 0.25 33.33 33.33
Concrete mixer 0.40 hr 573.00 229.20 229.20
Equipment
Generator 0.40 hr 305.00 122.00 122.00
Actual Rate 9853.19
For formwork add @ 4% of labour, material and
equipment 394.13
Overhead @ 15 % 1477.98
Sub Total 11725.29
Rate per m³ 11725.29

Providing and laying of Reinforced/prestressed cement concrete in superstructure as per Drawing and Technical
Specification : PCC Grade M 20

Ref: Clause 2000 of SS DoR & S.N. 20.8. A. of Norms DoR


UNIT m3 For 15 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.20 m-day 1030.00 206.00 206.00
Unskilled 2.00 m-day 750.00 1500.00 1500.00
Cement 341.33 kg 16.50 5632.00 5632.00
Aggregrate 20 mm 0.54 3351.60 1809.86 1809.86
Material Aggregrate 10 mm 0.36 cu.m. 2892.96 1041.47 1041.47
Coarse Sand 0.45 cu.m. 3175.20 1428.84 1428.84
Water 200.00 ltr 0.25 50.00 50.00
Concrete mixer 0.40 hr 573.00 229.20 229.20
Equipment
Generator 0.40 hr 305.00 122.00 122.00
Actual Rate 12019.37
For formwork and staging add 20% of labour,
material and equipment 2403.87
Overhead @ 15 % 1802.91
Sub Total 16226.15
` Rate per m³ 16226.15

Plum Concrete (1:3:6+40% Broken Stone)

Ref: SSTB Hand book of DoLIDAR


Unit cu m For 1 cum
SOURCE TYPE QUANTITY UNIT RATE AMOUNT Remarks
LABOUR Skilled labour 0.500 m-day 1030.00 515.00
Unskilled labour 4.000 m-day 750.00 3000.00
3515.00
MATERIAL Cement 2.6400 bag 825.00 2178.00
(INCLUDING Gravel (5-40 mm) 0.54 m3 2751.84 1485.99
ROYALTIES)
Sand 0.28 m3 3175.20 889.06
Broken stones (Max 225 mm) 0.50 m3 2469.60 1234.80
5787.85
Actual Rate 9302.85
Total 9302.85
15 % OH 1395.43
Total 10698.28
Providing and laying Reinforced Cement Concrete NP3 (300 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. A. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.08 m-day 1030.00 82.40 82.40
Unskilled 0.40 m-day 750.00 300.00 300.00
Sand 0.01 cum 3175.20 20.32 20.32
Materials Cement 60.00 kg 16.50 990.00 990.00
RCC pipe 300 mm Dia. (NP3) 1.00 rm 3140.00 3140.00 3140.00
Actual Rate 4532.72
Tools ,Plants & Equipments @ 3% 11.47
Sub Total 4544.19
Overhead @ 15 % 681.63
Rate per r. m. 5225.82
Providing and laying Reinforced Cement Concrete NP3 (450 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. B. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.08 m-day 1030.00 82.40 82.40
Unskilled 0.48 m-day 750.00 360.00 360.00
Sand 0.01 cum 3175.20 22.86 22.86
Materials Cement 70.00 kg 16.50 1155.00 1155.00
RCC pipe 450 mm Dia. (NP3) 1.00 rm 4500.00 4500.00 4500.00

Prepared by: Checked by: Approved by:


Page 19
Actual Rate 6120.26
Tools ,Plants & Equipments @ 3% 13.27
Sub Total 6133.53
Overhead @ 15 % 920.03
Rate per r. m. 7053.56
Providing and laying Reinforced Cement Concrete NP3 (600 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. B. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.08 m-day 1030.00 82.40 82.40
Unskilled 0.56 m-day 750.00 420.00 420.00
Sand 0.01 cum 3175.20 25.40 25.40
Materials Cement 80.00 kg 16.50 1320.00 1320.00
RCC pipe 600 mm Dia. (NP3) 1.00 rm 6200.00 6200.00 6200.00
Actual Rate 8047.80
Tools ,Plants & Equipments @ 3% 15.07
Sub Total 8062.87
Overhead @ 15 % 1209.43
Rate per r. m. 9272.30

Providing and laying Reinforced Cement Concrete NP3 (900 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. D. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.08 m-day 1030.00 82.40 82.40
Unskilled 0.64 m-day 750.00 480.00 480.00
Sand 0.01 cum 3175.20 30.48 30.48
Materials Cement 90.00 kg 16.50 1485.00 1485.00
RCC pipe 900 mm Dia. (NP3) 1.00 rm 12172.00 12172.00 12172.00
Actual Rate 14249.88
Tools ,Plants & Equipments @ 3% 16.87
Sub Total 14266.75
Overhead @ 15 % 2140.01
Rate per r. m. 16406.77
Providing and laying Reinforced Cement Concrete NP3 (1000 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. E. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.12 m-day 1030.00 123.60 123.60
Unskilled 0.80 m-day 750.00 600.00 600.00
Sand 0.01 cum 3175.20 35.56 35.56
Materials Cement 100.00 kg 16.50 1650.00 1650.00
RCC pipe 1000 mm Dia. (NP3) 1.00 rm 13525.00 13525.00 13525.00
Actual Rate 15934.16
Tools ,Plants & Equipments @ 3% 21.71
Sub Total 15955.87
Overhead @ 15 % 2393.38
Rate per r. m. 18349.25
Providing and laying Reinforced Cement Concrete NP3 (1200 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. E. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.16 m-day 1030.00 164.80 164.80
Unskilled 0.96 m-day 750.00 720.00 720.00
Sand 0.01 cum 3175.20 45.72 45.72
Materials Cement 140.00 kg 16.50 2310.00 2310.00
RCC pipe 1200 mm Dia. (NP3) 1.00 rm 16100.00 16100.00 16100.00
Actual Rate 19340.52
Tools ,Plants & Equipments @ 3% 26.54
Sub Total 19367.07
Overhead @ 15 % 2905.06
Rate per r. m. 22272.13

Providing and Laying of a Geo-Textile filter/geo membrane between pitching and embankment slopes,behind earth
GEO TEXTILE retaining structures as per drawing and Technical specification
Ref: Clause 2404,2403 of SS DoR & S.N. 24.5,24.6. of Norms DoR
UNIT m² For 300 sq.m Unit-Cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.0033 M/D 1030.00 3.43 3.43
Labour
b) Unskilled 0.00667 M/D 750.00 5.00 8.43
Material Geo-textile fabrics 1.2 Sqm. 110.00 132.00 132.00
Actual cost 143.87
Overhead @ 15 % 21.58
Rate per m² 165.45

Providing and painting two coats after filling the surface with synthetic enamel paint in all shades on concrete/plaster surfaces as
per drawing and technical specification
Ref: Clause 1501 of SS DoR & S.N. 15.4. of Norms DoR
UNIT m² For 10 sq.m
SOURCE TYPE QUANTITYUNIT RATE AMOUNT TOTAL
LABOUR Skilled labour 0.30 m-day 1030.00 309.00 309.00

Prepared by: Checked by: Approved by:


Page 20
Unskilled labour 0.20 m-day 750.00 150.00 150.00
Material Paint 0.60 Litre 509.00 305.40 305.40
Actual Rate 764.40
Add @5% Cost of Labour and material for 38.22
preparation of Surface for painting
Total 802.62
15% OH 114.66
Rate Per m2 917.28

Prepared by: Checked by: Approved by:


Page 21
Providing and laying bituminous concrete/asphalt concrete using crushed aggregate of specified grading, premixed with
bituminous binder and filler as per drawing and technical specification
Ref: Clause 1309 of SS DoR & S.N. 13.6 of Norms DoR
UNIT cum For 95.5 cum 225 tonne
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.157 750.00 117.80
Skilled m-day 0.052 1030.00 53.93
Sub - total 171.73
Materials Bitumen tonne 0.06 78100.00 4491.62
Aggregate Grading-II-13mm(nominal size)
13.2-10 mm cum 0.44 2892.96 1284.72
10-5 mm cum 0.37 2892.60 1070.41
5mm and Below cum 0.64 2892.60 1841.27
Filler Tonne 0.01 850.00 10.69
Sub - total 8698.71
Equipment Batch Mix HMP hr. 0.0628 14122.00 887.25
Paver Finisher hr. 0.0628 3539.00 222.35
Generator hr. 0.0628 305.00 19.16
Smooth Wheeled roller hr. 0.1257 3709.00 466.05
Pneumatic Roller hr. 0.0628 2434.00 152.92
Sub - total 1747.73
Total 10618.16
15% OH 1592.72
Rate per cum 12210.89

Bio-Engineering Works
Planting rooted grass slips on the slopes 45-60 deg including preparation of slips on site. A max of 5cm depth with metal
rod or Operation includes digging, planting hole to hard-wood peg, depending on the nature of the soil. The planting
drills should be space
Ref: Clause 2807 of SS DoR & S.N. 28.08.F of Norms DoR
UNIT sqm For 1 sqm

Labour
Unskilled md 0.3 750.00 225.00
Material
Grass slips/no of drills cuttings nos 100 0.3 30.00
Hessian jutes sq m 0.27 30 8.10
263.10
Equipment
3% tools and plants 6.75
Sub-total 269.85
15% OH 40.48

Rate per sqm 310.33


Kilometer Stone
Providing and fixing RCC M15 Grade Kilometer Post including painting and printing as per standard drawing-2070 and
technical specification, position
Five Km Post(Precast)

Ref: Clause 1506 of SS DoR & S.N. 15.11(i) of Norms DoR


UNIT no For 6 no
SN TYPE QUANTITY UNIT RATE AMOUNT Remarks
a M15 grade of concrete 0.200 cum 11725.29 2345.06

Prepared by: Checked by: Approved by:


Page 22
b Steel Reinforcement 10.600 kg 84.00 890.40
c Excavation in soil for foundation 0.2 cum 691.28 3235.46
d painting two coats on concrete surface 1.7 sqm 917.28 1559.38
e Lettering on Km post 300 cm-letter 1.00 300.00
Transportation and fixing
Labour

Skilled 0.1667 manday 1030.00


Unskilled 1.0000 manday 750.00 750.00
Equipments
Tractor Trolley 0.50 hr 1016.00 508.00
Actual Rate 9588.29
Total 9588.29
15 % OH 1438.24
Total 11026.54
One Km Post(Precast)

Ref: Clause 1506 of SS DoR & S.N. 15.11(ii) of Norms DoR


UNIT no For 14 no
SN TYPE QUANTITY UNIT RATE AMOUNT Remarks
a M15 grade of concrete 0.100 cum 11725.29 1172.53
b Steel Reinforcement 5.920 kg 84.00 497.28
c Excavation in soil for foundation 0.17 cum 691.28 1669.81
d painting two coats on concrete surface 0.85 sqm 917.28 779.69
e Lettering on Km post 120 cm-letter 1.00 120.00
Transportation and fixing
Labour

Skilled 0.1429 manday 1030.00


Unskilled 0.5000 manday 750.00 375.00
Equipments
Tractor Trolley 0.21 hr 1016.00 217.71
Actual Rate 4832.02
Total 4832.02
15 % OH 724.80
Total 5556.82

Prepared by: Checked by: Approved by:


Page 23
Road Delineator posts
Providing and installation of 150mm * 1.5 m long delineators (roadway indicator, hazard markers, object markers) 80-
100cm above ground level painted black and white in 20cm wide strips, burried or pressed into the ground and
confirming to the drawings and technical specifications.
Ref: Clause 1507 of SS DoR & S.N. 15.12 of Norms DoR
UNIT no For 30 no
SN TYPE QUANTITY UNIT RATE AMOUNT Remarks
a M15 grade of concrete 0.034 cum 11725.29 394.75
b Steel Reinforcement 3.760 kg 84.00 315.84
c Excavation in soil for foundation 0.01566667 cum 691.28 10.83
d painting two coats on concrete surface 0.48 sqm 917.28 440.29
Transportation and fixing
Labour

Skilled 0.0333 manday 1030.00 34.33


Unskilled 0.2333 manday 750.00 175.00
Equipments
Tractor Trolley 0.10 hr 1016.00 101.60
Actual Rate 1472.65
Total 1472.65
15 % OH 220.90
Total 1693.55
Traffic Sign
Providing and fixing non reflective warning mandatory and informatory sign board of two mm thick MS sheet with back
support frame fixed on heavy 50mm tube or channel section of 75mm*40mm firmly fixed to the ground by the means of
properly designed foundation with M10/40 grade cement concrete 300mm*300mm*300mm, as per drawing and technical
specification/DOR Publication

Ref: Clause 1501 of SS DoR & S.N. 15.1 of Norms DoR


UNIT no For 4 traffic signs
SOURCE TYPE QUANTITY UNIT RATE AMOUNT Remarks
Excavation in soil for foundation 0.0525 cum 691.28 36.292375
Cement Concrete M10 grade 0.0275 cum 11164.65 307.027981333333
Painting angle iron post two coats 0.8775 sqm 917.28 804.9132
LABOUR Skilled labour 0.250 m-day 1030.00 257.5
Unskilled labour 0.500 m-day 750.00 375
Material Heavy duty steel tube of internal dia (6.19Kg/m), 3m long 3.1500 450.00 1417.5
including 5% wastage m
60cm height equilateral triangle 0.1100 sqm 3000.00 330
Equipments Tractor Trolley 0.7500 hr 1016.00 762
2% of cost of steel tube toward cost of drilling holes, nuts, bolts, etc. 28.35
Actual Rate 4318.58
Total 4318.58
15 % OH 647.79
Total 4966.37

Prime coat

Providing and applying prime coat with hot bitumen(including Cutter) on prepared surface of grannular base including
cleaning of road surface and spraying by mechanical means as per technical specification
Ref: Clause 1302 of SS DoR & S.N. 13.1.A of Norms DoR
UNIT lit For 5000 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.010 750.00 7.50
Skilled m-day 0.001 1030.00 0.62
Materials Bitumen (30/70) kg 1.05 78.10 82.01 1litre=1sqm
Cost of Water L 2.00 0.25 0.50
Equipment Mechanical Broom hr. 0.0016 1165.00 1.86
Air Compressor hr. 0.0016 661.00 1.06
Bitumen Distributer hr. 0.0012 1876.00 2.25
Boiler hr. 0.0016 3235.00 5.18
Generator hr. 0.0016 305.00 0.49
Total 101.46
15% OH 15.22
Rate per Litre 116.68

Prepared by: Checked by: Approved by:


Page 24
Tack coat

Providing and applying tack coat with hot bitumen at specified rate on the prepared non-bituminous surfaces including
cleaning as per technical specification
Ref: Clause 1302 of SS DoR & S.N. 13.2.A of Norms DoR
UNIT lit For 5000 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.004 750.00 3.00
Skilled m-day 0.001 1030.00 0.62
Materials Bitumen (30/70) kg 1.05 78.10 82.01
Equipment Air Compressor hr. 0.0012 661.00 0.79
Bitumen Distributer hr. 0.0012 1876.00 2.25
Boiler hr. 0.0012 3235.00 3.88
Generator hr. 0.0012 305.00 0.37
Total 92.92
15% OH 13.93731
Total 106.85
Rate Per Litre 106.85

Bitumen Cutter
Providing and mixing of Bitumen cutter as per design/direction of Engineer
Ref: Clause 1300 of SS DoR & S.N. 13.17 of Norms DoR
UNIT lit For 200 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.005 750.00 3.75
Skilled m-day 0.00005 1030.00 0.05
Materials Kerosene/ Diesel cutter Lit 1.05 82.30 86.42
Equipment Add 3% of Labour component for T&P 0.11
Total 90.33
15% OH 13.54958175
Total 103.88
Rate Per Litre 103.88

Anti-Stripping agent
Providing and mixing of Anti-Stripping agent as per design/direction of Engineer
Ref: Clause 1300 of SS DoR & S.N. 13.16 of Norms DoR
UNIT Kg For 200 kg
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.005 750.00 3.75
Skilled m-day 0.00005 1030.00 0.05
Materials Additive material kg 1.05 320.00 336.00
Equipment Add 3% of Labour component for T&P 0.11
Total 339.92
15% OH 50.98733175
Total 390.90
Rate Per Kg 390.90

Surface Dressing
Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied
layer of bituminour binder on prepared surface as per Drawing and Technical Specifications.

Case I 19 mm nominal chipping size


Ref: Clause 1303 of SS DoR & S.N. 13.7 A of Norms DoR
UNIT Sqm For 6000 sqm
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.002 750.00 1.50
Skilled m-day 0.00050 1030.00 0.52
Materials Chips, 19 mm nominal size cum 0.02 3351.60 56.98
Chip Spreader hr 0.0010 2439.00 2.44
Equipment Roller (pneumatic) hr 0.0020 2434.00 4.87
Total 66.30
15% OH 9.94488
Total 76.24
Rate Per Sqm 76.24

Case II 13 mm nominal chipping size


Ref: Clause 1303 of SS DoR & S.N. 13.7 A of Norms DoR
UNIT Sqm For 7500 sqm
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.002 750.00 1.20
Skilled m-day 0.00040 1030.00 0.41
Materials Chips, 13 mm nominal size cum 0.01 3351.60 38.88
Chip Spreader hr 0.0008 2439.00 1.95
Equipment Roller (pneumatic) hr 0.0016 2434.00 3.89
Total 46.34
15% OH 6.950424
Total 53.29
Rate Per Sqm 53.29

Case III 10 mm nominal chipping size


Ref: Clause 1303 of SS DoR & S.N. 13.7 A of Norms DoR
UNIT Sqm For 9000 sqm
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.001 750.00 1.00

Prepared by: Checked by: Approved by:


Page 25
Skilled m-day 0.00033 1030.00 0.34
Materials Chips, 10 mm nominal size cum 0.01 2892.96 25.81
Chip Spreader hr 0.0007 2439.00 1.63
Equipment Roller (pneumatic) hr 0.0013 2434.00 3.25
Total 32.03
15% OH 4.8039448
Total 36.83
Rate Per Sqm 36.83

Case IV 6 mm nominal chipping size


Ref: Clause 1303 of SS DoR & S.N. 13.7 A of Norms DoR
UNIT Sqm For 9000 sqm
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.001 750.00 1.00
Skilled m-day 0.00033 1030.00 0.34
Materials Chips, 10 mm nominal size cum 0.01 2892.96 15.49
Chip Spreader hr 0.0007 2439.00 1.63
Equipment Roller (pneumatic) hr 0.0013 2434.00 3.25
Total 21.71
15% OH 3.2562112
Total 24.96
Rate Per Sqm 24.96

Norms Serial No:13.07 (Previous DOR Norms)


Clause No.: 1301 1305
Providing and Laying sand spreading over newly primed surface (1301,1305)

Unit : 10m2

S.No. Description Unit Quantity Rate in NRs Amount in NRs Remarks


1 Labour
Unskilled md 0.140 750.00 105.00
Skilled md 0.100 1,030.00 103.00

Sub Total Labor 208.00


2 Material
sand m3 0.120 3,175.20 381.02
Sub Total Material 381.02
3 Tools and equipment
3 % of labour cost
6.24

Sub Total Tool/Equipment 6.24


Sub Total (Labor+Material+Tools/Equipment) -I 595.26
Contractor Over head 15% of I 89.29
Total rate per m2 68.46

20mm thick Open-Graded Premix Carpet using Bituminous (Paving Bitumen / Modified Bitumen) Binder.
Providing and laying open-graded premix carpet of 20 mm thickness composed of 13.2 mm to5.6 mm aggregates as
wearing course on a previously prepared base as per drawing and Technical Specifications.

Ref: Clause 1311 of SS DoR & S.N. 13.9 B(i) of Norms DoR
UNIT Sqm For 500 sqm 10 cum
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.042 750.00 31.50
Skilled m-day 0.01600 1030.00 16.48
Paving bitumen or other as per Design Kg 1.46 0.00 0.00
Materials
Crushed stone chipping, 13.2 mm to 5.6mm For 0.03
Mixer hr 0.0080 0.00 0.00
Equipment Bitumen boiler oil fired hr 0.0080
Roller (Smooth wheeled) hr 0.0040 0.00 0.00
Total 47.98
15% OH 7.197
Total 55.18
Rate Per Sqm 55.18

Steel Reinforcement for RCC


Providing and laying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and technical
specification
Ref: Clause 2014 of SS DoR & S.N. 20.9 nof Norms DoR
UNIT Tonne For 1 Tonne
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Skilled m-day 4 1030.00 4120.00
Unskilled m-day 12 750.00 9000.00

Prepared by: Checked by: Approved by:


Page 26
Materials HYSD Bars Tonne 1.1 84000.00 92400.00
Binding Wire kg 8 92.00 736.00
Total 106256.00
15% OH 15938.4
Total 122194.40
Rate Per tonne 122194.40
Rate per kg 122.19

Providing suitable material and backfilling behind abutment, wingwall, return wall and other retaining structures complete as per drawing and
technical specification

Ref: Clause 908 of SS DoR & S.N.9.11 A,C of Norms DoR


UNIT m3 For 10.00 cu/m

Prepared by: Checked by: Approved by:


Page 27
Source Type Quantity Unit Rate Amount Total
A Grannular Material
a Labor
Skilled 0.02 m-day 0.00
Unskilled 0.50 m-day 0.00
b Material 0.00
Grannular Material 1.10 cum 0.00
Cost of Water 0.10 KL 0.00
c Equipment 0.00
C Locally available Material including Compaction by Tamping 0.00
Rod(without watering)
a Labor 0.00
Skilled 0.02 m-day 1,030.00 20.60
Unskilled 0.50 m-day 750.00 375.00
b Material 0.00
Compensation for locally available material 1.20 cum 50.00 60.00
Cost of Water 0.10 Kl 250.00 25.00
Total labor cost 395.60
Tamping 3% of Labour Cost 11.87
Actual RateAc 492.47
Overhead @ 15% 73.87
Rate per m3 566.34

Providing and filling stone/boulder in gabion boxes/mattress etc. including dressing, bedding, bonding all complete as per drawing and technical
specification
Ref: Clause 2402 of SS DoR & S.N.24.4of Norms DoR
UNIT m3 For 10.00 cu/m
Source Type Quantity Unit Rate Amount Total
A Labor
Skilled 0.20 m-day 1030.00 206.00
Unskilled 0.80 m-day 750.00 600.00
B Material
Boulder/Stone 1.10 cum 2469.60 2716.56
Actual RateAc 3522.56
Overhead @ 15% 528.38
Rate per m3 4050.94

Providing mechanically woven double twisted crates / mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 3 mm, selvedge wire 3.90
mm, lacing wire 2.40 mm ) including rolling cutting and with lacing wire and binding wire and filling stone/boulder in gabion boxes/mattress etc. including
dressing, bedding, bonding all complete as per drawing and technical specification
Ref: Clause 2402, of SS DoR & S.N.24.2(A,B),24.4of Norms DoR
Source Type Unit Rate Amount Total
Providing mechanically woven double twisted crates /
mattress including rolling cutting and with lacing wire and 1m3=4.82s
A binding wire sqm 1301.4 qm
Filling Stone/Boulder in Gabion boxes/mattress etc. including
B dressing, bedding, bonding all m3 3522.56
Actual RateAc 4823.96
Overhead @ 15% 723.59
Rate per m3 5547.55

Providing mechanically woven double twisted crates / mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40
mm, lacing wire 2.20 mm ) including rolling cutting and with lacing wire and binding wire and filling stone/boulder in gabion boxes/mattress etc.
including dressing, bedding, bonding all complete as per drawing and technical specification
Ref: Clause 2402, of SS DoR & S.N.24.2(A,B),24.4of Norms DoR
Source Type Unit Rate Amount Total
Providing mechanically woven double twisted crates /
mattress including rolling cutting and with lacing wire and 1m3=4.82s
A binding wire m3 1205 qm
Filling Stone/Boulder in Gabion boxes/mattress etc. including
B dressing, bedding, bonding all m3 3522.56
Actual RateAc 4727.56
Overhead @ 15% 709.13
Rate per m3 5436.69

Description of works:

Provide and erecting "W" metal beam crashbarrier comprising of 3.43mm thick corrugated sheet metal
beam rail, 70cm above road/ground level,fixed on ISMC serises channel vertical post, 150*75*5 mm spaced
2m c/c,1.8m high,1.1m below ground/road level,all steel paetsand fitment to be galvanized by hot dip
IRC 7.08
process,all fittings to confirm to IS 1367 and IS 1364,metal beam rail to be fixed on the vertical post with a
spacer of chaneel section 150*75*5mm 330mm long, all complete
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
Corrugated sheet, 3.43 mm thick,
Skilled md 0.393 1030.00 404.79 "W" beam section railing, 4.5 m in
length kg

Unskilled md 0.786 589.50 Channel post 150x75x5 mm, 1.8 m


750.00 long, 2 Nos @ 16.4 kg per meter kg

Spacer 150x75x5mm channel 0.33


m long, 3 Nos. @16.4 kg per meter kg
Nuts and bolts kg

Prepared by: Checked by: Approved by:


Page 28

Add 25% of material for fabrication


Hot dip galvanization type I as per
AASHTO 180-12 kg
Excavation Cum
M20 grade concrete Cum
Transportation to the site ton
Sub total of A = 994.29 Sub total of B =
Sub total of A +B + C = 28854.81 ractor's overhead expenses 15% =

Stone pitching
Providing and laying of hand packed stone solling with 150 to 200 mm thick stones and packing with smaller stones on prepared surface as per drawing and
technical specifications
Ref: Clause 1006 of SS DoR & S.N.24.15 A of Norms DoR
UNIT m3 For 1 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Skilled 1.20 m-day 1030.00 1236.00 1236.00
Labor
Unskilled 2.40 m-day 750.00 1800.00 1800.00
material Stone weighing >40kg 1.20 cu.m. 2469.60 2963.52 2963.52
Actual Rate 5999.52
Overhead @ 15 % 899.93
Sub Total 6899.45
Rate per m³ 6899.45

Prepared by: Checked by: Approved by:


Rates for Equipment

Fuel Quantity Amount of Fuel Total Rate (Wet


S.N. Equipment Unit DoR Rate(NR.) Fuel Rate Reference Remarks
Liter per Hour used per hour Lease)
Fuel Usage Factors in
Highway and Bridge
E1 Asphalt Concrete Plant Hour 400.00 82.30 56.00 4,608.00 5,008.00 upto 10 ton
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E2 Asphalt Paver Hour 1,400.00 82.30 26.00 2,139.00 3,539.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E3 Bitumen Distributor Hour 1,300.00 82.30 7.00 576.00 1,876.00 4 to 6 kL
Construction (2013) by
NCHRP
E4 Bitumen Boiler Hour 1,260.00 82.30 24.00 1,975.00 3,235.00 upto 2 kL
Fuel Usage Factors in
Highway and Bridge
E5 Stone Crushing Plant Hour 120.00 82.30 37.00 3,045.00 3,165.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E6 Screening Plant Hour 500.00 82.30 37.00 3,045.00 3,545.00
Construction (2013) by
NCHRP
E7 Chips Spreader, Self Propelled Hour 300.00 82.30 - - 300.00
Fuel Usage Factors in
Highway and Bridge
E7.1 Chips Spreader, Mechanical Hour 300.00 82.30 26.00 2,139.00 2,439.00
Construction (2013) by
NCHRP
DoR Previous Norms Appendix
E8 Excavator, Wheel Hour 1,200.00 82.30 12.00 987.00 2,187.00 upto 110 HP
2
DoR Previous Norms Appendix
E9 Dozer, Track Hour 3,000.00 82.30 17.00 1,399.00 4,399.00 120 to 125 HP
2
DoR Previous Norms Appendix
E10 Loader Hour 1,000.00 82.30 12.00 987.00 1,987.00 1 to 1.75 Cum
2
Fuel Usage Factors in
Highway and Bridge
E11 Back Hoe Loader Hour 1,000.00 82.30 11.00 905.00 1,905.00
Construction (2013) by
NCHRP

29 of 45
Fuel Usage Factors in
Highway and Bridge
E12 Motor Grader Hour 1,200.00 82.30 34.00 2,798.00 3,998.00 80 to 145 HP
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E13 Crane (5-10 Ton) Hour 3,100.00 82.30 11.00 905.00 4,005.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E14 Pneumatic Roller Hour 1,200.00 82.30 15.00 1,234.00 2,434.00 upto 20 ton
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E15 Roller 3 wheel ( Up to 12 ton ) Hour 500.00 82.30 39.00 3,209.00 3,709.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E16 Roller vib, Self propelled Hour 800.00 82.30 26.00 2,139.00 2,939.00 above 3 ton
Construction (2013) by
NCHRP
Vibrobliešu WEBER degv.
E17 Roller vib, Self propelled Hour 550.00 82.30 4.30 353.00 903.00 upto 3 Ton
patēriņš vec
Quantity of Diesel Based on
E18 Tipper (6mt) Hour 450.00 82.30 8.71 716.00 1,166.00
calculation
Quantity of Diesel Based on
E19 Truck(6mt) Hour 450.00 82.30 8.71 716.00 1,166.00
calculation
Quantity of Diesel Based on
E20 Mini Truck Hour 300.00 82.30 7.09 583.00 883.00
calculation
DoR Previous Norms Appendix
E21 Mini Dumper Hour 250.00 82.30 1.90 156.00 406.00
2
Fuel Usage Factors in
Highway and Bridge
E22 Tractor Hour 440.00 82.30 7.00 576.00 1,016.00
Construction (2013) by
NCHRP
DoR Previous Norms Appendix
E23 Concrete Mixer Hour 450.00 82.30 1.50 123.00 573.00
2
Fuel Usage Factors in
Highway and Bridge
E24 Concrete Cutter Hour 250.00 97.35 3.00 292.00 542.00
Construction (2013) by
NCHRP
DoR Previous Norms Activities
E25 Concrete Needle Vibrator Hour 100.00 97.35 0.10 9.00 109.00
Group no. 20
Fuel Usage Factors in
Highway and Bridge
E26 Compactor Hand Towed Hour 130.00 97.35 0.75 73.00 203.00 350 to 450 KG
Construction (2013) by
NCHRP

30 of 45
Fuel Usage Factors in
Highway and Bridge
E27 Air Compressor Hour 250.00 82.30 5.00 411.00 661.00 150 to 275 CFM
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E28 Drilling Machine Hour 130.00 82.30 17.00 1,399.00 1,529.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E29 Water Browser Hour 550.00 82.30 18.00 1,481.00 2,031.00 upto 6 kL
Construction (2013) by
NCHRP
DoR Previous Norms Appendix
E30 Water Pump Hour 200.00 82.30 0.35 28.00 228.00 upto 6" dia
2
Fuel Usage Factors in
Highway and Bridge
E31 Generator (2 KVA) Hour 150.00 82.30 1.89 155.00 305.00
Construction (2013) by
NCHRP
https://texags.com/forums/57/t
E32 Boring Equipment with Pump Hour 1,400.00 82.30 568.00 46,746.00 48,146.00
opics/2525768
DoR Previous Norms Appendix
E33 Excavator,Track Hour 1,800.00 82.30 12.00 987.00 2,787.00 upto 110 HP
2
DoR Previous Norms Appendix
E34 Excavator with Breaker Hour 2,100.00 82.30 12.00 987.00 3,087.00
3
Fuel Usage Factors in
Highway and Bridge
E35 Sprayer Hour 260.00 82.30 5.00 411.00 671.00 upto 1KL
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E36 Mechanical Broom Hour 260.00 82.30 11.00 905.00 1,165.00
Construction (2013) by
NCHRP

DoR Previous Norms Appendix


E37 Hot Mix Plant Hour 750.00 82.30 1.50 123.00 873.00
2 for Concrete Mixer

Fuel Usage Factors in


Highway and Bridge
E38 Road Marking Machine Hour 260.00 82.30 5.00 411.00 671.00
Construction (2013) by
NCHRP

31 of 45
Contract ID: Unskilled 750.00
Skilled 1,030.00
Analysis of Rates of Collection of Materials
Activity 15%
Resource Analyzed Quantity
S.No. Norms Description of Works/ Resource Type Unit Unit Rate Amount Overhead
No. Quantity per Unit
No. Charge
1 Stone cu.m.
1.1 8.7 B Making rubbles of required size including and stacking. cu.m. 1.00
A1 Skilled Labour pd 0.10 0.10 1,030.00 103.00 15.45
A3 Unskilled Labour pd 4.00 4.00 750.00 3,000.00 450.00
3% of Labor Cost Tools and Plants 93.09 13.96
Sum 3,196.09
9.1.IV.A Excavation in hardrock with rock breakers. cu.m. 16.00
A1 Skilled Labour pd 1.00 0.06 1,030.00 64.38 9.65
A3 Unskilled Labour pd 10.00 0.63 750.00 468.75 70.31
E34 Excavator with Breaker Hour 6.00 0.38 3,087.00 1,157.63 173.64
According to Norms 50% only is reusable. (845.37)
Sum 845.38
Col.M.1 Stone 962.92

2 8.6 Mechanically Crushing Aggregate


8.6.A 13.2 mm Nominal Size. cu.m. 600.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 3.43 0.51
A3 Unskilled Labour pd 18.00 0.03 750.00 22.50 3.37
Col.M.1 Stone cu.m. 800.00 1.33 962.92 1,283.89 192.58
E5 Stone Crushing Plant Hour 12.00 0.02 3,165.00 63.30 9.49
E6 Screening Plant Hour 12.00 0.02 3,545.00 70.90 10.63
E18 Tipper (6mt) Hour 18.00 0.03 1,166.00 34.98 5.24
E10 Loader Hour 18.00 0.03 1,987.00 59.61 8.94
Sum 1,538.62
8.6.B 20 mm Nominal Size. cu.m. 670.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 3.07 0.46
A3 Unskilled Labour pd 18.00 0.03 750.00 20.15 3.02
Col.M.1 Stone cu.m. 800.00 1.19 962.92 1,149.76 172.46
E5 Stone Crushing Plant Hour 18.00 0.03 3,165.00 94.95 14.24
E6 Screening Plant Hour 18.00 0.03 3,545.00 106.35 15.95
E18 Tipper (6mt) Hour 18.00 0.03 3,545.00 95.24 14.28
E10 Loader Hour 18.00 0.03 1,987.00 53.38 8.00
Sum 1,522.90
8.6.C 40 mm Nominal Size. cu.m. 750.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 2.75 0.41
A3 Unskilled Labour pd 17.00 0.02 750.00 17.00 2.55
Col.M.1 Stone cu.m. 800.00 1.07 962.92 1,027.11 154.06
E5 Stone Crushing Plant Hour 6.00 0.01 3,165.00 25.32 3.79
E6 Screening Plant Hour 6.00 0.01 3,545.00 28.36 4.25
E18 Tipper (6mt) Hour 18.00 0.02 3,545.00 85.08 12.76
E10 Loader Hour 18.00 0.02 1,987.00 47.69 7.15
Sum 1,233.31
3 8.6 Mechanically Screening Aggregate
8.6.A 13.2 mm Nominal Size. cu.m. 600.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 3.43 0.51
A3 Unskilled Labour pd 18.00 0.03 750.00 22.50 3.37
Col.M.1 Stone cu.m. 800.00 1.33 962.92 1,283.89 192.58
E6 Screening Plant Hour 12.00 0.02 3,545.00 70.90 10.63
E18 Tipper (6mt) Hour 18.00 0.03 3,545.00 106.35 15.95
E10 Loader Hour 18.00 0.03 1,987.00 59.61 8.94
Sum 1,546.69
8.6.B 20 mm Nominal Size. cu.m. 670.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 3.07 0.46
A3 Unskilled Labour pd 18.00 0.03 750.00 20.15 3.02
Col.M.1 Stone cu.m. 800.00 1.19 962.92 1,149.76 172.46
E6 Screening Plant Hour 18.00 0.03 3,545.00 95.24 14.28
E18 Tipper (6mt) Hour 18.00 0.03 3,545.00 95.24 14.28
E10 Loader Hour 18.00 0.03 1,987.00 53.38 8.00
Sum 1,416.84
8.6.C 40 mm Nominal Size. cu.m. 750.00
A1 Skilled Labour pd 2.00 0.00 1,030.00 2.75 0.41
A3 Unskilled Labour pd 17.00 0.02 750.00 17.00 2.55
Col.M.1 Stone cu.m. 800.00 1.07 962.92 1,027.11 154.06
E6 Screening Plant Hour 6.00 0.01 3,545.00 28.36 4.25
E18 Tipper (6mt) Hour 18.00 0.02 3,545.00 85.08 12.76
E10 Loader Hour 18.00 0.02 1,987.00 47.69 7.15
Sum 1,207.99
4 Col.M.2 Sub Base Aggregate cu.m. 1,335.70 200.35
5 Col.M.3 Base Aggregate cu.m. 1,443.88 216.58
6 Col.M.4 Capping Layer cu.m. 1,258.79 188.81
7 Col.M.5 Well Graded Filter Materials cu.m. 1,257.52 188.62

8 Sand
8.3.D Collection, quarrying and sieving sand in local river cu.m. 1.00
A3 Unskilled Labour pd 1.50 1.50 750.00 1,125.00 168.75
3% of Labor Cost Tools and Plants 33.75 5.06
8.4.A Washing Sand cu.m. 1.00
A3 Unskilled Labour pd 0.50 0.50 750.00 375.00 56.25
3% of Labor Cost Tools and Plants 11.25 1.68
Sum 1,545.00

9 Water
Collection of Water from Local River into the Water
8.04.02.17 Litre 1,000.00
Bowser
A1 Skilled Labour pd 0.01 0.000010 1,030.00 0.01 -
A3 Unskilled Labour pd 0.10 0.000100 750.00 0.08 0.01
E29 Water Browser Hour 0.05 0.000050 2,031.00 0.10 0.01
E30 Water Pump Hour 0.05 0.000050 228.00 0.01 -
3% of Labor Cost Tools and Plants - -
Sum 0.20
Net
Remarks
Amount

118.45
3,450.00
107.05
3,675.50

74.03
539.06
1,331.27
(972.17)
972.18
1,107.35

3.94
25.87
1,476.47
72.79
81.53
40.22
68.55
1,769.38

3.53
23.17
1,322.22
109.19
122.30
109.52
61.38
1,751.31

3.16
19.55
1,181.17
29.11
32.61
97.84
54.84
1,418.28

3.94
25.87
1,476.47
81.53
122.30
68.55
1,778.67

3.53
23.17
1,322.22
109.52
109.52
61.38
1,629.34
3.16
19.55
1,181.17
32.61
97.84
54.84
1,389.17
1,536.05 According
1,660.46 to
Standard
1,447.60 Specificati
1,446.14 on

1,293.75
38.81

431.25
12.93
1,776.74

Previous
Norms
0.01
0.09
0.11
0.01
-
0.22
Basic Rate

District Collection Transportation Royalty Total Rate(From


S.N. Descriptions Unit Remarks
Rate (D) Rate (C) Rate ( Tp ) (R) Municipality Rate)

A. Labour
1 Skilled Md 1030.00 1030.00 District Rate
2 Unskilled Md 750.00 750.00 District Rate
B. Material
1 Cement Bag 825.00 25.01 825.00 District Rate
2 Sand Cum 3175.20 1,776.74 412.72 105.94 3175.20 Tp+R+C
3 Natural Gravel Cum 2,751.84 1,250.00 606.50 158.90 2751.84 Tp+R+C
4 20mm- 40mm Aggregate Cum 3316.32 1,418.28 606.50 3316.32 District Rate
10mm- 20mm Aggregate Cum 3351.60 1,751.31 606.50 3351.60 District Rate
6mm-10mm Aggregate Cum 2892.96 1,769.38 606.50 2892.96 District Rate
<6mm Aggregate Cum 2892.96 606.50 2892.96 District Rate
5 Aggregate 16 mm Cum 3926.50 606.50 4533.00 District Rate
6 Soil Cum 318.60 318.60 District Rate
6 Stone Cum 2469.60 1,107.35 675.49 250.00 2469.60 Tp+R+C
7 Stone Dust Cum 1447.89 158.90 1447.89 District Rate
8 Gabion Wire
12 SWG kg 105.00 0.65 105.00 District Rate
10 SWG kg 105.00 0.65 105.00 District Rate
8 SWG kg 105.00 0.65 105.00 District Rate
9 Binding Wire Kg 92.00 0.65 92.00 District Rate
10 Reinforcement kg 84.00 0.65 84.00 District Rate
11 Bitumen kg 78.10 5.27 78.10 District Rate
12 Petrol Lt 97.35 97.35
13 Diesel Lt 82.30 82.30 NOC Rate Excluding VAT
14 Kerosene Lt 82.30 82.30
15 Nail kg 112.00 0.65 112.00 District Rate
16 Fire wood kg 18.00 18.00 District Rate
at site (Transportation Cost
25% of unit cost) from
17 NP3 pipe @300 mm dai with collar Rm 3140.00 785.00 3140.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @450 mm dai with collar Rm 4500.00 1,125.00 4500.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @600 mm dai with collar Rm 6200.00 1,550.00 6200.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @900 mm dai with collar Rm 12172.00 3,043.00 12172.00 Kathmandu
NP3 pipe @1000 mm dai with collar Rm 13525.00 3,381.25 13525.00
NP3 pipe @1200 mm dai with collar Rm 16100.00 4,025.00 16100.00
18 Natural Gravel Cum 2,751.84 1250.00 606.50 2751.84 Tp+R+C
19 Inferior Wood Cum 22072.00 22072.00 District Rate
20 Primer lit 365.00 0.65 365.00 District Rate
21 Enamel paint lit 509.00 0.65 509.00 District Rate
22 Anti stripping agent kg 320.00 320.00 District Rate
23 Geo-textile sqm 110.00 110.00 District Rate
24 Jute Kg 100.00 100.00 District Rate
25 Base cum 3001.75 1,660.46 3001.75 District Rate
26 Sub Base cum 2754.55 1,536.05 2754.55 District Rate
27 Graded Filter Materials cum 1446.14 1,446.14 1446.14

4290.60
SB 2754.55
B 3001.75
Rate Analysis(Transportation)
Travel Time (T) for truck to be used for this activity shall be determined as follows:

T = 2 * { d1/v1 + d2/v2 + d3/v3 + …………. Dn/vn}, where d1, d2, d3 … dn and v1, v2, v3……vn are the streches of distances to be
travelled and corresponding average speeds on these streches.

1 Transportation of Sand by Truck


Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(2)
Source Name Sunkoshi Nadi F/Y: 075/076
Lead Distance 9.25 Km
Description Unit Gravel Road Metallic Road Earthn Road Total Length
Distance from source to site KM 6 0 3.25 9.25
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.73 Hrs.
.
Description of Works Type Unit Quantity Remarks
A. Equipment Truck hr 0.13*(T+0.75) T= Travel Time for
Truck
0.19175
B. Labours Unskilled md 0.3

C. Materials Fuel ltr. 1.7*T T= Travel Time for


Truck
1.2325
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.19175 450.00 86.29
Labour md 0.3 750.00 225.00
Fuel ltr. 1.2325 82.30 101.43
Sub total 412.72
Royalty @ Rs 3 per cub ft m³ 105.94
Actual cost per m³ 518.67
Grand Total per m³ 518.67
2 Transportation of Aggregate by Truck
Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(3)
Source Name Sunkoshi Nadi F/Y: 075/076
Lead Distance 9.25 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 0 3.25 9.25
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.73 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.16*(T+0.75) T= Travel Time for
Truck
0.236
B. Labours Unskilled md 0.5

C. Materials Fuel ltr. 2.1*T T= Travel Time for


Truck
1.52
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.236 450.00 106.20
Labour md 0.5 750.00 375.00
Fuel ltr. 1.5225 82.30 125.30
Sub Total 606.50
Royalty-DDC Office @ Rs 4.5 per cft m³ 158.90
Actual cost per m³ 765.40
Grand Total per m³ 765.40

3 Transportation of river bed gravel by Truck


Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(3)
Source Name Sunkoshi Nadi F/Y: 075/076
Lead Distance 9.25 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 0 3.25 9.25
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.73 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.16*(T+0.75) T= Travel Time for
Truck
0.236
B. Labours Unskilled md 0.5

C. Materials Fuel ltr. 2.1*T T= Travel Time for


Truck
1.52
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.236 450.00 106.20
Labour md 0.5 750.00 375.00
Fuel ltr. 1.5225 82.30 125.30
Sub total 606.50
Royalty-DDC Office @ Rs 4 per cft m³ 158.90
Actual cost per m³ 765.40
Grand Total per m³ 765.40
4 Transportation of Boulder by Truck
Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(4)
Source Name Sunkoshi Nadi F/Y: 075/076
Lead Distance 9.25 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 0 3.25 9.25
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.73 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.21*(T+0.75) T= Travel Time for
Truck
0.30975
B. Labours Unskilled md 0.5

C. Materials Fuel ltr. 2.7*T T= Travel Time for


Truck
1.96
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.30975 450 139.39
Labour md 0.5 750.00 375.00
Fuel ltr. 1.96 82.30 161.10
Sub Total 675.49
Royalty-DDC Office @Rs 1.5 per cft m³ 158.90
Actual cost per m³ 834.38
Grand Total per m³ 834.38

5 Transportation of Bitumen by Truck


Unit 1000 lit.
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(4)
Source Name Birgunj F/Y: 075/076
Lead Distance 286 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 275 5 286
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 14.65 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.2*(T+0.75) T= Travel Time for
Truck
3.080
B. Labours Unskilled md 1.0

C. Materials Fuel ltr. 2.6*T T= Travel Time for


Truck
38.09
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 3.08 450.00 1386.00
Labour md 1.0 750.00 750.00
Fuel ltr. 38.09 82.30 3134.81
Actual cost per 1000 lit. 5270.81
Grand Total per lit. 5.27
6 Transportation of Cement by Truck
Unit 1 mt.
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(4)
Source Name Manthali F/Y: 075/076
Lead Distance 11 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 0 5 11
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.90 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.12*(T+0.75) T= Travel Time for
Truck
0.198
B. Labours Unskilled md 1.0

C. Materials Fuel ltr. 1.5*T T= Travel Time for


Truck
1.35
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.198 450.00 89.10
Labour md 0.4 750.00 300.00
Fuel ltr. 1.35 82.30 111.11
Actual cost per mt. 500.21
Grand Total per kg. 0.50

7 Transportation of Gabion box by Truck


Unit 1 mt.
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(4)
Source Name Manthali F/Y: 075/076
Lead Distance 11 Km
Description Unit Gravel Road Metallic Road Earthen Road Total Length
Distance from source to site KM 6 0 5 11
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.90 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.12*(T+0.75) T= Travel Time for
Truck
0.198
B. Labours Unskilled md 1.0

C. Materials Fuel ltr. 1.5*T T= Travel Time for


Truck
1.35
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.20 450.00 89.10
Labour md 0.6 750.00 450.00
Fuel ltr. 1.35 82.30 111.11
Actual cost per mt. 650.21
Grand Total per kg. 0.65
1 Transportation of Soil by Truck
Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(2)
Source Name from site F/Y: 070/071
Lead Distance 1 Km
Description Unit Gravel Road Metallic Road Earthn Road Total Length
Distance from source to site KM 0 0 1 1
Average speed of truck KM/Hr 30 40 20
T = 2 * {d1/v1+d2/v2+d3/v3} = 0.10 Hrs.
.
Description of Works Type Unit Quantity Remarks
A. Equipment Truck hr 0.13*(T+0.75) T= Travel Time for
Truck
0.1105
B. Labours Unskilled md 0.3

C. Materials Fuel ltr. 1.7*T T= Travel Time for


Truck
0.17
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.11 450.00 49.73
Labour md 0.30 750.00 225.00
Fuel ltr. 0.17 82.30 13.99

Actual cost per m³ 288.72


Grand Total per m³ 288.72
Transportation of Construction Materials by Truck (Truck Analysis)

Truck hiring cost per hour Rs/hr

Cost of truck of 6 m.t. capacity a ... 2,500,000.00


Total working hours b ... 10,000.00
Working hours per year c ... 2,000.00
1. Ownership cost
Depreciation cost per hour (a/b) ... 250.00
Insurance cost per hour (0.02 a/c) 25.00
Interest tax per hour (0.01 a/c) ... 12.50
Sub total of 1 ... 287.50
2. Operation cost
A. Maintenance cost per hour
Overhauling cost 0.55 a/b ... 137.50
Repair and maintenance cost 0.23 a/b ... 57.50
Sub total of A 195.00
B. Net operationg cost per hour
i) Fuel and lubrication cost
H.S. Diesel @ 5.5 lit/hr ... ... 486.73
Mobil @0.1 lit/hr ... ... 39.82
Gear oil @0.03 lit/hr ... ... 14.60
Grease @0.015 Kg/h ... ... 5.97
Sub total of i ... ... 547.12
ii) Spare parts
Life span of tyres L hrs 2,000.00
Cost of one tyre T Rs 18,000.00
Cost of tyres per hour 6T/L ... ... 54.00
Other Lump sum approx 8% of 6T/L ... 4.32
Sub total of ii ... ... 58.32
iii) Salary
Working hours, hrs. 8.00
Driver (Wages per day/8) ... ... 62.50
Helper (Wages per day/8) ... ... 41.67
Sub total of iii ... ... ... 104.17
iv) Improvement and other minor repair expenses, apporx 25% of (0.23a/b) 57.50
Sub total of B ( i +ii + iii + iv ) ... ... 767.11
Sub total 2 per hour ( A + B ) ... ... 962.11
3. Supervision and overhead expenses per hour 0.05 a/c 62.50
Sub total of 3 ... ... 62.50
TOTAL TRANSPORTATION COST per hour, E=∑ (1 + 2 + 3) 1,312.11
Transportation cost of Truck per hour 764.99
Rate Analysis (Summary of Local and Non Local Material)

1. ITEM Collection and providing of sand at Sunkoshi Nadi


UNIT cu.m.
Ref: S. No. 56.4 , Annex 1 Resp. Clause of Spec.G 13.2
Source Type Quantity Unit Rate Amount

Labour Collection of sand 1 m-day 750.00 750.00

Equipment Transportation by Truck 1 cu. m. 518.67 518.67


Actual Rate 1268.67

2. ITEM Collection and providing of sand at Sunkoshi Nadi


UNIT cu.m.
Ref: Activity No. - Annex - I (5.1), S. No. - 35 (DoLIDAR) DoR-8.01-02
Source Type Quantity Unit Rate Amount

Labour Collection of Gravel 1 m-day 750.00 750

Equipment Transportation by Truck 1 cu. m. 765.40 765.40


Actual Rate 1515.40

3. ITEM Collection of boulder of reqd size


UNIT cu.m.
Ref: 51.34, Annex-I
Source Type Quantity Unit Rate Amount

Labour Unskilled labour for collection 1 m-day 750.00 750

T&P Transportation by Truck 1 cu.m. 834.38 834.38

Actual Rate 1584.38


3. ITEM Collection of boulder of reqd size
UNIT cu.m.
Ref: 51.34, Annex-I
Source Type Quantity Unit Rate Amount

Labour Unskilled labour for collection 1 m-day 750.00 750

T&P Transportation by Truck 1 cu.m. 288.72 288.72

Actual Rate 1038.72

You might also like