Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

FMC/APIR

BILL OF ENGINEERING MEASUREMENT AND EVALUATION (BEME) FOR A PROPOSED LIGHTING,


CONSTRUCTION OF 2.50 km INTERNAL ROADS, LANDSCAPING AND COMPLETION OF 112 METER
COVERED WALKWAY AT FEDERAL MEDICAL CENTRE APIR, MAKURDI, BENUE STATE

ITEM DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT (N)

1 PRELIMINARIES

Allow provisional sum for Survey, Design


A 1.00 Sum Prov 5,000,000.00
and Supervision cost of the project

Allow provisional sum for


B Administrative/Management cost of the 1.00 Sum Prov 3,000,000.00
project
Preliminaries to Summary 8,000,000.00

ITEM DESCRIPTION OF ITEM QTY UNIT RATE (N) AMOUNT (N)

2 SOLAR STREET LIGHTS

Excavate pit 600mm x 600mm x 1500mm to


2.1 receive insitu reinforced concrete for pole 48.60 m3
basement. Rate is inclusive of backfilling

Provide and and place insitu concrete grade 10


in bases 500mm x 500mm x 1200mm. Rate is
2.2 33.75 m3
inclusive of hold down bolts to engineer's
specification

Provide and install galvanized steel pole 7m


2.3 7000.00 kg
114.33x5mmx13.5kg/m CHS

Supply and fix 100wtts solar discharge lamp


2.4 80.00 Nos
complete 3-in-1 stand-alone Europe standard

Solar Street Lights to Summary

Bill of Quantities FEDERAL MEDICAL CENTRE, MAKURDI


FMC/APIR

ITEM DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT (N)

3 INTERNAL ROADS (2.50 km)


A Site Clearance and Earthworks
Clear site on either side of centreline of road up
to limit of constrction width of all bushes,
i m2
grasses, anthills etc and carte to spoil. Rate is
inclusive of topsoil removal
Excavate from approved borrow pits, haul
excavated material any distance, deposit,
ii m3
spread and compact in 150mm layers to 100%
BS as filling
B Culvert and Drainages
Culverts:
Provide and lay new concrete pipe culverts
Diameter 600 mm as shown on the
i m
drawings including blinding, shuttering and
concrete surrounds.

Provide and place access slabs over


ii drainages at strategic places as may be m2
required
Drains:
Desilt existing drainages, cart silted material
iii 800.00 m
and carte to spoil

Provide and lay 225mm concrete filled


sandcrete block uncovered drains as
iv 200.00 m
specified and directed size 0.6 x 0.80. Rate
is inclusive of capping and rendering

Rehabilitate existng drainages, rate is


v inclusive of filling of weak concrete, capping 350.00 m
and rendering
C Pavement and Surfacing

Provide, shape and compact to 100% West


African Standard compaction approved
i m3
naturally occuring lateriate material as sub
base in a layer of 150 mm

Provide, shape and compact to 100% West


African Standard compaction approved
ii m3
naturally occuring lateriate material as sub
base in a layer of 150 mm
Provide and spray prime coat using MC1 at
iii 1.0 litre/m2 spray rate including blinding m2
with sharp sand.
Provide, lay and compact 50mm Ashplatic
iv concrete at required temperature as m2
reqiured. Rate is inclusive of tack coat

Internal Roads (2.5Km) to Summary

Bill of Quantities FEDERAL MEDICAL CENTRE, MAKURDI


FMC/APIR

ITEM DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT (N)


4 LANDSCAPING
Allow provisional sum for purchase of
4.1 3.00 nos
STIHL Fs 250 Professional Brushcutter

Clear, remove topsoil and level landscape


4.1 area. Rate is inclusive of carte to spoil of all m2
bushes, grass, shrubs and anthills

Excavate from approved borrow pits, haul


excavated material any distance, deposit,
4.2 m3
spread and compact in 150mm layers to
100% BS

Provide and install interlocking stone in the


areas required. Rate is inclusive of
4.3 m2
sharpsand of 75mm and Damp proof
membrane to receive the inter locks

4.4 Provide and install kerbstones as required m


Landscaping to Summary

5 ROOF WORK AND FLOOR FINISH


Steel Trusses

All Steel trusses used in this section should


be properly treated with a preservation
agent against rust infection in the following

5.1 114.3x5mmx13.5kg/m CHS 6503.40 kg


5.2 48.3x4mmx4.37kg/m 1633.30 kg
5.3 200x200x100mm Base plate 92.00 No.
5.4 Stiffners 380.00 No.

5.5 Hold down Bolts and Nuts M12 368.00 No.

5.6 40x40x4mmx4.39kg/m 1158.30 kg


5.7 Painting (Red Oxide and Gloss) 400.00 m2
Roof Covering
0.55mm thick guage Long span Aluminium
roofing sheet (OVEN BACK) laid and fixed to
5.8 600.00 m2
hardwood purlins in accordance with
manufacturer's specifications

5.90 Valley capping not exceeding 450mm girth 60.00 m

5.10 Eaves Trimmer 280.00 m


Floor Finishes
Provide 25mm polished in - situ terrazzo paving
5.11 laid on and including 25mm cement and sand 300.00 m2
(1:3) screeded bed

ROOF WORKS and FLOOR FINISH: TO


SUMMARY

Bill of Quantities FEDERAL MEDICAL CENTRE, MAKURDI


FMC/APIR/MAKURDI

BILL OF ENGINEERING MEASUREMENT AND EVALUATION (BEME) FOR A


PROPOSED LIGHTING, CONSTRUCTION OF 2.50 km INTERNAL ROADS,
LANDSCAPING AND COMPLETION OF 112 METER COVERED WALKWAY AT
FEDERAL MEDICAL CENTRE APIR, MAKURDI, BENUE STATE

SUMMARY

ITEM DESCRIPTION OF ITEM QTY UNIT RATE (N) AMOUNT (N)


PRELIMINARIES: Design,
1 Supervision, and Project 8,000,000.00
Management

2 SOLAR STREET LIGHT

3 INTERNAL ROADS (2.5km)

4 LANDSCAPING

ROOF WORK AND FLOOR


5
FINISH

SUB - TOTAL

ADD: VAT 7.5%

GRAND TOTAL

BILL OF QUANTITIES FEDERAL MEDICAL CENTRE , MAKURDI