Professional Documents
Culture Documents
Module 3. Harris - Bunagan - Laboratory Exercise
Module 3. Harris - Bunagan - Laboratory Exercise
“Drink for the Gods” managers (N). Of the 12 Project Managers, 4 rated t
"Optimistic" side, 6 rated "Most likely" and only 2 rate
Given the following activity,
Ingredients (Activity)
(Mixture of Drink for the “Gods”)
1. Apple (pealed and blended)
2. Banana (frozen, sliced)
3. Carrot (diced, boiled)
4. Dill (fresh from the gardens)
5. Egg (large, egg whites only)
6. Figs (from the Olympus hills)
7. Grapes (fresh from the Babylons)
2 F 6
7 4 11
A 2 11 X 11
2 6 11 0 11
2 D 5
6 3 9
B 6 9 G 11
6 9 9 2 11 Earliest Start
4 E 9 Earliest Finish
4 5 9 Latest Start
C 4 Latest Finish
4 4 ↑ Path 1
↑ Path 2
6 Duration of Path 3 8 ↑ Path 3
7 Duration of Path 4 11 → Critical Path ↑ Path 4
Activity Code Activity Name Predecessor Duration
A Apple (pealed and blended) - 2
B Banana (frozen, sliced) - 6
C Carrot (diced, boiled) - 4
D Dill (fresh from the gardens) A 3
E Egg (large, egg whites only) C 5
F Figs (from the Olympus hills) A 4
G Grapes (fresh from the Babylons) B, D, E 2
Probability Forecast
Target Duration (Minutes) 25.00
Z Score 13.82
Probability 100.00%
Answer to Question 2
Given 25 minutes to complete the project, the probability that the project will
be accomplished on time is 100%.
Project Manager Rating Expected Variance
Optimistic Most Likely Pessimistic Time
1 1 6 1.83 0.1736 Additional Data
3 2 8 3.33 0.1736 N 12
1 1 4 1.50 0.0625 O 4
10 8 24 11.33 1.3611 M 6
1 1 6 1.83 0.1736 P 2
3 1 16 4.17 1.1736
7 4 18 7.33 0.8403 Critical Path Activities
Duration Forecast
Desired Probability 90.00%
Z Score 1.28
Prescribed Duration (Minutes) 12.00
Answer to Question 3
If the Project Manager wants to see the project's completion rate of
90%, the prescribed duration should be 12 minutes.
Activity Code Activity Name Predecessor Duration
A Apple (pealed and blended) - 2
B Banana (frozen, sliced) - 6
C Carrot (diced, boiled) - 4
D Dill (fresh from the gardens) A 3
E Egg (large, egg whites only) C 5
F Figs (from the Olympus hills) A 4
G Grapes (fresh from the Babylons) B, D, E 2
Answer to Question 4
Based on the computed optimal time of completion (calculated duration of the Critical Path), the probability that th
will speed up the completion by 3 minutes is 0.51%
Probability Forecast
Target Duration (Minutes) 8.00
Z Score -2.57
Probability 0.51%
Question 4
tical Path), the probability that the project will be finished if the project manager