Installation of Hvac System and Standby Generator Set For DFPC Naia T3 - Landside Store
Installation of Hvac System and Standby Generator Set For DFPC Naia T3 - Landside Store
As a result of the Pre-Bid Conference held on 15 April 2016, the Bids and Awards
Committee of Duty Free Philippines Corporation would like to notify all prospective bidders
of the following revisions, forms/documents to be included in the submission of their bid for
the project Installation of HVAC System and Standby Generator Set for DFPC NAIA T3
– Landside Store.
1. Invitation to Bid, paragraph 5
From:
Interested bidders may obtain further information from DFPC and inspect the Bidding
Documents at the address given below from 9:00AM – 5:00PM, Mondays thru Fridays
until 26 April 2016.
To:
Interested bidders may obtain further information from DFPC and inspect the Bidding
Documents at the address given below from 9:00AM – 5:00PM, Mondays thru Fridays
until 28 April 2016.
2. Bid Data Sheet (BDS) under Instruction to Bidders (ITB) Clause 12.1(a)(i)
From:
Valid and current Philippine Contractors Accreditation Board (PCAB) license and
registration for size range Medium B/Category A contractor (Classification: SP-ME
Mechanical Works and/or SP-AC Air-conditioning or Refrigeration).
To:
Valid and current Philippine Contractors Accreditation Board (PCAB) license and
registration for size range Medium A/Category B contractor (Classification: SP-ME
Mechanical Works and/or SP-AC Air-conditioning or Refrigeration).
3. BDS under ITB Clause 17.1
FROM:
Bids will be valid until 25 August 2016.
TO:
Bids will be valid until 27 August 2016.
4. BDS under ITB Clause 18.2
FROM:
The bid security shall be valid 25 August 2016.
TO:
The bid security shall be valid 27 August 2016.
5. BDS under ITB Clause 21
FROM:
The Address for Submission of Bids is:
DUTY FREE PHILIPPINES CORPORATION
EHA Building, Fiestamall,
Columbia Complex, Ninoy Aquino Ave., Parañaque City
All the other provisions, requirements, forms/documents in the bidding documents, except
the foregoing revisions/modifications, shall remain in full force and effect.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 3 of 25
Bid Bulletin Addendum No. HSGS-001
Annex A
VI. Specifications
SECTION I - GENERALS
1.1 DESCRIPTION:
This division of the Specifications covers the supply, installation, testing and
commissioning of the PROJECT as specified herein. Provide all materials, labour,
equipment and supervision.
1.2.1 All works shall be in accordance with the following codes and agencies:
- Uniform Mechanical Code (Latest Edition)
- The Uniform Plumbing Code (Latest Edition)
- Philippine Society of Mechanical Engineer’s Code (PSME)
- Fire Code of the Philippines (Latest Edition)
- National Fire Protection Code (NFPC) (Latest Edition)
- National Plumbing Code of the Philippines (NPCP) (Latest Edition)
- The Philippine Electrical Code (PEC), latest edition
- Publications and Standards of the organizations listed below are
applicable to materials specified herein.
- American Society of Mechanical Engineers Code (ASME)
- American Society for Testing and Materials Publications (ASTM)
- Sheet Metal & Air Conditioning Contractors’ National Association
(SMACNA)
- Underwriters’ Laboratories, Inc. (UL)
- National Electrical Manufacturers Association (NEMA)
- Institute of Electrical and Electronic Engineers (IEEE)
- National Fire Protection Association Standards (NFPA) (latest edition)
- American National Standards Institute Standards (ANSI)
- International Electrotechnical Commission (IEC)
1.3 SUBMITTALS
Prior to start of any construction works, the contractor shall submit for the Duty Free
HVAC & Mechanical Consultant’s approval the following documents:
Within a week after award of the works, the contractor shall submit for Duty Free
HVAC & Mechanical Consultant’s approval, the technical data of materials
proposed to be incorporated into the works. Product sales & brochure are not
acceptable submittals and shall be returned without any action taken. Product
technical data shall show compliance with specifications. No product shall be
incorporated into the work unless approved by the Consultant. Turn around for
Consultant’s approval of technical data is normally three (3) working days after
receipt of the submittal. Product data shall be submitted in three (3) copies. Two
(2) copies will be returned to the contractor with the appropriate stamp.
1.3.3 SAMPLES
2. Approved sample boards will be returned to the contractor and shall be kept in
the contractor’s field office until completion of the works.
Approved product samples maybe installed into the works provided the samples
are free from damages.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 5 of 25
Bid Bulletin Addendum No. HSGS-001
1.3.4 TEST RESULTS
1. Report signed by authorized official of testing laboratory should show
that a material, product or system identical to the material, product or
system to be provided has been tested in accord with specified
requirements. (Testing must have been within three years of date of
contract award for the project.)
2. Report which includes findings of a test required to be performed by
the Contractor on an actual portion of the work or prototype prepared
for the project before shipment to job site.
3. Report which includes finding of a test made at the job site or on
sample taken from the job site, on portion of work during or after
installation.
a. Investigation reports.
b. Final acceptance test and operational test procedure.
Submit test results when called for by the specifications. Report shall be
submitted in three (3) copies. Two (2) copies will be returned to the contractor
upon FMD acceptance of the report.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 6 of 25
Bid Bulletin Addendum No. HSGS-001
SECTION II - PIPE AND FITTINGS
1. The works required under this section consists of the supply, installation,
testing and commissioning of the identification of Air Conditioning Equipment and
Generating set equipment & its fuel system, piping systems and associated
equipment, instrumentation and materials.
2.12 All above ground piping inside the building shall be primed coated with
primer epoxy paint, Sphero brand or equivalent and final coated with QDE paint,
Boysen brand or equivalent similar color with the existing installation.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 7 of 25
Bid Bulletin Addendum No. HSGS-001
2.3 PRODUCTS
2.4 EXECUTION
1. PREPARATION
2. INSTALLATION
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 9 of 25
Bid Bulletin Addendum No. HSGS-001
- Final coating should be 2 layers of QDE paint, Boysen brand or
equivalent. Existing colours should be followed.
- Provide clearance for access to valves and fittings.
- Provide access where valves and fittings are not exposed.
6. EQUIPMENT CONNECTIONS
- It shall be practicable to remove any item of equipment to which piping is
connected by removing only one (1) or two (2) sections of piping. Unions,
flanges or mechanical couplings shall be used at all locations where
connections are made to equipment.
- Connect piping system to mechanical equipment as indicated, and comply
with equipment manufacturer’s installation instructions.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 10 of 25
Bid Bulletin Addendum No. HSGS-001
8. PIPING TEST
- Every pipe system shall be tested at 1.5 times in operating pressure
- Pipe and fittings shall be tested before any insulation or other covering is
applied.
- Testing may be performed in sections before vital equipment is connected
if the test pressure is above the equipment rating.
- Test medium shall be water under hydrostatic pressure with all air
removed from the system. Hydrostatic pressure shall be help for no less
than two (2) hours, with no drop pressure.
- System shall maintain pressure and shall be checked for leaks. Any leaks
shall be repaired and the system retested.
- All components which may not be rated to withstand the test pressures
must be isolated and protected from damage.
- Notification to be provided a minimum of 48 hours in advance of tests.
- Copies of test reports must be submitted and signed by two (2) witnesses
from the owner.
9. CLEANING
- Upon completion of testing, all piping shall be cleaned and flushed.
- Every pipe system shall be cleaned to remove trash, mill scale, cutting oil
and welding splatters from the lines before any control devices are
installed. In such debris has connected in valves shall be disassembled
and cleaned prior to closing for the first time.
- After twenty-four (24) hours of operating, each strainer shall be blown
down. This shall be repeated as often as necessary to produce a clean
discharge from the blow down. Prior to turning system over, every strainer
shall be removed and cleaned.
3.1 DESCRIPTION
The works required under this section consists of the supply, installation, testing and
commissioning of the condenser water valves and associated equipment and materials.
Provide a schedule of all valves required, with quantities.
3.3 PRODUCT
3.3.1 GENERAL
- All valve hand wheels shall be non-slip, malleable or modular iron
unless indicated otherwise under the individual type valve
specification.
- Underwriter approved valves shall bear the underwriter’s label.
- All valves installed in horizontal piping system shall have the stems at
or above the centerline of the pipe. Valve hand wheels shall be
oriented when installed to provide maximum accessibility.
- Select valves and fittings to meet the operating pressures and
operating characteristics of the relevant systems and to meet higher
test pressures where applicable.
- Design pressure of valves and fittings not less than the system
design pressure.
- Valves up to 50mm diameter; screwed connections.
- Valves over 50mm diameter; flanged connections.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 12 of 25
Bid Bulletin Addendum No. HSGS-001
- Hand wheels and handles to be removable with the direction of
closing to be marked clearly.
- Where possible valves to be selected from one manufacturer
throughout the project.
- Where copper alloy valves used, select valves of dezincification
resistant type.
3.4 EXECUTION
3.4.1 GENERAL
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 14 of 25
Bid Bulletin Addendum No. HSGS-001
regulate and control the systems. Valves shall be the full size
of the lines and shall be designed for low pressure drop.
- Flexible pipe connections shall be installed, at pump suction
and discharges and at other locations shown on the
drawings.
4.1 DESCRIPTION:
4.1.1 The works required under this section consist of the supply,
installation, testing and commissioning of the thermal insulation for
mechanical systems and associated equipment and materials.
4.3 PRODUCTS
4.4 EXECUTION
4.4.1 Examination
4.5 GENERAL
4.5.1 Examination
a) Install materials in accordance with manufacturer’s instruction.
b) Samples shall not be used for securing insulation. Insulation and
vapor barrier shall be continuous through wall, ceiling, floor and
roof openings and sleeves, except for fire/smoke dampers.
c) Installation by skilled tradesmen experienced and competent in
this type of work.
d) Clean all surfaces thoroughly of rust, grease, oil and dirt, then
apply with primer epoxy paint prior to application of insulation.
e) Complete all pressure and leak testing prior to application of
insulation.
f) Make insulation continuous with joints firmly butted together,
cold racking eliminated and vapor barrier for cold pipes sealed.
g) Allow for thermal movement.
4.6 CLEANING
At the time scheduled for final inspection, the finished surface of all
exposed insulation shall be clean without any stains or blemishes.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 16 of 25
Bid Bulletin Addendum No. HSGS-001
SECTION V - WATER PUMPS INSTALLATION
5.1 DESCRIPTION
The works required under this section consists of the supply, installation, testing and
commissioning of the centrifugal water pumps and associated equipment and materials.
5.3 PRODUCT
5.4 EXECUTION
5.4.1 Installation
- Install in accordance with manufacturer’s instructions.
- Provide for connection to electrical service.
- Align pumps on concrete foundations and sub-bases. Level, grout,
and bolt in place.
- Install units on vibration isolators as indicated on the BOQ
- Provide flange connections for pipework.
- Pumps shall be supported independently of the piping system.
- Install identification labeling.
- Install drainage pipework from pump drain trays to nearest drain
connection point.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 18 of 25
Bid Bulletin Addendum No. HSGS-001
SECTION VI – AIR DUCT INSTALLATION
6.1 DUCT INSTALLATION
6.1.1 Galvanized steel
It is the preferred material except aluminum or stainless steel which may be
used depending on application.
- Duct fittings shall be factory fabricated.
- Cross break or bead rectangular ductwork (Fig 1-8 of SMACNA).
- Minimum rectangular gage is gage#24.
- Round and oval duct shall be spiral with metal gage as per
manufacturer’s recommendations.
6.1.3 Insulation
9. Cross linked polyolefin thermoplastic is the required material for duct and pipe
insulation.
10. All insulation shall meet the 25/50 Flame spread/smoke development rating.
11. Insulation should have a minimum thickness of 25mm
12. Insulation exposed to outside weather shall be provided with stainless steel
cladding of 0.4mm thickness.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 19 of 25
Bid Bulletin Addendum No. HSGS-001
- Use modulating actuators, Belimo brand model LMS230-SR, 5Nm with
matching digital thermostat controller, Belimo brand or equivalent with higher
quality.
7.1 DESCRIPTION
The works required under this section consists of the supply, installation, testing and
commissioning of the Chillers, Cooling Towers, Air Handling Units, Fan Coil Units,
Ventillation equipment, Genset and its associated equipment and materials.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 20 of 25
Bid Bulletin Addendum No. HSGS-001
7.2.3 Performance Requirements
- Capacity as per manufacturers rating as specified in the drawing and
BOQ.
7.3 EXECUTION
7.3.1 Installation
- Install in accordance with manufacturer’s instructions.
- Provide for connection to electrical service.
- Align equipment on concrete foundations and sub-bases. Level, grout,
and bolt in place.
- Install units on vibration isolators.
- Install identification labeling.
- Install drainage pipework from AHUs and FCUs stainless steel drain
trays to nearest drain connection point.
________________________________ _____________________________
Signature over printed name Position
Duly authorized to sign this Specifications for and on behalf of ________________
Date:____________________
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 21 of 25
Bid Bulletin Addendum No. HSGS-001
The revised Checklist of Requirements supersedes the previously issued.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 22 of 25
Bid Bulletin Addendum No. HSGS-001
b. List of all ongoing government and private contracts starting with the latest
including contracts awarded but not yet started.
CUSTOMER
PROJECTS
CONTACTS
Date of Contract Contractor’s role (whether
Description Total Company/
Contract and Completion sole contractor, subcontractor
(Nature of contract Owner’s Person Number/s
Name (mm/dd/yy and or partner in a JV) and Name
Work) value
mm/dd/yy) percentage of participation
5. Valid and current Philippine Contractors Accreditation Board (PCAB) license and
registration for size range Medium A/Category B contractor (Classification: SP-
ME Mechanical Works and/or SP-AC Air-conditioning or Refrigeration). ITB Clause
12.1(a)(iv)
6. 2015 Audited financial statements, stamped “received” by the BIR or its duly
accredited and authorized institutions, showing the total and current assets and
liabilities. ITB Clause 12.1(a)(v)
7. Duly signed computation of the bidder’s Net Financial Contracting Capacity (Refer to
Bidding Form 1, original). ITB Clause 12.1(a)(v)
8. Valid Joint Venture Agreement (JVA), in case of JV.
Each partner of a joint venture agreement shall likewise submit the requirements in
ITB Clauses 12.1(a)(i), 12.1(a)(ii) and 12.1(a)(vi). Submission of documents required
under ITB Clauses 12.1(a)(iii) to 12.1(a)(v) by any of the joint venture partners
constitutes compliance. ITB Clause 24.6.
2. TECHNICAL DOCUMENTS
1. Bid Security (Refer to BDS under ITB Clause 18.1 for the acceptable forms). ITB
Clause 12.1(b)(i)
2. Project Requirements, which shall include the following: ITB Clause 12.1(b)(ii)
a. Organizational chart for the contract to be bid;
b. List of contractor’s personnel (viz, Project Manager, Project Engineers, Materials
Engineers, and Foremen), to be assigned to the contract to be bid, with their
complete qualification and experience data; and
c. List of contractor’s equipment units, which are owned, leased, and/or under
purchase agreements, supported by certification of availability of equipment from
the equipment lessor/vendor for the duration of the project; and
d. Conformity with the specifications, as enumerated and specified in the following:
I. Specifications (Refer to Section VI, Bidding Documents)
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 23 of 25
Bid Bulletin Addendum No. HSGS-001
II. Drawings (Refer to Section VII, Bidding Documents)
3. Certificate of Site Inspection (Refer to Section IX, Bidding Form No 7 original)
4. Omnibus sworn statement by the prospective bidder or its duly authorized
representative in accordance with Section 25.2(a)(iv) of the IRR of RA 9184. (Refer
to Bidding Form No. 3, original and notarized) with corresponding attachment). ITB
Clause 12.1(b)(iii)
The second envelope shall contain the following:
II. FINANCIAL COMPONENT
1. Bid Form (Refer to Bidding Form 4, original). ITB Clause 13.1(a)
2. Bill of Quantities, (Refer to Section VIII of the Bidding Documents, original) ITB Clause
13.1(b)
3. Bill of Materials. (Refer to Section IX, Bidding Form No 5, original) ITB Clause 13.1(b)
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 24 of 25
Bid Bulletin Addendum No. HSGS-001
CHECKLIST OF ADDITIONAL REQUIREMENTS
Within a non-extendible period of three (3) calendar days from receipt of notice that the bidder is
declared as Lowest Calculated Bid (LCB), the Bidder shall submit in two (2) copies the following
documentary requirements:
1. Latest income and business tax returns in the form specified in the BDS under ITB
Clause 28.2(b);
a. 2015 Income Tax Return (form 1701/1702).
b. Business Tax Return (forms 2550M and 2550Q) for the last six (6) months
(October 2015 to March 2016) prior to opening of Bids filed thru Electronic Filing
and Payment System (EFPS).
Only tax returns filed and taxes paid through the BIR Electronic Filing and Payment
System (EFPS) shall be accepted.
2. Valid and current Certificate of PhilGEPS Registration. ITB Clause 28.2(c);
3. Other documents as per ITB and BDS Clause 31.4(g):
a. Construction schedule and S-curve
b. Manpower schedule
c. Construction methods
d. Equipment utilization schedule
e. PERT/CPM
f. Construction safety and health program approved by the Department of Labor
and Employment. (To be submitted prior to issuance of Notice to Proceed).
g. Contractor’s All Risk Insurance. (To be submitted prior to issuance of Notice to
Proceed).
4. Other appropriate licenses and permits required by law and stated in the BDS under ITB
Clause 28.2(d).
a. Company Profile with names and designation of the company’s officers/partners
(original).
b. Location map and photo of the office (original)
Failure of the Bidder declared as Lowest Calculated Bid to duly submit the requirements under
this Clause on time, or a finding against the veracity of such shall be ground for forfeiture of the
bid security and disqualification of the Bidder for award.
Installation of HVAC System and Standby Generator Set for DFPC NAIA T3 – Landside Store Page 25 of 25
Bid Bulletin Addendum No. HSGS-001