Foundation Plan

Volume of Footing
Phase 1
No. of Footing Designation Volume of Concrete cu.m
4 RF2C2 30
10 F2C2 80
1 CF1C2 106.523
Phase 2
No. of Footing Designation Volume of Concrete cu.m
3 RF2C2 22.5
2 F2C2 16
3 F2C1 24
2 F1C1 16
2 CF2C2 148.4505
Phase 3
No. of Footing Designation Volume of Concrete cu.m
1 F2C1 7.5
1 F2C2 8
2 C3F3 3.6
1 F7C1 13.86

TOTAL VOLUME: 476.4335 cu.m

Volume of Tie Beam


Phase 1
No. of Tie Beam Length Volume of Concrete cu.m
4 5.6733 3.97131
4 5.1784 3.62488
4 5.2 3.64
4 4.8891 3.42237
4 5.3309 3.73163
4 5.502 3.8514
1 1.7 0.2975
1 2.7 0.4725
1 3.3 0.5775
1 5.3 0.9275
1 5.3 0.9275
1 4.4 0.77
2 3.9 1.365
1 4.1 0.7175
1 4.8 0.84
Phase 2
No. of Tie Beam Length Volume of Concrete cu.m
1 17.3 3.0275
1 19 3.325
1 21.3 3.7275
1 22.6 3.955
1 10.35 1.81125
1 9.4 1.645
1 4.3 0.7525
1 2.3 0.4025
1 24.7 4.3225
2 3.4 1.19
1 13.7 2.3975
1 14.6 2.555
Phase 3
No. of Tie Beam Length Volume of Concrete cu.m
1 12.6 2.205
1 11.6 2.03
1 9.7 1.6975
1 4.2 0.735

TOTAL VOLUME: 64.91534 cu.m