Professional Documents
Culture Documents
For Estimation - Gabion - RTW
For Estimation - Gabion - RTW
For Estimation - Gabion - RTW
-n=;=_ -n=;=_
SUMMARY OF COST
B. General Items
a. Third Party Insurance (0.15 % of A) 155,956.72
b. Insurance of the work(0.15 % of A) 155,956.72
Insurance against accident of the worksman (0.15 %
c. 155,956.72
of A)
d. As built drawing preparation(0.05 % of A) 51,985.57
e. Commission of the performance bond (0.05 % of A) 51,985.57
f. Lab Test Work (0.05 % of A) 51,985.57
Sub-Total (B) 623,826.87
C. Miscellaneous Items
a. Environmental Protection (1% of A) 1039711.4444
b. Institutional Development(1% of A) 1039711.4444
Sub-Total (C) 2079422.8888
D Other Expenditure
a Work Charge (2.5% of A) 2,599,278.61
b Other Minor Expenses (0.5% of A) 519,855.72
c Physical Contingency (5% of A) 5,198,557.22
-n=;=_ -n=;=_
ABSTRACT OF COST
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
C Earthwork
Ref: Clause
Providing and laying of hand packed stone solling with
1006 of SS
150 to 200 mm thick stones and packing with smaller
#REF! DoR & m3 - 6,899.45 -
stones on prepared surface as per drawing and technical
S.N.24.15 A
specifications
of Norms DoR
SPEC
S No. Description Unit Gabion Wall Total
REF
3 Earthwork
3.2 SS DOR 905 Structure foundation excavation for all types of soil/rock
by both manual and mechanical means as per drawing and
technical specification, including removal of stumps and m3
other deleterious matter, with all lifts and lead as drawing
and instruction of engineer.
13475.811828 -
3.4 SS DOR Construction of embankments with material deposited from
909,910 Roadway Cutting: Providing, laying, spreading and
compacting embankment with roadway cutting material m3
and compact to the required density as per drawing and
Tech, specification.
-
3.5 SS DOR 908 Providing suitable material and backfilling behind abutment,
wingwall, return wall and other retaining structures m3
complete as per drawing and technical specification 4,042.74 4,042.74
5 River Bank Protection Works
5.1 SS DOR Providing and laying of dry stone masonry works as per
2602, 2603, drawing and technical specification
2608
m3
-
5.1 SS DOR Providing and laying of Random rubble stone masonry
2600,2607 works in cement mortar 1:4 in foundation and in structure
as per drawing and technical specification (assuming ratio
of foundation work and Structure works to be 25% :75%) m3
-
[SS2000] Providing and placing machine mixed M20/20 cement m3
concrete for the foundation, drain walls and footing etc.
5.1.2 including compaction,curing,testing all complete as per
specification and drawing
-
-
5.7 SS DOR Providing mechanically woven double twisted crates /
2402 mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm,
lacing wire 2.40 mm ) including rolling cutting and with
lacing wire and binding wire and filling stone/boulder in m3
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification
18,092.11 18,092.11
5.10 SS DOR Providing mechanically woven double twisted crates /
2402 mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40 mm,
lacing wire 2.20 mm ) including rolling cutting and with
lacing wire and binding wire and filling stone/boulder in m3
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification
-
5.9 SS DOR Providing and laying of PCC M: 10 (or 1:3:6 for nominal
2000 mix) in foundation complete as per Drawing and Technical m3
Specification -
#REF! SS DOR Providing and laying of Plain /Reinforced cement concrete
2000 in foundation complete as per Drawing and Technical m3
Specification : PCC Grade M 15 - -
5.1 SS DOR Providing and laying of Reinforced/prestressed cement
2000 concrete in superstructure as per Drawing and Technical
Specification : PCC Grade M 20
m3
- -
5.12 SS DOR Providing and Laying of a Geo-Textile filter/geo
2403,2404 membrane between pitching and embankment
slopes,behind earth retaining structures as per drawing and sqm
Technical specification
7945.86 7,945.86
5.19 SS DOR Providing and laying of stone pitching on slopes laid over
2416 prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and cum
technical specification
-
8 DAY WORKS
8.1 Supply of labour as required as per preamble and as
instructed by the Engineer.
Unskilled labour Nos -
skilled labour Nos -
8.2 Supply of excavator for maintenance of road or else as
required and instructed by engineer including operator and Hrs
other charges -
8.3 Provide Built up Drawing as completed Nos 3 3.00
Pay SPEC
S. No. Description Unit Rate Remarks
Item No. REF
1 General
Insurance of works, plants, materials, loss and damage to
1 1.1 GCC 13 equipments, Contractor's workmen and employees and third PS 1750000
party insurance against damage to other persons and property.
Previous
Providing and Laying sand spreading over newly primed surface
22 4.10 DOR Norms Sqm 68
(1301,1305)
(13.01,1305)
13 Miscellaneous Work
SS
36 13.2 Supply and place one kilometer stone Nos. 5,557
DOR1506
SS DOR
37 13.3 Supply and place 5th kilometer stone. Nos. 11,027
1506
14
40
41 14.1 SP G -15 Labour
b) Skilled labour day 1,030
c) Unskilled labour day 750
ITEM
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal
and disposal of top organic soil not exceeding 150 mm in thickness.
(A) In area of light jungle (less than 15 number per 100 sqm)
UNIT Sqm For 10000 Sqm
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 0.0225 M/D 750.00 16.88 16.88
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.0012 Hr 1016.00 1.22 1.22
Actual Rate 18.09
Overhead @ 15 % 2.71
Sub Total 20.81
Rate per Sqm. 20.81
(B) In area of Thorny jungle (more than 15 number per 100 sqm)
UNIT Sqm For 10000 Sqm
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 0.0325 M/D 750.00 24.38 24.38
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.0012 Hr 1016.00 1.22 1.22
Actual Rate 25.59
Overhead @ 15 % 3.84
Sub Total 29.43
Rate per Sqm. 29.43
(C) Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing of wastes
UNIT cum For 100 cum
Ref: Clause 201 of SS DoR & S.N. 2.1 (II) (i)of Norms DoR
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.00 M/D 0.00
Labour
b) Unskilled 2.2500 M/D 750.00 1687.50 1687.50
Material Disel 0 Lit 0.00 0.00
Lubricant (1 % of Fuel) 0.00 0.00
Equipment Tractor Trolley 0.12 Hr 1016.00 121.92 121.92
Actual Rate 1809.42
Overhead @ 15 % 271.41
Sub Total 2080.83
Rate per cum. 2080.83
Roadway excavation in all types of soil by mechanical means as per drawing and technical specification, including removal of stumps and other deleterious
matter, with all lifts and lead as drawing and instruction of engineer.
Road way and drain excavation for all types of soil with combination of Manual and Mechanical means
Unit Cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (20%) 0.2 Cum 691.28 138.26 138.26
Machine Excavation (80%) 0.8 Cum 63.90 51.12 51.12
Actual Cost 189.37
Total Rate 189.37
Structure foundation excavation for all types of soil with combination of Manual and Mechanical means
Unit Cu,m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (40%) 0.4 Cum 691.28 276.51 276.51
Machine Excavation (60%) 0.6 Cum 63.90 38.34 38.34
Actual Cost 314.85
Total Rate 314.85
Roadway and drain excavation in ordinary rock by manual means as per drawing and technical specification, including all lift and all lift as per
drawing and instruction of the engineer
Ref: Clause 905 of SS DoR & S.N. 9.1 II A of Norms DoR
Unit: Cu.m For 60 cum
Source Type Quantity Unit Rate Amount Remarks
Skilled 0.05 md 1,030.00 51.50
Skilled 0.83 750.00 625.00
Actul Rate 676.50
Tools, Plants & Equipment @3% 20.30
Overhead @ 15 % 101.48
Total 798.27
Unit Rate 798.27
Roadway and drain excavation in ordinary rock by mechanical means as per drawing and technical specification, including all lift and all lift as per
drawing and instruction of the engineer
Road way and drain excavation for ordinary rock with combination of Manual and Mechanical means
Earthwork in exacavation in foundation for structure for ordinary rock with a combination of Machine and Mechanical means
Roadway excavation in hard rock manually chiselling including breaking rocks, lifts and lead for disposal as per drawing and technical specification
Road way excavation in hard rock with rock breakers, including breaking rock lifts and lead for disposal as per drawing and technical specificationa;
mechanical lead upto 30 m
Ref: Clause 905 of SS DoR & S.N. 9.1 IV A of Norms DoR
Unit: Cu. M For 16 cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.0625 M/D 1030.00 64.38 64.38
Labour b) Unskilled 0.625 M/D 750.00 468.75 468.75
c)Operator 0 M/D 1030.00 0.00 0.00
Material Disel Lit 82.30 0.00 0.00
Road way and drain excavation in hard rock with combination of Manual and Mechanical means
Unit: cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (20%) 0.2 Cum 3436.01 687.20 687.20
Machine Excavation (80%) 0.8 Cum 1944.36 1555.49 1555.49
Actual Cost 2242.69
Total Rate 2242.69
Earthwork in excavation in foundation of structure with a combination of Manual and Mechanical means
Unit: cu.m
Description Particular Quantity Unit Rate Amount Total
Manual Excavation (40%) 0.4 Cum 3436.01 1374.41 1374.41
Machine Excavation (60%) 0.6 Cum 1944.36 1166.62 1166.62
Actual Cost 2541.02
Total Rate 2541.02
Construction of embankments with material deposited from Roadway Cutting: Providing, laying, spreading and compacting embankment with
roadway cutting material and compact to the required density as per drawing and Tech, specification.
Removal of unserviceable Soil with Disposal upto 1000 meters (Removal of unserviceable soil including excavation, loading and disposal upto 1000
meters lead.)
Ref: Clause 905 of SS DoR & S.N. 9.2 of Norms DoR
UNIT cu. m. For 360 cu.m
Scarifying the existing road surface to a depth of 50 mmand disposal of scarified Material with in all lifts and lead as per Drawing and Technical
Specifications.
Ref: Clause 1003 of SS DoR & S.N.10.2 of Norms DoR
UNIT Cu m For 600 Sqm
Source Type Quantity Unit Rate Amount Remarks
Skill 0.00166667 md 1,030.00 1.72
Labour
Unskill 0.01 md 750.00 7.50
Water - ltr 0.25 0.00
Material
Caping layer material - cum 150.00 0.00
Equipment Tractor with ripper 0.01 hr 1,016.00 10.16
Actul Rate 19.38
Overhead @ 15 % 2.91
Unit Rate per m2 22.28
Construction of subgrade and earthen shoulders with approved material (capping layer) obtained from borrow pits with with all lifts & leads lead as
per drawing and technical spacification
Providing and laying granular Sub base material by mechanical means on prepared surface, mixing at OMC, and compacting to achieve the desired
density, complete as per Drawing and Technical Specifications
Ref: Clause 1201 of SS DoR & S.N.12.1 A of Norms DoR
Unit: cum For 300 cum
m3 Ref: 26-A-a
Source Type Quantity Unit Rate Amount Total
Labour Skilled 0.007 m-day 1,030.00 6.87 6.87
Unskilled 0.04 m-day 750.00 30.00 30.00
Materials Sub base material S1 or S2 type 1.28 cu.m. 2,754.5 3525.82 3,525.82
Water 60.00 ltr. 0.25 15.00 15.00
Motor Grader 0.020 hr. 3,998.0 79.96 79.96
Equipment Vibratory Roller 0.040 hr. 2,939.00 117.56 117.56
Tractor/Loader 0.040 hr. 1,016.0 40.64 40.64
Actual Rate 3815.85
Overhead @ 15 % 572.38
Sub Total 4388.23
Rate per m3 4388.23
Providing laying , spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at
0OMC laying in uniform layers in sub-base on well preparedRef:
surface and0 compacting to
Clause 0 achieve requiered density as oer drawing
0.00 0 and technical
UNIT m3 For 225.00 cu/m 0.00 0
Source Type Quantity Unit Rate Amount Total
Skilled 0.013 m-day 1,030.00 13.73 13.73
Labour
Unskilled 0.04 m-day 750.00 33.33 33.33
Crushed stone 1.03 cu.m. 3,001.75 3091.80 3,091.80
Material
Water 80.00 ltr. 0.25 20.00 20.00
mixer 0.04 0 325 13.00 13.00
Equipment
Grader 0.027 hr. 2,798.00 74.61 74.61
Vibratory Roller 0.040 hr. 2,939.00 117.56 117.56
Actual RateAc 3364.04
Overhead @ 15% 504.61
Rate per m3 3868.65
Providing and laying crusher run macadam on a prepared surface, spreading and mixing, watering and compacting to form a layer of sub base/base
course as per drawing and technical specifications. (by mix in place method)
Ref: Clause 1204 of SS DoR & S.N.12.7 A of Norms DoR
UNIT m3 For 360.00 cu/m
Source Type Quantity Unit Rate Amount Total
Skilled 0.008 m-day 1,030.00 8.58 8.58
Labour
Unskilled 0.04 m-day 750.00 29.17 29.17
Crushed stone 1.32 cu.m. 3,001.8 3962.31 3,962.31
Material
Water 100.00 ltr. 0.25 25.00 25.00
Grader 0.017 hr. 2,798.0 46.63 46.63
Equipment
Vibratory Roller 0.017 hr. 2,939.0 48.98 48.98
Actual RateAc 4120.68
Overhead @ 15% 618.10
Rate per m3 4738.78
Providing and pointing with cement mortar on masonry work in structuire as per technical specification (cement mortar- 1:3)
S.N. Ref: Clause 2600 of SS DoR & S.N.26.7 A of Norms DoR
unit sqm For 100 sqm
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled labour 0.09 m-day 1030.00 92.70 92.70
Unskilled labour 0.09 m-day 750.00 67.50 67.50
Cement 3.10 kg 16.50 51.15 51.15
Material Collection of sand 0.01 cu.m. 3175.20 20.00 20.00
Water 0.50 ltr 0.25 0.13 0.13
Actual Rate 231.35
Overhead @ 15 % 34.70
Total 266.06
Rate per m2 266.06
Providing and laying of dry stone masonry works as per drawing and technical specification
Ref: Clause 2602, 2603, 2608 of SS DoR & S.N.26.1 of Norms DoR
UNIT m3 For 5 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.8 m-day 1030.00 824.00 824
Unskilled 1.60 m-day 750.00 1200.00 1200
material Collection of Stone 1.15 cu.m. 2469.60 2840.04 2840.04
Actual Rate 4864.04
Overhead @ 15 % 729.61
Sub Total 5593.65
Rate per m³ 5593.65
Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in foundation as per drawing and technical specification
Ref: Clause 2602, 2603, 2607 of SS DoR & S.N.26.3 B of Norms DoR
UNIT m4 For 5 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 1.400 m-day 1030.00 1442.00 1442.00
Unskilled 2.800 m-day 750.00 2100.00 2100.00
Rubble 1.15 cu.m. 2469.60 2840.04 2840.04
Material Cement 158.0 kg. 16.50 2607.00 2607.00
Sand 0.326 cu.m. 3175.20 1035.12 1035.12
Actual Rate 10024.16
Overhead @ 15 % 1503.62
Sub Total 11527.78
Rate per m3 11527.78
Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in Structure as per drawing and technical specification
Providing and laying of Random rubble stone masonry works in cement mortar 1:4 in foundation and in structure as per drawing and technical
specification (assuming ratio of foundation work and Structure works to be 25% :75%)
Ref: Clause 2600,2607 of SS DoR & S.N.26.5 A of Norms DoR
Stone pitching
Providing and laying of stone pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as
per drawing and technical specification
Providing mechanically woven double twisted crates / mattress including rolling cutting and with lacing wire and binding wire as per specification.
Rate per m2
270
Rate per m2
250
Assembling mechanical woven Gabion boxes/mattresses, placing in position including stretching; forming compartrments;
tying the sides and diaphragm with binding wire in each mesh; tying with bracing wires and tie wirews; and tying down the
lid complete as per specification (stone filling not included)
Providing and filling stone boulders in Gabion boxes/mattresses etc. including dressing ,, bedding, bonding all complete as
per drawing and technical specification
Overhead @ 15 % 528.38
Ref: Clause 1804, 1805 of SS DoR & S.N. 18.2 a. i. of Norms DoR
UNIT m2 For 10 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.22 m-day 1030.00 226.60 226.60
Unskilled 0.22 m-day 750.00 165.00 165.00
Materials Ply woods 9 mm thick 1.10 m³ 82.50 90.75 90.75
Struts ballies 0.04 cum 4166.67 166.67 166.67
Nails, Spikes etc. 0.25 k.g 112.00 28.00 28.00
Actual Rate per 10m² 677.02
Overhead @ 15 % 101.55
Sub Total 778.57
Actual rate per m² 778.57
Providing and laying of PCC M: 10 (or 1:3:6 for nominal mix) in foundation complete as per Drawing and Technical
Concrete Specification
Providing and laying of Reinforced/prestressed cement concrete in superstructure as per Drawing and Technical
Specification : PCC Grade M 20
Providing and laying Reinforced Cement Concrete NP3 (900 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. D. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.08 m-day 1030.00 82.40 82.40
Unskilled 0.64 m-day 750.00 480.00 480.00
Sand 0.01 cum 3175.20 30.48 30.48
Materials Cement 90.00 kg 16.50 1485.00 1485.00
RCC pipe 900 mm Dia. (NP3) 1.00 rm 12172.00 12172.00 12172.00
Actual Rate 14249.88
Tools ,Plants & Equipments @ 3% 16.87
Sub Total 14266.75
Overhead @ 15 % 2140.01
Rate per r. m. 16406.77
Providing and laying Reinforced Cement Concrete NP3 (1000 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. E. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.12 m-day 1030.00 123.60 123.60
Unskilled 0.80 m-day 750.00 600.00 600.00
Sand 0.01 cum 3175.20 35.56 35.56
Materials Cement 100.00 kg 16.50 1650.00 1650.00
RCC pipe 1000 mm Dia. (NP3) 1.00 rm 13525.00 13525.00 13525.00
Actual Rate 15934.16
Tools ,Plants & Equipments @ 3% 21.71
Sub Total 15955.87
Overhead @ 15 % 2393.38
Rate per r. m. 18349.25
Providing and laying Reinforced Cement Concrete NP3 (1200 mm Dia) Flush jointed pipe for culverts including fixing with
HP cement mortar 1:2 as per Drawing and Technical Specification
Ref: Clause 701 of SS DoR & S.N. 7.2. E. of Norms DoR
UNIT m For 12.5 sq.m
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.16 m-day 1030.00 164.80 164.80
Unskilled 0.96 m-day 750.00 720.00 720.00
Sand 0.01 cum 3175.20 45.72 45.72
Materials Cement 140.00 kg 16.50 2310.00 2310.00
RCC pipe 1200 mm Dia. (NP3) 1.00 rm 16100.00 16100.00 16100.00
Actual Rate 19340.52
Tools ,Plants & Equipments @ 3% 26.54
Sub Total 19367.07
Overhead @ 15 % 2905.06
Rate per r. m. 22272.13
Providing and Laying of a Geo-Textile filter/geo membrane between pitching and embankment slopes,behind earth
GEO TEXTILE retaining structures as per drawing and Technical specification
Ref: Clause 2404,2403 of SS DoR & S.N. 24.5,24.6. of Norms DoR
UNIT m² For 300 sq.m Unit-Cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.0033 M/D 1030.00 3.43 3.43
Labour
b) Unskilled 0.00667 M/D 750.00 5.00 8.43
Material Geo-textile fabrics 1.2 Sqm. 110.00 132.00 132.00
Actual cost 143.87
Overhead @ 15 % 21.58
Rate per m² 165.45
Providing and painting two coats after filling the surface with synthetic enamel paint in all shades on concrete/plaster surfaces as
per drawing and technical specification
Ref: Clause 1501 of SS DoR & S.N. 15.4. of Norms DoR
UNIT m² For 10 sq.m
SOURCE TYPE QUANTITYUNIT RATE AMOUNT TOTAL
LABOUR Skilled labour 0.30 m-day 1030.00 309.00 309.00
Bio-Engineering Works
Planting rooted grass slips on the slopes 45-60 deg including preparation of slips on site. A max of 5cm depth with metal
rod or Operation includes digging, planting hole to hard-wood peg, depending on the nature of the soil. The planting
drills should be space
Ref: Clause 2807 of SS DoR & S.N. 28.08.F of Norms DoR
UNIT sqm For 1 sqm
Labour
Unskilled md 0.3 750.00 225.00
Material
Grass slips/no of drills cuttings nos 100 0.3 30.00
Hessian jutes sq m 0.27 30 8.10
263.10
Equipment
3% tools and plants 6.75
Sub-total 269.85
15% OH 40.48
Prime coat
Providing and applying prime coat with hot bitumen(including Cutter) on prepared surface of grannular base including
cleaning of road surface and spraying by mechanical means as per technical specification
Ref: Clause 1302 of SS DoR & S.N. 13.1.A of Norms DoR
UNIT lit For 5000 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.010 750.00 7.50
Skilled m-day 0.001 1030.00 0.62
Materials Bitumen (30/70) kg 1.05 78.10 82.01 1litre=1sqm
Cost of Water L 2.00 0.25 0.50
Equipment Mechanical Broom hr. 0.0016 1165.00 1.86
Air Compressor hr. 0.0016 661.00 1.06
Bitumen Distributer hr. 0.0012 1876.00 2.25
Boiler hr. 0.0016 3235.00 5.18
Generator hr. 0.0016 305.00 0.49
Total 101.46
15% OH 15.22
Rate per Litre 116.68
Providing and applying tack coat with hot bitumen at specified rate on the prepared non-bituminous surfaces including
cleaning as per technical specification
Ref: Clause 1302 of SS DoR & S.N. 13.2.A of Norms DoR
UNIT lit For 5000 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.004 750.00 3.00
Skilled m-day 0.001 1030.00 0.62
Materials Bitumen (30/70) kg 1.05 78.10 82.01
Equipment Air Compressor hr. 0.0012 661.00 0.79
Bitumen Distributer hr. 0.0012 1876.00 2.25
Boiler hr. 0.0012 3235.00 3.88
Generator hr. 0.0012 305.00 0.37
Total 92.92
15% OH 13.93731
Total 106.85
Rate Per Litre 106.85
Bitumen Cutter
Providing and mixing of Bitumen cutter as per design/direction of Engineer
Ref: Clause 1300 of SS DoR & S.N. 13.17 of Norms DoR
UNIT lit For 200 lit
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.005 750.00 3.75
Skilled m-day 0.00005 1030.00 0.05
Materials Kerosene/ Diesel cutter Lit 1.05 82.30 86.42
Equipment Add 3% of Labour component for T&P 0.11
Total 90.33
15% OH 13.54958175
Total 103.88
Rate Per Litre 103.88
Anti-Stripping agent
Providing and mixing of Anti-Stripping agent as per design/direction of Engineer
Ref: Clause 1300 of SS DoR & S.N. 13.16 of Norms DoR
UNIT Kg For 200 kg
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.005 750.00 3.75
Skilled m-day 0.00005 1030.00 0.05
Materials Additive material kg 1.05 320.00 336.00
Equipment Add 3% of Labour component for T&P 0.11
Total 339.92
15% OH 50.98733175
Total 390.90
Rate Per Kg 390.90
Surface Dressing
Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied
layer of bituminour binder on prepared surface as per Drawing and Technical Specifications.
Unit : 10m2
20mm thick Open-Graded Premix Carpet using Bituminous (Paving Bitumen / Modified Bitumen) Binder.
Providing and laying open-graded premix carpet of 20 mm thickness composed of 13.2 mm to5.6 mm aggregates as
wearing course on a previously prepared base as per drawing and Technical Specifications.
Ref: Clause 1311 of SS DoR & S.N. 13.9 B(i) of Norms DoR
UNIT Sqm For 500 sqm 10 cum
SOURCE TYPE Unit Quantity Rate Amount Remarks
Labour Unskilled m-day 0.042 750.00 31.50
Skilled m-day 0.01600 1030.00 16.48
Paving bitumen or other as per Design Kg 1.46 0.00 0.00
Materials
Crushed stone chipping, 13.2 mm to 5.6mm For 0.03
Mixer hr 0.0080 0.00 0.00
Equipment Bitumen boiler oil fired hr 0.0080
Roller (Smooth wheeled) hr 0.0040 0.00 0.00
Total 47.98
15% OH 7.197
Total 55.18
Rate Per Sqm 55.18
Providing suitable material and backfilling behind abutment, wingwall, return wall and other retaining structures complete as per drawing and
technical specification
Providing and filling stone/boulder in gabion boxes/mattress etc. including dressing, bedding, bonding all complete as per drawing and technical
specification
Ref: Clause 2402 of SS DoR & S.N.24.4of Norms DoR
UNIT m3 For 10.00 cu/m
Source Type Quantity Unit Rate Amount Total
A Labor
Skilled 0.20 m-day 1030.00 206.00
Unskilled 0.80 m-day 750.00 600.00
B Material
Boulder/Stone 1.10 cum 2469.60 2716.56
Actual RateAc 3522.56
Overhead @ 15% 528.38
Rate per m3 4050.94
Providing mechanically woven double twisted crates / mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 3 mm, selvedge wire 3.90
mm, lacing wire 2.40 mm ) including rolling cutting and with lacing wire and binding wire and filling stone/boulder in gabion boxes/mattress etc. including
dressing, bedding, bonding all complete as per drawing and technical specification
Ref: Clause 2402, of SS DoR & S.N.24.2(A,B),24.4of Norms DoR
Source Type Unit Rate Amount Total
Providing mechanically woven double twisted crates /
mattress including rolling cutting and with lacing wire and 1m3=4.82s
A binding wire sqm 1301.4 qm
Filling Stone/Boulder in Gabion boxes/mattress etc. including
B dressing, bedding, bonding all m3 3522.56
Actual RateAc 4823.96
Overhead @ 15% 723.59
Rate per m3 5547.55
Providing mechanically woven double twisted crates / mattress(Heavy Zinc coated Hexagonal mesh type 100X120 mm, mesh wire 2.7 mm, selvedge wire 3.40
mm, lacing wire 2.20 mm ) including rolling cutting and with lacing wire and binding wire and filling stone/boulder in gabion boxes/mattress etc.
including dressing, bedding, bonding all complete as per drawing and technical specification
Ref: Clause 2402, of SS DoR & S.N.24.2(A,B),24.4of Norms DoR
Source Type Unit Rate Amount Total
Providing mechanically woven double twisted crates /
mattress including rolling cutting and with lacing wire and 1m3=4.82s
A binding wire m3 1205 qm
Filling Stone/Boulder in Gabion boxes/mattress etc. including
B dressing, bedding, bonding all m3 3522.56
Actual RateAc 4727.56
Overhead @ 15% 709.13
Rate per m3 5436.69
Description of works:
Provide and erecting "W" metal beam crashbarrier comprising of 3.43mm thick corrugated sheet metal
beam rail, 70cm above road/ground level,fixed on ISMC serises channel vertical post, 150*75*5 mm spaced
2m c/c,1.8m high,1.1m below ground/road level,all steel paetsand fitment to be galvanized by hot dip
IRC 7.08
process,all fittings to confirm to IS 1367 and IS 1364,metal beam rail to be fixed on the vertical post with a
spacer of chaneel section 150*75*5mm 330mm long, all complete
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
Corrugated sheet, 3.43 mm thick,
Skilled md 0.393 1030.00 404.79 "W" beam section railing, 4.5 m in
length kg
Stone pitching
Providing and laying of hand packed stone solling with 150 to 200 mm thick stones and packing with smaller stones on prepared surface as per drawing and
technical specifications
Ref: Clause 1006 of SS DoR & S.N.24.15 A of Norms DoR
UNIT m3 For 1 cu m
Source Type Quantity Unit Rate Amount Total (Rs.)
Skilled 1.20 m-day 1030.00 1236.00 1236.00
Labor
Unskilled 2.40 m-day 750.00 1800.00 1800.00
material Stone weighing >40kg 1.20 cu.m. 2469.60 2963.52 2963.52
Actual Rate 5999.52
Overhead @ 15 % 899.93
Sub Total 6899.45
Rate per m³ 6899.45
29 of 45
Fuel Usage Factors in
Highway and Bridge
E12 Motor Grader Hour 1,200.00 82.30 34.00 2,798.00 3,998.00 80 to 145 HP
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E13 Crane (5-10 Ton) Hour 3,100.00 82.30 11.00 905.00 4,005.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E14 Pneumatic Roller Hour 1,200.00 82.30 15.00 1,234.00 2,434.00 upto 20 ton
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E15 Roller 3 wheel ( Up to 12 ton ) Hour 500.00 82.30 39.00 3,209.00 3,709.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E16 Roller vib, Self propelled Hour 800.00 82.30 26.00 2,139.00 2,939.00 above 3 ton
Construction (2013) by
NCHRP
Vibrobliešu WEBER degv.
E17 Roller vib, Self propelled Hour 550.00 82.30 4.30 353.00 903.00 upto 3 Ton
patēriņš vec
Quantity of Diesel Based on
E18 Tipper (6mt) Hour 450.00 82.30 8.71 716.00 1,166.00
calculation
Quantity of Diesel Based on
E19 Truck(6mt) Hour 450.00 82.30 8.71 716.00 1,166.00
calculation
Quantity of Diesel Based on
E20 Mini Truck Hour 300.00 82.30 7.09 583.00 883.00
calculation
DoR Previous Norms Appendix
E21 Mini Dumper Hour 250.00 82.30 1.90 156.00 406.00
2
Fuel Usage Factors in
Highway and Bridge
E22 Tractor Hour 440.00 82.30 7.00 576.00 1,016.00
Construction (2013) by
NCHRP
DoR Previous Norms Appendix
E23 Concrete Mixer Hour 450.00 82.30 1.50 123.00 573.00
2
Fuel Usage Factors in
Highway and Bridge
E24 Concrete Cutter Hour 250.00 97.35 3.00 292.00 542.00
Construction (2013) by
NCHRP
DoR Previous Norms Activities
E25 Concrete Needle Vibrator Hour 100.00 97.35 0.10 9.00 109.00
Group no. 20
Fuel Usage Factors in
Highway and Bridge
E26 Compactor Hand Towed Hour 130.00 97.35 0.75 73.00 203.00 350 to 450 KG
Construction (2013) by
NCHRP
30 of 45
Fuel Usage Factors in
Highway and Bridge
E27 Air Compressor Hour 250.00 82.30 5.00 411.00 661.00 150 to 275 CFM
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E28 Drilling Machine Hour 130.00 82.30 17.00 1,399.00 1,529.00
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E29 Water Browser Hour 550.00 82.30 18.00 1,481.00 2,031.00 upto 6 kL
Construction (2013) by
NCHRP
DoR Previous Norms Appendix
E30 Water Pump Hour 200.00 82.30 0.35 28.00 228.00 upto 6" dia
2
Fuel Usage Factors in
Highway and Bridge
E31 Generator (2 KVA) Hour 150.00 82.30 1.89 155.00 305.00
Construction (2013) by
NCHRP
https://texags.com/forums/57/t
E32 Boring Equipment with Pump Hour 1,400.00 82.30 568.00 46,746.00 48,146.00
opics/2525768
DoR Previous Norms Appendix
E33 Excavator,Track Hour 1,800.00 82.30 12.00 987.00 2,787.00 upto 110 HP
2
DoR Previous Norms Appendix
E34 Excavator with Breaker Hour 2,100.00 82.30 12.00 987.00 3,087.00
3
Fuel Usage Factors in
Highway and Bridge
E35 Sprayer Hour 260.00 82.30 5.00 411.00 671.00 upto 1KL
Construction (2013) by
NCHRP
Fuel Usage Factors in
Highway and Bridge
E36 Mechanical Broom Hour 260.00 82.30 11.00 905.00 1,165.00
Construction (2013) by
NCHRP
31 of 45
Contract ID: Unskilled 750.00
Skilled 1,030.00
Analysis of Rates of Collection of Materials
Activity 15%
Resource Analyzed Quantity
S.No. Norms Description of Works/ Resource Type Unit Unit Rate Amount Overhead
No. Quantity per Unit
No. Charge
1 Stone cu.m.
1.1 8.7 B Making rubbles of required size including and stacking. cu.m. 1.00
A1 Skilled Labour pd 0.10 0.10 1,030.00 103.00 15.45
A3 Unskilled Labour pd 4.00 4.00 750.00 3,000.00 450.00
3% of Labor Cost Tools and Plants 93.09 13.96
Sum 3,196.09
9.1.IV.A Excavation in hardrock with rock breakers. cu.m. 16.00
A1 Skilled Labour pd 1.00 0.06 1,030.00 64.38 9.65
A3 Unskilled Labour pd 10.00 0.63 750.00 468.75 70.31
E34 Excavator with Breaker Hour 6.00 0.38 3,087.00 1,157.63 173.64
According to Norms 50% only is reusable. (845.37)
Sum 845.38
Col.M.1 Stone 962.92
8 Sand
8.3.D Collection, quarrying and sieving sand in local river cu.m. 1.00
A3 Unskilled Labour pd 1.50 1.50 750.00 1,125.00 168.75
3% of Labor Cost Tools and Plants 33.75 5.06
8.4.A Washing Sand cu.m. 1.00
A3 Unskilled Labour pd 0.50 0.50 750.00 375.00 56.25
3% of Labor Cost Tools and Plants 11.25 1.68
Sum 1,545.00
9 Water
Collection of Water from Local River into the Water
8.04.02.17 Litre 1,000.00
Bowser
A1 Skilled Labour pd 0.01 0.000010 1,030.00 0.01 -
A3 Unskilled Labour pd 0.10 0.000100 750.00 0.08 0.01
E29 Water Browser Hour 0.05 0.000050 2,031.00 0.10 0.01
E30 Water Pump Hour 0.05 0.000050 228.00 0.01 -
3% of Labor Cost Tools and Plants - -
Sum 0.20
Net
Remarks
Amount
118.45
3,450.00
107.05
3,675.50
74.03
539.06
1,331.27
(972.17)
972.18
1,107.35
3.94
25.87
1,476.47
72.79
81.53
40.22
68.55
1,769.38
3.53
23.17
1,322.22
109.19
122.30
109.52
61.38
1,751.31
3.16
19.55
1,181.17
29.11
32.61
97.84
54.84
1,418.28
3.94
25.87
1,476.47
81.53
122.30
68.55
1,778.67
3.53
23.17
1,322.22
109.52
109.52
61.38
1,629.34
3.16
19.55
1,181.17
32.61
97.84
54.84
1,389.17
1,536.05 According
1,660.46 to
Standard
1,447.60 Specificati
1,446.14 on
1,293.75
38.81
431.25
12.93
1,776.74
Previous
Norms
0.01
0.09
0.11
0.01
-
0.22
Basic Rate
A. Labour
1 Skilled Md 1030.00 1030.00 District Rate
2 Unskilled Md 750.00 750.00 District Rate
B. Material
1 Cement Bag 825.00 25.01 825.00 District Rate
2 Sand Cum 3175.20 1,776.74 412.72 105.94 3175.20 Tp+R+C
3 Natural Gravel Cum 2,751.84 1,250.00 606.50 158.90 2751.84 Tp+R+C
4 20mm- 40mm Aggregate Cum 3316.32 1,418.28 606.50 3316.32 District Rate
10mm- 20mm Aggregate Cum 3351.60 1,751.31 606.50 3351.60 District Rate
6mm-10mm Aggregate Cum 2892.96 1,769.38 606.50 2892.96 District Rate
<6mm Aggregate Cum 2892.96 606.50 2892.96 District Rate
5 Aggregate 16 mm Cum 3926.50 606.50 4533.00 District Rate
6 Soil Cum 318.60 318.60 District Rate
6 Stone Cum 2469.60 1,107.35 675.49 250.00 2469.60 Tp+R+C
7 Stone Dust Cum 1447.89 158.90 1447.89 District Rate
8 Gabion Wire
12 SWG kg 105.00 0.65 105.00 District Rate
10 SWG kg 105.00 0.65 105.00 District Rate
8 SWG kg 105.00 0.65 105.00 District Rate
9 Binding Wire Kg 92.00 0.65 92.00 District Rate
10 Reinforcement kg 84.00 0.65 84.00 District Rate
11 Bitumen kg 78.10 5.27 78.10 District Rate
12 Petrol Lt 97.35 97.35
13 Diesel Lt 82.30 82.30 NOC Rate Excluding VAT
14 Kerosene Lt 82.30 82.30
15 Nail kg 112.00 0.65 112.00 District Rate
16 Fire wood kg 18.00 18.00 District Rate
at site (Transportation Cost
25% of unit cost) from
17 NP3 pipe @300 mm dai with collar Rm 3140.00 785.00 3140.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @450 mm dai with collar Rm 4500.00 1,125.00 4500.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @600 mm dai with collar Rm 6200.00 1,550.00 6200.00 Kathmandu
at site (Transportation Cost
25% of unit cost) from
NP3 pipe @900 mm dai with collar Rm 12172.00 3,043.00 12172.00 Kathmandu
NP3 pipe @1000 mm dai with collar Rm 13525.00 3,381.25 13525.00
NP3 pipe @1200 mm dai with collar Rm 16100.00 4,025.00 16100.00
18 Natural Gravel Cum 2,751.84 1250.00 606.50 2751.84 Tp+R+C
19 Inferior Wood Cum 22072.00 22072.00 District Rate
20 Primer lit 365.00 0.65 365.00 District Rate
21 Enamel paint lit 509.00 0.65 509.00 District Rate
22 Anti stripping agent kg 320.00 320.00 District Rate
23 Geo-textile sqm 110.00 110.00 District Rate
24 Jute Kg 100.00 100.00 District Rate
25 Base cum 3001.75 1,660.46 3001.75 District Rate
26 Sub Base cum 2754.55 1,536.05 2754.55 District Rate
27 Graded Filter Materials cum 1446.14 1,446.14 1446.14
4290.60
SB 2754.55
B 3001.75
Rate Analysis(Transportation)
Travel Time (T) for truck to be used for this activity shall be determined as follows:
T = 2 * { d1/v1 + d2/v2 + d3/v3 + …………. Dn/vn}, where d1, d2, d3 … dn and v1, v2, v3……vn are the streches of distances to be
travelled and corresponding average speeds on these streches.